CN103422469A - 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法 - Google Patents

一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法 Download PDF

Info

Publication number
CN103422469A
CN103422469A CN201310354100XA CN201310354100A CN103422469A CN 103422469 A CN103422469 A CN 103422469A CN 201310354100X A CN201310354100X A CN 201310354100XA CN 201310354100 A CN201310354100 A CN 201310354100A CN 103422469 A CN103422469 A CN 103422469A
Authority
CN
China
Prior art keywords
artificial checkdam
coal
artificial
dam body
country rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310354100XA
Other languages
English (en)
Other versions
CN103422469B (zh
Inventor
顾大钊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shenhua Energy Co Ltd
Original Assignee
China Shenhua Energy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shenhua Energy Co Ltd filed Critical China Shenhua Energy Co Ltd
Priority to CN201310354100.XA priority Critical patent/CN103422469B/zh
Publication of CN103422469A publication Critical patent/CN103422469A/zh
Priority to PCT/CN2014/075084 priority patent/WO2015021783A1/zh
Priority to AU2014308406A priority patent/AU2014308406B2/en
Priority to US14/910,149 priority patent/US20160176639A1/en
Priority to RU2016103784A priority patent/RU2606790C1/ru
Application granted granted Critical
Publication of CN103422469B publication Critical patent/CN103422469B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G5/00Storing fluids in natural or artificial cavities or chambers in the earth
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/08Wall dams
    • E02B7/12Arch dams
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Abstract

本发明公开一种煤矿地下水库的人工挡水坝,所述人工挡水坝嵌入到所述辅助巷道周围的煤柱坝体和围岩中。本发明还公开了一种煤矿地下水库的人工挡水坝与煤柱坝体和围岩的连接方法,包括以下步骤:在辅助巷道中的煤柱坝体之间选取所述人工挡水坝的筑坝位置;在所述辅助巷道周围的所述煤柱坝体和围岩中开槽,形成凹槽;在所述凹槽中向所述煤柱坝体和围岩中打入多根锚杆;高压喷射混凝土,在所述凹槽中形成所述人工挡水坝。由于将人工挡水坝嵌入到煤柱坝体和围岩中,增强了人工挡水坝与煤柱坝体和围岩的连接,提高人工挡水坝抗滑性能。

Description

一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
技术领域
本发明涉及煤炭开采与水利工程交叉领域,尤其涉及一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法。
背景技术
能源“金三角”(晋陕蒙甘宁)煤炭资源具有浅埋深、薄基岩和煤层厚等特征,2011年该地区煤炭产量23.82亿吨,占全国总产量的67.7%,已成为我国煤炭资源的主产区。但是,西部“能源金三角”生态环境脆弱,该地区长期气候干旱,水资源短缺且时空分布不均匀。以陕北地区为例,该区域地处内陆,降水稀少,蒸发量大,人均水资源仅为927立方米,为全国平均水平的35.7%,属于典型的资源型缺水地区。
在该区域实施大规模高强度的煤炭开采,不可避免对水资源产生负面影响。煤炭开采形成的巷道和采空区,对地表水和地下水运移、赋存状态造成影响,改变了地下水的循环规律,引发一系列问题,如河水断流、地下水位下降、泉水流量锐减或干涸。目前主要实施措施是矿井水外排。矿井水外排有多种不利,一方面造成了水资源浪费,另一方面对地表生态环境产生污染。
因此,在“能源金三角”地区保水开采的关键技术是如何实现矿井水不外排,而井工煤矿开采会形成采空区,若能对采空区加以利用,将煤炭开采过程中的矿井水储存于该空间内,建设地下水库,同时辅以工程措施,实现水资源在地下的过滤净化,利用钻孔与地面相通,为未来水资源利用提供条件。人工防水坝位于组成煤矿地下水库的各个采空区的回风巷、运输巷与主巷连接处等部位,是水库建设的重要环节,人工挡水坝与煤柱坝体的接触部位是坝体的薄弱环节,如何通过科学合理的设计保障其抗滑性,是人工挡水坝建设的关键环节,也是水库运行安全的决定因素。
目前,尚无煤矿地下水库人工挡水坝与煤柱坝体接触部位的建设工艺和实例参考,井下狭小空间内刻槽施工难度大,注浆不便控制,因此有必要设计一种能提高人工挡水坝抗滑性能的煤矿地下水库的人工挡水坝。
发明内容
本发明的目的在于克服现有技术的不足,提供一种能提高人工挡水坝抗滑性能的煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法。
本发明的一个技术方案提供一种煤矿地下水库的人工挡水坝,所述人工挡水坝嵌入到所述辅助巷道周围的煤柱坝体和围岩中。
优选地,所述人工挡水坝嵌入到所述煤柱坝体的深度为50-80cm和所述人工挡水坝嵌入到所述围岩的深度为30-60cm。
优选地,所述人工挡水坝与所述煤柱坝体和所述围岩之间设有多根锚杆。
优选地,所述锚杆的长度为180-210cm,所述锚杆插入到所述煤柱坝体的深度为50-80cm,所述锚杆插入到所述围岩的深度为30-60cm。
优选地,所述人工挡水坝的横截面为矩形或弧形,弧形的所述人工挡水坝的凹面朝向所述地下水库。
优选地,所述人工挡水坝与所述煤柱坝体和所述围岩的接触处安装有应力应变和位移监测仪器。
本发明的另一技术方案提供一种煤矿地下水库的人工挡水坝与煤柱坝体和围岩的连接方法,包括以下步骤:
在辅助巷道中的煤柱坝体之间选取所述人工挡水坝的筑坝位置;
在所述辅助巷道周围的所述煤柱坝体和围岩中开槽,形成凹槽;
在所述凹槽中向所述煤柱坝体和围岩中打入多根锚杆;
高压喷射混凝土,在所述凹槽中形成所述人工挡水坝。
优选地,所述选取所述人工挡水坝的筑坝位置的步骤进一步包括:
利用物探和钻探手段,对待施工巷道的煤岩性质、地层、构造进行勘探;
选择构造简单、煤岩性质稳定的部位作为所述人工挡水坝的筑坝位置。
优选地,所述在所述辅助巷道周围的所述煤柱坝体和围岩中开槽,形成凹槽的步骤之前还包括:
预估所述辅助巷道中的水压;
根据水压来设定所述人工挡水坝的截面形状。
采用上述技术方案后,具有如下有益效果:由于将人工挡水坝嵌入到煤柱坝体和围岩中,增强了人工挡水坝与煤柱坝体和围岩的连接,提高人工挡水坝抗滑性能。
附图说明
图1是本发明一实施例中地下水库的结构示意图;
图2是本发明一实施例中人工挡水坝的结构示意图;
图3是图2中A-A的截面图。
附图标记对照表:
1——辅助巷道     2——煤柱坝体     3——围岩
4——采空区       5——主巷         11——联络巷道
30——人工挡水坝  31——锚杆        32——凹槽
具体实施方式
下面结合附图来进一步说明本发明的具体实施方式。
如图1所示,煤柱坝体2是为保护地表地貌、地面建筑、构筑物和主要井巷,防止塌陷,分隔矿田、井田、含水层、火区及破碎带等而留下不采或暂时不采的部分矿体,起到支撑作用,位于辅助巷道1的左右侧。围岩3(参见图3)是辅助巷道1掘进时候形成的,位于辅助巷道1的上下侧。相邻辅助巷道1之间通过联络巷道11连通。当工作面开采完后形成采空区4,辅助巷道1的上覆岩层冒落,辅助巷道1和采空区4一起形成地下水库。本发明中,煤柱坝体2位于地下水库与主巷5之间,利用煤柱坝体2形成地下水库坝体的一部分。由于辅助巷道1与主巷5相通,因此只需要封堵辅助巷道1与主巷5之间的位置。
如图2所示,本发明中煤矿地下水库的人工挡水坝,人工挡水坝30嵌入到辅助巷道1周围的煤柱坝体2和围岩3中。人工挡水坝30一方面具有很好的防渗性能,更重要的是人工挡水坝30嵌入到辅助巷道1左右侧的煤柱坝体2和辅助巷道1上下侧的围岩3中,增加了人工挡水坝的抗滑性能。
本实施例中,如图2-3所示,人工挡水坝30嵌入到煤柱坝体2的深度为50-80cm和人工挡水坝30嵌入到围岩3的深度为30-60cm,深度的方向与人工挡水坝30的宽度方向相同。人工挡水坝30与煤柱坝体2和围岩3之间均设有三根锚杆31,锚杆31的数量还可以为三根以上,多根锚杆31间隔排布,可以每隔20cm设置一根锚杆31。锚杆31的长度为180-210cm,锚杆31插入到煤柱坝体2的深度为50-80cm,锚杆31插入到围岩3的深度为30-60cm。同时锚杆31要保证垂直,以保证具有较好的稳定性。锚杆31可由钢筋支撑,起到连接人工挡水坝30与煤柱坝体2或围岩3的作用,进一步增强了人工挡水坝的抗滑性能。
本实施例中,如图2所示,人工挡水坝30的横截面为矩形。
较佳地,人工挡水坝的横截面还可以为弧形,弧形的人工挡水坝的凹面朝向地下水库。能有效缓冲突然水压增大对坝体的冲击。
较佳地,为确保人工挡水坝安全,人工挡水坝30与煤柱坝体2和围岩3的接触处安装有应力应变和位移监测仪器。通过井下通讯光缆,实时传输至地面监控中心,防止发生溃坝风险。一般四周各安装一台即可,可根据需要适当增设。
本发明中煤矿地下水库的人工挡水坝与煤柱坝体和围岩的连接方法,包括以下步骤:
步骤S101:在辅助巷道中的煤柱坝体之间选取人工挡水坝30的筑坝位置;
步骤S102:在辅助巷道1周围的煤柱坝体2和围岩3中开槽,形成凹槽32;
步骤S103:在凹槽32中向煤柱坝体2和围岩3中打入多根锚杆31;
步骤S104:高压喷射混凝土,在凹槽32中形成人工挡水坝30。
如图2所示,图2中指显示了形成在煤柱坝体2中的凹槽32。凹槽32的深度可为30-80cm,并根据周边地质条件和地下水库库容进行调整。具体地,煤柱坝体2的凹槽32的深度可以为50-80cm,围岩3的凹槽32的深度可以为30-60cm。本发明连接方法的优点与上述人工挡水坝的优点相同,在此不再累述。
较佳地,选取人工挡水坝的筑坝位置的步骤S101进一步包括:
步骤S201:利用物探和钻探手段,对待施工巷道的煤岩性质、地层、构造进行勘探;
步骤S202:选择构造简单、煤岩性质稳定的部位作为人工挡水坝的筑坝位置。
较佳地,在辅助巷道周围的煤柱坝体和围岩中开槽,形成凹槽的步骤S102之前还包括:
步骤S301:预估辅助巷道1中的水压;
步骤S302:根据水压来设定人工挡水坝的截面形状。
当水压较高时,或者处于水库较低位置的人工挡水坝可优先选择弧形,以缓冲水压。弧形的人工挡水坝在形成凹槽32时,围岩中的凹槽32也形成弧形。
通过对人工挡水坝与煤柱坝体及围岩连接部位的设计,可形成具有良好抗滑性能的人工挡水坝,实现地下水库的安全运行,同时利用监测仪器可实时监测其运行情况,进行应急处置。对于实现矿井水在井下的储存,避免其外排地表蒸发浪费,实现煤炭开采地下水资源的保护利用,具有重要的意义。
以上所述的仅是本发明的原理和较佳的实施例。应当指出,对于本领域的普通技术人员来说,在本发明原理的基础上,还可以做出若干其它变型,也应视为本发明的保护范围。

Claims (9)

1.一种煤矿地下水库的人工挡水坝,其特征在于,所述人工挡水坝嵌入到所述辅助巷道周围的煤柱坝体和围岩中。
2.根据权利要求1所述的人工挡水坝,其特征在于,所述人工挡水坝嵌入到所述煤柱坝体的深度为50-80cm和所述人工挡水坝嵌入到所述围岩的深度为30-60cm。
3.根据权利要求1所述的人工挡水坝,其特征在于,所述人工挡水坝与所述煤柱坝体和所述围岩之间设有多根锚杆。
4.根据权利要求3所述的人工挡水坝,其特征在于,所述锚杆的长度为180-210cm,所述锚杆插入到所述煤柱坝体的深度为50-80cm,所述锚杆插入到所述围岩的深度为30-60cm。
5.根据权利要求1所述的人工挡水坝,其特征在于,所述人工挡水坝的横截面为矩形或弧形,弧形的所述人工挡水坝的凹面朝向所述地下水库。
6.根据权利要求1所述的人工挡水坝,其特征在于,所述人工挡水坝与所述煤柱坝体和所述围岩的接触处安装有应力应变和位移监测仪器。
7.一种煤矿地下水库的人工挡水坝与煤柱坝体和围岩的连接方法,其特征在于,包括以下步骤:
在辅助巷道中的煤柱坝体之间选取所述人工挡水坝的筑坝位置;
在所述辅助巷道周围的所述煤柱坝体和围岩中开槽,形成凹槽;
在所述凹槽中向所述煤柱坝体和围岩中打入多根锚杆;
高压喷射混凝土,在所述凹槽中形成所述人工挡水坝。
8.根据权利要求7所述的连接方法,其特征在于,所述选取所述人工挡水坝的筑坝位置的步骤进一步包括:
利用物探和钻探手段,对待施工巷道的煤岩性质、地层、构造进行勘探;
选择构造简单、煤岩性质稳定的部位作为所述人工挡水坝的筑坝位置。
9.根据权利要求7所述的连接方法,其特征在于,所述在所述辅助巷道周围的所述煤柱坝体和围岩中开槽,形成凹槽的步骤之前还包括:
预估所述辅助巷道中的水压;
根据水压来设定所述人工挡水坝的截面形状。
CN201310354100.XA 2013-08-14 2013-08-14 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法 Active CN103422469B (zh)

Priority Applications (5)

Application Number Priority Date Filing Date Title
CN201310354100.XA CN103422469B (zh) 2013-08-14 2013-08-14 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
PCT/CN2014/075084 WO2015021783A1 (zh) 2013-08-14 2014-04-10 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
AU2014308406A AU2014308406B2 (en) 2013-08-14 2014-04-10 An artificial retaining dam of coal mine underground reservoir and method for connecting security coal pillar, surrounding rock with the retaining dam
US14/910,149 US20160176639A1 (en) 2013-08-14 2014-04-10 An artificial retaining dam of coal mine underground reservoir and method for connecting security coal pillar, surrounding rock with the retaining dam
RU2016103784A RU2606790C1 (ru) 2013-08-14 2014-04-10 Искусственная сдерживающая плотина подземного резервуара угольной шахты и способ соединения угольного целика безопасности, окружающей горной породы и сдерживающей плотины

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310354100.XA CN103422469B (zh) 2013-08-14 2013-08-14 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法

Publications (2)

Publication Number Publication Date
CN103422469A true CN103422469A (zh) 2013-12-04
CN103422469B CN103422469B (zh) 2014-09-10

Family

ID=49647818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310354100.XA Active CN103422469B (zh) 2013-08-14 2013-08-14 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法

Country Status (5)

Country Link
US (1) US20160176639A1 (zh)
CN (1) CN103422469B (zh)
AU (1) AU2014308406B2 (zh)
RU (1) RU2606790C1 (zh)
WO (1) WO2015021783A1 (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015021783A1 (zh) * 2013-08-14 2015-02-19 中国神华能源股份有限公司 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
CN107237651A (zh) * 2017-06-23 2017-10-10 中国矿业大学 一种煤矿地下水库及水库坝体的多层次注浆防渗加固方法
CN108755836A (zh) * 2018-06-05 2018-11-06 中煤科工集团西安研究院有限公司 基于矿井水地下储存的矿区水资源综合利用方法
CN109594527A (zh) * 2018-12-06 2019-04-09 安徽理工大学 一种带锯齿状卡槽的地下水库人工坝体
CN109630195A (zh) * 2019-01-29 2019-04-16 中国矿业大学(北京) 煤矿地下水库强帮阻渗挡水坝
CN109763862A (zh) * 2018-12-06 2019-05-17 国家能源投资集团有限责任公司 一种地下水库坝体及其构筑方法
CN109826667A (zh) * 2019-01-29 2019-05-31 中国矿业大学(北京) 煤矿地下水库工字型挡水坝
CN110396982A (zh) * 2019-07-31 2019-11-01 中国神华能源股份有限公司 一种人工坝体连接结构及施工方法
CN113863985A (zh) * 2020-06-30 2021-12-31 神华神东煤炭集团有限责任公司 一种量质耦合的矿井水收集与供应系统及方法
CN114763695A (zh) * 2021-01-14 2022-07-19 神华神东煤炭集团有限责任公司 一种地下水库人工坝体及其建造方法
CN114763695B (zh) * 2021-01-14 2024-04-26 神华神东煤炭集团有限责任公司 一种地下水库人工坝体及其建造方法

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109141573B (zh) * 2018-07-30 2019-10-15 太原理工大学 一种矿井突水后水位预警算法
CN110981368A (zh) * 2019-12-27 2020-04-10 陕西煤业化工技术研究院有限责任公司 一种煤矿井下临时密闭墙用材料及其密闭墙建立方法
CN114075994A (zh) * 2020-08-13 2022-02-22 神华神东煤炭集团有限责任公司 一种煤矿地下水库的人工挡水坝
CN113026678B (zh) * 2021-04-05 2022-02-22 天地科技股份有限公司 一种带自动张紧功能的可重复利用煤矿地下水库坝体
CN116291716A (zh) * 2023-04-26 2023-06-23 中矿地科技术研究院(江苏)有限公司 一种矿山用采空区密封装置

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH071000B2 (ja) * 1989-01-10 1995-01-11 同和鉱業株式会社 地下水の浸入抑制法
CN1858405A (zh) * 2006-06-06 2006-11-08 宋彦波 软煤巷道高压涌水条件下快速构筑水闸墙的方法
US20100266341A1 (en) * 2009-04-16 2010-10-21 Wayne Poerio Process for in-ground water collection
CN102121388A (zh) * 2011-01-11 2011-07-13 河北同成矿业科技有限公司 一种快速构筑水闸墙的方法
CN102767395A (zh) * 2012-07-23 2012-11-07 中国神华能源股份有限公司 一种矿井地下水库的防渗方法
CN103195477A (zh) * 2013-04-19 2013-07-10 中国矿业大学 一种井下巷道高承压涌水的自流排水系统

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4797821A (en) * 1987-04-02 1989-01-10 Halliburton Company Method of analyzing naturally fractured reservoirs
RU2060398C1 (ru) * 1993-03-02 1996-05-20 Уральский филиал Всесоюзного научно-исследовательского и проектного института галургии Способ подготовки гидроизолирующей перемычки к эксплуатации в аварийной ситуации
US7034660B2 (en) * 1999-02-26 2006-04-25 Sri International Sensor devices for structural health monitoring
US6870975B1 (en) * 2001-11-14 2005-03-22 Fiber Optic Systems Technology, Inc. Fiber optic sensor usable over wide range of gage lengths
US6948282B2 (en) * 2003-01-09 2005-09-27 Allan Block Corporation Interlocking building block
DE102005009036B8 (de) * 2005-02-18 2006-12-07 Gts Grube Teutschenthal Sicherungs Gmbh & Co. Kg Verfahren und Zusammensetzung zum Abdichten von Strecken im Bergbau und/oder eines Baukörpers
US8485873B2 (en) * 2007-07-03 2013-07-16 Frank A. Sisk Steel anchored reinforced mine seal
US8224631B2 (en) * 2008-08-18 2012-07-17 Fci Holdings Delaware, Inc. Stress, geologic, and support analysis methodology for underground openings
US20100189507A1 (en) * 2009-01-29 2010-07-29 Duncan Hird Method and product for absorbing and consolidating nuisance water or slurry accumulations
US9315992B2 (en) * 2012-02-18 2016-04-19 Geovent LLC Convex structural block for constructing parabolic walls
CN103422469B (zh) * 2013-08-14 2014-09-10 中国神华能源股份有限公司 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH071000B2 (ja) * 1989-01-10 1995-01-11 同和鉱業株式会社 地下水の浸入抑制法
CN1858405A (zh) * 2006-06-06 2006-11-08 宋彦波 软煤巷道高压涌水条件下快速构筑水闸墙的方法
US20100266341A1 (en) * 2009-04-16 2010-10-21 Wayne Poerio Process for in-ground water collection
CN102121388A (zh) * 2011-01-11 2011-07-13 河北同成矿业科技有限公司 一种快速构筑水闸墙的方法
CN102767395A (zh) * 2012-07-23 2012-11-07 中国神华能源股份有限公司 一种矿井地下水库的防渗方法
CN103195477A (zh) * 2013-04-19 2013-07-10 中国矿业大学 一种井下巷道高承压涌水的自流排水系统

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
贾永生: "井下防水密闭的构筑和应用", 《同煤科技》, no. 127, 31 March 2011 (2011-03-31) *
邵晨钟,吕华浦: "济三煤矿矿井水资源化工程的实践与研究", 《山东煤炭科技》, no. 3, 31 March 2012 (2012-03-31) *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015021783A1 (zh) * 2013-08-14 2015-02-19 中国神华能源股份有限公司 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
CN107237651B (zh) * 2017-06-23 2019-10-01 中国矿业大学 一种煤矿地下水库及水库坝体的多层次注浆防渗加固方法
CN107237651A (zh) * 2017-06-23 2017-10-10 中国矿业大学 一种煤矿地下水库及水库坝体的多层次注浆防渗加固方法
CN108755836A (zh) * 2018-06-05 2018-11-06 中煤科工集团西安研究院有限公司 基于矿井水地下储存的矿区水资源综合利用方法
CN109594527A (zh) * 2018-12-06 2019-04-09 安徽理工大学 一种带锯齿状卡槽的地下水库人工坝体
CN109763862A (zh) * 2018-12-06 2019-05-17 国家能源投资集团有限责任公司 一种地下水库坝体及其构筑方法
CN109763862B (zh) * 2018-12-06 2020-08-11 国家能源投资集团有限责任公司 一种地下水库坝体及其构筑方法
US10941659B2 (en) 2019-01-29 2021-03-09 China University Of Mining And Technology (Beijing) I-shaped water-retaining dam for underground reservoir in coal mine
CN109630195B (zh) * 2019-01-29 2020-05-19 中国矿业大学(北京) 煤矿地下水库强帮阻渗挡水坝
CN109826667B (zh) * 2019-01-29 2020-05-19 中国矿业大学(北京) 煤矿地下水库工字型挡水坝
CN109826667A (zh) * 2019-01-29 2019-05-31 中国矿业大学(北京) 煤矿地下水库工字型挡水坝
CN109630195A (zh) * 2019-01-29 2019-04-16 中国矿业大学(北京) 煤矿地下水库强帮阻渗挡水坝
CN110396982A (zh) * 2019-07-31 2019-11-01 中国神华能源股份有限公司 一种人工坝体连接结构及施工方法
CN113863985A (zh) * 2020-06-30 2021-12-31 神华神东煤炭集团有限责任公司 一种量质耦合的矿井水收集与供应系统及方法
CN114763695A (zh) * 2021-01-14 2022-07-19 神华神东煤炭集团有限责任公司 一种地下水库人工坝体及其建造方法
CN114763695B (zh) * 2021-01-14 2024-04-26 神华神东煤炭集团有限责任公司 一种地下水库人工坝体及其建造方法

Also Published As

Publication number Publication date
AU2014308406A1 (en) 2016-03-03
CN103422469B (zh) 2014-09-10
RU2606790C1 (ru) 2017-01-10
WO2015021783A1 (zh) 2015-02-19
US20160176639A1 (en) 2016-06-23
AU2014308406B2 (en) 2016-07-21

Similar Documents

Publication Publication Date Title
CN103422469B (zh) 一种煤矿地下水库的人工挡水坝及其与煤柱坝体和围岩的连接方法
CN103422886A (zh) 一种煤矿分布式地下水库的人工挡水坝及其筑坝方法
CN107237651B (zh) 一种煤矿地下水库及水库坝体的多层次注浆防渗加固方法
CN103498696B (zh) 一种从顶板巷道注浆充填压实采空区充填体的方法
CN204299622U (zh) 一种煤矿地下水库的人工挡水坝
CN104533467B (zh) 一种高承压水、断层破碎巷道的支护方法
CN101705838A (zh) 一种采空区阻隔式充填方法
CN100560937C (zh) 一种薄基岩浅埋煤层长壁工作面保水开采方法
CN203412629U (zh) 一种煤矿分布式地下水库的人工挡水坝
CN109595034B (zh) 煤矿地下水库工字型强帮阻渗挡水坝
CN107100625B (zh) 覆岩注水充填降低导高的保水开采方法
CN101608552A (zh) 煤层底板含水层加固并在加固过程中保护隔水层的方法
CN102587859A (zh) 返流注浆封堵矿井突水技术
CN102943690A (zh) 采煤工作面顶板离层水的防治方法
CN112593853A (zh) 一种煤矿矸石充填与减水开采的施工方法
CN102777180A (zh) 一种煤矿主动式区域性防治冲击地压的方法
CN102493831A (zh) 地面压裂井下水平钻孔抽放煤层气方法
CN103321233B (zh) 滑坡深层排水及滑坡体内地下水资源回收装置的制作方法
CN104863588A (zh) 超前预设墩柱沿空留巷方法
CN102797492A (zh) 切顶巷预裂顶板布置方法
CN105781552A (zh) 一种高瓦斯突出煤层立体冲孔石门揭煤新方法
CN103184871A (zh) 一种保护重要水体的煤柱留设开采方法
CN201288586Y (zh) 一种防止沿空留巷充填墙体滑移结构
CN104179511A (zh) 地面预注浆加固巷道穿过断层破碎带处围岩的新型布孔注浆方法
CN201635745U (zh) 一种肋拱式连拱隧道

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Gu Dazhao

Inventor after: Li Quansheng

Inventor after: Chen Sushe

Inventor after: Zhang Kai

Inventor before: Gu Dazhao

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: GU DAZHAO TO: GU DAZHAO LI QUANSHENG CHEN SUSHE ZHANG KAI

C14 Grant of patent or utility model
GR01 Patent grant