CN103397779A - 一种大高度剪力墙模板的支撑方法 - Google Patents

一种大高度剪力墙模板的支撑方法 Download PDF

Info

Publication number
CN103397779A
CN103397779A CN2013103102587A CN201310310258A CN103397779A CN 103397779 A CN103397779 A CN 103397779A CN 2013103102587 A CN2013103102587 A CN 2013103102587A CN 201310310258 A CN201310310258 A CN 201310310258A CN 103397779 A CN103397779 A CN 103397779A
Authority
CN
China
Prior art keywords
shear wall
frame
concrete
supporting
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103102587A
Other languages
English (en)
Other versions
CN103397779B (zh
Inventor
刘文峰
刘伟
刘文雷
陈敬磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201310310258.7A priority Critical patent/CN103397779B/zh
Publication of CN103397779A publication Critical patent/CN103397779A/zh
Application granted granted Critical
Publication of CN103397779B publication Critical patent/CN103397779B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开了一种大高度剪力墙模板的支撑方法,其具体技术方案如下:第一步:对剪力墙下部3米内的钢筋进行绑扎,支模板,浇筑混凝土;第二步:拆除模板;第三步:在三角支架上放置400*50mm的脚手板,然后在每个三角支架的插头上使用脚手架钢管搭设1100mm高的防护栏杆;第四步:在已有剪力墙顶边贴双面胶,再将模板紧贴已有剪力墙,模板下部放置三角支架上;第五步:两边重复以上步骤,完成后浇筑混凝土,养护,拆模。本发明所述的一种大高度剪力墙模板的支撑方法,受力性能好,保障了模板刚度、强度安全可靠,在浇筑混凝土施工荷载作用下无超标变形,确保了混凝土施工成形后几何尺寸准确。

Description

一种大高度剪力墙模板的支撑方法
技术领域
本发明属于建筑施工领域,尤其涉及现场浇筑混凝土的模板支撑体系,具体的是一种大高度剪力墙模板的支撑方法。
背景技术
随着建筑结构施工技术的发展,出现了大量的大纵深、大高度的剪力墙结构,给施工中结构体系的稳定性和安全性带来诸多难题,特别是给模板支撑体系的设计与施工带来新的研究课题,模板支撑体系是混凝土结构施工过程的重要临时承载和传力结构,直接影响结构施工安全、工期、质量等重要问题;目前,还没有针对大高度的剪力墙模板的支撑还没有一套完善的技术方案。
发明内容
本发明所要解决的技术问题是提出一种大高度剪力墙模板的支撑方法,保障模板刚度、强度安全可靠,在浇筑混凝土施工荷载作用下无超标变形,确保混凝土施工成形后几何尺寸准确。
为实现上述目的,本发明一种大高度剪力墙模板的支撑方法,其具体技术方案如下:
第一步:对剪力墙下部3米内的钢筋进行绑扎,支模板,浇筑混凝土;
第二步:在剪力墙下部混凝土的硬度达到75%以后,拆除模板,在已有剪力墙顶以下1米处使用高强螺栓安装三角支架,间距1米;
第三步:在三角支架上放置400*50mm的脚手板,然后在每个三角支架的插头上使用脚手架钢管搭设1100mm高的防护栏杆;
第四步:在已有剪力墙顶边贴双面胶,再将模板紧贴已有剪力墙,模板下部放置三角支架上,模板外部放置竖向木方,间距300mm,然后放置横向木方,间距600mm,用直径20mm的对拉螺栓固定;
   第五步:两边重复以上步骤,完成后浇筑混凝土,养护,拆模。
所述三角支架为∠50*50*5mm的角钢和直径20mm焊接而成,直角边为600*800mm,短边为固定边,其中,三角支架的端部焊有外径38mm高200mm的插头。
在所述对拉螺栓在两模板之间的部分穿PVC管,以利于拆模。 
本发明所述的一种大高度剪力墙模板的支撑方法,受力性能好,保障了模板刚度、强度安全可靠,在浇筑混凝土施工荷载作用下无超标变形,确保了混凝土施工成形后几何尺寸准确;支撑构造简单,无需搭设下部支撑,适应工期要求,能快速进行模板拼装及拆卸,经济效益较显著。 
附图说明
图1是本发明一种大高度剪力墙模板的支撑设置示意图。  
具体实施方式
参见附图,一种大高度剪力墙模板的支撑方法,其具体技术方案如下:
第一步:对剪力墙6下部3米内的钢筋进行绑扎,支模板7,浇筑混凝土;
第二步:在剪力墙下部混凝土的硬度达到75%以后,拆除模板,在已有剪力墙顶以下1米处使用高强螺栓安装三角支架1,间距1米;
第三步:在三角支架上放置400*50mm的脚手板2,然后在每个三角支架的插头上使用脚手架钢管搭设1100mm高的防护栏杆3;
第四步:在已有剪力墙顶边贴双面胶,再将模板紧贴已有剪力墙,模板下部放置三角支架上,模板外部放置竖向木方4,间距300mm,然后放置横向木方,间距600mm,用直径20mm的对拉螺栓5固定;
   第五步:两边重复以上步骤,完成后浇筑混凝土,养护,拆模。
所述三角支架为∠50*50*5mm的角钢和直径20mm焊接而成,直角边为600*800mm,短边为固定边,其中,三角支架的端部焊有外径38mm高200mm的插头。
在所述对拉螺栓在两模板之间的部分穿PVC管8,以利于拆模。 
本发明所述的一种大高度剪力墙模板的支撑方法,受力性能好,保障了模板刚度、强度安全可靠,在浇筑混凝土施工荷载作用下无超标变形,确保了混凝土施工成形后几何尺寸准确;支撑构造简单,无需搭设下部支撑,适应工期要求,能快速进行模板拼装及拆卸,经济效益较显著。

Claims (3)

1.一种大高度剪力墙模板的支撑方法,其具体技术方案如下:
第一步:对剪力墙下部3米内的钢筋进行绑扎,支模板,浇筑混凝土;
第二步:在剪力墙下部混凝土的硬度达到75%以后,拆除模板,在已有剪力墙顶以下1米处使用高强螺栓安装三角支架,间距1米;
第三步:在三角支架上放置400*50mm的脚手板,然后在每个三角支架的插头上使用脚手架钢管搭设1100mm高的防护栏杆;
第四步:在已有剪力墙顶边贴双面胶,再将模板紧贴已有剪力墙,模板下部放置三角支架上,模板外部放置竖向木方,间距300mm,然后放置横向木方,间距600mm,用直径20mm的对拉螺栓固定;
第五步:两边重复以上步骤,完成后浇筑混凝土,养护,拆模。
2.根据权利要求1所述的一种大高度剪力墙模板的支撑方法,其特征在于所述三角支架为∠50*50*5mm的角钢和直径20mm焊接而成,直角边为600*800mm,短边为固定边,其中,三角支架的端部焊有外径38mm高200mm的插头。
3.根据权利要求1所述的一种大高度剪力墙模板的支撑方法,其特征在于在所述对拉螺栓在两模板之间的部分穿PVC管。
CN201310310258.7A 2013-07-23 2013-07-23 一种大高度剪力墙模板的支撑方法 Active CN103397779B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310310258.7A CN103397779B (zh) 2013-07-23 2013-07-23 一种大高度剪力墙模板的支撑方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310310258.7A CN103397779B (zh) 2013-07-23 2013-07-23 一种大高度剪力墙模板的支撑方法

Publications (2)

Publication Number Publication Date
CN103397779A true CN103397779A (zh) 2013-11-20
CN103397779B CN103397779B (zh) 2015-11-04

Family

ID=49561474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310310258.7A Active CN103397779B (zh) 2013-07-23 2013-07-23 一种大高度剪力墙模板的支撑方法

Country Status (1)

Country Link
CN (1) CN103397779B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795121A (zh) * 2017-11-08 2018-03-13 山西建集团有限公司 主体结构加高层铝合金模板顶升施工方法
CN108118782A (zh) * 2016-11-29 2018-06-05 中国二十冶集团有限公司 超大面积的混凝土二次支模施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864818A (zh) * 2009-04-14 2010-10-20 武汉建工股份有限公司 现浇倾斜悬弧混凝土剪力墙施工方法
CN102304953A (zh) * 2011-07-07 2012-01-04 李富厚 夹芯保温钢筋混凝土剪力墙及施工方法
CN102587543A (zh) * 2012-01-18 2012-07-18 浙江海天建设集团有限公司 一种建筑遮阳现浇混凝土花格墙及施工方法
US8448387B2 (en) * 2009-09-01 2013-05-28 Integrity Wall, LLC Wall panel and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864818A (zh) * 2009-04-14 2010-10-20 武汉建工股份有限公司 现浇倾斜悬弧混凝土剪力墙施工方法
US8448387B2 (en) * 2009-09-01 2013-05-28 Integrity Wall, LLC Wall panel and method
CN102304953A (zh) * 2011-07-07 2012-01-04 李富厚 夹芯保温钢筋混凝土剪力墙及施工方法
CN102587543A (zh) * 2012-01-18 2012-07-18 浙江海天建设集团有限公司 一种建筑遮阳现浇混凝土花格墙及施工方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118782A (zh) * 2016-11-29 2018-06-05 中国二十冶集团有限公司 超大面积的混凝土二次支模施工方法
CN107795121A (zh) * 2017-11-08 2018-03-13 山西建集团有限公司 主体结构加高层铝合金模板顶升施工方法
CN107795121B (zh) * 2017-11-08 2019-07-26 山西一建集团有限公司 主体结构加高层铝合金模板顶升施工方法

Also Published As

Publication number Publication date
CN103397779B (zh) 2015-11-04

Similar Documents

Publication Publication Date Title
CN104631512A (zh) 吊模法后浇带梁板施工方法
CN104453224A (zh) 一种地下室外墙的模板支护结构及其施工方法
CN103306208A (zh) 1.6次抛物线形新型四柱板式空心变截面高墩爬模方法
CN203808484U (zh) 一种整体悬挑附着式外脚手架
CN104295088A (zh) 一种变形缝两侧剪力墙的钢木组合模板结构及其施工方法
CN204174935U (zh) 一种地下室外墙单侧模板支护结构
CN103556826A (zh) 后浇带区域及其两侧的楼盖区域支撑体系施工方法
CN203429641U (zh) 建筑施工用单侧支模加固结构体系
CN204212447U (zh) 门窗混凝土拱形过梁加固施工装置
CN103397779B (zh) 一种大高度剪力墙模板的支撑方法
CN205036077U (zh) 一种适用于狭小空间使用的剪力墙支模架
CN202509764U (zh) 构造柱模板支模结构
CN205153515U (zh) 一种悬挑承力架组合定位装置
CN204000885U (zh) 地铁深基坑混凝土支撑吊模模具
CN202990407U (zh) 快拆脚手架
CN104295093B (zh) 框架结构双柱间变形缝浇筑支模系统的施工方法
CN202031309U (zh) 一种结构混凝土施工用悬空作业平台
CN204510688U (zh) 一种预制外墙板的临时固定结构
CN105275198A (zh) 一种剪力墙模板加固施工方法
CN204679074U (zh) 一种新型表面观测墩结构
CN204081468U (zh) 一种剪力墙加固模板结构
CN203795824U (zh) 悬挂式扣件脚手架搭设装置
CN205100433U (zh) 一种用于支撑后浇带的格构柱
CN207469752U (zh) 一种通气孔免拆模板
CN202299419U (zh) 伸缩式模板支撑装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant