CN103437288B - Forming method built by the high pier being applied to bridge construction - Google Patents
Forming method built by the high pier being applied to bridge construction Download PDFInfo
- Publication number
- CN103437288B CN103437288B CN201310297437.1A CN201310297437A CN103437288B CN 103437288 B CN103437288 B CN 103437288B CN 201310297437 A CN201310297437 A CN 201310297437A CN 103437288 B CN103437288 B CN 103437288B
- Authority
- CN
- China
- Prior art keywords
- shaft
- pier
- high pier
- template
- roof insulating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310297437.1A CN103437288B (en) | 2013-07-16 | 2013-07-16 | Forming method built by the high pier being applied to bridge construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310297437.1A CN103437288B (en) | 2013-07-16 | 2013-07-16 | Forming method built by the high pier being applied to bridge construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103437288A CN103437288A (en) | 2013-12-11 |
CN103437288B true CN103437288B (en) | 2015-12-02 |
Family
ID=49690997
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310297437.1A Active CN103437288B (en) | 2013-07-16 | 2013-07-16 | Forming method built by the high pier being applied to bridge construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103437288B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105625189B (en) * | 2016-01-25 | 2020-05-15 | 赵立财 | Hollow high pier concrete placement heat preservation maintenance system |
CN105951599B (en) * | 2016-05-23 | 2018-10-09 | 中交第一航务工程局有限公司 | High column mould bases integrated construction technique |
CN108385528B (en) * | 2016-09-18 | 2019-06-28 | 山东省交通科学研究院 | A kind of application method of low temperature season pier stud concrete heat-insulating health preserving equipment |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050082024A (en) * | 2004-02-17 | 2005-08-22 | (주)다산컨설턴트 | Heating panel of bridge for winter work |
CN102108678A (en) * | 2011-01-18 | 2011-06-29 | 龙建路桥股份有限公司 | High-altitude construction complete set device and method in winter |
CN202194074U (en) * | 2011-09-02 | 2012-04-18 | 中铁上海工程局有限公司 | Pier body heat-insulating template |
CN202416186U (en) * | 2012-01-16 | 2012-09-05 | 中交第一公路工程局有限公司 | Concrete insulation hood for piers in winter construction |
-
2013
- 2013-07-16 CN CN201310297437.1A patent/CN103437288B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050082024A (en) * | 2004-02-17 | 2005-08-22 | (주)다산컨설턴트 | Heating panel of bridge for winter work |
CN102108678A (en) * | 2011-01-18 | 2011-06-29 | 龙建路桥股份有限公司 | High-altitude construction complete set device and method in winter |
CN202194074U (en) * | 2011-09-02 | 2012-04-18 | 中铁上海工程局有限公司 | Pier body heat-insulating template |
CN202416186U (en) * | 2012-01-16 | 2012-09-05 | 中交第一公路工程局有限公司 | Concrete insulation hood for piers in winter construction |
Non-Patent Citations (1)
Title |
---|
青藏铁路三岔河特大桥空心薄壁高墩寒季混凝土施工技术;曹玉新;《中国安全科学学报》;20060131;第16卷(第1期);第99页右栏最后一段、第100页右栏最后一段、第101页左栏第1段及图1 * |
Also Published As
Publication number | Publication date |
---|---|
CN103437288A (en) | 2013-12-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102767235B (en) | Long-span spherical reticulated shell coal yard structure construction method | |
CN103437288B (en) | Forming method built by the high pier being applied to bridge construction | |
WO2014053688A2 (en) | Supporting structure for wind turbines and a mould for obtaining such structures | |
CN206987465U (en) | A kind of portable simplified construction shed made for hydraulic turbine embedded part | |
CN105201527A (en) | Raw soil cave dwelling wooden arch rib reinforcement system and construction technology thereof | |
CN108049666B (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
US9637944B2 (en) | Method for assembling decreasing section concrete towers for wind turbines and associated wind turbines | |
CN203200906U (en) | Combined house of unit structure | |
CN204475921U (en) | The dismountable firm structural construction factory building of a kind of safety | |
CN201722702U (en) | Factory prefabricated component splicing foundation | |
CN205369872U (en) | Large -scale air cooling tower X pillar crowd structure scaffold | |
CN206290016U (en) | A kind of railway station building and its platform canopy structure | |
CN201539372U (en) | Raft plate type wind generator foundation structure | |
CN103437286A (en) | Full-span box girder segmental prefabricating method applied to bridge construction | |
CN201310202Y (en) | Unitized lifting functional house | |
CN203795459U (en) | Foundation structure of tower crane for high-altitude roofs | |
CN203546601U (en) | Steel truss assembling support | |
WO2020136288A8 (en) | Floating platform for high-power wind turbines | |
CN205531410U (en) | A simply can dismantle construction canopy for steel construction job site | |
CN113404199B (en) | Installation method of umbrella-shaped roof structure | |
ES2319103T3 (en) | CONSTRUCTION OF ROOF AND ROOF OF COMPOSITE DOUBLE PRETENSED WITH FLAT SOFITE FOR LARGE INDUSTRIAL BUILDINGS. | |
CN103590419A (en) | Assembled type adjustable high-voltage reactor foundation | |
CN103437287B (en) | Be applied to the whole opening box girder section assembling method of bridge construction | |
CN208668601U (en) | A kind of environment-friendly and energy-efficient steel plant structure | |
CN205000250U (en) | Be applied to heat preservation big -arch shelter of pier construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB02 | Change of applicant information |
Address after: The eastern section of the town of Xueyuan Road Xindu Xindu District of Chengdu city of Sichuan Province, No. 289 610000 Applicant after: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP OF THE FIFTH ENGINEERING Co.,Ltd. Applicant after: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP Co.,Ltd. Address before: The eastern section of the town of Xueyuan Road Xindu Xindu District of Chengdu city of Sichuan Province, No. 289 610000 Applicant before: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP OF THE FIFTH ENGINEERING Co.,Ltd. Applicant before: China thirteen Railway Construction Bureau Group Co.,Ltd. Address after: The eastern section of the town of Xueyuan Road Xindu Xindu District of Chengdu city of Sichuan Province, No. 289 610000 Applicant after: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP OF THE FIFTH ENGINEERING Co.,Ltd. Applicant after: China thirteen Railway Construction Bureau Group Co.,Ltd. Address before: The eastern section of the town of Xueyuan Road Xindu Xindu District of Chengdu city of Sichuan Province, No. 289 610000 Applicant before: Fifth Engineering Co.,Ltd. of China Railway 13th Bureau Group Applicant before: CHINA RAILWAY 13TH BUREAU GROUP Co.,Ltd. |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: CHINESE RAILWAY CONSTRUCTION 13TH BUREAU GROUP CO., LTD. TO: CHINESE RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP CO., LTD. Free format text: CORRECT: APPLICANT; FROM: CHINA RAILWAY 13TH BUREAU GROUP CO., LTD. TO: CHINESE RAILWAY CONSTRUCTION 13TH BUREAU GROUP CO., LTD. Free format text: CORRECT: APPLICANT; FROM: CR13BG NO.5 ENGINEERING CO., LTD. TO: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP OF THE FIFTH ENGINEERING CO., LTD. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |