CN103544654A CN201310482363.9A CN201310482363A CN103544654A CN 103544654 A CN103544654 A CN 103544654A CN 201310482363 A CN201310482363 A CN 201310482363A CN 103544654 A CN103544654 A CN 103544654A
Authority
CN
China
Prior art keywords
solution
unit
fuel cost
derivative
oneself
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310482363.9A
Other languages
English (en)
Other versions
CN103544654B (zh
Inventor
吴青华
詹俊鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology SCUT
Original Assignee
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by South China University of Technology SCUT filed Critical South China University of Technology SCUT
Priority to CN201310482363.9A priority Critical patent/CN103544654B/zh
Publication of CN103544654A publication Critical patent/CN103544654A/zh
Application granted granted Critical
Publication of CN103544654B publication Critical patent/CN103544654B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D10/00Energy efficient computing, e.g. low power processors, power management or thermal management

Landscapes

  • Electrical Control Of Air Or Fuel Supplied To Internal-Combustion Engine (AREA)

Abstract

本发明公开了一种电网经济调度局部最小解确定和全局最小解搜索方法,包括下述步骤:(1)获取具有N台发电机组的电力系统中每台机组相关数据;(2)建立电网经济调度问题的数学优化模型;(3)求得每台机组的由阀点和出力上限构成的奇异点集合;(4)可行解中至多有一台机组的出力不处于奇异点位置;(5)可行解中至少有两台机组的出力不处于奇异点位置,此类机组的燃料费用函数对其出力的一阶导数值相等,遍历搜索满足(4)或(5)的可行解;(6)从步骤(4)和(5)得到的具有最小燃料费用值的可行解即为问题的全局最小解。本发明提出问题解空间中局部最小解所需满足的必要条件,并遍历搜索满足该条件的解,得到问题的全局最小解。

Description

电网经济调度局部最小解确定和全局最小解搜索方法
技术领域
本发明涉及电力系统的运行、分析与调度技术领域,特别是涉及一种电网经济调度局部最小解确定和全局最小解搜索方法。
背景技术
考虑发电机组的阀点效应的电网经济调度问题是一个非凸、不可微和多局部最小解的优化问题,传统的梯度法和牛顿法等方法无法对其进行求解,为更好地求解该问题,学者们提出了进化规划算法(Q.H.Wu,and J.T.Ma.Powersystem optimal reactive power dispatch using evolutionary programming[J].IEEETransactions on Power Systems,1995,10(3):1243-1249.吴青华,J.T.Ma.采用进化规划的电力系统最优无功经济调度[J].美国电气与电子工程师协会电力系统汇刊,1995,10(3):1243-1249.),遗传算法(Q.H.Wu,and Y.J.Cao.Dispatching.Encyclopedia of Electrical and Electronics Engineering,JohnWiley&Sons Inc.,edited by John G.Webster,1999.吴青华,曹一家.调度.威利电力与电子工程百科全书,John Wiley&Sons Inc.,John G.Webster编辑,1999.)、(C.-L.Chiang.Improved genetic algorithm for power economic dispatch ofunits with valve-point effects and multiple fuels[J].IEEE Transactions on PowerSystems,2005,20(4):1690-1699.C.-L.Chiang.考虑机组阀点效应和多燃料的电力系统经济调度的改进遗传算法[J].美国电气与电子工程师协会电力系统汇刊,2005,20(4):1690-1699.),蚁群算法(侯云鹤,熊信艮,吴耀武,等.基于广义蚁群算法的电力系统经济负荷分配[J].中国电机工程学报,2003,23(3):59-64.),禁忌搜索算法(W.-M.Lin,F.-S.Cheng,and M.-T.Tsay.An improvedtabu search for economic dispatch with multiple minima[J].IEEE Transactions onPower Systems,2002,17(1):108-112.W.-M.Lin,F.-S.Cheng,M.-T.Tsay.含多最小值的经济调度的改进禁忌搜索算法[J].美国电气与电子工程师协会电力系统汇刊,2002,17(1):108-112.),粒子群优化算法(侯云鹤,鲁丽娟,熊信银,等.改进粒子群算法及其在电力系统经济负荷分配中的应用[J].中国电机工程学报,2004,24(7):95-100.),群搜索优化算法(C.X.Guo,J.P.Zhan,andQ.H.Wu.Dynamic economic emission dispatch based on group search optimizerwith multiple producers[J].Electric Power Systems Research,2012,86:8-16.郭创新,詹俊鹏,吴青华.基于含多个发现者的群搜索优化算法的动态经济排放调度研究[J].电力系统研究,2012,86:8-16.),蜂群算法(S.Hemamalini,andS.P.Simon.Artificial bee colony algorithm for economic load dispatch problem withnon-smooth cost functions[J].Electric Power Components and Systems,2010,38(7):786-803.S.Hemamalini,S.P.Simon.含不平滑成本函数的经济负荷调度问题的人工蜂群算法[J].电力部件与系统,2010,38(7):786-803.)和萤火虫算法(X.-S.Yang,S.S.S.Hosseini,and A.H.Gandomi.Firefly algorithm for solvingnon-convex economic dispatch problems with valve loading effect[J].Applied SoftComputing,2012,12(3):1180-1186.X.-S.Yang,S.S.S.Hosseini,A.H.Gandomi.用于求解含阀点负荷效应的非凸经济调度问题的萤火虫算法[J].应用软计算,2012,12(3):1180-1186.)等随机搜索算法,得到了较好的求解效果,但是不能保证收敛到所述问题的全局最小解。现有的对所述问题的研究主要集中在优化算法的改进,然而针对问题本身的特性研究却鲜见于文献中,更是缺乏能够充分利用问题解空间的特性的求解方法。
发明内容
本发明的目的是为了解决上述现有技术无法保证收敛到考虑发电机组阀点效应的电网经济调度问题的全局最小解的问题,提供一种电网经济调度局部最小解确定和全局最小解搜索方法。
本发明的目的通过下述技术方案实现:
电网经济调度局部最小解确定和全局最小解搜索方法,包括下述步骤:
(1)获取具有N台发电机组的电力系统中每台机组出力上下限数据、出力-燃料费用函数的系数数据和系统负荷数据;
(2)建立考虑机组阀点效应的电网经济调度问题的数学优化模型;
(3)根据机组的出力-燃料费用函数求得每台机组的由阀点和出力上限构成的奇异点集合及燃料费用函数对其出力的二阶导数大于零的区域;
(4)问题的可行解中至多有一台机组的出力不处于奇异点位置,对满足上述条件的可行解进行遍历搜索;
(5)问题的可行解中有两台或两台以上机组的出力不处于奇异点位置,此类机组的燃料费用函数对其出力的一阶导数值相等,且其中至多有一台此类机组不处于燃料费用函数对其出力的二阶导数大于零的区域,对满足上述条件的可行解进行遍历搜索;
(6)从步骤(4)和(5)中得到的具有最小燃料费用值的可行解即为问题的全局最小解,将该全局最小解作为指令通过自动发电控制装置发送给相关发电厂或机组,通过发电厂或机组的自动控制调节装置实现对机组功率的控制。
优选的,所述步骤(4)和(5)中,问题的可行解由N台机组的出力构成,且N台机组的出力总和等于系统负荷。
优选的,根据燃料费用函数一阶导数是否存在,上述电网经济调度模型的可行解
Figure BDA0000396045760000034
中的元素可分成两个集合:PI={Pi:一阶导数fi'(Pi)不存在}和PII={Pi:一阶导数fi'(Pi)存在},根据集合PII中元素个数不同,
Figure BDA0000396045760000035
可分成两类:第一类解,
Figure BDA0000396045760000036
中至多有1个元素属于集合PII,将此类解称为第一类潜在局部最小解,对此类解的遍历搜索在步骤(4)中进行;第二类解,
Figure BDA0000396045760000037
中有两个或两个以上元素属于集合PII,对此类解的遍历搜索在步骤(5)中进行。
优选的,对第一类潜在局部最小解的遍历搜索具体步骤如下:
(1.1)求得每一台发电机组的出力-燃料费用曲线的奇异点(含出力上下限),构成奇异点集合Sg(g=1,2,…,N);
(1.2)选取机组i=1作为平衡机组,平衡机组的作用是当其它机组出力确定时,调整平衡机组的出力以达到负荷平衡;
(1.3)让余下的每一台机组j(j=1,2,…,N,j≠i)均运行在奇异点,共有种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(1.4)对每一种组合(P1,P2,…,Pi-1,Pi+1,PN),令
Figure BDA0000396045760000032
验证机组i出力上下限约束是否越限,即验证不等式是否成立,若不成立该组合无效,若成立则X=(P1,P2,…,Pi-1,Pi,Pi+1,PN)可能是局部最小解;求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X;
(1.5)选取不同的平衡机组,即i=2,3,…,N,对每个不同的取值i,重新执行(1.3)和(1.4)。
优选的,若
Figure BDA0000396045760000041
为所述的第二类解,即
Figure BDA0000396045760000042
中有两个或两个以上元素属于集合PII,则
Figure BDA0000396045760000043
成为上述电网经济调度模型的一个局部最小解的必要条件是:属于所述集合PII中的元素其燃料费用函数的一阶导数值相等,且至多只能有一个元素可以不位于燃料费用函数对其出力的二阶导数大于零的区域,满足所述必要条件的第二类解称为第二类潜在局部最小解。
优选的,步骤(5)中对第二类潜在局部最小解的遍历搜索具体步骤如下:
(2.1)求得每一台机组的出力-燃料费用曲线二阶导数非负的出力区域Ag(g=1,2,…,N);
(2.2)求得每一台机组区域Ag的一阶导数取值范围,确定其区域Ag的一阶导数有交集的机组,记这些机组编号的集合为I,暂时让集合I中机组的出力为在相应的奇异点;
(2.3)让余下的每一台机组
Figure BDA0000396045760000047
均运行在奇异点,共有
Figure BDA0000396045760000044
种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(2.4)对每一种组合(P1,P2,…,PN),验证不等式
Figure BDA0000396045760000045
是否成立,其中l1为集合I中的所有机组[A,B]区域的最大值,l2为集合I中的所有机组[C,D]区域的最大值,‖I‖表示集合I中机组的个数,若不成立该组合无效,若成立则根据库恩-塔克条件确定集合I中机组的出力,使集合I中机组出力满足等微增率法则从而达到总燃料费用最小,同时使负荷平衡约束得到满足,考虑到实际中,一般只有参数完全相同的机组之间其区域Ag的一阶导数才有交集,集合I中每台机组出力增量取为
Figure BDA0000396045760000046
即可,记调整出力后的解为X,求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X。
优选的,[A,B]区域的燃料费用函数二次导数大于零,且其一阶导数值较大;[C,D]区域的燃料费用函数二次导数也大于零,但其一阶导数值较小,甚至出现负值。
本发明相对于现有技术具有如下的优点及效果:
1)本发明提供了考虑机组阀点效应的电网经济调度问题的局部最小解所需满足的必要条件,从而无需对连续解空间进行搜索,仅需搜索满足该必要条件的潜在局部最小解组成的离散解空间,极大地缩小了待搜索空间的范围,提高了搜索效率。
2)本发明提供了一种求解所述问题的新思路:求解方法应充分利用问题的局部最小解所需满足的必要条件。
3)本发明通过对所述问题的满足所述必要条件的潜在局部最小解进行遍历搜索,能够保证收敛到问题的全局最小解。
4)本发明极大地提高了电力系统的发电经济性和效率。
附图说明
图1是本发明的流程图。
图2是本发明机组的出力-燃料费用曲线图。
具体实施方式
下面结合实施例及附图对本发明作进一步详细的描述,但本发明的实施方式不限于此。
实施例1:
本发明的电网经济调度局部最小解确定和全局最小解搜索方法,如图1所示,按以下步骤进行:
步骤(1),获取具有N台发电机组的电力系统中每台机组出力上下限数据
Figure BDA0000396045760000051
出力-燃料费用函数的系数数据ag,bg,cg,eg,fg和系统负荷数据Pd
步骤(2),建立考虑机组阀点效应的电网经济调度问题的数学优化模型。
传统经济调度问题中,机组的出力-燃料费用曲线近似取为平滑的二次多项式。需要说明的是,机组的出力-燃料费用曲线是从机组固有的出力-燃料消耗曲线乘以燃料费用系数得到的。然而,涡轮机的进气阀突然开启时的拔丝效应将使机组的出力-燃料费用曲线产生阀点效应。为更精确地表示机组的出力-燃料费用曲线,考虑机组阀点效应的燃料费用函数取为二次多项式与正弦函数的叠加:
f g ( P g ) = a g + b g P g + c g P g 2 + | e g sin [ f g ( P g min - P g ) ] | - - - ( 1 )
其中fg(Pg)为机组g的燃料费用函数,ag,bg,cg,eg和fg为考虑阀点效应的机组g的燃料费用系数。模型约束条件包括机组出力约束和负荷平衡约束:
P g min ≤ P g ≤ P g max - - - ( 2 )
Σ g = 1 N P g = P d - - - ( 3 )
其中Pg为机组g的有功出力;N为机组总数;
Figure BDA0000396045760000063
分别为机组g的出力上、下限;Pd为系统总负荷;本发明中不考虑线路损耗。
故考虑机组阀点效应电网经济调度模型可如下表示:
min Σ g = 1 N f g ( P g ) - - - ( 4 )
s.t.(2)(3)
其中fg(Pg)由式(1)表示。
步骤(3),根据机组的出力-燃料费用函数求得每台机组的由阀点和出力上限构成的奇异点集合及燃料费用函数对其出力的二阶导数大于零的区域。
如图2所示,A点和D点为阀点所在位置,燃料费用函数二次导数大于零区域由两部分组成,即(A,B)区域和(C,D)区域,其中(A,B)区域的一阶导数值较大,而(C,D)区域的一阶导数值较小,甚至出现负值。图2中A'点的燃料费用函数的一阶导数与A点的燃料费用函数的一阶正导数相等,即f'(A')=f+'(A);图2中D'点的燃料费用函数的一阶导数与D点的燃料费用函数的一阶负导数相等,即
f’(D')=f_'(D)。
步骤(4),问题的可行解中至多有一台机组的出力不处于奇异点位置,对满足上述条件的可行解进行遍历搜索。
根据燃料费用函数一阶导数是否存在,式(4)所示电网经济调度模型的可行解
Figure BDA0000396045760000065
中的元素可分成两个集合:PI={Pi:一阶导数fi'(Pi)不存在}和PII={Pi:一阶导数fi'(Pi)存在}。根据集合PII中元素个数不同,可分成两类:第一类解,
Figure BDA0000396045760000067
中至多有1个元素属于集合PII,将此类解称为第一类潜在局部最小解,对此类解的遍历搜索在本步骤(4)中进行;第二类解,
Figure BDA0000396045760000068
中有两个或两个以上元素属于集合PII,对此类解的遍历搜索在步骤(5)中进行。
对第一类潜在局部最小解的遍历搜索具体步骤如下:
(1)求得每一台发电机组的出力-燃料费用曲线的奇异点(含出力上下限),构成奇异点集合Sg(g=1,2,…,N);
(2)选取机组i=1作为平衡机组,平衡机组的作用是当其它机组出力确定时,调整平衡机组的出力以达到负荷平衡;
(3)让余下的每一台机组j(j=1,2,…,N,j≠i)均运行在奇异点,共有种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(4)对每一种组合(P1,P2,…,Pi-1,Pi+1,PN),令验证机组i出力上下限约束是否越限,即验证不等式
Figure BDA0000396045760000073
是否成立,若不成立该组合无效,若成立则X=(P1,P2,…,Pi-1,Pi,Pi+1,PN)可能是局部最小解;求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X;
(5)选取不同的平衡机组,即i=2,3,…,N,对每个不同的取值i,重新执行(3)和(4)。
步骤(5),问题的可行解中有两台或两台以上机组的出力不处于奇异点位置,此类机组的燃料费用函数对其出力的一阶导数值相等,且其中至多有一台此类机组不处于燃料费用函数对其出力的二阶导数大于零的区域,对满足上述条件的可行解进行遍历搜索。
Figure BDA0000396045760000074
为步骤(4)中所述的第二类解,即
Figure BDA0000396045760000075
中有两个或两个以上元素属于集合PII,则
Figure BDA0000396045760000076
成为式(4)所示电网经济调度模型的一个局部最小解的必要条件是:属于步骤(4)中所述集合PII中的元素其燃料费用函数的一阶导数值相等,且至多只能有一个元素可以不位于燃料费用函数对其出力的二阶导数大于零的区域。满足所述必要条件的第二类解称为第二类潜在局部最小解。所述二阶导数大于零的区域对应于图2的(A,B)区域和(C,D)区域。
在对所述必要条件进行证明之前首先给出局部最小解的定义和有关局部最小解的定理1及其证明。
局部最小解的定义:X为一个局部最小解,当存在一个正实数ε>0使得对于所有{X|‖X-X*‖<ε}都有f(X)≥f(X*),其中‖·‖表示欧几里得二阶范数。
定理1:对于式(4)所示电网经济调度模型的解
Figure BDA0000396045760000077
如果不是式(5)所示的两机组电网经济调度模型的一个局部最小解,那么
Figure BDA00003960457600000712
也不是式(4)所示电网经济调度模型的局部最小解。
minF2(X2)=fi(Pi)+fj(Pj)
s . t . P i + P j - P d = 0 P i min &le; P i &le; P i max P j min &le; P j &le; P j max - - - ( 5 )
其中 P d = P i 0 + P j 0 .
证明:若
Figure BDA00003960457600000711
不是式(5)所示模型的局部最小解,则对于任意小正实数ε>0,在
Figure BDA0000396045760000081
的满足
Figure BDA0000396045760000082
的邻域内存在一个可行解使 f i ( P i 1 ) + f i ( P j 1 ) < f i ( P i 0 ) + f i ( P j 0 ) , 其中 P i 1 + P j 1 = P i 0 + P j 0 . 构造一个式(4)所示电网经济调度模型的新的可行解 X n 1 = ( P 1 0 , &CenterDot; &CenterDot; &CenterDot; , P i - 1 0 , P i 1 , P i + 1 0 , &CenterDot; &CenterDot; &CenterDot; , P j - 1 0 , P j 1 , P j + 1 0 , &CenterDot; &CenterDot; &CenterDot; , P n 0 ) ,
Figure BDA0000396045760000086
由将
Figure BDA0000396045760000087
的第i和j维替换成
Figure BDA0000396045760000088
Figure BDA0000396045760000089
得到,则 F n ( X n 1 ) = F n ( X n 0 ) - f i ( P i 0 ) - f j ( P j 0 ) + f j ( P j 1 ) + f j ( P j 1 ) < F n ( X n 0 ) . 因此,对于任意一个正实数ε>0,在的满足
Figure BDA00003960457600000812
的邻域内,存在一个可行解
Figure BDA00003960457600000813
使得
Figure BDA00003960457600000814
因此
Figure BDA00003960457600000815
不是式(4)所示电网经济调度模型的局部最小解。
在对所述必要条件的证明之前,我们首先给出式(5)所示模型的解(P1,P2)的局部最大/最小特性的证明,该证明分成6种情况,即以下的PRO1.1~PRO1.6。为简化表达但又不影响理解,在PRO1.1~PRO1.6的证明过程中,f1(P1)和f2(P2)中f1和f2的下标均省略,分别表示为f(P1)和f(P2)。
(PRO1.1)假设P1,P2∈(A,D)且f'(P1)>f'(P2),即2台机组均不位于奇异点且其一阶导数值不同。令ε为一个任意小的正实数。若P1增加ε,则P2减少ε,则
(f(P1+ε)-f(P1))/ε>(f(P2)-f(P2-ε))/ε
&DoubleRightArrow; f ( P 1 + &epsiv; ) + f ( P 2 - &epsiv; ) > f ( P 2 ) + f ( P 1 ) ;
若P1减少ε,则P2增加ε,则
(f(P1)-f(P1-ε))/ε>(f(P2+ε)-f(P2))/ε
&DoubleRightArrow; f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) < f ( P 2 ) + f ( P 1 ) .
故两台机组的总燃料费用函数是P1的单调递增函数。类似地,可以证明当P1,P2∈(A,D)且f'(P1)<f'(P2),两台机组的总燃料费用函数是P1的单调递减函数。
假设f'(P1)=f'(P2)。若P1增加ε,则P2减少ε,则
f &prime; ( P 1 ) = f &prime; ( P 2 ) &DoubleRightArrow; f ( P 1 + &epsiv; ) + f ( P 2 - &epsiv; ) = f ( P 2 ) + f ( P 1 ) ;
若P1增加ε,则P2减少ε,则
f &prime; ( P 1 ) = f &prime; ( P 2 ) &DoubleRightArrow; f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 2 ) + f ( P 1 ) .
此时(P1,P2)是一个拐点,若要判断其单调性,需进一步分析,以下分成PRO1.2~PRO1.6分别进行讨论。
(PRO1.2)假设P1,P2∈(A,B)。若P1进一步增加ε,则P2进一步减少ε,则
f’(P1+ε)>f’(P1)=f’(P2)>f’(P2-ε)
&DoubleRightArrow; ( f ( P 1 + 2 &epsiv; ) - f ( P 1 + &epsiv; ) ) / &epsiv; > ( f ( P 2 - &epsiv; ) - f ( P 2 - 2 &epsiv; ) ) / &epsiv;
&DoubleRightArrow; f ( P 1 + 2 &epsiv; ) + f ( P 2 - 2 &epsiv; ) > f ( P 1 + &epsiv; ) + f ( P 2 - &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
另一方面,若P1进一步减少ε,则P2进一步增加ε,则
f’(P1-ε)<f’(P1)=f’(P2)<f’(P2+ε)
&DoubleRightArrow; f ( P 1 - 2 &epsiv; ) + f ( P 2 + 2 &epsiv; > f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
故(P1,P2)是一个局部最小解。
(PRO1.3)假设P1∈(A,B]且P2∈[B,A')。根据燃料费用函数的二阶导数绝对值大小,分成两部分进行讨论:
●|f″(P1)|<|f″(P2)|:若P1进一步增加ε,则P2进一步减少ε,则
(f'(P1+ε)-f'(P1))/ε<(f'(P2-ε)-f'(P2))/ε
&DoubleRightArrow; f &prime; ( P 1 + &epsiv; ) > f &prime; ( P 2 - &epsiv; )
&DoubleRightArrow; f ( P 1 + 2 &epsiv; ) - f ( P 1 + &epsiv; ) < f ( P 2 - &epsiv; ) - f ( P 2 - 2 &epsiv; )
&DoubleRightArrow; f ( P 1 + 2 &epsiv; ) + f ( P 2 - 2 &epsiv; ) < f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
另一方面,若P1进一步减少ε,则P2进一步增加ε,则
(f'(P1)-f'(P-ε1))/ε<(f'(P2)-f'(P2+ε))/ε
&DoubleRightArrow; f ( P 1 - &epsiv; ) - f ( P 1 - 2 &epsiv; ) > f ( P 2 + 2 &epsiv; ) - f ( P 2 + &epsiv; )
&DoubleRightArrow; f ( P 1 - 2 &epsiv; ) + f ( P 2 + 2 &epsiv; ) < f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
故(P1,P2)是一个局部最大解。
●|f″(P1)|>|f″(P2)|:类似地可以证明(P1,P2)是一个局部最小解。
(PRO1.4)假设P1,P2∈[B,C]。若P1进一步增加ε,则P2进一步减少ε,则
f’(P1+ε)<f’(P1)=f’(P2)<f’(P2-ε)
&DoubleRightArrow; f ( P 1 + 2 &epsiv; ) + f ( P 2 - 2 &epsiv; ) < f ( P 1 + &epsiv; ) + f ( P 2 - &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
另一方面,若P1进一步减少ε,则P2进一步增加ε,则
f’(P1-ε)>f’(P1)=f’(P2)>f’(P2+ε)
&DoubleRightArrow; f ( P 1 - 2 &epsiv; ) + f ( P 2 + 2 &epsiv; ) < f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
故(P1,P2)是一个局部最大解。
(PRO1.5)假设P1∈(D',C]且P2∈[C,D)。根据燃料费用函数的二阶导数绝对值大小,分成两部分进行讨论:
●|f″(P1)|<|f″(P2)|:若P1进一步增加ε,则P2进一步减少ε,则
(f'(P1)-f'(P1+ε))/ε<(f'(P2)-f'(P2-ε))/ε
&DoubleRightArrow; f &prime; ( P 1 + &epsiv; ) > f &prime; ( P 2 - &epsiv; )
&DoubleRightArrow; f &prime; ( P 1 + 2 &epsiv; ) - f ( P 1 + &epsiv; ) < f &prime; ( P 2 - &epsiv; ) - f ( P 2 - 2 &epsiv; )
&DoubleRightArrow; f ( P 1 + 2 &epsiv; ) + f ( P 2 - 2 &epsiv; ) > f ( P 1 + &epsiv; ) + f ( P 2 - &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
另一方面,若P1进一步减少ε,则P2进一步增加ε,则
(f'(P11)-f'(P))/ε<(f'(P2+ε)-f'(P2))/ε
&DoubleRightArrow; f ( P 1 - &epsiv; ) - f ( P 1 - 2 &epsiv; ) < f ( P 2 + 2 &epsiv; ) - f ( P 2 + &epsiv; )
&DoubleRightArrow; f ( P 1 - 2 &epsiv; ) + f ( P 2 + 2 &epsiv; ) > f ( P 1 - &epsiv; ) + f ( P 2 + &epsiv; ) = f ( P 1 ) + f ( P 2 ) .
故(P1,P2)是一个局部最小解。
●|f″(P1)|>|f″(P2)|:类似地可以证明(P1,P2)是一个局部最大解。
(PRO1.6)假设P1,P2∈[C,D)。此种情况与PRO1.2类似,可类似地证明(P1,P2)是一个局部最小解。
为方便对比,将PRO1.1~PRO1.6的情况列于表1。
表1考虑阀点效应2机组经济调度问题的局部最小解分析
Figure BDA0000396045760000101
以下是对所述必要条件的证明。首先对所述必要条件中的“属于步骤(4)中所述的集合PII中的元素其燃料费用函数的一阶导数值相等”部分采用反证法进行证明:假设
Figure BDA0000396045760000111
是式(4)所示电网经济调度模型的一个局部最小解,且其中存在2台机组i和j,其燃料费用函数的一阶导数值不相等,即
Figure BDA0000396045760000112
由PRO1.1可知(Pi,Pj)不是式(5)所示模型的局部最小解,进而由定理1可知
Figure BDA0000396045760000113
不是式(4)所示电网经济调度模型的局部最小解,存在矛盾,故而集合PII中的元素其燃料费用函数的一阶导数值必须相等。
然后对所述必要条件中的“至多只能有一个元素可以不位于燃料费用函数对其出力的二阶导数大于零的区域”部分同样采用反证法进行证明:假设至少存在两个元素不位于燃料费用函数对其出力的二阶导数大于零的区域,即 P i &NotElement; ( A , B ) , P i &NotElement; ( C , D ) , P j &NotElement; ( A , B ) , P j &NotElement; ( C , D ) , i , j = 1,2 , &CenterDot; &CenterDot; &CenterDot; , n , i &NotEqual; j . 根据PRO1.1~PRO1.6可知(Pi,Pj)不是式(5)所示模型的局部最小解,进而由定理1可知
Figure BDA0000396045760000114
不是式(4)所示电网经济调度模型的局部最小解,存在矛盾,故至多只能有一个元素可以不位于燃料费用函数对其出力的二阶导数大于零的区域。
步骤(5)中对第二类潜在局部最小解的遍历搜索具体步骤如下:
(1)求得每一台机组的出力-燃料费用曲线二阶导数非负的出力区域Ag(g=1,2,…,N);
(2)求得每一台机组区域Ag的一阶导数取值范围,确定其区域Ag的一阶导数有交集的机组,记这些机组编号的集合为I,暂时让集合I中机组的出力为在相应的奇异点;
(3)让余下的每一台机组
Figure BDA0000396045760000118
均运行在奇异点,共有种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(4)对每一种组合(P1,P2,…,PN),验证不等式
Figure BDA0000396045760000116
是否成立,其中l1为集合I中的所有机组[A,B]区域的最大值,l2为集合I中的所有机组[C,D]区域的最大值,‖I‖表示集合I中机组的个数。若不成立该组合无效,若成立则根据库恩-塔克条件确定集合I中机组的出力,使集合I中机组出力满足等微增率法则从而达到总燃料费用最小,同时使负荷平衡约束得到满足。考虑到实际中,一般只有参数完全相同的机组之间其区域Ag的一阶导数才有交集,集合I中每台机组出力增量取为
Figure BDA0000396045760000121
即可。记调整出力后的解为X,求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X。
步骤(6),从步骤(4)和(5)中得到的具有最小燃料费用值的可行解即为问题的全局最小解,将该全局最小解作为指令通过自动发电控制装置发送给相关发电厂或机组,通过发电厂或机组的自动控制调节装置实现对机组功率的控制。
实施例2:
以一个3机组和一个13机组的标准测试系统为例,3机组系统的总负荷取850MW,13机组系统的总负荷取1800MW。表2和表3列出了采用本发明采用的遍历搜索法求解得到的全局最小解和已发表文献中最好的结果。与已发表的最好结果相比,本发明采用的遍历搜索法能够得到相同或更小的解,这表明本发明采用的遍历搜索法确实能得到全局最小解,也验证了本发明中电网经济调度局部最小解确定和全局最小解搜索方法的合理性、有效性和优越性。
表2不同算法得到的3机组标准测试系统最小解
Figure BDA0000396045760000122
表3不同算法得到的13机组标准测试系统最小解
Figure BDA0000396045760000123
Figure BDA0000396045760000131
上述实施例为本发明较佳的实施方式,但本发明的实施方式并不受上述实施例的限制,其他的任何未背离本发明的精神实质与原理下所作的改变、修饰、替代、组合、简化,均应为等效的置换方式,都包含在本发明的保护范围之内。

Claims (7)

1.电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,包括下述步骤:
(1)获取具有N台发电机组的电力系统中每台机组出力上下限数据、出力-燃料费用函数的系数数据和系统负荷数据;
(2)建立考虑机组阀点效应的电网经济调度问题的数学优化模型;
(3)根据机组的出力-燃料费用函数求得每台机组的由阀点和出力上限构成的奇异点集合及燃料费用函数对其出力的二阶导数大于零的区域;
(4)问题的可行解中至多有一台机组的出力不处于奇异点位置,对满足上述条件的可行解进行遍历搜索;
(5)问题的可行解中有两台或两台以上机组的出力不处于奇异点位置,此类机组的燃料费用函数对其出力的一阶导数值相等,且其中至多有一台此类机组不处于燃料费用函数对其出力的二阶导数大于零的区域,对满足上述条件的可行解进行遍历搜索;
(6)从步骤(4)和(5)中得到的具有最小燃料费用值的可行解即为问题的全局最小解,将该全局最小解作为指令通过自动发电控制装置发送给相关发电厂或机组,通过发电厂或机组的自动控制调节装置实现对机组功率的控制。
2.根据权利要求1所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,所述步骤(4)和(5)中,问题的可行解由N台机组的出力构成,且N台机组的出力总和等于系统负荷。
3.根据权利要求1所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,根据燃料费用函数一阶导数是否存在,上述电网经济调度模型的可行解
Figure FDA0000396045750000011
中的元素可分成两个集合:PI={Pi:一阶导数fi'(Pi)不存在}和PII={Pi:一阶导数fi'(Pi)存在},根据集合PII中元素个数不同,可分成两类:第一类解,
Figure FDA0000396045750000013
中至多有1个元素属于集合PII,将此类解称为第一类潜在局部最小解,对此类解的遍历搜索在步骤(4)中进行;第二类解,
Figure FDA0000396045750000014
中有两个或两个以上元素属于集合PII,对此类解的遍历搜索在步骤(5)中进行。
4.根据权利要求3所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,对第一类潜在局部最小解的遍历搜索具体步骤如下:
(1.1)求得每一台发电机组的出力-燃料费用曲线的奇异点(含出力上下限),构成奇异点集合Sg(g=1,2,…,N);
(1.2)选取机组i=1作为平衡机组,平衡机组的作用是当其它机组出力确定时,调整平衡机组的出力以达到负荷平衡;
(1.3)让余下的每一台机组j(j=1,2,…,N,j≠i)均运行在奇异点,共有
Figure FDA0000396045750000021
种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(1.4)对每一种组合(P1,P2,…,Pi-1,Pi+1,PN),令
Figure FDA0000396045750000022
验证机组i出力上下限约束是否越限,即验证不等式
Figure FDA0000396045750000023
是否成立,若不成立该组合无效,若成立则X=(P1,P2,…,Pi-1,Pi,Pi+1,PN)可能是局部最小解;求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X;
(1.5)选取不同的平衡机组,即i=2,3,…,N,对每个不同的取值i,重新执行(1.3)和(1.4)。
5.根据权利要求3所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,若
Figure FDA0000396045750000026
为所述的第二类解,即
Figure FDA0000396045750000027
中有两个或两个以上元素属于集合PII,则
Figure FDA0000396045750000028
成为上述电网经济调度模型的一个局部最小解的必要条件是:属于所述集合PII中的元素其燃料费用函数的一阶导数值相等,且至多只能有一个元素可以不位于燃料费用函数对其出力的二阶导数大于零的区域,满足所述必要条件的第二类解称为第二类潜在局部最小解。
6.根据权利要求3所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,步骤(5)中对第二类潜在局部最小解的遍历搜索具体步骤如下:
(2.1)求得每一台机组的出力-燃料费用曲线二阶导数非负的出力区域Ag(g=1,2,…,N);
(2.2)求得每一台机组区域Ag的一阶导数取值范围,确定其区域Ag的一阶导数有交集的机组,记这些机组编号的集合为I,暂时让集合I中机组的出力为在相应的奇异点;
(2.3)让余下的每一台机组
Figure FDA0000396045750000029
均运行在奇异点,共有
Figure FDA0000396045750000024
种排列组合,其中II为连乘符号,‖Sj‖表示集合Sj中奇异点的个数;
(2.4)对每一种组合(P1,P2,…,PN),验证不等式
Figure FDA0000396045750000025
是否成立,其中l1为集合I中的所有机组[A,B]区域的最大值,l2为集合I中的所有机组[C,D]区域的最大值,‖I‖表示集合I中机组的个数,若不成立该组合无效,若成立则根据库恩-塔克条件确定集合I中机组的出力,使集合I中机组出力满足等微增率法则从而达到总燃料费用最小,同时使负荷平衡约束得到满足,考虑到实际中,一般只有参数完全相同的机组之间其区域Ag的一阶导数才有交集,集合I中每台机组出力增量取为
Figure FDA0000396045750000031
即可,记调整出力后的解为X,求解其燃料费用值f(X),若f(X)≤fmin则更新最小燃料费用值fmin=f(X)并记录对应最小解X。
7.根据权利要求6所述的电网经济调度局部最小解确定和全局最小解搜索方法,其特征在于,[A,B]区域的燃料费用函数二次导数大于零,且其一阶导数值较大;[C,D]区域的燃料费用函数二次导数也大于零,但其一阶导数值较小,甚至出现负值。
CN201310482363.9A 2013-10-15 2013-10-15 电网经济调度局部最小解确定和全局最小解搜索方法 Active CN103544654B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310482363.9A CN103544654B (zh) 2013-10-15 2013-10-15 电网经济调度局部最小解确定和全局最小解搜索方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310482363.9A CN103544654B (zh) 2013-10-15 2013-10-15 电网经济调度局部最小解确定和全局最小解搜索方法

Publications (2)

Publication Number Publication Date
CN103544654A true CN103544654A (zh) 2014-01-29
CN103544654B CN103544654B (zh) 2016-10-05

Family

ID=49968081

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310482363.9A Active CN103544654B (zh) 2013-10-15 2013-10-15 电网经济调度局部最小解确定和全局最小解搜索方法

Country Status (1)

Country Link
CN (1) CN103544654B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104333048A (zh) * 2014-10-31 2015-02-04 广州供电局有限公司 火电机组的调度方法及系统
CN105317475A (zh) * 2014-07-31 2016-02-10 上海明华电力技术工程有限公司 基于汽轮机调门阀点的机组负荷协调控制方法
CN110097212A (zh) * 2019-04-08 2019-08-06 华南理工大学 一种无人艇高能效协同区域探测方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101763089A (zh) * 2009-12-14 2010-06-30 江西省电力科学研究院 基于电力市场化环境下的火电厂机组出力优化运行方法
CN102737351A (zh) * 2012-06-15 2012-10-17 广东电网公司电力科学研究院 燃气-蒸汽联合循环发电机组多目标多约束优化调度方法
US20130018517A1 (en) * 2011-07-15 2013-01-17 International Business Machines Corporation Solving large-scale security-constrained economic dispatch problem in real-time
CN103050998A (zh) * 2012-11-26 2013-04-17 西安理工大学 一种风电并网的火电系统动态调度方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101763089A (zh) * 2009-12-14 2010-06-30 江西省电力科学研究院 基于电力市场化环境下的火电厂机组出力优化运行方法
US20130018517A1 (en) * 2011-07-15 2013-01-17 International Business Machines Corporation Solving large-scale security-constrained economic dispatch problem in real-time
CN102737351A (zh) * 2012-06-15 2012-10-17 广东电网公司电力科学研究院 燃气-蒸汽联合循环发电机组多目标多约束优化调度方法
CN103050998A (zh) * 2012-11-26 2013-04-17 西安理工大学 一种风电并网的火电系统动态调度方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
袁晓辉,袁艳斌,王乘: ""计及阀点效应的电力系统经济运行方法"", 《电工技术学报》, vol. 20, no. 6, 30 June 2005 (2005-06-30), pages 92 - 96 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105317475A (zh) * 2014-07-31 2016-02-10 上海明华电力技术工程有限公司 基于汽轮机调门阀点的机组负荷协调控制方法
CN105317475B (zh) * 2014-07-31 2017-06-23 上海明华电力技术工程有限公司 基于汽轮机调门阀点的机组负荷协调控制方法
CN104333048A (zh) * 2014-10-31 2015-02-04 广州供电局有限公司 火电机组的调度方法及系统
CN110097212A (zh) * 2019-04-08 2019-08-06 华南理工大学 一种无人艇高能效协同区域探测方法

Also Published As

Publication number Publication date
CN103544654B (zh) 2016-10-05

Similar Documents

Publication Publication Date Title
Mohamed et al. Sizing and techno-economic analysis of stand-alone hybrid photovoltaic/wind/diesel/battery power generation systems
Bai et al. Robust AC optimal power flow for power networks with wind power generation
Fathima et al. Optimization in microgrids with hybrid energy systems–A review
Zhao et al. Deep learning based model-free robust load restoration to enhance bulk system resilience with wind power penetration
CN109034587B (zh) 一种协调多种可控单元的主动配电系统优化调度方法
Dhamanda et al. A traditional approach to solve economic load dispatch problem of thermal generating unit using MATLAB programming
Mi et al. Frequency control strategy of multi‐area hybrid power system based on frequency division and sliding mode algorithm
Li et al. Differential evolution-based load frequency robust control for micro-grids with energy storage systems
Yang et al. Levenberg‐Marquardt backpropagation algorithm for parameter identification of solid oxide fuel cells
Mumtaz et al. Adaptive control paradigm for photovoltaic and solid oxide fuel cell in a grid-integrated hybrid renewable energy system
CN103544654A (zh) 电网经济调度局部最小解确定和全局最小解搜索方法
Belkhier et al. Novel design and adaptive coordinated energy management of hybrid fuel‐cells/tidal/wind/PV array energy systems with battery storage for microgrids
CN113346484B (zh) 一种考虑暂态不确定性的配电网弹性提升方法及系统
Mohan et al. Optimized power flow management based on Harris Hawks optimization for an islanded DC microgrid
Yu et al. Application of an improved Particle Swarm Optimization to economic load dispatch in power plant
Liu et al. Optimal sitting and sizing of distributed generators based on a modified primal-dual interior point algorithm
Du et al. An optimization framework for dynamic hybrid energy systems
CN103559387A (zh) 考虑阀点效应电网经济调度问题的分维最速下降求解方法
Li et al. A comprehensive review on energy storage system optimal planning and benefit evaluation methods in smart grids
CN104408531B (zh) 一种多维多阶段复杂决策问题的均匀动态规划方法
Saini et al. Digital Twin of a commercial building microgrid: Economic & environmental sustainability analysis
CN115545340A (zh) 一种考虑双重不确定性的综合能源站-网协同规划方法
Zali Equivalent dynamic model of distribution network with distributed generation
Yang et al. Coordinated Optimal Configuration Method of Hybrid Energy Storage Systems in Energy Internet System
CN113496298A (zh) 一种综合能源系统的优化方法、装置和电子设备

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant