CN103243621B - Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar - Google Patents
Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar Download PDFInfo
- Publication number
- CN103243621B CN103243621B CN201310172048.6A CN201310172048A CN103243621B CN 103243621 B CN103243621 B CN 103243621B CN 201310172048 A CN201310172048 A CN 201310172048A CN 103243621 B CN103243621 B CN 103243621B
- Authority
- CN
- China
- Prior art keywords
- rail
- adjustment
- bracing frame
- track
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
Disclosed is a method for mounting an integrated steel rail supporting frame for adjustment of groove type steel rails of a tramcar. The integrated steel rail supporting frame is formed by assembling three sets of tooling equipment in a common steel rail supporting system into a whole. The steel rails are adjusted on a set of tooling during adjustment, space between the steel rails is adjusted through fine adjustment screws on two sides of the supporting frame, the height and the levelness of the steel rails are adjusted through vertical adjusting screws on two sides of the supporting frame, and directions of the steel rails are adjusted by depending on inclined draw bars on the supporting frame. A vertical adjusting device is added on the inner side of each steel rail to adjust the levelness of the rail bottom of the single steel rail simultaneously. Vertical adjustment screws on two sides of the steel rails can be adjusted to achieve standard technical requirements if the rail bottoms of the steel rails fail to meet standard design requirements after the steel rails are erected. According to the method, the efficiency and the accuracy of paving adjustment of groove type steel rails of modern tramcars are improved effectively, operation processes can be simplified, the construction progress can be accelerated, and the production cost can be reduced.
Description
Technical field
The invention belongs to modern tram construction, particularly relate to a kind of mounting method of modern tram groove-shape rail orbit adjusting integral type rail bracing frame.
Background technology
In modern tram track engineering without tiny fragments of stone, coal, etc. grooved track laying be construction in technological difficulties and emphasis.Rail erection mode common in current track Traffic Engineering Construction is that three cover tooling devices adjust simultaneously.Three cover frocks are respectively vertical tune, rail distance rod, diagonal member, and in rail adjustment time-division three step by the height of the whole track of vertical key and level, rail distance rod regulates the gauge of rail, the direction of diagonal member adjustment rail.The regulating step of traditional handicraft installation is loaded down with trivial details, and regulate difficulty large, the qualification rate after adjustment is low, needs just can reach technical standard requirement through repeatedly adjusting.
Summary of the invention
Object of the present invention will overcome the above problems exactly, a kind of mounting method of tram groove-shape rail adjustment integral type rail bracing frame is provided, solve the technical barrier that in modern tram trackways engineering construction, in the construction of grooved track laying, grooved orbit adjusting difficulty is large, effectively improve modern tram track engineering steel rail laying efficiency of construction, accelerating construction progress, reduces cost of production.
Technical scheme of the present invention is achieved like this: a kind of mounting method of tram groove-shape rail adjustment integral type rail bracing frame, is characterized in: use integral type rail bracing frame to be by as a whole for three cover tooling device combinations in common rail brace system; When adjusting rail at the enterprising Row sum-equal matrix of a set of frock, the adjustment of gauge relies on the fine setting screw rod of bracing frame both sides to adjust, height and level rely on the vertical adjustment screw rod of both sides on bracing frame to adjust, and the direction of rail relies on the diagonal member on bracing frame to adjust; Increase the flange of rail level of a vertical adjustment device to single rail at rail inside line to adjust simultaneously, when after rail erection, if when not reaching design standard requirement at the bottom of Rail, the vertical adjustment screw of rail both sides is regulated to reach the requirement of technical standard;
Construction sequence of the present invention is:
(1), integral type rail bracing frame is assembled in advance:
The assembled in advance of integral type rail bracing frame is, outside the venue, the part of the integral type rail bracing frame of machine-shaping composition component (vertical adjustment screw rod 1, WidFin screw 3, lateral connection bar 4, flange of rail junction plate 6, vertical tune connecting rod 8) is connected into entirety by screw;
(2), rail raises track:
After groove-shape rail 10 being winched to the position being about to construction, sleeper is installed, adopts 4 special rail rail jacks to be raised track by rail extremely certain height;
(3), integral type rail bracing frame is in place:
The pre-splicing part integral type rail bracing frame (vertical adjustment screw rod 1, WidFin screw 3, lateral connection bar 4, flange of rail junction plate 6, vertical tune connecting rod 8) installed is mounted to groove-shape rail 10 times, installation site adjusts, after accurately in place, rail rail jack is put down, by the load-bearing of integral type rail bracing frame, remove rail rail jack, rail just frame completes;
(4), lower margin fastening devices is set:
After rail just frame, lower margin fastening devices is set, lower margin fastening devices is made up of separately lower margin set bolt 7, be arranged at the railway roadbed both sides of rail, position is parallel with the part integral type rail bracing frame just filled, fixed form adopts electric drill perforating pre-embedded bolt on integral concrete railway roadbed to fix, fixing position should be accurate, and fixing should be firm;
(5), diagonal brace pull bar is installed:
Install diagonal brace pull bar 2, diagonal brace pull bar 2 is made up of two adjusting screw(rod)s and a regulating sleeve, can be stretched by the rotatably mounted of two adjusting screw(rod)s;
(6), the hoisted in position of outer steel formwork plate:
Utilize light weight crane by each outer steel formwork plate 9 hoisted in position, after hoisted in position, be positioned over outside solid concrete roabed, wouldn't fix;
(7), bolt is heightened in installation:
To heighten bolt 5 to be installed under lateral connection bar 4, and tighten the bolt heightened on bolt 5, and make it tentatively stressed, the integral installation that this step terminates rear integral type rail bracing frame completes, and can carry out next step track accurate adjustment operation;
(8), gauge is adjusted:
The adjustment of groove-shape rail 10 gauge is carried out after the integral installation of integral type rail bracing frame completes, the adjustment of gauge by the WidFin screw 3 of groove-shape rail 10 both sides flexible come, a place is tightened according to the standard gauge of design, the WidFin screw 3 simultaneously unclamping opposite side makes rail move left and right to reach the requirement of standard gauge, tightens WidFin screw 3 simultaneously and fix rail and make the distance of two one steel rails be fixed on standard size no longer to move after reaching requirement;
(9) direction of track, is adjusted:
The direction of adjustment track is realized by diagonal brace pull bar 2, implementation process is after the gauge of groove-shape rail 10 is fixing, utilize the deviation of the disjunction mark control point survey orbital direction buried underground, determine that track should offset to the left or to the right, then the diagonal brace pull bar 2 shrinking opposite side while extending the diagonal brace pull bar 2 of side realizes overall the movement to side of integral type rail bracing frame and reaches two parallel objects offseted to one side of groove-shape rail 10, and after reaching designing requirement, this step terminates;
(10) height of track, is adjusted:
The height of adjustment track is realized by vertical adjustment screw rod 1, implementation process is after the direction of groove-shape rail 10 is fixing, utilize the deviation of the disjunction mark control point survey rail height buried underground, determine that track should adjust up or down, then according to the data point reuse vertical adjustment screw rod 1 measured, rotating vertical can make vertically to adjust connecting rod 8 to move up and down to adjusting screw(rod) 1, moving up and down of vertical tune connecting rod 8 can drive flange of rail junction plate 6 and lateral connection bar 4 entirety to move up and down the adjustment realizing rail height, and after reaching designing requirement, this step terminates;
The level of (11), adjustment track:
The level of adjustment track realizes by heightening bolt 5, implementation process be the gauge of groove-shape rail 10, direction, height data accurately after, spirit level is used to measure the rail cant of track, if the rail cant of groove-shape rail 10 does not reach designing requirement, namely when the flange of rail of groove-shape rail 10 is to lopsidedness, rotation is heightened bolt 5 and is realized moving up and down of lateral connection bar 4, the flange of rail side of groove-shape rail 10 is raised or reduces the object reaching rail level, after the level of rail arrives designing requirement, this step terminates;
Fixing and the installation of (12) outer steel formwork plate:
After every detection data of groove-shape rail 10 reach designing requirement, carry out the installation of outer steel formwork plate 9, according to the size of the monolithic railway roadbed of design, outer steel formwork plate 9 is fixed on position accurately, whole implementation process terminates.
The present invention improves efficiency and the accuracy of the adjustment of modern tram groove-shape rail track laying effectively, and can simplify the operation flow process, accelerating construction progress, reduces cost of production.
Now the invention will be further described in conjunction with the accompanying drawings and embodiments.
Accompanying drawing explanation
Fig. 1 is site operation schematic diagram of the present invention.
In figure: 1, vertical adjustment screw rod 2, diagonal brace pull bar 3, WidFin screw 4, lateral connection bar 5, heighten bolt 6, flange of rail junction plate 7, lower margin set bolt 8, vertical adjust connecting rod 9, outer steel formwork plate 10, groove-shape rail
Detailed description of the invention
As seen from Figure 1, the present invention uses integral type rail bracing frame to be by as a whole for three cover tooling device combinations in common rail brace system; When adjusting rail at the enterprising Row sum-equal matrix of a set of frock, the step of adjustment simplifies, the adjustment of gauge relies on the fine setting screw rod of bracing frame both sides to adjust, height and level rely on the vertical adjustment screw rod of both sides on bracing frame to adjust, and the direction of rail relies on the diagonal member on bracing frame to adjust; Increase the flange of rail level of a vertical adjustment device to single rail at rail inside line to adjust simultaneously, overcome the difficult problem that double-block type sleeper steel rail base slope not easily adjusts, when after rail erection, if when not reaching design standard requirement at the bottom of Rail, the vertical adjustment screw of rail both sides is regulated to reach the requirement of technical standard;
Construction sequence of the present invention is:
(1), integral type rail bracing frame is assembled in advance;
(2), rail raises track;
(3), integral type rail bracing frame is in place;
(4), lower margin fastening devices is set;
(5), diagonal brace pull bar is installed;
(6), the hoisted in position of outer steel formwork plate;
(7), bolt is heightened in installation;
(8), gauge is adjusted;
(9) direction of track, is adjusted;
(10) height of track, is adjusted;
The level of (11), adjustment track;
Fixing and the installation of (12) outer steel formwork plate.
Wherein:
(1), integral type rail bracing frame is assembled in advance:
The assembled in advance of integral type rail bracing frame is, outside the venue, the part of the integral type rail bracing frame of machine-shaping composition component (vertical adjustment screw rod 1, WidFin screw 3, lateral connection bar 4, flange of rail junction plate 6, vertical tune connecting rod 8) is connected into entirety by screw;
(2), rail raises track:
After groove-shape rail 10 being winched to the position being about to construction, sleeper is installed, adopts four special rail rail jacks to be raised track by rail extremely certain height;
(3), integral type rail bracing frame is in place:
The pre-splicing part integral type rail bracing frame (vertical adjustment screw rod 1, WidFin screw 3, lateral connection bar 4, flange of rail junction plate 6, vertical tune connecting rod 8) installed is mounted to groove-shape rail 10 times, installation site adjusts, after accurately in place, rail rail jack is put down, by the load-bearing of integral type rail bracing frame, remove rail rail jack, rail just frame completes;
(4), lower margin fastening devices is set:
After rail just frame, lower margin fastening devices is set, lower margin fastening devices is made up of separately lower margin set bolt 7, be arranged at the railway roadbed both sides of rail, position is parallel with the part integral type rail bracing frame just filled, fixed form adopts electric drill perforating pre-embedded bolt on integral concrete railway roadbed to fix, fixing position should be accurate, and fixing should be firm;
(5), diagonal brace pull bar is installed:
Install diagonal brace pull bar 2, diagonal brace pull bar 2 is made up of two adjusting screw(rod)s and a regulating sleeve, can be stretched by the rotatably mounted of two adjusting screw(rod)s;
(6), the hoisted in position of outer steel formwork plate:
Utilize light weight crane by each outer steel formwork plate 9 hoisted in position, after hoisted in position, be positioned over outside solid concrete roabed, wouldn't fix;
(7), bolt is heightened in installation:
To heighten bolt 5 to be installed under lateral connection bar 4, and tighten the bolt heightened on bolt 5, and make it tentatively stressed, the integral installation that this step terminates rear integral type rail bracing frame completes, and can carry out next step track accurate adjustment operation;
(8), gauge is adjusted:
The adjustment of groove-shape rail 10 gauge is carried out after the integral installation of integral type rail bracing frame completes, the adjustment of gauge by the WidFin screw 3 of groove-shape rail 10 both sides flexible come, a place is tightened according to the standard gauge of design, the WidFin screw 3 simultaneously unclamping opposite side makes rail move left and right to reach the requirement of standard gauge, tightens WidFin screw 3 simultaneously and fix rail and make the distance of two one steel rails be fixed on standard size no longer to move after reaching requirement;
(9) direction of track, is adjusted:
The direction of adjustment track is realized by diagonal brace pull bar 2, implementation process is after the gauge of groove-shape rail 10 is fixing, utilize the deviation of the disjunction mark control point survey orbital direction buried underground, determine that track should offset to the left or to the right, then the diagonal brace pull bar 2 shrinking opposite side while extending the diagonal brace pull bar 2 of side realizes overall the movement to side of integral type rail bracing frame and reaches two parallel objects offseted to one side of groove-shape rail 10, and after reaching designing requirement, this step terminates;
(10) height of track, is adjusted:
The height of adjustment track is realized by vertical adjustment screw rod 1, implementation process is after the direction of groove-shape rail 10 is fixing, utilize the deviation of the disjunction mark control point survey rail height buried underground, determine that track should adjust up or down, then according to the data point reuse vertical adjustment screw rod 1 measured, rotating vertical can make vertically to adjust connecting rod 8 to move up and down to adjusting screw(rod) 1, moving up and down of vertical tune connecting rod 8 can drive flange of rail junction plate 6 and lateral connection bar 4 entirety to move up and down the adjustment realizing rail height, and after reaching designing requirement, this step terminates;
The level of (11), adjustment track:
The level of adjustment track realizes by heightening bolt 5, implementation process be the gauge of groove-shape rail 10, direction, height data accurately after, spirit level is used to measure the rail cant of track, if the rail cant of groove-shape rail 10 does not reach designing requirement, namely when the flange of rail of groove-shape rail 10 is to lopsidedness, rotation is heightened bolt 5 and is realized moving up and down of lateral connection bar 4, the flange of rail side of groove-shape rail 10 is raised or reduces the object reaching rail level, after the level of rail arrives designing requirement, this step terminates;
Fixing and the installation of (12) outer steel formwork plate:
After every detection data of groove-shape rail 10 reach designing requirement, carry out the installation of outer steel formwork plate 9, according to the size of the monolithic railway roadbed of design, outer steel formwork plate 9 is fixed on position accurately, whole implementation process terminates.
Embodiment:
Hun Nan, Shenyang City, Liaoning Province new city modern tram first stage of the project Line 1 project adopts this mounting method to construct:
Pass through the mounting cost comparison of two sections of identical groove-shape rail monolithic railway roadbed track laying engineerings of this project structure type, adopt the every 300 meters of groove-shape rail track laying project installation of this mounting method construction can save 2 days durations, save construction and safety measure Meteorological 158910 yuan; This project amounts to 24000m track laying engineering and have employed the construction of this mounting method, saves 160 days durations altogether, saves construction and safety measure Meteorological 12712800 yuan altogether.
Do not adopt modern tram groove-shape rail track laying integral type rail supporting frame construction technology, the 300m track of employing traditional construction technique is main manually, machinery, material drop into situation and be: 1,6 days construction periods, 2, various frock 270 is overlapped, 3, model sheetinstallat work day on artificial work day 240,4, template 900m, 5, electric welding machine 126 machine-team, 6, orbit adjusting 480 work day, amount to and drop into 6 days durations, it is 321650 yuan that main operating expenses drops into, and security costs drops into 57100 yuan.
The every 300m track of employing modern tram groove-shape rail track laying integral type rail supporting frame construction technology is main manually, machinery, material drop into situation and be: 1,4 days construction periods, 2, integral type frock 90 is overlapped, 3, model sheetinstallat work day on artificial work day 240,4, template 900m, 5, electric welding machine 126 machine-team, 6, orbit adjusting 280 work day, amount to and drop into 4 days durations, it is 185460 yuan that main operating expenses drops into, and security costs drops into 34380 yuan.
Whole project 24000m adopts modern tram groove-shape rail track laying integral type rail supporting frame construction technology cumulative investment operating expenses 185460 × 240 ÷ 3=14836800 unit, security costs 34380 × 240 ÷ 3=2750400 unit.Save operating expenses (321650+57100-185460-34380) × 240 ÷ 3=12712800 unit.
Claims (1)
1. a tram groove-shape rail adjustment mounting method for integral type rail bracing frame, is characterized in that: use integral type rail bracing frame to be by as a whole for three cover tooling device combinations in common rail brace system; When adjusting rail at the enterprising Row sum-equal matrix of a set of frock, the adjustment of gauge relies on the fine setting screw rod of bracing frame both sides to adjust, height and level rely on the vertical adjustment screw rod of both sides on bracing frame to adjust, and the direction of rail relies on the diagonal member on bracing frame to adjust; Increase the flange of rail level of a vertical adjustment device to single rail at rail inside line to adjust simultaneously, when after rail erection, if when not reaching design standard requirement at the bottom of Rail, the vertical adjustment screw of rail both sides is regulated to reach the requirement of technical standard;
Construction sequence of the present invention is:
(1), integral type rail bracing frame is assembled in advance:
Integral type rail bracing frame assembled be in advance outside the venue by the part of the integral type rail bracing frame of machine-shaping composition component: vertical adjustment screw rod (1), WidFin screw (3), lateral connection bar (4), flange of rail junction plate (6), vertically adjust connecting rod (8) to connect into entirety by screw;
(2), rail raises track:
After groove-shape rail (10) is worked the position winching to and be about to construction, sleeper is installed, adopts 4 special rail rail jacks to be raised track by rail extremely certain height;
(3), integral type rail bracing frame is in place:
By the pre-splicing part integral type rail bracing frame installed: vertical adjustment screw rod (1), WidFin screw (3), lateral connection bar (4), flange of rail junction plate (6), vertically adjust connecting rod (8) to be mounted to groove-shape rail (10) under, installation site adjusts, after accurately in place, rail rail jack is put down, by the load-bearing of integral type rail bracing frame, remove rail rail jack, rail just frame completes;
(4), lower margin fastening devices is set:
After rail just frame, lower margin fastening devices is set, lower margin fastening devices is made up of separately lower margin set bolt (7), be arranged at the railway roadbed both sides of rail, position is parallel with the part integral type rail bracing frame just filled, fixed form adopts electric drill perforating pre-embedded bolt on integral concrete railway roadbed to fix, fixing position should be accurate, and fixing should be firm;
(5), diagonal brace pull bar is installed:
Install diagonal brace pull bar (2), diagonal brace pull bar (2) is made up of two adjusting screw(rod)s and a regulating sleeve, can be stretched by the rotatably mounted of two adjusting screw(rod)s;
(6), the hoisted in position of outer steel formwork plate:
Utilize light weight crane by each outer steel formwork plate (9) hoisted in position, after hoisted in position, be positioned over outside solid concrete roabed, wouldn't fix;
(7), bolt is heightened in installation:
To heighten bolt (5) is installed under lateral connection bar (4), tighten the bolt heightened on bolt (5), make it tentatively stressed, the integral installation that this step terminates rear integral type rail bracing frame completes, and can carry out next step track accurate adjustment operation;
(8), gauge is adjusted:
The adjustment of groove-shape rail (10) gauge is carried out after the integral installation of integral type rail bracing frame completes, the adjustment of gauge by the WidFin screw (3) of groove-shape rail (10) both sides flexible come, a place is tightened according to the standard gauge of design, the WidFin screw (3) simultaneously unclamping opposite side makes rail move left and right to reach the requirement of standard gauge, tightens WidFin screw (3) simultaneously and fix rail and make the distance of two one steel rails be fixed on standard size no longer to move after reaching requirement;
(9) direction of track, is adjusted:
The direction of adjustment track is realized by diagonal brace pull bar (2), implementation process is after the gauge of groove-shape rail (10) is fixing, utilize the deviation of the disjunction mark control point survey orbital direction buried underground, determine that track should offset to the left or to the right, then the diagonal brace pull bar (2) shrinking opposite side while extending the diagonal brace pull bar (2) of side realizes overall the movement to side of integral type rail bracing frame and reaches two parallel objects offseted to one side of groove-shape rail (10), and after reaching designing requirement, this step terminates;
(10) height of track, is adjusted:
The height of adjustment track is realized by vertical adjustment screw rod (1), implementation process is after the direction of groove-shape rail (10) is fixing, utilize the deviation of the disjunction mark control point survey rail height buried underground, determine that track should adjust up or down, then according to the data point reuse vertical adjustment screw rod (1) measured, rotating vertical can make vertically to adjust connecting rod (8) to move up and down to adjusting screw(rod) (1), moving up and down of vertical tune connecting rod (8) can drive flange of rail junction plate (6) and lateral connection bar (4) entirety to move up and down the adjustment realizing rail height, after reaching designing requirement, this step terminates,
The level of (11), adjustment track:
The level of adjustment track realizes by heightening bolt (5), implementation process is the gauge in groove-shape rail (10), direction, after height data are accurate, spirit level is used to measure the rail cant of track, if the rail cant of groove-shape rail (10) does not reach designing requirement, namely when the flange of rail of groove-shape rail (10) is to lopsidedness, rotation is heightened bolt (5) and is realized moving up and down of lateral connection bar (4), the flange of rail side of groove-shape rail (10) is raised or reduces the object reaching rail level, after the level of rail arrives designing requirement, this step terminates,
Fixing and the installation of (12) outer steel formwork plate:
The installation of outer steel formwork plate (9) is carried out after every detection data of groove-shape rail (10) reach designing requirement, according to the size of the monolithic railway roadbed of design, outer steel formwork plate (9) is fixed on position accurately, whole implementation process terminates.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310172048.6A CN103243621B (en) | 2013-05-12 | 2013-05-12 | Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310172048.6A CN103243621B (en) | 2013-05-12 | 2013-05-12 | Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103243621A CN103243621A (en) | 2013-08-14 |
CN103243621B true CN103243621B (en) | 2015-05-20 |
Family
ID=48923474
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310172048.6A Active CN103243621B (en) | 2013-05-12 | 2013-05-12 | Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103243621B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104711911A (en) * | 2015-02-27 | 2015-06-17 | 枣庄矿业(集团)有限责任公司柴里煤矿 | Downhole rail mounting dies |
CN106087616A (en) * | 2016-06-08 | 2016-11-09 | 中国十七冶集团有限公司 | A kind of track precise adjusting device and installation method |
CN106436499B (en) * | 2016-11-01 | 2019-01-22 | 五冶集团上海有限公司 | A kind of streetcar track mounting device and its installation and application |
CN107380204B (en) * | 2017-08-11 | 2023-12-01 | 暨南大学 | Track geometric parameter detection vehicle and track geometric parameter detection method |
CN111395055A (en) * | 2020-03-16 | 2020-07-10 | 中铁上海工程局集团有限公司 | Construction method of track integral ballast bed |
CN111733636B (en) * | 2020-06-12 | 2021-09-24 | 山东莱钢磁浮列车轨道工程有限公司 | Installation method of multi-track system |
CN112252087A (en) * | 2020-12-08 | 2021-01-22 | 安徽兴宇轨道装备有限公司 | Precast slab ballast bed construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE29909390U1 (en) * | 1999-05-29 | 1999-08-12 | Lepka, Andreas, 50859 Köln | Screw wedge |
US6263800B1 (en) * | 1999-09-03 | 2001-07-24 | Timothy R. Wilson | Rail support system |
CN201074288Y (en) * | 2007-07-23 | 2008-06-18 | 中铁二十三局集团有限公司 | Adjustable means of support |
CN101418535A (en) * | 2008-10-10 | 2009-04-29 | 中铁十一局集团第三工程有限公司 | Construction method of monolithic road-bed in rail tunnel |
EP2206831A2 (en) * | 2009-01-13 | 2010-07-14 | GSG Knape Gleissanierung GmbH | Device for lifting and aligning rails |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ATE328156T1 (en) * | 2003-01-21 | 2006-06-15 | Pfleiderer Infrastrukturt Gmbh | SPINDLE DEVICE FOR ADJUSTING THE HEIGHT OF TRACK GRATES |
-
2013
- 2013-05-12 CN CN201310172048.6A patent/CN103243621B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE29909390U1 (en) * | 1999-05-29 | 1999-08-12 | Lepka, Andreas, 50859 Köln | Screw wedge |
US6263800B1 (en) * | 1999-09-03 | 2001-07-24 | Timothy R. Wilson | Rail support system |
CN201074288Y (en) * | 2007-07-23 | 2008-06-18 | 中铁二十三局集团有限公司 | Adjustable means of support |
CN101418535A (en) * | 2008-10-10 | 2009-04-29 | 中铁十一局集团第三工程有限公司 | Construction method of monolithic road-bed in rail tunnel |
EP2206831A2 (en) * | 2009-01-13 | 2010-07-14 | GSG Knape Gleissanierung GmbH | Device for lifting and aligning rails |
Also Published As
Publication number | Publication date |
---|---|
CN103243621A (en) | 2013-08-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103243621B (en) | Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar | |
CN101418535B (en) | Construction method of monolithic road-bed in rail tunnel | |
CN103757993B (en) | High-speed railway subgrade sedimentation repair system and method | |
CN202849880U (en) | A magnetic suspension track section measuring and adjusting system | |
CN109778612A (en) | Ballastless track structure method for correcting error in railway tunnel | |
CN202390730U (en) | Fine adjustment device for mounting a track | |
CN106702834A (en) | Midline deviation rectifying method for sedimentary offset ballastless track | |
CN204607405U (en) | A kind of large deformation Rock Crane Rail Support orbital arrangement structure | |
CN104179365A (en) | Construction method for overall iron tower displacement | |
CN201650302U (en) | Eiking clear hole structure of existing high speed railway tunnel | |
CN207047613U (en) | A kind of railway roadbed changeover portion support meanss and railway roadbed changeover portion support system | |
CN102733307B (en) | Method for constructing cast-in-place beam falsework | |
CN206306232U (en) | A kind of ballastless track slab mold | |
CN102286939A (en) | Beam moving and connecting construction method of existing viaducts in urban rail transits | |
CN103967332B (en) | The construction method of a kind of building site enclosing | |
CN103967052B (en) | A kind of method of protecting the new and old frame core-tube system substrate discrepancy in elevation soil body | |
CN206289476U (en) | The construction beam of railroad track is changed under the conditions of for not stopping transport | |
CN202099699U (en) | Elastic supporting vibration isolation component ballast bed | |
CN104153451A (en) | Construction method for installing concrete pipeline through prefabricated supporting block | |
CN203702180U (en) | Single-track railway outer mold tunnel trolley | |
CN110863652A (en) | Precise positioning and mounting method for prefabricated and assembled double-section stand column | |
CN110043279A (en) | Tunnel mould shotcrete support constructing device and method | |
CN202622992U (en) | Universal-type post-tensioned T-beam precast pedestal with detachable modules and adjustable steel members | |
CN114197258A (en) | Installation method of independent fine adjustment device for ballastless track of depot line | |
CN205476528U (en) | Precast pile device of taking one's place fast |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |