CN101397800B - Deep pile survey mark burying method - Google Patents
Deep pile survey mark burying method Download PDFInfo
- Publication number
- CN101397800B CN101397800B CN200810196977XA CN200810196977A CN101397800B CN 101397800 B CN101397800 B CN 101397800B CN 200810196977X A CN200810196977X A CN 200810196977XA CN 200810196977 A CN200810196977 A CN 200810196977A CN 101397800 B CN101397800 B CN 101397800B
- Authority
- CN
- China
- Prior art keywords
- deep pile
- pile
- depth
- concrete
- stake
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention discloses a method for embedding a deep pile survey marker, which includes the follow steps: (1) the embedding depth of a deep pile (1) is designed; (2) marker embedment is carried out; (3) the top of the deep pile (1) is embedded into a stainless steel survey marker core (2) and the upper part of the deep pile (1) is sheathed with a steel outer sleeve (3); (4) silver sand (4) is filled between the steel outer sleeve (3) and the deep pile (1) so as to separate the steel outer sleeve (3) and the deep pile (1); (5) the top of the steel outer sleeve (3) is connected with the bottom of a protection pot (5) which is sheathed outside the stainless steel survey marker core (2); and (6) a concrete reinforcing bar is installed outside the steel outer sleeve (3), and then concrete (7) is poured; and after the concrete is well maintained, a ground part of a platform outside the concrete (7) is decorated by marble (8). The method has the advantages that: silver sand is filled between an upper platform and the deep pile so as to separate the upper platform and the deep pile to ensure that the deadweight of the upper platform is not transferred to the deep pile, namely that the deep pile is in a stable state without any load. When the upper platform is bumped by an external force, the stainless steel survey marker core is not influenced, which is of significance to construction survey with high precision in industrial factories.
Description
Technical field
The present invention relates to the exploration engineering field, a kind of specifically deep pile survey mark burying method.
Background technology
The stability of measuring the control point is the prerequisite that guarantees to measure the achievement reliability, regulation and stipulation is shallow embedding (degree of depth is about the 1m) technology and the requirement at general control point at present, for the general measure control point in area is buried underground preferably for foundation condition, basic feasible solution.
But, for coastal soft foundation and the very thick area of weak soil layer, as the Baosteel in Shanghai, the Guangdong Yu Feng steel mill in Zhuhai, the Binhai New District of Tianjin, the Shoudu Iron and Steel Co of Cao Feidian etc., these coastal area weak soil layers generally very dark (the Baosteel weak soil layer in Shanghai reach more than 400 meter dark), adopt conventional shallow embedding technology stability relatively poor if measure the control point sign, the control point sign is easy to generate horizontal movement and sinking, and the accuracy and the reliability of achievement measured in influence.
Summary of the invention
The objective of the invention is to develop a kind of deep pile survey mark burying method of measuring control point stability, guaranteeing to measure the achievement reliability that improves.
Deep pile survey mark burying method of the present invention, its step is as follows:
The depth of burying of 1. dark stake 1 should be according to the design of geological mapping data, and the bottom of dark stake 1 requires to reach 2~5m in the bearing stratum of ground, with mainly build, the Pile Foundations Design degree of depth of structure is identical;
2. dark pile constructing process can be selected following method construction according to the degree of depth and foundation soil stability:
The a hand excavated pile about diameter 1.2m, is applicable to that the degree of depth buries underground less than the sign of 20m;
B diameter 400~550mm PHC stake is squeezed into, and is applicable to that the sign of the degree of depth 20~50m is buried underground;
The c bored pile, diameter 1~1.2m adopts mud off, is applicable to that the degree of depth buries underground greater than the sign of 50m;
3. dark stake 1 top embeds stainless steel and measures mark core 2, and dark stake 1 top puts steel sleeve pipe 3;
4. adopt fine sand 4 to fill between steel sleeve pipe 3 and the dark stake 1, make the two separation;
5. the top of steel sleeve pipe 3 links to each other with the bottom of protective pot 5, and protective pot 5 is enclosed within the outside that stainless steel is measured mark core 2, stainless steel is measured mark core 2 play a protective role;
6. load onto reinforcing bar 6 in the outside of steel sleeve pipe 3, fluid concrete 7 then, and after concrete curing was good, the platform face portion outside concrete seven was decorated with marble 8.
A hinged cover is arranged above the protective pot 5.
In the industrial working construction, the generally experiment stake that will squeeze into some earlier, some stake may not can be used, and at this moment can use as dark stake control point to use, and saves and buries cost underground.
The advantage of deep pile survey mark burying method of the present invention is: adopt fine sand to fill between upper brace and the dark stake, make the two separation, the deadweight of guaranteeing upper brace can not passed in the dark stake, promptly dark stake is in complete uncharge stable state, when upper brace is collided by external force, stainless steel is measured the mark core and not influenced by it, and this point has its significance in the construction survey of industrial working high accuracy.
Description of drawings
Fig. 1 is the structural representation of deep pile survey mark burying.
The specific embodiment
Embodiment one
According to shown in Figure 1, a kind of deep pile survey mark burying method, its step is as follows:
The depth of burying of 1. dark stake 1 should be according to the design of geological mapping data, and the bottom of dark stake 1 requires to reach 2~5m in the bearing stratum of ground, with mainly build, the Pile Foundations Design degree of depth of structure is identical;
2. bored pile, diameter 1m adopts mud off, is applicable to that the degree of depth buries underground greater than the sign of 50m;
3. dark stake 1 top embeds stainless steel and measures mark core 2, and dark stake 1 top puts steel sleeve pipe 3;
4. adopt fine sand 4 to fill between steel sleeve pipe 3 and the dark stake 1, make the two separation;
5. the top of steel sleeve pipe 3 links to each other with the bottom of protective pot 5, and protective pot 5 is enclosed within the outside that stainless steel is measured mark core 2;
6. load onto reinforcing bar 6 in the outside of steel sleeve pipe 3, fluid concrete 7 then, and after concrete curing was good, the platform face portion outside concrete seven was decorated with marble 8.
A hinged cover is arranged above the protective pot 5.
Embodiment two
According to shown in Figure 1, a kind of deep pile survey mark burying method, its step is as follows:
The depth of burying of 1. dark stake 1 should be according to the design of geological mapping data, and the bottom of dark stake 1 requires to reach 2~5m in the bearing stratum of ground, with mainly build, the Pile Foundations Design degree of depth of structure is identical;
2. diameter 400~550mm PHC stake is squeezed into, and is applicable to that the sign of the degree of depth 20~50m is buried underground;
3. dark stake 1 top embeds stainless steel and measures mark core 2, and dark stake 1 top puts steel sleeve pipe 3;
4. adopt fine sand 4 to fill between steel sleeve pipe 3 and the dark stake 1, make the two separation;
5. the top of steel sleeve pipe 3 links to each other with the bottom of protective pot 5, and protective pot 5 is enclosed within the outside that stainless steel is measured mark core 2;
6. load onto reinforcing bar 6 in the outside of steel sleeve pipe 3, fluid concrete 7 then, and after concrete curing was good, the platform face portion outside concrete seven was decorated with marble 8.
A hinged cover is arranged above the protective pot 5.
Claims (1)
1. deep pile survey mark burying method, it is characterized in that: its step is as follows:
The depth of burying of 1. dark stake (1) should be according to the design of geological mapping data, and the bottom of dark stake (1) requires to reach 2~5m in the bearing stratum of ground, with mainly build, the Pile Foundations Design degree of depth of structure is identical;
2. dark pile constructing process is selected following method construction according to the degree of depth and foundation soil stability:
The a hand excavated pile about diameter 1.2m, is applicable to that the degree of depth buries underground less than the sign of 20m;
B diameter 400~550mmPHC stake is squeezed into, and is applicable to that the sign of the degree of depth 20~50m is buried underground;
The c bored pile, diameter 1~1.2m adopts mud off, is applicable to that the degree of depth buries underground greater than the sign of 50m;
3. dark stake (1) top embeds stainless steel and measures mark core (2), and dark stake (1) top puts steel sleeve pipe (3);
4. adopt fine sand (4) to fill between steel sleeve pipe (3) and the dark stake (1), make the two separation;
5. the top of steel sleeve pipe (3) links to each other with the bottom of protective pot (5), and protective pot (5) is enclosed within the outside that stainless steel is measured mark core (2);
6. load onto reinforcing bar (6) in the outside of steel sleeve pipe (3), fluid concrete (7) then, after concrete curing was good, the platform face portion outside concrete (7) was decorated with marble (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810196977XA CN101397800B (en) | 2008-09-17 | 2008-09-17 | Deep pile survey mark burying method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810196977XA CN101397800B (en) | 2008-09-17 | 2008-09-17 | Deep pile survey mark burying method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101397800A CN101397800A (en) | 2009-04-01 |
CN101397800B true CN101397800B (en) | 2010-04-21 |
Family
ID=40516624
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200810196977XA Active CN101397800B (en) | 2008-09-17 | 2008-09-17 | Deep pile survey mark burying method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101397800B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102465525B (en) * | 2010-11-11 | 2015-11-25 | 铁道第三勘察设计院集团有限公司 | The Deep Embedded Piles of freezing and defrosting area plane vertical control point and method for embedding thereof |
CN105862901B (en) * | 2016-06-01 | 2018-04-20 | 青岛市勘察测绘研究院 | Docking formula bedrock survey mark and its construction method |
CN108411901A (en) * | 2018-03-16 | 2018-08-17 | 昆明水啸科技有限公司 | A kind of non-concrete fills pile and pile-driving method |
CN110542365B (en) * | 2019-09-04 | 2021-03-02 | 山东普泰工程检测鉴定有限公司 | Soil-wood pile foundation construction pile foundation hole fixed-point detection device |
CN111174755B (en) * | 2020-01-09 | 2022-02-15 | 青岛市勘察测绘研究院 | Expansive soil area plane elevation measurement control point device and installation method |
CN112595298B (en) * | 2020-11-26 | 2022-05-20 | 武汉致远市政建设工程有限公司 | Identification device for measuring control point |
CN113029054B (en) * | 2021-04-09 | 2022-10-25 | 中国海洋大学 | Device and method for monitoring pile foundation scouring depth in real time |
-
2008
- 2008-09-17 CN CN200810196977XA patent/CN101397800B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN101397800A (en) | 2009-04-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101397800B (en) | Deep pile survey mark burying method | |
Meng et al. | Observed behaviors of a long and deep excavation and collinear underlying tunnels in Shenzhen granite residual soil | |
Liu et al. | Observed performance of a deep multistrutted excavation in Shanghai soft clays | |
CN104018512B (en) | The caisson sinking construction method dynamic to environment micro-turbulence | |
CN102221332A (en) | Fiber grating multi-point sensing device for unconsolidated strata as well as monitoring system and method | |
CN102635113A (en) | Construction method for hydraulic vibrating sinking pipe cast-in-place piles | |
CN103243747A (en) | Deviation rectifying method of prestressed concrete pipe pile foundation | |
CN105019485B (en) | A kind of excavation of foundation pit dead load test on pile foundation detection method | |
CN103422495B (en) | A kind of hollow bored pipe and construction method thereof | |
Bian et al. | Centrifuge testing and numerical modeling of single pile and long-pile groups adjacent to surcharge loads in silt soil | |
CN205502092U (en) | Testing arrangement of bored concrete pile burden frictional resistance neutral point in deep back filling | |
CN109113049B (en) | Prefabricated pile with adjustable post-construction stress deformation and construction method thereof | |
CN107063178B (en) | Concrete leveling markstone with displacement sensor and elevation observation and calculation method thereof | |
CN103267464A (en) | Tool for measuring concrete pouring height | |
CN203274729U (en) | Soft soil area horizontal elevation measuring control point | |
CN211285728U (en) | One-hole multi-standard layered settlement monitoring system adopting composite anchor rod | |
Peng et al. | Field Tests′ Study of Deviation Correction of Building near Excavation | |
CN102278975B (en) | Non-contact soft soil large deformation displacement meter | |
Zhang et al. | Experimental Study on Bending Moment of Double‐Row Steel Pipe Piles in Foundation Excavation | |
CN110607810B (en) | One-hole multi-standard layered settlement monitoring system adopting composite anchor rod | |
CN201809776U (en) | Batter post chuck pile foundation | |
CN202767123U (en) | Fill foundation creep normal position testing device | |
CN101458013A (en) | Laying method of soil source heat pump vertical buried tube heat exchanger between foundation piles | |
Liu et al. | Numerical simulation analysis of supporting stability of cast-in-place piles in pipe jacking | |
Sepehrmanesh et al. | Impact of EPB Tunneling on Pile Foundations and Existing Tunnels |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |