CN103406715A - Method for installing and precontrolling high-strength bolts with complicated space structure - Google Patents

Method for installing and precontrolling high-strength bolts with complicated space structure Download PDF

Info

Publication number
CN103406715A
CN103406715A CN2013103965952A CN201310396595A CN103406715A CN 103406715 A CN103406715 A CN 103406715A CN 2013103965952 A CN2013103965952 A CN 2013103965952A CN 201310396595 A CN201310396595 A CN 201310396595A CN 103406715 A CN103406715 A CN 103406715A
Authority
CN
China
Prior art keywords
bolt
connecting plate
connecting plates
strength bolt
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103965952A
Other languages
Chinese (zh)
Inventor
王明秀
于国印
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN2013103965952A priority Critical patent/CN103406715A/en
Publication of CN103406715A publication Critical patent/CN103406715A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a method for installing and precontrolling high-strength bolts with a complicated space structure. The method comprises the steps of: selecting connecting plates with the same specification and model, and carrying out alignment drilling on the connecting plates with the same specification and model in a complete set by a fixed mould; assembling a plurality of connecting elements into a mounting unit on the ground by the connecting plates and temporary installation bolts on the ground, lifting the whole mounting unit in position, adjusting and welding; after welding, sequentially replacing the temporary installation bolts by the high-strength bolts, and screwing and fixing the high-strength bolts. A method of firstly welding and then installing the elements in a traditional mode is changed; the method provided by the invention is simple in operation, reduces the times of overhead installation and hoisting, improves the construction efficiency, and reduces the construction cost and safety risk. The connecting plates are cut in a precise or semi-automatic way, and the alignment drilling is carried out on the connecting plates with the same specification and model in the complete set by the fixed mould, so that drilling accuracy and efficiency are guaranteed, the hole passing rate of the high-strength bolts can be further increased, and the connecting plates with the same specification and model have interchangeability.

Description

The installation pre-control method of Complicated Spatial Structure high-strength bolt
Technical field
The present invention relates to the installation pre-control method of a kind of coke dry quenching body steel construction and other Complicated Spatial Structure high-strength bolt.
Background technology
Coke dry quenching body steel structure connection form mostly is high-strength bolt and connects, and the method adopted before it is: join factually the brill method, assemble and join brill method, pre-installation method.The pattern of these methods of operating is: first member and column such as connecting short beam welded together, and auger shell keyhole one by one on connecting plate, then work high above the ground is connected short beam by connecting plate with long beam again with high-strength bolt.The weak point of this operator scheme is: 1, loose mail is many, and the aloft work amount is large, and efficiency of construction is low, and potential safety hazard is large; 2, high because space structure is complicated, hole group's quantity reaches the installation accuracy requirement more, it is low that high-strength bolt is crossed porosity; 3, because connecting plate is too much, the bolt hole machining accuracy is low, and connecting plate interchangeability is poor, and installation effectiveness is low.
Summary of the invention
Goal of the invention of the present invention is for the deficiencies in the prior art, and the installation pre-control method of the Complicated Spatial Structure high-strength bolt that a kind of high-strength bolt punching rate is high, simple to operate, efficiency of construction is high is provided.
Realize that above-mentioned purpose by the following technical solutions: a kind of Complicated Spatial Structure is high
The installation pre-control method of strength bolt, comprise connecting plate, connector, high-strength bolt and interim construction bolt; Described method comprises the steps:
A. select specification, connecting plate that model is identical, specification, connecting plate that model is identical are carried out to complete centering boring with fixed mould;
B. some connecting elements are assembled into to an installation unit by connecting plate and interim construction bolt on ground, the installation unit integral hoisting is in place, weld after adjusting;
C. after the welding, jury interim construction bolt is replaced with to high-strength bolt successively, twist solid high-strength bolt and install.
Further, the drilling hole on described connecting plate is apart from equating.
Further, the number of connection of described interim construction bolt is no less than 1/3 of track bolt sum.
Further, described interim construction bolt is evenly distributed on connecting plate.
Adopt technique scheme, compared with prior art, the present invention has changed the method that member in the traditional mode first welds rear installation, first member is assembled into to an installation unit on ground with interim construction bolt, integral hoisting is welded again, and method of operating is simple, has reduced high-altitude the number of times of lifting is installed, improve efficiency of construction, reduced construction cost and security risk.Connecting plate adopts accurate cutting or semi-automatic cutting, the connecting plate of same size adopts fixed mould to carry out complete centering boring, guarantee the precision of holing and efficiency, and then improve the mistake porosity of high-strength bolt, and the connecting plate of same size, model has interchangeability.
The accompanying drawing explanation
Fig. 1 is beam of the present invention ground assembling schematic diagram.
Fig. 2 is that Figure 1A-A is to profile.
Fig. 3 is beam integral installation welding schematic diagram of the present invention.
Fig. 4 is high-strength bolt installation method schematic diagram of the present invention.
In figure, short beam 1, long beam 2, short beam 3, assembly platform 4, connecting plate 5, bolt hole 6, interim construction bolt 7, bolt hole 8, upright of frame 9, weld seam 10, high-strength bolt 11.
The specific embodiment
The present invention will be further described below in conjunction with accompanying drawing.
The invention discloses a kind of installation pre-control method of Complicated Spatial Structure high-strength bolt, this mounting technique is applicable to coke dry quenching body steel construction and the integral installation of other porous group high-strength bolt.The parts that this method is used have: connecting plate 5, high-strength bolt 11.Concrete steps are:
Select connecting plate: select specification, connecting plate that model is identical, specification, connecting plate that model is identical are carried out to complete centering boring with FIxed abrasive article.Boring 6 pitch-rows on connecting plate 5 equate.Not possessing complete connecting plate 5 of joining brill needs to adopt the import core drill to hole, and guarantees the precision of holing and efficiency.
See Fig. 1, connecting plate 5 first is connected with interim construction bolt 7 with long beam 2 with short beam 1, short beam 3; Interim construction bolt 7 numbers of connection be no less than the track bolt sum 1/3 and to be uniformly distributed.
Short beam 1, short beam 3 are assembled into to an installation unit with the interim bolt 7 of long beam 2 use temporarily on assembly platform 4, the installation unit integral hoisting is got up.
See Fig. 2, installation unit and upright of frame 9 are welded together, stay weld seam 10.
See Fig. 3, after welding, interim construction bolt 7 is changed to high-strength bolt 11 successively, high-strength bolt 11 is evenly distributed on connecting plate 5, twists solid high-strength bolt 11 and installs.
When high-strength bolt 11 is installed, runs into little the adopted reamer of bolt hole 8 dislocation and revise, after correction, carry out again the installation of high-strength bolt 11.
Above-described embodiment has only been expressed one embodiment of the present invention, but can not therefore be interpreted as limitation of the scope of the invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.

Claims (4)

1. the installation pre-control method of a Complicated Spatial Structure high-strength bolt, comprise connecting plate, connector, high-strength bolt and interim construction bolt; It is characterized in that, described method comprises the steps:
A. select specification, connecting plate that model is identical, specification, connecting plate that model is identical are carried out to complete centering boring with fixed mould;
B. some connecting elements are assembled into to an installation unit by connecting plate and interim construction bolt on ground, the installation unit integral hoisting is in place, weld after adjusting;
C. after the welding, jury interim construction bolt is replaced with to high-strength bolt successively, twist solid high-strength bolt and install.
2. the installation pre-control method of Complicated Spatial Structure high-strength bolt according to claim 1, is characterized in that, the drilling hole on described connecting plate is apart from equating.
3. the installation pre-control method of Complicated Spatial Structure high-strength bolt according to claim 1, is characterized in that, the number of connection of described interim construction bolt is no less than 1/3 of track bolt sum.
4. according to the installation pre-control method of the described Complicated Spatial Structure high-strength bolt of claim 1 or 3, it is characterized in that, described interim construction bolt is evenly distributed on connecting plate.
CN2013103965952A 2013-09-04 2013-09-04 Method for installing and precontrolling high-strength bolts with complicated space structure Pending CN103406715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103965952A CN103406715A (en) 2013-09-04 2013-09-04 Method for installing and precontrolling high-strength bolts with complicated space structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103965952A CN103406715A (en) 2013-09-04 2013-09-04 Method for installing and precontrolling high-strength bolts with complicated space structure

Publications (1)

Publication Number Publication Date
CN103406715A true CN103406715A (en) 2013-11-27

Family

ID=49599781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103965952A Pending CN103406715A (en) 2013-09-04 2013-09-04 Method for installing and precontrolling high-strength bolts with complicated space structure

Country Status (1)

Country Link
CN (1) CN103406715A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104439917A (en) * 2014-10-17 2015-03-25 重庆大江工业有限责任公司 Machining method of hinge holes in hydraulic support top beam

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3844084A (en) * 1970-04-03 1974-10-29 American Metal Climax Inc Construction element assembly
JPH11210094A (en) * 1998-01-26 1999-08-03 Showa Alum Corp Structural material and connecting method thereof
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN101862942A (en) * 2010-06-25 2010-10-20 鞍山东方钢结构有限公司 Production process method of pipe whip restraint steel structure of main power house of nuclear power station conventional island
CN102758499A (en) * 2012-07-05 2012-10-31 北京工业大学 Precast prestressed steel girder with post-seismic restorable function
CN103774854A (en) * 2014-01-15 2014-05-07 浙江东驰钢结构有限公司 Construction method for hoisting heavy type ultrahigh steel member

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3844084A (en) * 1970-04-03 1974-10-29 American Metal Climax Inc Construction element assembly
JPH11210094A (en) * 1998-01-26 1999-08-03 Showa Alum Corp Structural material and connecting method thereof
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN101862942A (en) * 2010-06-25 2010-10-20 鞍山东方钢结构有限公司 Production process method of pipe whip restraint steel structure of main power house of nuclear power station conventional island
CN102758499A (en) * 2012-07-05 2012-10-31 北京工业大学 Precast prestressed steel girder with post-seismic restorable function
CN103774854A (en) * 2014-01-15 2014-05-07 浙江东驰钢结构有限公司 Construction method for hoisting heavy type ultrahigh steel member

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
颜钰: "干熄焦设备安装技术研究与实践", 《中国优秀硕士学位论文全文数据库 工程科技Ⅰ辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104439917A (en) * 2014-10-17 2015-03-25 重庆大江工业有限责任公司 Machining method of hinge holes in hydraulic support top beam

Similar Documents

Publication Publication Date Title
CN203201562U (en) Shield tunneling machine initial counter-force frame convenient to detach, install and transport
CN103835511A (en) Integral lifting method for ultra-long light thin giant steel tube truss
CN202894651U (en) Clamping fixture for cone-shaped housing member
CN206844322U (en) A kind of rigid joint of steel pipe column and H profile steel beam
CN101020288A (en) Large circular tank assembling process
CN204858400U (en) Slope shaft tower unscrambler
CN103406715A (en) Method for installing and precontrolling high-strength bolts with complicated space structure
CN203475422U (en) Concrete tubular pile extension device
CN201943361U (en) Rapid positioning device for installation of steel pipe truss structures
CN201712492U (en) Fixing structure of contact network in tunnel
CN104499577A (en) Angle-variable assembled joint for space free-form surface wooden reticulated shell
CN104420543A (en) Joint drum structure for connecting steel structural part
CN204175533U (en) A kind of tower door of wind-driven generator set hole and tower barrel of wind generating set
CN206375596U (en) Girder steel attachment structure is climbed in a kind of assembled
CN202726365U (en) Connecting lug installing and welding device for rack section of derrick
CN104100002A (en) Connecting structure of floor and column
CN103203584B (en) A kind of marine wind electric field major diameter tower drum flange bolt hole dislocation processing method
CN203008479U (en) Temporary standing platform for iron tower assembly
CN105804293A (en) Prefabricated concrete-filled steel tube construction column rammed earth wall
CN209429279U (en) A kind of beam-column connection for assembling type steel structure
CN204940528U (en) A kind of steel structure platform beam syndeton
CN203578007U (en) Integrated ash bucket beam component structure of dust collector
CN204920415U (en) Outer flange joint high strength concrete pole
CN203082363U (en) Vertical shaft cable bridge integral installation structure
CN204456883U (en) A kind of prefabricated detachable discharging platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131127