CN103422495A - Hollow cast-in-place pile and construction method thereof - Google Patents

Hollow cast-in-place pile and construction method thereof Download PDF

Info

Publication number
CN103422495A
CN103422495A CN2013103158934A CN201310315893A CN103422495A CN 103422495 A CN103422495 A CN 103422495A CN 2013103158934 A CN2013103158934 A CN 2013103158934A CN 201310315893 A CN201310315893 A CN 201310315893A CN 103422495 A CN103422495 A CN 103422495A
Authority
CN
China
Prior art keywords
pile
hollow body
hollow
concrete
meters
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103158934A
Other languages
Chinese (zh)
Other versions
CN103422495B (en
Inventor
王为凯
潘相军
肖长财
李雷
燕书红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG JIUQIANG ROAD & BRIDGE CO., LTD.
Original Assignee
KEDA GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KEDA GROUP CO Ltd filed Critical KEDA GROUP CO Ltd
Priority to CN201310315893.4A priority Critical patent/CN103422495B/en
Publication of CN103422495A publication Critical patent/CN103422495A/en
Application granted granted Critical
Publication of CN103422495B publication Critical patent/CN103422495B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a hollow cast-in-place pile and a construction method thereof. The hollow cast-in-place pile comprises a solid pile body and a reinforcing cage arranged inside the solid pile body. The hollow cast-in-place pile is characterized in that a hollow body is arranged inside the solid pile body, the designed pile length of the solid pile body is no less than 30 meters, the diameter of the solid pile body is no less than 2.0 meters, the length of the hollow body is a value that 10 meters are subtracted from the 2/3 of the designed pile length, and the top face of the hollow body is located at the position below the pile top with the designed elevation by 1/3 of the designed pile length plus 5 meters. According to the hollow cast-in-place pile, a lifting device of a drilling machine is utilized for hoisting a vibration hammer, a drilling rod serves as a guiding rod, and the hollow body is vibrated to sink to the appointed position. Compared with an existing solid cast-in-place pile, the hollow cast-in-place pile has the advantage that the total bearing capacity of a pile foundation is improved by reducing the weight of the pile foundation under the premise that the pile end borne pressure and pile wall side friction are not changed.

Description

A kind of hollow bored pipe and job practices thereof
Technical field
The present invention relates to a kind of base form of field of civil engineering, relate in particular to the large diameter bored pile basis for construction work and bridge engineering.
Background technology
Bored pile foundation is as a kind of common base form, because construction technology is simply ripe, and is applicable to various geological conditionss, therefore is widely used in the every field such as all kinds of bridge engineering, construction work and hydraulic engineering.
Known by the force analysis to bored pile, pile foundation be take and born the pressure at right angle load as main, and horizontal loading is auxiliary, bridge engineering horizontal loading brake control power, wind load and other incidental loads; Construction work and hydraulic engineering horizontal loading are mainly wind load, fluid levels compressive load etc.The horizontal loading that pile foundation is born, because the top soil body and effect of elastic resistance, the horizontal force action effect is progressively decay from top to bottom.It is main that the cloth muscle of pile foundation mainly considers to bear horizontal loading, so the cloth muscle of pile foundation is also that top 1/3rd long cloth muscle are more, middle 1/3rd long cloth muscle reduce by half, and the long cloth muscle of generally not doing in 1/3rd of bottoms is considered.
For increasing the bearing capacity of bored pile, designing unit is generally according to the mechanics parameter of each soil layer in the geology exploration report, according to the computation rule of design specifications, by increasing Pile Diameter or increasing long realization of stake.But the increase in stake footpath and the long increase of stake also can cause the increase of the weight of pile foundation own, virtually increase gravity load and eat up part of the part supporting capacity simultaneously.So traditional bored pile exists deadweight larger, the deficiency that the part supporting capacity is eaten up part of.How by the deadweight that reduces pile foundation, to improve bearing capacity of pile foundation, it is a problem that is worth research, forefathers also once carried out discussion many times to this problem, but all because implementing difficulty, were not used widely greatly, and this difficult problem all is not well solved so far.
Summary of the invention
The objective of the invention is the deficiency existed for existing drill-pouring pile bearing capacity aspect, a kind of deadweight that can alleviate pile body is provided, improves novel hollow bored pile and the job practices thereof of effective bearing capacity of pile foundation.
The present invention is achieved through the following technical solutions:
The structure of given first hollow bored pipe, comprise the entity pile body with and interior reinforcing cage, it is characterized in that: be provided with hollow body in described entity pile body, the designing pile length of described entity pile body is not less than 30 meters, and the diameter of described entity pile body is not less than 2.0 meters; The length of described hollow body is that 2/3 designing pile length deducts 10 meters, and the hollow body end face is positioned at following 1/3 designing pile length of design of pile top absolute altitude and adds 5 meters.
Said structure is more preferably:
Described hollow body diameter is less 1.0 meters than entity pile body diameter.
Described hollow body bottom is conical.
Described hollow body is polymer fiber hollow body or HPDE hollow body.
Then provide the job practices of above-mentioned hollow bored pipe, comprise the following steps:
At first holed, carried out hole clearly after pore-forming, reinforcing cage is installed, then built pile concrete to calculating side's amount and predetermined elevation;
Secondly press down installation at the pile concrete initial set capable hollow body that advances, concrete steps are:
The first step: the top that first with drill's lifting tap lifting hollow body, is positioned to pile concrete;
Second step: with the drill's lifting tap, hang the peace vibro driver;
The 3rd step: connect first segment drilling rod guide rod at the vibropiling motor spindle with connector, hollow body suit cap is installed in drilling rod guide rod bottom;
The 4th step: transfer vibro driver to hollow body suit cap and hollow body top and coincide, first with the deadweight of vibro driver, press down hollow body;
The 5th step: then start the vibropiling machine vibration and press down hollow body, when first segment drilling rod guide rod presses to drilling machine platform, promote vibro driver, second section drilling rod guide rod is installed, then continue vibration and press down, so loop, until hollow body is transferred to design attitude;
The 6th step: after hollow body is depressed into design attitude, vibro driver stops vibration; Then remove hollow body suit cap, respectively save drilling rod guide rod and vibro driver;
After last hollow body installation, with the lining rope repetition measurement, the later stake top concrete surface elevation of hollow body is installed, after meeting standard and designing requirement, mobile drill is proceeded pile foundation construction to position, next hole.
Above-mentioned job practices can further be improved to:
Whether, after described vibro driver stops vibration, voltage stabilizing 10 minutes, will carry 20cm on the drilling rod guide rod, observe hollow body in 2 minutes and float, if floating presses down hollow body rear repetition voltage stabilizing operation again.
Described pile concrete is efficient slow setting underwater concrete, and guarantees to start to transfer and be controlled at pile concrete the total time put in place in the initial setting time to hollow body from the pile concrete perfusion.
Implant hollow body in pile concrete after, the stake top concrete elevation after the implantation hollow body exceeds and is not less than 0.5 meter than design altitude.
Hollow bored pipe of the present invention is the lifting gear that utilizes rig itself, and the vibration hammer that plays, to assigned address, is compared the hollow body vibration-sunk as guide rod with drilling rod with existing solid bored pile, have following remarkable advantage:
1, under stake end pressure-bearing and the constant prerequisite of pile lining side friction, by alleviating the deadweight of pile foundation itself, improve the overall bearing capacity of pile foundation.
2, the implantation of hollow body, save the pile foundation concrete amount, is conducive to economize on resources, and meets the policy development direction of national energy-saving environmental protection.
3, hollow body can adopt the mode of factory's customization, and machining accuracy is high, and cost is lower.
When 4, vibration presses down hollow body, the effect of vibration of vibro driver makes the pile concrete of having built more closely knit.
5, the sinking of hollow body can utilize the crane gear of rig self, utilizes the guide rod of drilling rod as the below hollow body, does not need to process special-purpose guide rod in addition, and construction cost is lower, and construction technology is simple, is convenient to apply on a large scale.
The accompanying drawing explanation
Fig. 1 is the hollow bored pipe organigram;
The lateral view that Fig. 2 is Fig. 1;
Fig. 3 is the hollow position view of hollow bored pipe;
Fig. 4 is hollow bored pipe construction schematic diagram;
In figure: 1, cushion cap (binder), 2, reinforcing cage, 3, the entity pile body, 4, hollow body, 5, rig.6, vibro driver, 7, connector, 8, the drilling rod guide rod, 9, hollow body socket cap.
The specific embodiment
Below in conjunction with accompanying drawing and instantiation, the invention will be further described, but not as a limitation of the invention.
A kind of hollow bored pipe mainly is comprised of several parts such as reinforcing cage 2, entity pile body 3 and hollow bodies 4,
The size of hollow body 4, designing pile length (being not less than 30 meters) according to design drawing, deduct 10 meters according to 2/3 designing pile length, and external diameter is done for design stake footpath (being not less than 2.0 meters) deducts 1.0 metric systems, material can adopt polymer fiber or HPDE material, by producer's customization, is formed.The position of hollow body 4 in pile body, determine according to Fig. 2 schematic diagram.
At first according to the boring of existing mature technology, through clear hole once, reinforcing cage 2 is installed after pore-forming, then according to existing technique, build pile concrete and measure and predetermined elevation to the side of calculatinging;
It is as follows that next hollow body presses down installation steps:
The first step: first with the lifting tap of rig 5 lifting hollow body 4 own, put in place and locate temporarily;
Second step: with the drill's lifting tap, hang peace vibro driver 6;
The 3rd step: connect first segment drilling rod guide rod 8 in pile driver 6 bottoms with connector 7, hollow body suit cap 9 is installed in drilling rod guide rod 8 bottoms;
The 4th step: first with the deadweight of vibro driver 6, press down hollow body 4;
The 5th step: when hollow body 4 leans on when weight is not gone down, start vibro driver 6 vibrations and press down hollow body, when first segment drilling rod guide rod 8 presses to drilling machine platform, promote vibro driver 6, second section drilling rod guide rod 8 is installed, then continue vibration and press down, so loop, until hollow body 4 is transferred to design attitude;
The 6th step: after hollow body 4 is depressed into design attitude, stop vibration, voltage stabilizing 10 minutes, to on drilling rod guide rod 8, carry 20cm, observe hollow body 4 whether float (slight mobile if the hollow body floating can make the drilling rod guide rod upwards occur) in 2 minutes, if floating, press down hollow body 4 rear repetition voltage stabilizing operation again; After hollow body 4 position stabilities, remove section by section drilling rod guide rod 8, then remove first segment drilling rod guide rod and hollow body suit cap 9, finally remove vibro driver 6.
By the time after hollow body 4 installations, with the lining rope repetition measurement, the later stake top concrete surface elevation of hollow body 4 is installed, after meeting standard and designing requirement, mobile drill 5 is proceeded pile foundation construction to position, next hole.
The concrete of pile body should be selected efficient slow setting underwater concrete, from the pile concrete perfusion, to hollow body 4, transfers the total time put in place, should be controlled at concrete initial set in the time.
Except the described technical characterictic of this manual, be the known technology of those skilled in the art.

Claims (8)

1. a hollow bored pipe, it is characterized in that: comprise the entity pile body with and interior reinforcing cage, it is characterized in that: be provided with hollow body in described entity pile body, the designing pile length of described entity pile body is not less than 30 meters, and the diameter of described entity pile body is not less than 2.0 meters; The length of described hollow body is that 2/3 designing pile length deducts 10 meters, and the hollow body end face is positioned at following 1/3 designing pile length of design of pile top absolute altitude and adds 5 meters.
2. hollow bored pipe according to claim 1, it is characterized in that: described hollow body diameter is less 1.0 meters than entity pile body diameter.
3. hollow bored pipe according to claim 1 and 2, is characterized in that: be conical bottom described hollow body.
4. hollow bored pipe according to claim 1 and 2, it is characterized in that: described hollow body is polymer fiber hollow body or HPDE hollow body.
5. the job practices of the arbitrary described hollow bored pipe of claim 1-4, is characterized in that, comprises the following steps:
At first holed, carried out hole clearly after pore-forming, reinforcing cage is installed, then built pile concrete to calculating side's amount and predetermined elevation;
Secondly press down installation at the pile concrete initial set capable hollow body that advances, concrete steps are:
The first step: the top that first with drill's lifting tap lifting hollow body, is positioned to pile concrete;
Second step: with the drill's lifting tap, hang the peace vibro driver;
The 3rd step: connect first segment drilling rod guide rod at the vibropiling motor spindle with connector, hollow body suit cap is installed in drilling rod guide rod bottom;
The 4th step: transfer vibro driver to hollow body suit cap and hollow body top and coincide, first with the deadweight of vibro driver, press down hollow body;
The 5th step: then start the vibropiling machine vibration and press down hollow body, when first segment drilling rod guide rod presses to drilling machine platform, promote vibro driver, second section drilling rod guide rod is installed, then continue vibration and press down, so loop, until hollow body is transferred to design attitude;
The 6th step: after hollow body is depressed into design attitude, vibro driver stops vibration; Then remove hollow body suit cap, respectively save drilling rod guide rod and vibro driver;
After last hollow body installation, with the lining rope repetition measurement, the later stake top concrete surface elevation of hollow body is installed, after meeting standard and designing requirement, mobile drill is proceeded pile foundation construction to position, next hole.
6. the job practices of hollow bored pipe according to claim 5, it is characterized in that, after described vibro driver stops vibration, voltage stabilizing 10 minutes, to on the drilling rod guide rod, carry 20cm, observe hollow body in 2 minutes and whether float, if floating presses down hollow body rear repetition voltage stabilizing operation again.
7. according to the job practices of claim 5 or 6 described hollow bored pipes, it is characterized in that, described pile concrete is efficient slow setting underwater concrete, and guarantees to start to transfer and be controlled at pile concrete the total time put in place in the initial setting time to hollow body from the pile concrete perfusion.
8. according to the job practices of claim 5 or 6 described hollow bored pipes, it is characterized in that, implant hollow body in pile concrete after, the stake top concrete elevation after the implantation hollow body exceeds and is not less than 0.5 meter than design altitude.
CN201310315893.4A 2013-07-25 2013-07-25 A kind of hollow bored pipe and construction method thereof Expired - Fee Related CN103422495B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310315893.4A CN103422495B (en) 2013-07-25 2013-07-25 A kind of hollow bored pipe and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310315893.4A CN103422495B (en) 2013-07-25 2013-07-25 A kind of hollow bored pipe and construction method thereof

Publications (2)

Publication Number Publication Date
CN103422495A true CN103422495A (en) 2013-12-04
CN103422495B CN103422495B (en) 2016-01-20

Family

ID=49647844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310315893.4A Expired - Fee Related CN103422495B (en) 2013-07-25 2013-07-25 A kind of hollow bored pipe and construction method thereof

Country Status (1)

Country Link
CN (1) CN103422495B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499480A (en) * 2014-12-12 2015-04-08 董相东 Method for drilling and filling concrete hollow pile
CN104895053A (en) * 2015-06-16 2015-09-09 苏交科集团股份有限公司 Construction method of sectional type cavity grouting pile
CN105040685A (en) * 2015-06-09 2015-11-11 周兆弟 Prefabricated member with hollow structure
CN106759300A (en) * 2016-11-25 2017-05-31 淮阴工学院 Using the root key construction method of the root key constructing device of radical bored concrete pile
CN108775010A (en) * 2018-05-29 2018-11-09 河海大学 A kind of PCC energy stake and its construction method
CN111335347A (en) * 2020-03-12 2020-06-26 广东金衡建筑工程有限公司 Cast-in-situ bored pile and construction method thereof
WO2023098672A1 (en) * 2021-12-03 2023-06-08 中交第二航务工程勘察设计院有限公司 Gas bag type bored hollow pile structure and construction method therefor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH073782A (en) * 1993-06-18 1995-01-06 Kajima Corp Method for constructing cast-in-place hollow concrete pile, and cast-in-place concrete pile
CN1186141A (en) * 1997-12-25 1998-07-01 叶长生 Bored concrete piles and its construction
CN2353795Y (en) * 1999-01-13 1999-12-15 中国建筑科学研究院地基基础研究所 Prefabricated-tube composite pile of cement and soil
CN2370065Y (en) * 1998-09-21 2000-03-22 叶长生 Hydraulic hammered hollow prefabricated pile
CN2729150Y (en) * 2004-09-15 2005-09-28 蔡崇晓 Concrete placed hollow pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH073782A (en) * 1993-06-18 1995-01-06 Kajima Corp Method for constructing cast-in-place hollow concrete pile, and cast-in-place concrete pile
CN1186141A (en) * 1997-12-25 1998-07-01 叶长生 Bored concrete piles and its construction
CN2370065Y (en) * 1998-09-21 2000-03-22 叶长生 Hydraulic hammered hollow prefabricated pile
CN2353795Y (en) * 1999-01-13 1999-12-15 中国建筑科学研究院地基基础研究所 Prefabricated-tube composite pile of cement and soil
CN2729150Y (en) * 2004-09-15 2005-09-28 蔡崇晓 Concrete placed hollow pile

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499480A (en) * 2014-12-12 2015-04-08 董相东 Method for drilling and filling concrete hollow pile
CN105040685A (en) * 2015-06-09 2015-11-11 周兆弟 Prefabricated member with hollow structure
CN104895053A (en) * 2015-06-16 2015-09-09 苏交科集团股份有限公司 Construction method of sectional type cavity grouting pile
CN106759300A (en) * 2016-11-25 2017-05-31 淮阴工学院 Using the root key construction method of the root key constructing device of radical bored concrete pile
CN108775010A (en) * 2018-05-29 2018-11-09 河海大学 A kind of PCC energy stake and its construction method
CN111335347A (en) * 2020-03-12 2020-06-26 广东金衡建筑工程有限公司 Cast-in-situ bored pile and construction method thereof
WO2023098672A1 (en) * 2021-12-03 2023-06-08 中交第二航务工程勘察设计院有限公司 Gas bag type bored hollow pile structure and construction method therefor

Also Published As

Publication number Publication date
CN103422495B (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN103422495B (en) A kind of hollow bored pipe and construction method thereof
CN104018512B (en) The caisson sinking construction method dynamic to environment micro-turbulence
CN103643668B (en) A kind of method of architectural engineering pit monitoring
CN108956285B (en) Drawing test method for single-anchor fiber rib anti-floating anchor rod system
CN204590104U (en) A kind of bath scaled model experimental device of simulating self-balance testing pile method
CN107238458A (en) Dry hole relief valve and hydrofracturing detecting earth stress device
Abdrabbo et al. Behaviour of single pile in consolidating soil
CN104294816B (en) Large diameter bored pile steel reinforcement cage anti-floating construction method and device
CN203795485U (en) Horizontal bearing characteristics test model of prestressed concrete pipe pile
CN101397800B (en) Deep pile survey mark burying method
CN102535527A (en) Testing device and method of breast wall slurry pressure during pore-forming construction of cast-in-situ bored pile
CN113513054B (en) Pile foundation grouting pressure testing device and method based on optical fiber sensing
CN106088172B (en) A kind of experimental rig of simultaneous determination bored concrete pile stake top and pile end displacement
CN203250466U (en) Self-elevation type sea drilling platform model
CN112982509B (en) Construction method of pre-stressed anchor cable axial force transmission rule mathematical model in composite stratum based on field drawing test
CN102134861B (en) Method for testing precast pile in soil body
CN207003463U (en) Solution cavity area Bridge Pile Foundation Construction device and construction system
CN105241648A (en) Loading device simulating loess tunnel lock foot anchor pipe end stress and use method thereof
CN206905955U (en) Dry hole relief valve and hydrofracturing detecting earth stress device
CN107992673B (en) Exploration depth determination method for karst area bridge pile foundation
CN206114063U (en) Underground water level monitoring device
CN207295773U (en) A kind of underground trough-shaped body anti-floating construction
CN209841650U (en) Pipe jacking of pipe jacking experimental box
CN208685681U (en) A kind of end seals precast concrete enlarged footing cast stake
CN103498467B (en) High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Chen Qiang

Inventor before: Wang Weikai

Inventor before: Pan Xiangjun

Inventor before: Xiao Changcai

Inventor before: Li Lei

Inventor before: Yan Shuhong

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20151124

Address after: 255000 Cao Nan village, four Baoshan office, hi tech Industrial Development Zone, Shandong, Zibo

Applicant after: SHANDONG JIUQIANG ROAD & BRIDGE CO., LTD.

Address before: 257091 Shandong city of Dongying province Dongying District Front Street No. 65

Applicant before: Keda Group Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120

Termination date: 20160725

CF01 Termination of patent right due to non-payment of annual fee