A kind of center line method for correcting error for settling skew non-fragment orbit
Technical field
The invention belongs to high speed railway track Structural defect remedial technology field, in particular to one kind for settling skew nothing
The center line method for correcting error of tiny fragments of stone, coal, etc. track.
Background technology
The bulk solid road that ballastless track structure is made firm by ramming using the concrete integral channel bed of big rigidity instead of rubble railway ballast
Bed, the features such as lacking with smooth-going, stabilization, durable, maintenance workload, has turned into the primary trace of newly-built high-speed railway at present
Structural shape.For ensure high-speed railway it is safe efficient run, China under ballastless track structure line basis sedimentation and deformation
Strict demand is proposed, remarkable effect is also achieved.But China's non-fragment orbit circuit is long, span big, when it is by special sector
Especially during soft soil foundation, part non-fragment orbit circuit can be disturbed due to the soil body of residing complex geologic conditions or nearby lines
Midline shift is produced etc. reason.Fastener system in ballastless track structure can provide limited tune for line midline offset problem
Whole amount, but when line midline side-play amount exceedes fastener system adjustment amount, would have to the side by limiting train running speed
Formula carrys out guarantee driving safety, so as to influence the normal operation of train.
At present, the center line method for correcting error research for ballastless track of high-speed railway is less." one kind is for settling without the tiny fragments of stone, coal, etc. for patent
Track centre offsets method for correcting error "(CN 104131499 B)The core of the non-fragment orbit midline shift deviation correcting technology is online
Road outside sets curtain, by carrying out slip casting on the inside of curtain, makes slurries that extension, solidification and shape are oriented under curtain iris action
Into sideways against power, to realize laterally rectifying a deviation track structure to opposite side, the technology is high to curtain setting requirements, field conduct
Difficulty is big, high cost, and is not suitable for the larger non-fragment orbit line midline correction of side-play amount.Patent is " high for soft clay area
The method for correcting error of fast railway ballastless track roadbed "(CN 103821039 B)The means of used rotary churning pile solid soil,
Promoted using the moment injection pressure of rotary churning pile generation of constructing and produce displacement positioned at the pile foundation reinforcement area of high-speed railway embankment bottom,
Pile foundation reinforcement zone moves the foundation stabilization bed course and high-speed railway embankment synchronizing moving above pile foundation reinforcement area, and it is right to realize
The correction of high-speed railway subgrade, this method is only applicable to soft clay area, and equipment needed for construction is huge, Construction control precision
It is low, it is not suitable for the quick correction operation in Window time." CRTS I-type plate-types are without tiny fragments of stone, coal, etc. rail on a kind of high-speed railway subgrade for patent
Road lifting deviation correcting device and method "(201510341806.1)Lifting frock is installed on bedplate, using hydraulic system the bottom of to
Seat board and upper rail guidance tape carry out overall lifting, translation, but this method must be arranged above multiple H types and indulge in track structure
Girder steel, its required plant equipment is huge, it is difficult to rectification work is completed in Window time." one kind is for roadbed section high speed for patent
Railway ballastless track center line method for correcting error "(CN 106049193 A)Will be overall by mechanical lifting devices such as jack or air bags
Pine is first pushed up between railway roadbed and graded broken stone to fall after rise again, bottom solid concrete roabed is translated using thrustor then, this method
Required plant equipment is huge, and operating process is cumbersome, and efficiency of construction is relatively low.
Therefore, how fast and safely simultaneously energy economy enduringly solves the midline shift of ballastless track of high-speed railway structure, still
It is so current problem demanding prompt solution.
The content of the invention
It is an object of the invention to solve the above problems, there is provided a kind of center line correction side for settling skew non-fragment orbit
Method, technical scheme is as follows.
A kind of center line method for correcting error for settling skew non-fragment orbit, it is characterised in that comprise the following steps:(1)It is determined that
Sedimentation non-fragment orbit circuit Uplifting amount and side-play amount;(2)With reference to track structure feature, slip casting is set in ballastless track structure top surface
Lifting hole, and high-pressure slip-casting equipment is used, under certain grouting pressure, according to the device parameter and slip casting step that determine, will note
Slurry lifting material is injected into ballastless track supporting layer or bedplate lower section by the Grouting Pipe being installed in injected hole, realizes without the tiny fragments of stone, coal, etc.
The lifting of track solid concrete roabed and superstructure;(3)Pushing tow point is set in ballastless track structure side, and thrustor is installed,
By being grouped the pushing process of loading, pushing tow step by step, non-fragment orbit circuit is rectified a deviation to design attitude;(4)Line midline is rectified a deviation
After finishing, row line is entered in time and is resumed operation, non-fragment orbit solid concrete roabed lower space is filled full using packing material, led to
Accurate adjustment fastener system is crossed, recovers Track regularity.
The injected hole is 1m~10m along the spacing of line direction, and horizontal direction spacing is 0.5m~3m, injected hole
Internal diameter be 10mm~50mm, injected hole should be deep to 5cm below ballastless track structure supporting course or base board concrete~
100cm positions.
There is fast connector to play directed flow to injecting paste material on the Grouting Pipe top;Grouting Pipe bottom has
, can be fixed on Grouting Pipe in the injected hole of ballastless track supporting layer or base board concrete by stopping means.
The pushing tow point is arranged at the ballastless track structure side of skew circuit, wherein, pushing tow point is along between line direction
Away from being 1m~10m.
Described thrustor, is made up of jack, power transmission steelframe, power transmission steel plate, adjustment backing plate and counter-force pier(See attached
Fig. 1).
The slip-casting lifting material be with dilatancy or without expansile fast hard material, operable time be 5s~
Up to more than the 50% of design strength, shearing strength is 0.01 ~ 1 with compression strength ratio to 600s, 1h compression strength;Fast hard material
It is the one kind in the fast hard material of organic rapid hardening, polyurethane, polyureas, epoxy resin, acrylic resin and unsaturated polyester (UP) etc., or
It is the one kind in the fast hard material waterglass-cement system of inorganic rapid hardening, aluminium sulfate system, aluminate and phosphate system.
The packing material is high polymer grouting material or resin mortar.
The present invention is a kind of to be for settling the good effect of the center line method for correcting error of skew non-fragment orbit:
(1)The method of slip-casting lifting is carried out using special material to reduce the constraint of supporting course or bedplate bottom, it is this to be used for
The fast hard material of rapid hardening of slip-casting lifting has high compressive strength and low shearing strength simultaneously so that the jacking force needed for correction is significantly
Reduce, so as to reduce the setting of counterforce device needed for correction pushing tow operation, while reducing correction task difficulty and cost.
(2)Compared to the operating type for using means such as air bag liftings rectified a deviation after first lifting, the method in the present invention
Required equipment is simple, and upper and lower road is convenient, it is easy to carry out sharp work in skylight point.
(3)The scope of application is big, and the sedimentation non-fragment orbit center line correction to soft clay area and non-soft clay area is applicable, to straight
Line segment non-fragment orbit and the correction of curved section non-fragment orbit center line are applicable.
Brief description of the drawings
Fig. 1 and Fig. 2 are the structural representation of the thrustor.
In figure:1- jack, 2- power transmissions steel plate, 3- adjustment backing plate, 4- counter-forces pier, 5- power transmission steelframes.
Specific embodiment
Below by embodiment, and with reference to accompanying drawing, technical scheme is further illustrated.
Embodiment 1:The embodiment of the invention provides a kind of for high-speed railway subgrade straightway sedimentation non-fragment orbit center line
Correction restorative procedure, methods described includes herein below:
(1)Slip-casting lifting material used is the fast hard material of polyurathamc class, and operable time is 6s, and 1h compression strength reaches and sets
The 90% of meter intensity, material shearing strength is 0.02 with compression strength ratio;
(2)Construction pronucleus treats the correction linear data of section non-fragment orbit, and each track is numbered, and sets up measurement control
Net, and determine Uplifting amount and correction amount.There is midline shift, circuit correction section 1# to 40# support rails to circuit outside in the section
The design correction amount and design Uplifting amount of platform are shown in Table 1.
The design correction amount and design rising height of straightway 1# to the 40# tracks of table 1
Track is numbered |
Design correction amount(mm)* |
Design Uplifting amount(mm) |
Track is numbered |
Design correction amount(mm)* |
Design Uplifting amount(mm) |
1# |
5 |
15 |
21# |
19 |
19 |
2# |
6 |
16 |
22# |
18 |
19 |
3# |
7 |
17 |
23# |
17 |
18 |
4# |
8 |
18 |
24# |
16 |
17 |
5# |
9 |
19 |
25# |
15 |
16 |
6# |
10 |
20 |
26# |
14 |
15 |
7# |
11 |
20 |
27# |
13 |
15 |
8# |
12 |
20 |
28# |
13 |
15 |
9# |
13 |
21 |
29# |
13 |
15 |
10# |
14 |
21 |
30# |
13 |
15 |
11# |
15 |
22 |
31# |
12 |
15 |
12# |
16 |
22 |
32# |
11 |
15 |
13# |
17 |
22 |
33# |
10 |
14 |
14# |
18 |
23 |
34# |
10 |
14 |
15# |
18 |
22 |
35# |
10 |
14 |
16# |
18 |
22 |
36# |
9 |
14 |
17# |
19 |
21 |
37# |
8 |
14 |
18# |
20 |
20 |
38# |
7 |
14 |
19# |
20 |
20 |
39# |
6 |
14 |
20# |
20 |
20 |
40# |
5 |
14 |
* on the occasion of for circuit lateral offset, negative value is to circuit offset inboard
(2)With reference to ballastless track structure feature, slip-casting lifting hole is set, wherein, slip-casting lifting hole is along the spacing of line direction
2m, horizontal direction spacing is 1m, and slip-casting lifting hole internal diameter is 20mm, slip-casting lifting hole depth to ballastless track structure supporting course coagulation
Native following about 50cm positions.
(3)Slip-casting lifting operation is carried out using above-mentioned slip-casting lifting material at injected hole, by non-fragment orbit solid concrete roabed
And superstructure lifting 15mm or so.
(4)With reference to ballastless track structure feature and design correction amount, carry out center line rectify a deviation pushing tow point setting, pushing tow point with
The spacing of 8m is arranged at ballastless track structure side along line direction.
(5)The thrustor for be made up of jack, power transmission steelframe, power transmission steel plate, adjustment backing plate and counterforce device is pacified
Each pushing tow point of dress, wherein counterforce device correspondence is arranged.
(6)Correction operation is proceeded by from side-play amount maximum, after this pushing tow terminates, at new maximum offset again
It is secondary to carry out pushing tow operation, until non-fragment orbit line midline recovers to design load.
(7)After the correction of non-fragment orbit center line terminates, ballastless track structure is raised to using high polymer grouting lifting material
Design altitude, and non-fragment orbit cavity is filled up completely with resin mortar.
(8)Construction is checked the linear data of non-fragment orbit after terminating, the reality of circuit correction section 1# to 40# tracks
Border correction amount and actual Uplifting amount are shown in Table 2.
The actual correction amount and actual rising height of straightway 1# to the 40# tracks of table 2
Track is numbered |
Actual correction amount(mm)* |
Actual Uplifting amount(mm) |
Track is numbered |
Actual correction amount(mm)* |
Actual Uplifting amount(mm) |
1# |
5 |
15 |
21# |
18 |
20 |
2# |
6 |
16 |
22# |
17 |
19 |
3# |
7 |
16 |
23# |
16 |
18 |
4# |
8 |
17 |
24# |
16 |
17 |
5# |
9 |
18 |
25# |
15 |
16 |
6# |
10 |
19 |
26# |
14 |
16 |
7# |
11 |
20 |
27# |
13 |
15 |
8# |
11 |
20 |
28# |
13 |
15 |
9# |
12 |
21 |
29# |
13 |
15 |
10# |
13 |
21 |
30# |
12 |
15 |
11# |
14 |
21 |
31# |
11 |
15 |
12# |
15 |
22 |
32# |
11 |
14 |
13# |
16 |
22 |
33# |
10 |
14 |
14# |
17 |
23 |
34# |
10 |
14 |
15# |
18 |
22 |
35# |
10 |
14 |
16# |
18 |
22 |
36# |
9 |
14 |
17# |
19 |
22 |
37# |
8 |
14 |
18# |
20 |
21 |
38# |
7 |
14 |
19# |
20 |
20 |
39# |
6 |
14 |
20# |
19 |
20 |
40# |
5 |
14 |
* on the occasion of for circuit lateral offset, negative value is to circuit offset inboard
Described non-fragment orbit center line method for correcting error, can exist the control of high-speed railway subgrade ballastless track structure center line correction precision
Within 1mm, and the setting requirements of counterforce device are greatly reduced.
Embodiment 2:The embodiment of the invention provides a kind of for the sedimentation non-fragment orbit center line correction of high-speed railway subgrade curved section
Restorative procedure, methods described includes herein below:
(1)Slip-casting lifting material used is the fast hard material of aluminium sulfate class, and operable time is 200s, and 1h compression strength reaches and sets
The 55% of meter intensity, material shearing strength is 0.5 with compression strength ratio;
(2)Construction pronucleus treats the correction linear data of section non-fragment orbit, and each track is numbered, and sets up measurement control
Net, and determine Uplifting amount and correction amount.There is midline shift, circuit correction section 1# to 40# support rails to circuit inner side in the section
The design correction amount and design Uplifting amount of platform are shown in Table 3.
The design correction amount and design rising height of curved section 1# to the 40# tracks of table 3
Track is numbered |
Design correction amount(mm)* |
Design Uplifting amount(mm) |
Track is numbered |
Design correction amount(mm)* |
Design Uplifting amount(mm) |
1# |
-6 |
18 |
21# |
-16 |
24 |
2# |
-7 |
19 |
22# |
-16 |
24 |
3# |
-8 |
19 |
23# |
-15 |
24 |
4# |
-9 |
19 |
24# |
-15 |
23 |
5# |
-10 |
20 |
25# |
-15 |
22 |
6# |
-11 |
21 |
26# |
-15 |
21 |
7# |
-12 |
21 |
27# |
-14 |
20 |
8# |
-12 |
21 |
28# |
-14 |
19 |
9# |
-12 |
22 |
29# |
-13 |
18 |
10# |
-13 |
22 |
30# |
-12 |
17 |
11# |
-13 |
23 |
31# |
-11 |
17 |
12# |
-14 |
23 |
32# |
-10 |
16 |
13# |
-15 |
23 |
33# |
-9 |
15 |
14# |
-15 |
24 |
34# |
-9 |
15 |
15# |
-15 |
24 |
35# |
-9 |
14 |
16# |
-15 |
24 |
36# |
-9 |
13 |
17# |
-16 |
24 |
37# |
-9 |
12 |
18# |
-16 |
25 |
38# |
-8 |
11 |
19# |
-16 |
25 |
39# |
-7 |
11 |
20# |
-16 |
25 |
40# |
-6 |
10 |
* on the occasion of for circuit lateral offset, negative value is to circuit offset inboard
(2)With reference to ballastless track structure feature, slip-casting lifting hole is set, wherein, slip-casting lifting hole is along the spacing of line direction
2m, horizontal direction spacing is 1.5m, and slip-casting lifting hole internal diameter is 30mm, and slip-casting lifting hole depth is mixed to ballastless track structure supporting course
The solidifying following about 10cm positions of soil.
(3)Slip-casting lifting operation is carried out using above-mentioned slip-casting lifting material at injected hole, by non-fragment orbit solid concrete roabed
And superstructure lifting 8mm or so.
(4)With reference to ballastless track structure feature and design correction amount, carry out center line rectify a deviation pushing tow point setting, pushing tow point with
The spacing of 1.5 m is arranged at ballastless track structure side along line direction.
(5)The thrustor for be made up of jack, power transmission steelframe, power transmission steel plate, adjustment backing plate and counterforce device is pacified
Each pushing tow point of dress, wherein counterforce device correspondence is arranged.
(6)Correction operation is proceeded by from side-play amount maximum, after this pushing tow terminates, at new maximum offset again
It is secondary to carry out pushing tow operation, until non-fragment orbit line midline recovers to design load.
(7)After the correction of non-fragment orbit center line terminates, ballastless track structure is raised to using high polymer grouting lifting material
Design altitude, and non-fragment orbit cavity is filled up completely with resin mortar.
(8)Construction is checked the linear data of non-fragment orbit after terminating, the reality of circuit correction section 1# to 40# tracks
Border correction amount and actual Uplifting amount are shown in Table 4.
The actual correction amount and actual rising height of curved section 1# to the 40# tracks of table 4
Track is numbered |
Actual correction amount(mm)* |
Actual Uplifting amount(mm) |
Track is numbered |
Actual correction amount(mm)* |
Actual Uplifting amount(mm) |
1# |
-6 |
18 |
21# |
-16 |
24 |
2# |
-7 |
19 |
22# |
-15 |
24 |
3# |
-8 |
19 |
23# |
-15 |
23 |
4# |
-9 |
19 |
24# |
-15 |
23 |
5# |
-10 |
20 |
25# |
-15 |
22 |
6# |
-11 |
21 |
26# |
-14 |
21 |
7# |
-12 |
21 |
27# |
-14 |
20 |
8# |
-12 |
21 |
28# |
-14 |
19 |
9# |
-13 |
21 |
29# |
-14 |
18 |
10# |
-13 |
22 |
30# |
-13 |
17 |
11# |
-14 |
22 |
31# |
-12 |
16 |
12# |
-14 |
23 |
32# |
-11 |
15 |
13# |
-14 |
23 |
33# |
-10 |
15 |
14# |
-15 |
23 |
34# |
-9 |
15 |
15# |
-15 |
24 |
35# |
-9 |
14 |
16# |
-15 |
24 |
36# |
-9 |
13 |
17# |
-15 |
24 |
37# |
-9 |
12 |
18# |
-16 |
24 |
38# |
-8 |
11 |
19# |
-16 |
25 |
39# |
-7 |
10 |
20# |
-16 |
25 |
40# |
-6 |
10 |
* on the occasion of for circuit lateral offset, negative value is to circuit offset inboard
Described non-fragment orbit center line method for correcting error, can exist the control of high-speed railway subgrade ballastless track structure center line correction precision
Within 1mm, and the setting requirements of counterforce device are greatly reduced.
The above-mentioned description to embodiment is for ease of those skilled in the art it will be appreciated that and the application present invention.
Person skilled in the art obviously can easily make various modifications to these embodiments, and described herein general
Principle is applied in other embodiment without by performing creative labour.Therefore, the invention is not restricted to embodiment here, this
Art personnel announcement of the invention, the improvement made for the present invention and modification all should be in protection models of the invention
Within enclosing.