CN103498467B - 高承载力基础桩及其与基础的处理方法 - Google Patents

高承载力基础桩及其与基础的处理方法 Download PDF

Info

Publication number
CN103498467B
CN103498467B CN201310476777.0A CN201310476777A CN103498467B CN 103498467 B CN103498467 B CN 103498467B CN 201310476777 A CN201310476777 A CN 201310476777A CN 103498467 B CN103498467 B CN 103498467B
Authority
CN
China
Prior art keywords
pile
foundation
pile body
bearing
survey meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310476777.0A
Other languages
English (en)
Other versions
CN103498467A (zh
Inventor
程文
成军
沈乐平
姜雪涛
沈强儒
强骅
黄坤坤
成张佳宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Liyang Urban Construction Group Co ltd
Nantong Century Building Science And Technology Institute
Nantong University
Original Assignee
Nantong Century Building Science And Technology Academy
Liyang Chengjian Group Co Ltd
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Century Building Science And Technology Academy, Liyang Chengjian Group Co Ltd, Nantong University filed Critical Nantong Century Building Science And Technology Academy
Priority to CN201310476777.0A priority Critical patent/CN103498467B/zh
Publication of CN103498467A publication Critical patent/CN103498467A/zh
Application granted granted Critical
Publication of CN103498467B publication Critical patent/CN103498467B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种高承载力基础桩及其与基础的处理方法,先采用压入多级锥形面的管状结构预制桩,再通过高压泵注入水泥浆,使水泥浆渗透与桩周围的持力层并进行凝固,增大了桩体的摩擦力,使得桩体稳定性能好,同时在发生地震以及地基土质发生位移时使桩体的稳定性明显增强,大大提高了桩体的抗震性能,从而使得一些因桩基沉降较大而必须采用现浇混凝土基础的工程,可以安全地使用本高承载力基础桩及其与基础的处理工法。本发明施工方便,效果好。采用高承载力基础桩单桩竖向极限承载力较混凝土预制桩单桩竖向极限承载力高15%--25%。

Description

高承载力基础桩及其与基础的处理方法
技术领域
本发明涉及一种高承载力基础桩及其与基础的处理方法。
背景技术
现有建筑业在高层建筑物基础施工过程中,采用预制桩作为基础桩,通过压入的方法将基础桩压入地基中已在广泛使用,但由于很多地方土体承载力较差,不能满足实际要求,而无法解决承载问题,常常发现预制桩沉降量大于设计范围倾向,使得工程上放弃对预制桩的使用,更改为其它设计方案,这主要是由于预制桩在持力层不能满足荷载要求,或由于摩擦阻力不够,使得放弃预制桩的选择与施工,且在施工过程中当一根桩压入后,要在相邻区域内再次压入装置,因为产生了对前根桩的挤压损坏,使得桩基破坏,产生空隙,从而影响桩基效果,为了增大端面阻力和摩擦阻力,所以有时只能采取增大桩的直径和增加桩的长度,来增大端面阻力和摩擦阻力,实际上这样的施工带来了管形桩的长度增加和直径增大,使工程的造价明显提高,所以有必要对现有的基础桩加以改进。
发明内容
本发明的目的在于提供一种施工方便,效果好的高承载力基础桩及其与基础的处理方法。
本发明的技术解决方案是:
一种高承载力基础桩及其与基础的处理方法,其特征是:包括下列步骤:
(1)桩基施工
确定桩基位置,进行定位预制孔;
(2)将压桩机安置在相应的预制孔位置上,将桩头放置于预制孔中;
(3)吊装底桩体至桩头上,在桩头与底桩体之间设置下端压力探测仪,并将下端压力探测仪的数据线通过底桩中心孔引出,并与压力检测仪相连接;
(4)通过压桩机将底桩体压入地基,并吊装上桩体,通过连接盘将底桩体与上桩体连接;
(5)在上桩体的上端设置上端压力探测仪,并将底桩体中的数据线通过上桩中心孔引出与压力检测仪相连接,将上端压力探测仪的数据线与压力检测仪相连接;
(6)根据承压要求逐级将上桩体压入地基,并通过下端压力探测仪、上端压力探测仪检测压力数据,使压力数据至设计要求,压桩结束;
(7)采用高压泵将水泥浆通过桩体中心孔注入,水泥浆通过中心孔进入桩体端部浇灌槽,并通过锥面浇灌槽注入到桩体外围与持力层之间,水泥浆凝固;
(8)通过数据线分别检测下端压力探测仪、上端压力探测仪压力,使其符合要求;
(9)压浆后的静载荷检测在压浆后的28天进行,并根据检测结果确定该高承载力基础桩是否需要再次压入及其压入量,保证各桩体的竖向极限承载力在一致的规定范围内,确保质量。
本发明施工方便,效果好。采用高承载力基础桩单桩竖向极限承载力较混凝土预制桩单桩竖向极限承载力高15%--25%。
高承载力基础桩及其与基础的处理工法是在软基、地质条件较差及地下水位较高的工程中,先采用压入多级锥形面的管状结构预制桩,再通过高压泵注入水泥浆,使水泥浆渗透与桩周围的持力层并进行凝固,增大了桩体的摩擦力,使得桩体稳定性能好,同时在发生地震以及地基土质发生位移时使桩体的稳定性明显增强,大大提高了桩体的抗震性能,从而使得一些因桩基沉降较大而必须采用现浇混凝土基础的工程,可以安全地使用本高承载力基础桩及其与基础的处理工法;在高承载力基础桩的下端及上端设置压力探测仪,从而在施工过程中以及施工结束后能及时准确地掌握到地基的承载力,并使各桩体受力均匀,确保施工以及质量得到控制。
附图说明
下面结合附图和实施例对本发明作进一步说明。
图1是本发明高承载力基础桩及其基础示意图。
图中:1、桩头;2、下端压力探测仪;3、下桩体;4、上桩体;5、上端压力探测仪。
具体实施方式
一种高承载力基础桩及其与基础的处理方法,包括下列步骤:
(1)桩基施工
确定桩基位置,进行定位预制孔;
(2)将压桩机安置在相应的预制孔位置上,将桩头放置于预制孔中;
(3)吊装底桩体至桩头上,在桩头与底桩体之间设置下端压力探测仪,并将下端压力探测仪的数据线通过底桩中心孔引出,并与压力检测仪相连接;
(4)通过压桩机将底桩体压入地基,并吊装上桩体,通过连接盘将底桩体与上桩体连接;
(5)在上桩体的上端设置上端压力探测仪,并将底桩体中的数据线通过上桩中心孔引出与压力检测仪相连接,将上端压力探测仪的数据线与压力检测仪相连接;
(6)根据承压要求逐级将上桩体压入地基,并通过下端压力探测仪、上端压力探测仪检测压力数据,使压力数据至设计要求,压桩结束;
(7)采用高压泵将水泥浆通过桩体中心孔注入,水泥浆通过中心孔进入桩体端部浇灌槽,并通过锥面浇灌槽注入到桩体外围与持力层之间,水泥浆凝固;
(8)通过数据线分别检测下端压力探测仪、上端压力探测仪压力,使其符合要求;
(9)压浆后的静载荷检测在压浆后的28天进行,并根据检测结果确定该高承载力基础桩是否需要再次压入及其压入量,保证各桩体的竖向极限承载力在一致的规定范围内,确保质量。

Claims (1)

1.一种高承载力基础桩的处理方法,其特征是:包括下列步骤:
(1)桩基施工
确定桩基位置,进行定位预制孔;
(2)将压桩机安置在相应的预制孔位置上,将桩头放置于预制孔中;
(3)吊装底桩体至桩头上,在桩头与底桩体之间设置下端压力探测仪,并将下端压力探测仪的数据线通过底桩中心孔引出,并与压力检测仪相连接;
(4)通过压桩机将底桩体压入地基,并吊装上桩体,通过连接盘将底桩体与上桩体连接;
(5)在上桩体的上端设置上端压力探测仪,并将底桩体中的数据线通过上桩中心孔引出与压力检测仪相连接,将上端压力探测仪的数据线与压力检测仪相连接;
(6)根据承压要求逐级将上桩体压入地基,并通过下端压力探测仪、上端压力探测仪检测压力数据,使压力数据至设计要求,压桩结束;
(7)采用高压泵将水泥浆通过桩体中心孔注入,水泥浆通过中心孔进入桩体端部浇灌槽,并通过锥面浇灌槽注入到桩体外围与持力层之间,水泥浆凝固;
(8)通过数据线分别检测下端压力探测仪、上端压力探测仪压力,使其符合要求;
(9)压浆后的静载荷检测在压浆后的28天进行,并根据检测结果确定该高承载力基础桩是否需要再次压入及其压入量,保证各桩体的竖向极限承载力在一致的规定范围内,确保质量。
CN201310476777.0A 2013-10-14 2013-10-14 高承载力基础桩及其与基础的处理方法 Expired - Fee Related CN103498467B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310476777.0A CN103498467B (zh) 2013-10-14 2013-10-14 高承载力基础桩及其与基础的处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310476777.0A CN103498467B (zh) 2013-10-14 2013-10-14 高承载力基础桩及其与基础的处理方法

Publications (2)

Publication Number Publication Date
CN103498467A CN103498467A (zh) 2014-01-08
CN103498467B true CN103498467B (zh) 2015-07-22

Family

ID=49863717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310476777.0A Expired - Fee Related CN103498467B (zh) 2013-10-14 2013-10-14 高承载力基础桩及其与基础的处理方法

Country Status (1)

Country Link
CN (1) CN103498467B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351222A (zh) * 2016-08-30 2017-01-25 中国建筑西南勘察设计研究院有限公司 软岩地基坐浆植入管桩的施工方法
CN109826221A (zh) * 2019-03-27 2019-05-31 华北水利水电大学 一种桩承载力高的大型桥梁桩基施工方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2730940Y (zh) * 2004-08-24 2005-10-05 陈忠 预制钢筋砼桩心后注浆桩
CN1912253A (zh) * 2006-06-21 2007-02-14 闫雪晖 预应力管桩的施工方法
CN102330438A (zh) * 2011-07-13 2012-01-25 中国地质科学院地质力学研究所 滑坡防治中微型桩性状的测试方法
CN102535452A (zh) * 2010-12-15 2012-07-04 王云艇 一种新型工程桩
CN202672139U (zh) * 2012-06-05 2013-01-16 江苏兴厦建筑安装有限公司 预制钢筋混凝土方桩
CN202767071U (zh) * 2012-09-26 2013-03-06 长沙学院 桩底桩侧联合后注浆预应力管桩
JP2013155485A (ja) * 2012-01-26 2013-08-15 Kfc Ltd 地盤補強構造及びその形成方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2730940Y (zh) * 2004-08-24 2005-10-05 陈忠 预制钢筋砼桩心后注浆桩
CN1912253A (zh) * 2006-06-21 2007-02-14 闫雪晖 预应力管桩的施工方法
CN102535452A (zh) * 2010-12-15 2012-07-04 王云艇 一种新型工程桩
CN102330438A (zh) * 2011-07-13 2012-01-25 中国地质科学院地质力学研究所 滑坡防治中微型桩性状的测试方法
JP2013155485A (ja) * 2012-01-26 2013-08-15 Kfc Ltd 地盤補強構造及びその形成方法
CN202672139U (zh) * 2012-06-05 2013-01-16 江苏兴厦建筑安装有限公司 预制钢筋混凝土方桩
CN202767071U (zh) * 2012-09-26 2013-03-06 长沙学院 桩底桩侧联合后注浆预应力管桩

Also Published As

Publication number Publication date
CN103498467A (zh) 2014-01-08

Similar Documents

Publication Publication Date Title
CN104018512B (zh) 对环境微扰动的沉井下沉施工方法
CN205530247U (zh) 一种预钻孔囊袋注浆锚杆结构
CN105350527A (zh) 一种基于bim的预应力管桩的施工方法和预应力管桩
CN103835287B (zh) 一种挤密变径桩的施工方法
CN103669385A (zh) 利用网状桩基础提高桩群承载力的方法
CN110158585A (zh) 一种消减软土区桩基负摩阻力的装置及施工方法
CN103498467B (zh) 高承载力基础桩及其与基础的处理方法
CN105133641A (zh) 一种薄壁型连续墙式地基基础加固结构及方法
CN102134861B (zh) 土体内预制桩试桩方法
CN103334428B (zh) 一种圆盘式混凝土灌注桩及其施工工艺
CN206220101U (zh) 一种深基坑的支护加固结构
CN201411685Y (zh) 一种防止负摩阻力的装置
CN208501762U (zh) 一种桩基础沉降加固顶升调平结构
CN203284775U (zh) 高承载力基础桩
CN104863126B (zh) 采用压浆技术处理大直径钻孔灌注桩塌孔的方法
CN113789779A (zh) 一种应用于软土地基和珊瑚砂地基的桩基结构及施工方法
CN203977418U (zh) 防止灌注桩混凝土流失装置
CN104110031B (zh) 高承载力基础桩及其与基础的处理方法
CN203960852U (zh) 人工挖孔桩
CN100482897C (zh) 自张式人字形桩
CN205604310U (zh) 一种用于研究桩基负摩阻力时间效应的试验装置
CN104120714B (zh) 人工挖孔桩的施工方法
CN204059372U (zh) 一种垂直岩体永久性支护装置
CN203684251U (zh) 倒t型单桩基础
CN204738290U (zh) 一种阶梯型变截面旋扩灌注桩

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: JIANGSU LIYANG URBAN CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: CHENG JUN

Effective date: 20150610

Owner name: NANTONG UNIVERSITY NANTONG SHIJI INSTITUTE OF BUIL

Effective date: 20150610

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Cheng Wen

Inventor after: Cheng Jun

Inventor after: Shen Leping

Inventor after: Jiang Xuetao

Inventor after: Shen Qiangru

Inventor after: Qiang Hua

Inventor after: Huang Kunkun

Inventor after: Cheng Zhangjianing

Inventor before: Cheng Jun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHENG JUN TO: CHENG WEN CHENG JUN SHEN LEPING JIANG XUETAO SHEN QIANGRU QIANG HUA HUANG KUNKUN ZHANGJIANING CHENG

TA01 Transfer of patent application right

Effective date of registration: 20150610

Address after: Yanshan Liyang Town of Liyang City, Jiangsu province 213300 Changzhou City Road No. 5

Applicant after: JIANGSU LIYANG URBAN CONSTRUCTION GROUP CO.,LTD.

Applicant after: NANTONG University

Applicant after: NANTONG CENTURY BUILDING SCIENCE AND TECHNOLOGY INSTITUTE

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 room 2208

Applicant before: Cheng Jun

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150722

Termination date: 20211014

CF01 Termination of patent right due to non-payment of annual fee