CN103469978B CN201310049369.7A CN201310049369A CN103469978B CN 103469978 B CN103469978 B CN 103469978B CN 201310049369 A CN201310049369 A CN 201310049369A CN 103469978 B CN103469978 B CN 103469978B
Authority
CN
China
Prior art keywords
wall
metope
mill
construction
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310049369.7A
Other languages
Chinese (zh)
Other versions
CN103469978A (en
Inventor
郭矿平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310049369.7A priority Critical patent/CN103469978B/en
Publication of CN103469978A publication Critical patent/CN103469978A/en
Application granted granted Critical
Publication of CN103469978B publication Critical patent/CN103469978B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

Wall surface construction technology disclosed by the invention, is changed into traditional wall plastering and cuts mill body of wall, and the body of wall after cutting mill carries out daub again. Not only increase house usage space, and this technique can make the verticality of metope, flatness deviation value reduce further, it is to increase the construction quality of metope; Do not adopt plastering material and plastering process, decrease engineering materials and reduce labour cost.<b />

Description

A kind of wall surface construction technology
Technical field
The present invention relates to technical field of building construction.
Background technology
Traditional brick metope or concrete construction major structure of construction complete, and after relevant department's acceptance(check), need brick metope or concrete wall surface paint coating before moving in. Traditional coating whitewashes technique: body of wall �� plaster �� coating. The body of wall constructed through this technique also exists the phenomenon of metope bulge after applying for some time; And this technique construction process internally carries out in opposite directions in certain space, room body usable floor area after construction, is made to reduce unavoidably; This technique is before coating whitewashes in addition, need to plaster on metope matrix, undertakes user and also to be spent not a small amount of material of construction expense on the basis of high price house-purchase expense.
About the problems referred to above, publication No. is CN101781921A, announces in the patent document that day is on July 21st, 2010, discloses a kind of construction technology that can reduce surface of wall construction thickness, thus improves effective usable floor area in house. On the metope of certain planeness, specifically smear the thick crack-resistant putty coating of 2-3mm, then smear decoration putty coating on the surface of crack-resistant putty coating. Wherein, crack-resistant putty coating is made up of the raw material of following weight parts: cement 3-5 part, fine sand 4-6 part, talcum powder 0.8-1.2 part, and every cubic metre of crack-resistant putty coating contains Polypropylene Tiny Fiber 1-4Kg, water and glue. The standard width of a room in an old-style house and the depth in room can be made to increase 30-38mm, and effective usable floor area increases 1%-1.5%, and the corresponding consumption decreasing material of construction, has saved building cost. But this technique is only the basic coat of plaster which floor tradition divides smear to be combined with each other, and its individual layer crack-resistant putty coating materials still need the building materials such as cement, sand, talcum powder; In addition, it is still and inwardly constructs in certain space, or inevitable reduction house usable floor area.
Summary of the invention
The invention technical problem to be solved be to provide a kind of reach wall construction effect while, also increase the wall surface construction technology of house usage space, this technique improves construction quality simultaneously, decreases engineering materials and reduce labour cost.
The invention for solving the problems of the technologies described above, by the following technical solutions:
The wall surface construction technology of the invention, comprises the step cutting mill body of wall, the step of daub on the body of wall after cutting mill.
Further, it is 2.5-5mm that described body of wall cuts the degree of depth of mill.
Further, it is 3-4mm that described body of wall cuts the degree of depth of mill. According to country's construction quality specification requirement, build by laying bricks or stones or the perpendicularity deviation��5mm of concrete walls surface, surface of wall planeness��8mm; According to country's building decoration specification requirement, the perpendicularity deviation��3mm on wall plastering surface, surface of wall planeness��3mm. After learn, the difference of verticality is 2mm, and the difference of planeness is 5mm. Thus, will reaching country's building code requirement, it is 5mm that metope cuts the maximum gauge of mill; It is 3��4mm that the best cuts mill thickness.
Further, the concave surface being also included in the surface of wall after cutting mill uses anticracking grout layering to scrape and fills out, until with the step cut flour milling and strike off.
Further, the step being also included on the metope after cutting mill the overall anticracking grout scraping painting 2��3mm. Easily come off owing to directly carrying out smearing of common putty coating at brick wall, this step is set; This step is also the conventional setting steps that daily wallcovering whitewashes.
Further, glasscloth is pasted at the position being also included in metope easy to crack, then carries out the step of putty coating construction.
Owing to have employed technique scheme, the invention has following useful effect:
1, the invention by building by laying bricks or stones, concrete wall surface itself cut mill processing, substitute which floor traditional wall plastering technique; And metope through overground whole after, reach and on metope, directly carry out next road scrape the technique construction being coated with surface layer, operate easier.
2, first it is inwardly wear down on existing metope basis due to the invention technique, it is possible to the verticality of metope, flatness deviation value are reduced further, carries out improving the construction quality of metope.
3, the invention technique can save a large amount of human and material resources, greatly reduces engineering cost, increases economic benefit. By the every 10000 square metres of calculating of house architectural area, wall plastering area about has 20000 square meter, wall plastering cost about every square metre calculate by 15 yuan (containing artificial), its value is 300000 yuans. Using present method every square metre to be about 5 yuan, its value is only 100000 yuans, thus saves 200000 yuans, and economic worth is considerable.
The invention technique possesses following social benefit simultaneously.
4, due to this technique be first to building by laying bricks or stones, concrete wall surface itself cut mill processing, owing to group part of brick body, concrete itself is configured to cement, sand etc., this group part is formed and composition of plastering in original wall body constructional method is similar to, and build by laying bricks or stones, concrete self hole and coating form effective combination, the phenomenon of metope hollowing can not be formed. Also reduce the specification to wall plastering project after adopting this technique and check and accept link.
5, due to this technique be first to building by laying bricks or stones, concrete wall surface itself cuts mill processing, then carries out coating and whitewash; Coating does not take the original area in house, increases the actual usable floor area in house. Calculating with the houses of a set of 130 square metres, its actual usable floor area to be increased by 2 square metres than traditional engineering way.
6, from, whole building body, owing to each room decreases the weight of floated coat, in fact reducing the supporting capacity of ground, suitable has saved steel.
7, decreasing the produced quantity of engineering sand, the construction work of every 10000 square metres of floor area of building, it is plastered and also needs about 400 cubic metres with sand. Along with the increase of China's floor area of building, sand source is fewer and feweri, and the quality of sand is more and more poorer, and shipment distance problem is also given prominence to gradually, adopts present method can not only save a large amount of sand resources and also can save a large amount of soil of country simultaneously.
8, saving the consumption of cement, the construction work of every 10000 square metres, it is plastered and also needs about 80 tons with cement; Reduce obnoxious flavour while saving cement to the pollution of air, be conducive to national environmental protection construction.
9, this technique is adopted can effectively to accelerate engineering construction.
Embodiment
The wall surface construction technology of the present embodiment, carries out cutting mill on the body of wall of brick metope or concrete construction major structure of construction, and wherein, it is 2.5-5mm, more preferably 3-4mm that body of wall cuts the degree of depth of mill. Common service tool can be adopted when wearing down, as alloy cuts cage dish, alloy millstone etc. Mill back wall is cut in inspection, and the concave surface of the surface of wall after cutting mill uses anticracking grout layering to scrape and fills out, until with cut flour milling and strike off. The overall anticracking grout scraping painting 2��3mm on metope after cutting mill, glasscloth is pasted at the position easy to crack at metope, then carries out putty coating construction.

Claims (4)

1. an inner wall surface construction technology, is characterized in that: comprises entirety and cuts the brick metope of mill or the step of concrete construction major structure of construction body of wall, and building by laying bricks or stones after entirety cuts mill, concrete wall smear the step being not more than the coating cutting the thickness of wall body ground off; It is 3-4mm that described body of wall cuts the degree of depth of mill.
2. inner wall surface construction technology according to claim 1, is characterized in that: the concave surface being also included in the surface of wall after cutting mill uses anticracking grout layering to scrape and fill out, until with the step cut flour milling and strike off.
3. inner wall surface construction technology according to claim 1, is characterized in that: the step being also included on the metope after cutting mill the overall anticracking grout scraping painting 2��3mm.
4. inner wall surface construction technology according to claim 1, is characterized in that: glasscloth is pasted at the position being also included in metope easy to crack, then carries out the step of putty coating construction.
CN201310049369.7A 2013-02-07 2013-02-07 A kind of wall surface construction technology Expired - Fee Related CN103469978B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310049369.7A CN103469978B (en) 2013-02-07 2013-02-07 A kind of wall surface construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310049369.7A CN103469978B (en) 2013-02-07 2013-02-07 A kind of wall surface construction technology

Publications (2)

Publication Number Publication Date
CN103469978A CN103469978A (en) 2013-12-25
CN103469978B true CN103469978B (en) 2016-06-01

Family

ID=49795006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310049369.7A Expired - Fee Related CN103469978B (en) 2013-02-07 2013-02-07 A kind of wall surface construction technology

Country Status (1)

Country Link
CN (1) CN103469978B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107778952A (en) * 2017-11-18 2018-03-09 宁波同舟文化传媒有限公司 Iron wall surface construction technology and material prescription
CN108979034A (en) * 2018-08-24 2018-12-11 温州世纪明珠装饰设计工程有限公司 Wall surface construction technology

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
CN101125748A (en) * 2007-07-16 2008-02-20 黄礼文 Crack resisting coating for exterior wall and preparation method thereof
CN101134859A (en) * 2006-08-30 2008-03-05 北京阔达建筑装饰工程有限责任公司 Inner wall special-purpose chromatic powdery waterproof putty and construction method
CN101215916A (en) * 2008-01-17 2008-07-09 中设建工集团有限公司 Indoor wall surface putty construction process
CN101255717A (en) * 2007-12-11 2008-09-03 刘健 Construction technique for building block and wall board

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100130777A (en) * 2009-06-04 2010-12-14 주식회사숲이지움 Construction method with interior materials having stone layer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
CN101134859A (en) * 2006-08-30 2008-03-05 北京阔达建筑装饰工程有限责任公司 Inner wall special-purpose chromatic powdery waterproof putty and construction method
CN101125748A (en) * 2007-07-16 2008-02-20 黄礼文 Crack resisting coating for exterior wall and preparation method thereof
CN101255717A (en) * 2007-12-11 2008-09-03 刘健 Construction technique for building block and wall board
CN101215916A (en) * 2008-01-17 2008-07-09 中设建工集团有限公司 Indoor wall surface putty construction process

Also Published As

Publication number Publication date
CN103469978A (en) 2013-12-25

Similar Documents

Publication Publication Date Title
CN101886460B (en) Press polishing method of plastered mesh cloth of inner wall
CN201502164U (en) Tool for paving floor tile
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN105525726A (en) Aerated brick wall plastering construction method
CN107151125A (en) A kind of steam pressure sand aerated concrete block builds adhesive by laying bricks or stones
CN103469978B (en) A kind of wall surface construction technology
CN101781921B (en) Process for constructing surface of wall body
CN204663016U (en) For the seat slurry device of hollow blocks built
CN204662762U (en) The ardealite combined wall board that a kind of bamboo reinforcement is strengthened
CN204826468U (en) Environment -friendly perron
CN104234425B (en) A kind of shear wall structure trowel free process
CN101619613A (en) Gridding structure playing a ceramic tile imitating role on wall surface
CN108612253A (en) A kind of prefabricated high-durability lightweight steel construction compound core plate and its construction method entirely
CN106284917A (en) A kind of construction technology utilizing flowable mortar adhesively face brick
CN106150020A (en) A kind of construction technology utilizing flowing mortar adhesively face brick
CN109610764B (en) Granite facade paving construction technology
CN101671501B (en) Crack-resistant putty coating, production method and wall structure containing same
CN208650382U (en) A kind of complete prefabricated high-durability lightweight steel construction compound core plate
CN208088720U (en) A kind of decoration integrated rammed earth plate of calcium silicate board
CN104975689A (en) Thin cast-in-place concrete thin plastering component and construction process thereof
CN205223794U (en) Barren rock powder infiltration floor tile
CN102296795B (en) Method for scraping wall face floated coat flatly and member for implementing same
CN202467102U (en) Paving structure of microlite plate
CN107311548A (en) Permeable stone and preparation method thereof
CN206000096U (en) A kind of cracking resistance and anti-hollowing exempt from block wall structure of plastering

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160601

Termination date: 20190207

CF01 Termination of patent right due to non-payment of annual fee