CN103438282A - Assembling integrated support hanger and connecting pieces thereof - Google Patents
Assembling integrated support hanger and connecting pieces thereof Download PDFInfo
- Publication number
- CN103438282A CN103438282A CN2013102363039A CN201310236303A CN103438282A CN 103438282 A CN103438282 A CN 103438282A CN 2013102363039 A CN2013102363039 A CN 2013102363039A CN 201310236303 A CN201310236303 A CN 201310236303A CN 103438282 A CN103438282 A CN 103438282A
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- link
- column
- upright column
- support hanger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention discloses an assembling integrated support hanger and connecting pieces thereof. The assembling integrated support hanger structurally comprises a base, an upright column, a crossbeam, a first connecting piece and a second connecting piece; the upright column is made of C-type steel, and the crossbeam is made of H-type steel; connecting holes are respectively formed in the base, the two ends of the upright column and the two ends of the crossbeam. Aiming at the special structure of the H-type beam, the first connecting piece is shaped like a T-shaped structure when being connected with the upright column and the crossbeam, and aiming at the stability of a central upright column, the second connecting piece is in a trapezoidal structure when being connected with the upright column and the crossbeam. The assembling integrated support hanger provided by the invention adopts special connecting pieces, namely T-shaped and trapezoidal connecting pieces, aiming at different stress requirements of different structures, so that the stability degree of the support hanger is improved while the mounting is facilitated as well, the stress is reliable, and the construction is safe.
Description
Technical field
The present invention relates to suspension bracket, particularly a kind of integrated suspension and support and link thereof assembled.
Background technique
Suspension and support is mainly used in power plant's steam-water pipe or boiler equipment, being in operation produces on thermal walking and apparatus thereof.The heavy suspension and support of general traditional large diameter pipeline all adopts on-site cutting, welding, boring, can produce following several situation:
1. wayward for the consumption of material, often cause serious waste;
2. on-the-spot meeting produces the toxic gas that bits slag, noise, dust, arc light and mopping produce, and causes diversification to pollute;
3. handwork is difficult to standardization, can't accomplish uniform appearance;
4. job site easily produces fire and personal security hidden danger;
5. the fabrication and installation cost is high, and tratitional technology needs numerous personnel to participate in from charging, cutting, welding, boring, paint to installing, and operation is many, and the time is long, and complicated operation is time-consuming, takes a lot of work, and takes material, integral solder heaviness, inconvenience carrying.
Although the patent of invention that the patent No. is 200920077819.2 provides a kind of detachable suspension and support, its link is L-type, finds that in actual use its contiguity is firm not, easily occurs to become flexible, and causes potential safety hazard.
Summary of the invention
The objective of the invention is in order to overcome above deficiency, a kind of integrated suspension and support and link thereof assembled is provided, can significantly speed up the work, when raising the efficiency, firmly connect all parts, guarantee easy construction safety.
Purpose of the present invention realizes like this:
A kind of integrated suspension and support and link thereof assembled of the present invention.Its structure comprises: base, column, crossbeam, the first link, the second link form; Described column is C shaped steel, and crossbeam is reinforcement H shaped steel; Described base, column two ends, crossbeam two ends are equipped with attachment hole.
Above-mentioned a kind of integrated suspension and support and link thereof assembled, wherein, when described the first link connects column and crossbeam, the special construction for H type crossbeam, be " ╥ " shape structure, can, from middle two sides double team crossbeam, H type crossbeam be fixed.
Above-mentioned a kind of integrated suspension and support and link thereof assembled, wherein, when described the second link connects column and crossbeam, for the stability of gin pole, when playing connection function, coat column from outside, be trapezium structure.
Above-mentioned a kind of integrated suspension and support and link thereof assembled, wherein, described base, column, crossbeam, the first link, the second link in use, directly make to be screwed by attachment hole, utilize a plurality of attachment hole settings also can regulate the size of suspension and support.
Compared with prior art, the present invention has the following advantages:
1) direct-assembling moulding, avoid welding process, simple and easy installation.
2) reduce operation, reduce costs.
3) for different component, Tong Guo “ ╥ " shape and trapezoidal special construction link, stressed reliable, construction safety.
4) crossbeam is reinforcement H shaped steel, adds the large bearing capacity degree, improves working strength.
5) if certain damage parts can directly be pulled down replacement by it, miscellaneous part can be recycled, and economizes on resources.
The present invention is a kind of assembles integrated suspension and support, for the different force requests of different structure, uses " ╥ " shape and trapezoidal special link, can in convenient the installation, improve the soundness of suspension and support, stressed reliably, construction safety.
The accompanying drawing explanation
Fig. 1 is structural drawing of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the invention will be further described.
A kind of integrated suspension and support and link thereof assembled of the present invention.Its structure comprises: base 1, column 2, crossbeam 3, the first link 4, the second link 5 form; Described column 2 is C shaped steel, and crossbeam 3 is reinforcement H shaped steel; Described base 1, column 2 two ends, crossbeam 3 two ends are equipped with attachment hole 6; When described the first link 4 connects column 2 with crossbeam 3, for the special construction of H type crossbeam 3, be " ╥ " shape structure, can, from middle two sides double team crossbeam 3, H type crossbeam 3 be fixed; When described the second link 5 connects column 2 with crossbeam 3, for the stability of gin pole, when playing connection function, coat column 2 from outside, be trapezium structure; Described base 1, column 2, crossbeam, the first link 4, the second link 5 in use, directly make to be screwed by attachment hole 6, utilize a plurality of attachment holes 6 to arrange and also can regulate the size of suspension and support.
The present invention is a kind of assembles integrated suspension and support, for the different force requests of different structure, uses " ╥ " shape and trapezoidal special link, can in convenient the installation, improve the soundness of suspension and support, stressed reliably, construction safety.
Here description of the invention and application is illustrative, not wants that therefore, the present invention is not subject to the restriction of the present embodiment by scope restriction of the present invention in the above-described embodiments, and the technological scheme that any employing equivalence replacement obtains is all in the scope of protection of the invention.
Claims (4)
1. can assemble integrated suspension and support and link thereof for one kind, its structure comprises: base, column, crossbeam, it is characterized in that: between column and crossbeam, by the first link, the second link, be connected respectively.
2. a kind of integrated suspension and support and link thereof assembled according to claim 1, is characterized in that, described column is C shaped steel, and crossbeam is reinforcement H shaped steel.
3. a kind of integrated suspension and support and link thereof assembled according to claim 1, is characterized in that, when described the first link connects column and crossbeam, is " ╥ " shape structure, can, from middle two sides double team crossbeam, H type crossbeam be fixed.
4. a kind of integrated suspension and support and link thereof assembled according to claim 1, is characterized in that, when described the second link connects column and crossbeam, is trapezium structure, coats column from outside.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102363039A CN103438282A (en) | 2013-06-14 | 2013-06-14 | Assembling integrated support hanger and connecting pieces thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102363039A CN103438282A (en) | 2013-06-14 | 2013-06-14 | Assembling integrated support hanger and connecting pieces thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103438282A true CN103438282A (en) | 2013-12-11 |
Family
ID=49691984
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013102363039A Pending CN103438282A (en) | 2013-06-14 | 2013-06-14 | Assembling integrated support hanger and connecting pieces thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103438282A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105626966A (en) * | 2016-03-30 | 2016-06-01 | 南京海拓复合材料有限责任公司 | Combined type composite material bearing support |
CN105927836A (en) * | 2016-05-24 | 2016-09-07 | 上海剑桥科技股份有限公司 | Ceiling mounting rack of communication terminal, communication terminal and communication terminal mounting system |
CN106764075A (en) * | 2016-12-14 | 2017-05-31 | 上海市安装工程集团有限公司 | For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed |
CN106958694A (en) * | 2017-04-06 | 2017-07-18 | 中铁建设集团有限公司 | A kind of electromechanical installation comprehensive support |
CN109578698A (en) * | 2019-01-25 | 2019-04-05 | 湖北工业大学 | A kind of assembled suspension and support and its assembly method |
CN109915446A (en) * | 2018-07-03 | 2019-06-21 | 苏州华固建筑配套工程有限公司 | A kind of holder combination |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1413918A (en) * | 1920-10-16 | 1922-04-25 | Landers Frary & Clark | Metallic frame |
US5595363A (en) * | 1995-09-18 | 1997-01-21 | De Leebeeck; Marcel | Plastic pipe beam support |
US20020148191A1 (en) * | 2001-04-11 | 2002-10-17 | Hynes Thomas C. | Composite plastic/wood flour building construction system |
US20020168220A1 (en) * | 2001-05-10 | 2002-11-14 | Stasney Wilson Frank | Novel clamping assembly |
CN201496669U (en) * | 2009-07-03 | 2010-06-02 | 刘纪才 | Pipeline supporting and hanging frame |
CN201636142U (en) * | 2009-12-21 | 2010-11-17 | 华电重工装备有限公司 | Support and hanger steel grider clamp |
CN203297765U (en) * | 2013-06-14 | 2013-11-20 | 镇江奇佩支吊架有限公司 | Integrated support and hanger capable of being assembled and connecting pieces thereof |
-
2013
- 2013-06-14 CN CN2013102363039A patent/CN103438282A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1413918A (en) * | 1920-10-16 | 1922-04-25 | Landers Frary & Clark | Metallic frame |
US5595363A (en) * | 1995-09-18 | 1997-01-21 | De Leebeeck; Marcel | Plastic pipe beam support |
US20020148191A1 (en) * | 2001-04-11 | 2002-10-17 | Hynes Thomas C. | Composite plastic/wood flour building construction system |
US20020168220A1 (en) * | 2001-05-10 | 2002-11-14 | Stasney Wilson Frank | Novel clamping assembly |
CN201496669U (en) * | 2009-07-03 | 2010-06-02 | 刘纪才 | Pipeline supporting and hanging frame |
CN201636142U (en) * | 2009-12-21 | 2010-11-17 | 华电重工装备有限公司 | Support and hanger steel grider clamp |
CN203297765U (en) * | 2013-06-14 | 2013-11-20 | 镇江奇佩支吊架有限公司 | Integrated support and hanger capable of being assembled and connecting pieces thereof |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105626966A (en) * | 2016-03-30 | 2016-06-01 | 南京海拓复合材料有限责任公司 | Combined type composite material bearing support |
CN105927836A (en) * | 2016-05-24 | 2016-09-07 | 上海剑桥科技股份有限公司 | Ceiling mounting rack of communication terminal, communication terminal and communication terminal mounting system |
CN105927836B (en) * | 2016-05-24 | 2017-11-17 | 上海剑桥科技股份有限公司 | Ceiling mounting bracket, communicating terminal and the communicating terminal installation system of communicating terminal |
CN106764075A (en) * | 2016-12-14 | 2017-05-31 | 上海市安装工程集团有限公司 | For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed |
CN106958694A (en) * | 2017-04-06 | 2017-07-18 | 中铁建设集团有限公司 | A kind of electromechanical installation comprehensive support |
CN109915446A (en) * | 2018-07-03 | 2019-06-21 | 苏州华固建筑配套工程有限公司 | A kind of holder combination |
CN109578698A (en) * | 2019-01-25 | 2019-04-05 | 湖北工业大学 | A kind of assembled suspension and support and its assembly method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103438282A (en) | Assembling integrated support hanger and connecting pieces thereof | |
CN205371829U (en) | A multilayer pipeline gallows convenient to equipment | |
CN201496669U (en) | Pipeline supporting and hanging frame | |
CN203297765U (en) | Integrated support and hanger capable of being assembled and connecting pieces thereof | |
CN207522112U (en) | A kind of steel pipe's production cutter device | |
CN204611104U (en) | A kind of fixture being applicable to I-shape beam | |
CN203498843U (en) | Supporting connecting piece for ultra-long double spliced steel pipes | |
CN202017352U (en) | Combined supporting pillar | |
CN204356910U (en) | A kind of Space Free-Form Surface wood net shell assembling type node to wearing bolt | |
CN201501730U (en) | Special hanger for blade of large-scale wind generator | |
CN104141823B (en) | A kind of detachable suspension and support | |
CN204983212U (en) | Intercolumniation of steel construction building supports | |
CN110185161A (en) | A kind of bamboo-wood structure T-type energy-dissipating and shock-absorbing node | |
CN205935618U (en) | Scaffold puts up localization support device | |
CN203924659U (en) | Hanging frame type construction platform device | |
CN104032944A (en) | Suspension frame construction platform device | |
CN204416969U (en) | The adjustable arm head of a kind of tower machine | |
CN204754175U (en) | Construction is with simply climbing a support | |
CN204326953U (en) | There is the rotary disk driller of guide function | |
CN204662937U (en) | A kind of fixture being fixed on steel structure girder | |
CN203161459U (en) | Fixing device used for fixing wind power generator tower barrel with platform | |
CN103618253B (en) | Iron tower operation turns to combination unit | |
CN203008479U (en) | Temporary standing platform for iron tower assembly | |
CN202755491U (en) | Stone curtain wall connection node | |
CN205063325U (en) | Novel scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20131211 |
|
RJ01 | Rejection of invention patent application after publication |