CN103410271A - Wall fabricating method for industrialized residence - Google Patents

Wall fabricating method for industrialized residence Download PDF

Info

Publication number
CN103410271A
CN103410271A CN2013103708968A CN201310370896A CN103410271A CN 103410271 A CN103410271 A CN 103410271A CN 2013103708968 A CN2013103708968 A CN 2013103708968A CN 201310370896 A CN201310370896 A CN 201310370896A CN 103410271 A CN103410271 A CN 103410271A
Authority
CN
China
Prior art keywords
wall
layer
industrialized
prefabricating
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103708968A
Other languages
Chinese (zh)
Inventor
刘会盈
邱玉华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao New Century Prefabricated Components Co Ltd
Original Assignee
Qingdao New Century Prefabricated Components Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao New Century Prefabricated Components Co Ltd filed Critical Qingdao New Century Prefabricated Components Co Ltd
Priority to CN2013103708968A priority Critical patent/CN103410271A/en
Publication of CN103410271A publication Critical patent/CN103410271A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Panels For Use In Building Construction (AREA)

Abstract

The invention relates to a wall fabricating technology in industrialized residence in the fled of civil construction. A fabricated wall consists of a concrete inner layer, a heat insulating layer, a wall outer layer, a reinforcing steel bar framework structure, reserved pipe fittings, a reserved cast clamp layer and a mold. The wall fabricating method comprises the steps of fixing the mold, building up a reinforcing steel bar framework, embedding the reserved pipe fittings, casting the concrete inner layer, building the heat insulating layer, casting the wall outer layer and standing still. The wall fabricating method can promote the industrial construction of residence very well. At present, the building manners used in the construction field are relatively backward. The industrialized residence focuses on energy conservation, consumption reduction, labor saving and material saving; moreover, spare parts of automobiles are possibly universal in the future and extremely high lifting efficiency in the operation of the construction filed is achieved. In addition, the wall fabricating method provides a good reference to the construction of economically affordable housing.

Description

The body of wall method for prefabricating of industrialized house
Technical field
The present invention relates to the prefabricated technology of body of wall in the house industrialization in a kind of civil construction field.
Background technology
The domestic construction industry, when carrying out dwelling construction, adopts whole building framework and body of wall all to carry out the mode of concreting mostly at present.Although this construction method adopts brick mix structure for well than before on building body intensity, there will be long in time limit, the building progress is slow, and production efficiency is low, expends more buildings and resources and human cost; And if construction quality is defective, very difficult while doing over again.
Application modern architecture industrial technology, the construction method comparatively fallen behind with the advanced person's that concentrates large industrial mode of production agency, set up the standardization designed, the production system that builds production plant, mechanization of building operation, address management scientification, solve a large amount of dwelling construction problems.
Summary of the invention
Technical problem solved by the invention is to provide a kind of body of wall method for prefabricating of industrialized house, the defect existed with the building trade solved in above-mentioned technical background.
Industrialized house precast wall body of the present invention is comprised of following part: concrete internal layer, insulation layer, wall external layer, steel bar framework structure, reserved pipe fitting, reserved casting card layer, mould.
Its preparation method is as follows:
1, according to relate to drawing mould is fixing after, build the steel bar framework structure, after steel bar framework is put up, reserve the pre-buried of pipe fitting;
2, after treating that steel bar framework and reserved pipe fitting are put up on mould, carry out the casting of concrete internal layer, the concrete grade of casting is mixed with national standard according to design drawing;
3, after the concrete internal layer tentatively solidifies, carry out the insulation layer construction, insulation layer adopts the high-density polystyrene foamed plastics;
4, after concrete internal layer and insulation layer tentatively solidify, carry out the casting of wall external layer, the employing standard is consistent with the concrete internal layer.Body of wall is standing after having cast, and carries out coherent detection after treating to solidify fully, qualified namely can be used for dwelling construction.
5, this precast wall body is when building, according to design drawing, reserve and building body supporting frame between reserved casting card floor, the card floor on this card Ceng Yingyu building body carries out interlock and casts, and has reached enough seal degree and firmness degrees.
Beneficial effect of the present invention is: the body of wall method for prefabricating of industrialized house of the present invention has good facilitation for the industrialization construction of house.The construction method adopted in building trade at present still comparatively falls behind, and the industrialized meaning of house is to save energy and reduce the cost, and uses manpower and material resources sparingly.And following may realize the phenomenon that similar auto parts and components are general, make building trade high raising efficiency at work.Simultaneously, the construction for affordable housing also can provide good reference.
The accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present invention.
Wherein, 1 concrete internal layer, 2 insulation layers, 3 wall external layer, 4 steel bar framework structures, 5 reserved pipe fittings.
The specific embodiment
Below in conjunction with accompanying drawing, illustrate the present invention.
Referring to Fig. 1, as follows with the prefabricated process of the body of wall of window:
1, according to the size of design drawing, carry out the construction of mould, build the size that should reserve window in mold process;
2, after mould has been built, carry out building and reserved pipe fitting pre-buried of steel bar framework, should note especially the reserved draw-in groove that window is installed;
3, mould horizontal, carry out the casting construction of concrete internal layer 1, the rear interpolation insulation layer 2 of having cast;
4, treat that interior layer concrete internal layer 1 and insulation layer 2 tentatively solidify, and carry out the casting of wall external layer 3;
5, after the body of wall manufacture process completes, that body of wall is standing, after bone dry, mould is removed;
While 6, carrying out the body of wall installation, at first the reserved card floor on body of wall and building body supporting frame is carried out to interlock, then carry out concrete casting, make it reach normal intensity.
Method for prefabricating of the present invention, can be for the building body other bodies of wall except load bearing wall.

Claims (6)

1. method for prefabricating of the body of wall for industrialized house is characterized in that: the industrialized precast wall body of house, precast wall body comprise concrete internal layer, insulation layer, wall external layer, steel bar framework structure, reserved pipe fitting, reserved casting card layer, mould.
2. the body of wall method for prefabricating of industrialized house according to claim 1 is characterized in that: concrete internal layer thickness, between 15~20cm, and will be reserved pipe fitting, be arranged in the concrete internal layer.
3. the body of wall method for prefabricating of industrialized house according to claim 1, is characterized in that: reserve pipe fitting and reserve according to mould, include but not limited to electric wire built-in pipe, wire socket preformed hole etc.
4. the body of wall method for prefabricating of industrialized house according to claim 1 is characterized in that: the steel bar framework structure should limit according to mould, before concreting, builds carrying out.
5. the body of wall method for prefabricating of industrialized house according to claim 1, it is characterized in that: the prefabricated procedural order of body of wall is mold structure → build steel bar framework structure → casting concrete internal layer → installation insulation layer → casting wall external layer, after having built, be placed on mould after the dry typing of whole face wall soma, carry out dwelling construction.
6. the body of wall method for prefabricating of industrialized house according to claim 1, it is characterized in that: described precast wall body can carry out prefabricated finishing at the concrete internal layer according to the difference of installation site, as bathroom or kitchen body of wall tile fixing in advance.
CN2013103708968A 2013-08-22 2013-08-22 Wall fabricating method for industrialized residence Pending CN103410271A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103708968A CN103410271A (en) 2013-08-22 2013-08-22 Wall fabricating method for industrialized residence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103708968A CN103410271A (en) 2013-08-22 2013-08-22 Wall fabricating method for industrialized residence

Publications (1)

Publication Number Publication Date
CN103410271A true CN103410271A (en) 2013-11-27

Family

ID=49603308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103708968A Pending CN103410271A (en) 2013-08-22 2013-08-22 Wall fabricating method for industrialized residence

Country Status (1)

Country Link
CN (1) CN103410271A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110014505A (en) * 2018-01-08 2019-07-16 艾乐迈铁科集团 Method and side wall element for fixed sidewall unit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110014505A (en) * 2018-01-08 2019-07-16 艾乐迈铁科集团 Method and side wall element for fixed sidewall unit

Similar Documents

Publication Publication Date Title
CN205100427U (en) Compound concrete outer wall board of prefabricated heat preservation
CN204960022U (en) Prefabricated exterior wall template structure system with heat preservation function
CN105019573A (en) Prefabricated external wall template structure system with heat insulation function, and construction method thereof
CN103306501B (en) Energy-saving domestic architecture with cast-in-place industrial gypsum bearing wall and manufacturing method thereof
CN101196069A (en) Combined disposal pouring steel reinforced concrete polyphenyl board thermal insulation board
CN107700697B (en) A kind of exterior wall prefabricated construction
CN203834771U (en) Prefabricated light floor cover plate and industrial building floor plate structure
CN103526872B (en) A kind of preparation method of composite thermal insulation energy-saving lightweight concrete wall panel
CN201495627U (en) Gypsum-concrete mixed energy saving housing construction structure
CN103410271A (en) Wall fabricating method for industrialized residence
CN207296087U (en) A kind of Prefabricated outer wall non-load bearing wall standard component
CN209468856U (en) A kind of assembly concrete column beam connecting node
CN103255834B (en) Prefabricated heat preservation balcony suitable for industrial production and construction method of prefabricated heat preservation balcony
CN215717575U (en) Toilet structure body integrally built by assembled formwork
CN203307925U (en) Prefabricated heat-insulating balcony suitable for industrial production
CN101871237A (en) Exterior wall insulated structure and building method thereof
CN205894354U (en) Assembled coincide wallboard
CN201991113U (en) Composite heat-preserving wall body adopting dismantling-free prefabricated reinforced-concrete cross-hole template
CN201614679U (en) Assembled building reinforced concrete precast plate
CN205577171U (en) Cast -in -place light composite wall that builds of assembled non -bearing
CN106284739B (en) Assembly concrete is whole without heat bridge gusset
CN203238767U (en) Novel house with walls combined in spot
CN203307962U (en) Outer wall ring beam of building house
CN202985764U (en) Model block for construction of reserved connector of pipe of composite slab
CN104018614B (en) The preparation of precast concrete assembled plate and monolithic architecture constructive method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131127