CN103485357B - 一种轻型井点降水管成孔装置及其方法 - Google Patents

一种轻型井点降水管成孔装置及其方法 Download PDF

Info

Publication number
CN103485357B
CN103485357B CN201310395319.4A CN201310395319A CN103485357B CN 103485357 B CN103485357 B CN 103485357B CN 201310395319 A CN201310395319 A CN 201310395319A CN 103485357 B CN103485357 B CN 103485357B
Authority
CN
China
Prior art keywords
downcomer
application
hammer
well point
light well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310395319.4A
Other languages
English (en)
Other versions
CN103485357A (zh
Inventor
刘刚
刘晓军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
China Railway Construction Group Southern Engineering Co Ltd
China Railway Construction Group Infrastructure Construction Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN201310395319.4A priority Critical patent/CN103485357B/zh
Publication of CN103485357A publication Critical patent/CN103485357A/zh
Application granted granted Critical
Publication of CN103485357B publication Critical patent/CN103485357B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及一种轻型井点降水管成孔装置及其方法,所述方法包括以下步骤:1)根据工程要求制备降水管;2)利用外力强夯降水管入土;3)利用高压水对降水管进行洗井;4)将各降水管连接至总管进行试抽。所述装置包括降水管和配合使用的锤击下沉装置,所述降水管顶端设有开口,降水管下部分布有透水孔,降水管底端为封闭端;所述锤击下沉装置包括锤击器和空气压缩机,空气压缩机与所述锤击器之间连接有压力软管。本发明的有益效果为:结构简单、价格低廉、使用方便、成井迅速,不便于冲孔成井区域也可使用,利用降水管当作抽水管及入土所成孔护壁,一管两用,管体满足真空抽水及入土强度稳定性要求。

Description

一种轻型井点降水管成孔装置及其方法
技术领域
本发明涉及施工技术领域,尤其涉及一种轻型井点降水管成孔装置及其方法。
背景技术
目前,井点降水成孔一般采用冲击式或者回转式钻机成孔。冲击式是利用高压水泵,通过软管与一根特制的钢管相连,钢管端部设有喷水孔,由两名操作工人手持钢管在集水管位置上下抽动,直至成孔,成孔深度一般比滤管深,冲孔时需注意冲水管垂直插入水中,并做左右上下摆动,成孔后要立即拔出冲水管,插入降水管,以免坍塌,操作复杂,成孔慢。而利用回转钻机成孔类似桩基施工,需要泥浆池或者场地,机械要求相对较高。
发明内容
本发明的目的是提供一种轻型井点降水管成孔装置及其方法,以解决现有技术存在的上述问题。
本发明的目的是通过以下技术方案来实现:
一种轻型井点降水管成孔装置,包括降水管和配合使用的锤击下沉装置,所述降水管顶端设有开口,降水管下部分布有透水孔,降水管底端为封闭端;所述锤击下沉装置包括锤击器和空气压缩机,空气压缩机与所述锤击器之间连接有压力软管。
进一步的,所述透水孔呈梅花状分布。
进一步的,所述降水管底端的封闭端呈圆锥形。
一种轻型井点降水管成孔方法,包括以下步骤:
1)根据工程要求制备降水管;
2)利用外力强夯降水管入土:使用空气压缩机作为动力机械,用锤击器将降水管锤入土体内,空气压缩机与锤击器之间通过软管连接,锤击器直接作用于降水管之上,操作人员作业于脚手架之上,脚手架选用门式脚手架平台;
3)利用高压水对降水管进行洗井:用软管插入降水管中,利用高压水灌入降水管,然后再抽取地下水带着细小扰动土体颗粒出水,反复操作直到水量均匀或者出清水为止;
4)将各降水管采用橡胶软管连接至总管,用真空水泵进行试抽。
本发明的有益效果为:结构简单、价格低廉、使用方便、成井迅速,不便于冲孔成井区域也可使用,利用降水管当作抽水管及入土所成孔护壁,一管两用,管体满足真空抽水及入土强度稳定性要求。
附图说明
下面根据附图对本发明作进一步详细说明。
图1是本发明实施例所述轻型井点降水管成孔装置的结构示意图。
图中:
1、降水管;2、开口;3、透水孔;4、锤击器;5、空气压缩机;6、压力软管;7、门式脚手架。
具体实施方式
如图1所示,本发明实施例所述的轻型井点降水管成孔装置,包括降水管1和配合使用的锤击下沉装置,所述降水管1顶端设有开口2,降水管1下部分布有透水孔3,降水管1底端为封闭端;所述锤击下沉装置包括锤击器4和空气压缩机5,空气压缩机5与所述锤击器4之间连接有压力软管6;所述透水孔3呈梅花状分布;所述降水管1底端的封闭端呈圆锥形。
本发明实施例所述的轻型井点降水管成孔方法,包括以下步骤:
1)根据工程要求制备降水管:长约6m,直径48.3mm,壁厚3.5mm,下部0.7m内钻有间距100mm梅花形布置的透水孔,降水管下端做成封闭的圆锥形。
2)使用空气压缩机(75m3/min)作为动力机械,用特制的锤击器将降水管锤入土体内,空气压缩机与锤击器之间通过直径50mm软管连接,锤击器直接作用于降水管之上,操作人员作业于脚手架之上,操作时注意安全防护。
3)用直径32或者25的PVC软管插入已经打入地下的焊接钢管降水管中,利用高压水灌入降水管,然后再抽取地下水带着细小扰动土体颗粒出水,反复操作直到水量均匀或者出清水为止。
4)降水管与总管之间采用L=1.2m,Φ40的橡胶软管连接,两头用铁丝拧紧,外涂抹黄泥,以防漏气,最后连接真空水泵进行试抽。
降水管1采用6米左右Φ48.3×3.0mm壁厚以上焊接钢管,下部0.7m内钻有透水孔的钢管,透水孔间距100mm,梅花形成孔,钢管下端做成封闭的圆锥形便于锤入。锤击器4直接作用于降水管1,用采用75到150kw的空气压缩机5压缩空气冲力转化为对降水管1锤击下沉的动力,将降水管1用锤击器4锤击入土,实现打压降水管入土无泥浆排除,无大型机械操作,同时使用门式脚手架7作为降水管1的锤入支架,架高约5m。
洗井过程是因为把降水管1锤击入土过程中,降水管1中可能会有粉土等渗入内部,另外降水管入土扰动原先土层结构平衡,不清孔会影响后期出水效果。将直径30mm的胶管插入降水管1底部进行注水清洗,直到流出清水为止,应逐根进行清洗,避免出现“死管”。
试抽时真空泵的作用是提供负压将土体中地下水通过降水管1、连接软管、总管抽出到地表,达到降低地下水位的作用,一般井点系统的真空度应保持在55.3~66.7kPa,压力应保持在0.16MPa,此处由于真空泵提供真空能力原因,一般轻型井点降水深度只有6~9m,无法抽出再深的水。
本发明不局限于上述最佳实施方式,任何人在本发明的启示下都可得出其他各种形式的产品,但不论在其形状或结构上作任何变化,凡是具有与本申请相同或相近似的技术方案,均落在本发明的保护范围之内。

Claims (6)

1.一种轻型井点降水管成孔装置,包括降水管(1)和配合使用的锤击下沉装置,其特征在于:所述降水管(1)顶端设有开口(2),降水管(1)下部分布有透水孔(3),降水管(1)底端为封闭端;所述锤击下沉装置包括锤击器(4)和空气压缩机(5),空气压缩机(5)与所述锤击器(4)之间连接有压力软管(6)。
2.根据权利要求1 所述的轻型井点降水管成孔装置,其特征在于:所述降水管(1)长6m、直径48.3mm、壁厚3.5mm且下部0.7m内钻有间距100mm梅花形布置的透水孔。
3.根据权利要求2 所述的轻型井点降水管成孔装置,其特征在于:所述降水管(1)底端的封闭端呈圆锥形。
4.一种轻型井点降水管成孔方法,其特征在于,包括以下步骤:
1)根据工程要求制备降水管:降水管长6m、直径48.3mm、壁厚3.5mm且下部0.7m内钻有间距100mm梅花形布置的透水孔,降水管下端做成封闭的圆锥形;
2)利用外力强夯降水管入土:使用空气压缩机作为动力机械,用锤击器将降水管锤入土体内,空气压缩机与锤击器之间通过软管连接,锤击器直接作用于降水管之上,操作人员作业于脚手架之上;
3)利用高压水对降水管进行洗井,用软管插入降水管中,利用高压水灌入降水管,然后再抽取地下水带着细小扰动土体颗粒出水,反复操作直到水量均匀或者出清水为止;以及
4)将各降水管连接至总管进行试抽。
5.根据权利要求4所述的轻型井点降水管成孔方法,其特征在于:步骤2)中,所述脚手架选用门式脚手架平台。
6.根据权利要求5所述的轻型井点降水管成孔方法,其特征在于:步骤4)中,总管与降水管之间的连接采用橡胶软管连接,用真空水泵进行试抽。
CN201310395319.4A 2013-09-03 2013-09-03 一种轻型井点降水管成孔装置及其方法 Active CN103485357B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310395319.4A CN103485357B (zh) 2013-09-03 2013-09-03 一种轻型井点降水管成孔装置及其方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310395319.4A CN103485357B (zh) 2013-09-03 2013-09-03 一种轻型井点降水管成孔装置及其方法

Publications (2)

Publication Number Publication Date
CN103485357A CN103485357A (zh) 2014-01-01
CN103485357B true CN103485357B (zh) 2015-09-09

Family

ID=49825912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310395319.4A Active CN103485357B (zh) 2013-09-03 2013-09-03 一种轻型井点降水管成孔装置及其方法

Country Status (1)

Country Link
CN (1) CN103485357B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083177B (zh) * 2018-07-26 2023-06-23 河南省水利第一工程局 一体式定向真空井点管的降水工艺
CN110206481A (zh) * 2019-04-24 2019-09-06 武汉一冶建筑安装工程有限责任公司 降水井施工装置

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2302337Y (zh) * 1998-02-19 1998-12-30 上海宝钢冶金建设公司第五工程公司 自沉式轻型井点装置
CN2823328Y (zh) * 2005-10-20 2006-10-04 中国水电顾问集团华东勘测设计研究院 井点成孔冲击管
JP2008025132A (ja) * 2006-07-19 2008-02-07 Maruyama Komuten:Kk 地下水位低下工法
JP5320728B2 (ja) * 2007-11-12 2013-10-23 株式会社大林組 常用井戸、常用井戸の構築方法及び常用井戸の構造
CN201539209U (zh) * 2009-09-29 2010-08-04 中冶天工上海十三冶建设有限公司 轻型井点降水冲孔器
CN101672160A (zh) * 2009-10-15 2010-03-17 中国地质科学院水文地质环境地质研究所 软土层快速成井装置
CN102051886B (zh) * 2011-01-24 2012-08-15 惠州市水电建筑工程有限公司 一种轻型井点降水施工方法
CN202578488U (zh) * 2012-05-02 2012-12-05 中国建筑第八工程局有限公司 一种管井成孔装置
CN102912806B (zh) * 2012-09-27 2016-01-20 中交三航局第二工程有限公司 一种降水井的施工方法
CN203498848U (zh) * 2013-09-03 2014-03-26 中铁建设集团有限公司 一种轻型井点降水管成孔装置

Also Published As

Publication number Publication date
CN103485357A (zh) 2014-01-01

Similar Documents

Publication Publication Date Title
CN103883796B (zh) 泥砂淤泥区手掘式顶管施工装置及方法
CN103603342B (zh) 大直径组合套管超长灌注桩施工方法
CN203684211U (zh) 一种钻孔灌注桩的桩头处理装置
CN103741705B (zh) 双层桶盖吸力式桶桩复合基础及施工方法
CN203498848U (zh) 一种轻型井点降水管成孔装置
CN103485357B (zh) 一种轻型井点降水管成孔装置及其方法
CN206204972U (zh) 一种兼作井点降水的预制管桩
CN105544573A (zh) 一种降水管井的水压喷冲式成井施工方法
CN102134861B (zh) 土体内预制桩试桩方法
CN109441355A (zh) 粉土或沙层管井高压水冲快速成孔施工方法
CN203755310U (zh) 一种自升式平台桩靴的冲桩喷嘴
CN103615014B (zh) 一种软土基坑的降水装置及其使用方法
CN100557145C (zh) Phc桩内冲内排辅助沉桩施工方法
CN203757177U (zh) 泥砂淤泥区手掘式顶管施工装置
CN208472692U (zh) 一种用于坝面接管法的测斜管保护装置
CN202546006U (zh) 用于顶管设备中继间耐高压密封装置
CN102116019A (zh) 快速“高真空击密”软地基处理方法
CN102758434B (zh) 中掘预应力离心管桩沉桩装置及其沉桩法
CN205348204U (zh) 一种轻型井点降水系统
CN201232184Y (zh) 钢管护壁干取土灌注桩成桩装置
CN108005065A (zh) Phc静压管桩的施工结构及施工方法
CN203891045U (zh) 深基坑围护桩间的堵漏注浆装置
CN204326061U (zh) 一种易拔出的管桩
CN109356211B (zh) 高层纠偏疏干井施工装置、减压井施工装置及纠偏方法
CN205917682U (zh) 软土地基一体式井点塑排真空系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20171207

Address after: 511458 Guangdong city of Guangzhou province Nansha District City Road South Ring Shacheng office building A

Patentee after: China Railway Construction Group South Engineering Co., Ltd.

Address before: 100131 Shijingshan Road, Beijing, No. 20, No.

Patentee before: Zhongtie Construction Group Corporation Limited

TR01 Transfer of patent right

Effective date of registration: 20180111

Address after: 100131 Shijingshan Road, Beijing, No. 20, No.

Co-patentee after: China Railway Construction Group South Engineering Co., Ltd.

Patentee after: Zhongtie Construction Group Corporation Limited

Address before: 511458 Guangdong city of Guangzhou province Nansha District City Road South Ring Shacheng office building A

Patentee before: China Railway Construction Group South Engineering Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201014

Address after: 100040 No. 20, Shijingshan Road, Beijing, Shijingshan District

Patentee after: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY CONSTRUCTION GROUP SOUTH ENGINEERING Co.,Ltd.

Patentee after: China Railway Construction Group Infrastructure Construction Co., Ltd

Address before: 100131 No. 20, Shijingshan Road, Beijing, Shijingshan District

Patentee before: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

Patentee before: CHINA RAILWAY CONSTRUCTION GROUP SOUTH ENGINEERING Co.,Ltd.

TR01 Transfer of patent right