CN103206066A - Construction method of laminated suspension gypsum plaster board combinational suspended ceiling - Google Patents

Construction method of laminated suspension gypsum plaster board combinational suspended ceiling Download PDF

Info

Publication number
CN103206066A
CN103206066A CN2013101652671A CN201310165267A CN103206066A CN 103206066 A CN103206066 A CN 103206066A CN 2013101652671 A CN2013101652671 A CN 2013101652671A CN 201310165267 A CN201310165267 A CN 201310165267A CN 103206066 A CN103206066 A CN 103206066A
Authority
CN
China
Prior art keywords
coating
thistle board
self
tapping screw
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101652671A
Other languages
Chinese (zh)
Inventor
秦国华
宁儒华
张雯
朱本志
刘桂霞
马政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd
Original Assignee
INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd filed Critical INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd
Priority to CN2013101652671A priority Critical patent/CN103206066A/en
Publication of CN103206066A publication Critical patent/CN103206066A/en
Pending legal-status Critical Current

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention relates to a construction method of a laminated suspension gypsum plaster board combinational suspended ceiling. The method comprises the steps of (1) leveling and snapping lines; (2) installing a hanger rod and a main keel; (3) installing a side keel, a secondary keel and a cross-brace keel; (4) installing a first layer of gypsum plaster board; (5) squeegeeing, attaching a bandage, locally applying the putty, and painting an upper layer; (6) installing a second layer of gypsum plaster board; (7) carrying out dot grooming on the antirust paint; (8) squeegeeing, attaching the bandage and locally leveling the putty; (9) fully applying the putty for the first time; (10) fully applying the putty for the second time; (11) polishing; (12) painting a bottom layer; (13) painting a middle layer; and (14) painting a surface layer.

Description

A kind of folded level hangs the job practices of Thistle board combination furred ceiling
Technical field
The present invention relates to building field.
Background technology
Along with the further raising of China's rapid economy development and living standards of the people, the market demand of senior building is increasing, and high-grade block of flats, office premises, star hotel etc. emerge in an endless stream.The work more comfortable in order to build, hommization more of this type of building, living environment, the higher and inner function of use of decoration standard is complete, has satisfied the requirements at the higher level of people to work, living environment and function of use to greatest extent.But for senior building, the division of each functional region strictness, for code requirement and the best visual effect that satisfies environmental functional, the designer uses the smallpox furred ceiling of a large amount of folded levels, stage construction, various material combination, modern design, makes the furred ceiling engineering become a diversification, complex process, many, the loaded down with trivial details the work items of working of the repetition scope of operation.
Lightgage steel joist Thistle board furred ceiling is because low, the easy moulding of its cost, environmental protection, fireproof performance are good, be widely used in the indoor decoration furred ceiling engineering, the moulding of all kinds of large-scale frock smallpox is complicated and changeable, design all to meet its environmental functional, the sound reflection function in corresponding space, and corresponding light is configured to reach the most perfect design effect.Visually stereovision is strong owing to a folded level smallpox gives, and can reach the effectively sound function that subtracts, so in big more employings of public space of the amount of assembling a crowd such as large conference room, banquet hall, multi function halls.But multilayer keel structure and stage construction operation repeatedly; can not effectively shorten the number of working processes; the per pass inter process interval is longer; and next procedure destroys the scope of operation of last process through regular meeting; repeat the stained patch work repeatedly of bringing in a large number; workmanship is relatively poor, and it is serious manually to reach waste of material, causes the cost cost that raises up obviously to increase.
Need to strengthen technological innovation in work progress, take new technology, rationally arrange operation, avoid artificial and waste of material, better control cost, the inventor regroups technological process at this situation, and the management means of combined innovation, sums up and forms the method.
Summary of the invention
Shortcoming at the prior art existence, the invention provides the job practices that a kind of new folded level hangs Thistle board combination furred ceiling, take the operation simultaneously of son subitem stage construction Split Method, last layering stack assembling is once finished, effectively shorten construction period, guaranteed workmanship, also obviously reduced construction cost simultaneously.
The characteristics of the method for the invention and advantage are arrangement and technical management are unified in order, rationalized to each operation, save time and reduce cost.
The method of the invention is applicable to the folded level Thistle board combination furred ceiling engineering construction of all kinds of buildings.
The method of the invention may further comprise the steps: (1) levelling, snap the line; (2) suspension rod and main joist are installed; (3) limit, inferior, stull keel are installed; (4) the first floor Thistle board is installed; (5) squeegee, paste bandage, local Puttying, upper layer coating; (6) second layer Thistle board is installed; (7) brush rustproof paint; (8) squeegee, paste bandage, local putty levelling; (9) the full Puttying of first pass; (10) second times full Puttying; (11) polishing; (12) subbing; (13) middle coating intermediate; (14) investment precoat.
Especially, the concrete technology of each step comprises:
(1) levelling, snap the line
According to the absolute altitude control point that the scene provides, press each regional absolute altitude of construction drawing, eject the absolute altitude control line at metope, cylinder end face, instruments such as level gauge are adopted in levelling, require horizon, absolute altitude unanimity, accurate.
(2) suspension rod and main joist are installed
1, suspension rod is installed:
In the cross hairs place punching of having reserved, the degree of depth 60-70mm in hole determines the length of suspension rod and suspension rod is installed that expansion tube must not exceed flooring, and packing ring is arranged behind the nut according to the drop of folded level furred ceiling with jump bit, and nut must be tightened.The suspension rod termination protruded length that installs is not less than 3mm, is connected with hanging piece behind the mantle fiber of lower end, when length of boom must arrange anti-support during greater than 1.5 meters.
2, main joist is installed:
With suspender member main joist is installed, tighten the screws, the joint of adjacent main joist should stagger, and answers arch camber (room short span 1/200) simultaneously.The termination is in wall 300mm.Main joist is installed the main joist of first floor base plate furred ceiling at first is installed, reserve the main joist of staggered floor part.
(3) limit, inferior, stull keel are installed
According to playing good position in advance, pass through the special-shaped part of folded level successively, install successively from high in the end, secondary joist and keelson junction, the two-sided 20mm of cutting mouth is located for 90 ° in the secondary joist termination, and outwards rolls over 90 °, fix (forbid to use gas nail fixing) with rivet for three in the time of fixedly, for access hole, keel corresponding increase keel are simultaneously being installed at the position of last manhole ventilation opening, when running into large-scale furred ceiling, carry out built-in fitting in advance.After keel are installed, the suspension rod verticality is adjusted.Because of the equipment occupation space position, during suspension rod spacing>1200mm, should adjust and additional suspension rod.Channel planeness, camber (arranging at the short 1/200mm that strides according to span control) are adjusted in backguy, with pliers the secondary joist suspension member are clamped.After main joist of suspended ceiling, secondary joist and reserved opening edge sealing keel installed, backguy (should draw steel wire when room-sized is big) checked the secondary joist spacing and plays camber, reserved opening position, after keel spacing, camber are adjusted, with pliers the secondary joist suspension member is clamped.
(4) the first floor Thistle board is installed
Pass through successively according to field condition, middle successively to fixing all around from Thistle board with self-tapping screw from high in the end, should stay 3~5mm between the gypsum plank, the self-tapping screw top will be sunk to about paper 1mm, the self-tapping screw spacing is answered≤20mm, Thistle board is wanted all around when mounted, the corresponding fissure of displacement is installed up and down, avoids the later stage cracking.
(5) squeegee, paste bandage, local levelling processing
Do antirust processing in the self-tapping screw corresponding position after installing the first floor Thistle board, with the filleting gypsum self-tapping screw hole for nailing of squeegeeing, paste at all seam crossings with 5mm kraft or corresponding anti-cracking material.At needs the foundation slab part Puttying of second layer Thistle board exposed parts is installed with putty, and is polished flat and looks for, gypsum plank and metope junction will be pasted behind the kraft in Puttying, after the levelling of polishing, and last respective face coating.
Attention: after mainly avoiding the intact gypsum plank of multilayer moulding gypsum furred ceiling once mounting, out-of-flatness is handled in bottom part gypsum plank difficult extension putty or corner.
(6) second layer Thistle board is installed
Pass through successively according to field condition, middle successively to fixing all around from Thistle board with self-tapping screw from high in the end, should stay 3~5mm between the gypsum plank, the self-tapping screw top will be sunk to about paper 1mm, the self-tapping screw spacing is answered≤20mm, Thistle board is wanted all around when mounted, the corresponding fissure of displacement is installed up and down, avoids the later stage cracking.
(7) brush rustproof paint
After Thistle board installed, self-tapping screw should carry out antirust processing (rustproof paint preferably adopts silver gray), and uses the putty levelling.
(8) squeegee, paste bandage, local putty levelling
Do antirust processing in the self-tapping screw corresponding position after installing second layer Thistle board, with the filleting gypsum self-tapping screw hole for nailing of squeegeeing, paste with all seam crossings of 5mm kraft or corresponding anti-cracking material.
(9) the full Puttying of first pass
1, all covering with paint positions all should completely be scraped, and metope is horizontal to be scraped, and end face is vertical with available light;
2, scrape as far as possible thin, must not leak and scrape; Joint must not stay stranding.
(10) second times full Puttying
All are covered with paint, lacquer, colour wash, etc. the position and all should completely scrape, and metope is perpendicular to be scraped, and end face is parallel with available light.
(11) polishing
1, polish flat, smooth; Clean out floating dust with row brush;
2, check that the external corner Founder is not more than 2mm, straightness accuracy, flatness 2mm.
(12) subbing
Construction should be carried out at drying, cleaning, firm laminar surface, sprays one time, and coating needs evenly, must not holiday.
(13) middle coating intermediate
As finding to have the out-of-flatness part, mend plain grinding light with putty before the brushing first pass middle coating intermediate.Coating is used portable electric stirring rifle before use and is stirred.Bigger as denseness, can suitably add the clear water dilution, but each amount of water needs unanimity, must not rare thick differing.Pour coating into pallet then, with coating roller libation at an ancient wedding ceremony material brushing first pass.Roller should laterally be brushed, and then longitudinal rolling, and coating is caught up with out, and is coated with flat.Roller coating is generally from top to bottom in proper order, and from left to right, back far away is near earlier, big face behind first corner corner angle, the facet.The requirement thickness is even, prevents that settling off stream from weighing down.Roller is coated with less than the inner corner trim place is arranged, and needs to replenish with hairbrush, must not holiday.To reject the roller hair of being stained with on the wall at any time.One face wall will accomplish without any letup.Avoid connecing raft brush mark overlapping phenomenon, stain and in time to clean with clear water to the coating at other positions.After the construction of first pass middle coating intermediate, generally need more than the dry 4H, just can descend road polishing operation.As wet weather, answer proper extension blanking time.Then, polish with fine sandpaper, firmly want light during polishing and spare, and must not worn out coating, mill with the surface cleaning totally; Second time middle level is coated with that to produce brush identical with first pass, but do not repolish.After the brushing, should reach the requirement of the senior swabbing of general emulsion paint; (if the dark brush that can not carry out this layer well of front putty and coating bottom layer treatment)
(14) resin emulsion paint surface layer spraying
Because basic unit's material, tooth phase, alkalescence, degree of drying difference should be tried spray at local metope in advance, with the compatible situation of definite basic unit and coating, and determine suitable coating weight simultaneously; Emulsion paint coating will fully shake container before use, and it is fully mixed, and opens container then, fully stirs with waddy; During spraying, mouth should remain vertical with Decorative watch (especially at the inner corner trim place), and distance is about 0.3-0.5M (adjusting according to finishing face size), and nozzle exit pressure is pushed ahead for the 0.2-0.3MM2 spray gun is zigzag, and horizontal vertical intersection is carried out.Spray gun moves wants the balance coating weight to want consistent, must not the time stopping time move, bound forward, to avoid windrow, sagging or leak the spray phenomenon; For improving spray efficiency and quality, the spraying order should be pacified: metope position → post position → pre-facial position → door and window position, this order should be grasped flexibly, blocks again not increase weight and do not influence completed facing to be as the criterion.
The benefit advantage of the method for the invention is:
(1) this method simple science of constructing, speed of application is fast, can satisfy the needs of duration anxiety.
(2) by rationally arranging operation, avoid waste of material, saved cost of materials; Owing to adopt the operation simultaneously of son subitem stage construction Split Method, avoid crossed construction, make the every square meter of general similar engineering reduce by 0.4 work day, save labour cost greatly.By problem innovation, improved my company's construction ability on the one hand, for carrying out engineering of the same type, other construction enterprises from now on provide experience.On the other hand, by high-quality, finish construction task efficiently, obtained Party A, management certainly and favorable comment.This achievement has bigger reference and directive function to similar engineering, and higher application and popularization value is arranged.
The specific embodiment
1, material and equipment
1.1 material
1, main material:
1) U series lightgage steel joist (containing accessory): keel adopt the supporting zinc-plated keel of former factory product, meet National Standard lightgage steel joist for building " (GB11981-89), the carrying keel are not less than requirement, and the double side zinc coating amount is no less than 120g/m 2The furred ceiling lightgage steel joist divides by supporting capacity to be gone up people's keel and does not descend people's keel.By the purposes branch big keel, middle keel, carinula are arranged.By the series classification UC38 is arranged, UC50, three series of UC60, these three series are followed successively by light-duty, medium-sized and heavy keel.
A. light-duty series: can not bear people's load.
B. medium-sized series: can bear the accidental people's load of going up, can lay simple and easy check packway thereon.
C. heavy series: can bear the people and overhaul the 80kg point load and can lay permanent check packway thereon, the packway of specific (special) requirements is arranged, as above people's number of times is frequent, or overweight load is arranged, and then need be hung packway on top board voluntarily, separate with ceiling system.
2) Thistle board (9.5mm or 12mm are thick)
2, auxilliary material:
Zinc-plated Φ 8 harness cord bars, rustproof paint, filleting gypsum, water proof putty, emulsion paint, 25mm self-tapping screw, seam paper tape, white glue with vinyl, sand paper.
1.2 plant
1.2.1
Construction equipment: hand riveter, electronic self-tapping drill, dc welding machine, toothless saw, hand plane, Churn drill, perching knife, breaker, scraper plate, pencil, air compressor, spray gun etc.
1.2.2
Detecting instrument: level gauge, the horizontal guiding ruler of 2m, clearance gauge, invar tape, vertical, vertical etc.
2, quality control
2.1 quality control standard
Pressing GB-50210-2001 6.2.7 to the 6.3.11 bar carries out.
2.2 key Quality Control
2.2.1.
The concealed work quality of furred ceiling should meet following pertinent regulations.
2.2.2.
About when the furred ceiling Thistle board is installed, about want the fissure of displacement to fix, avoid whole cracking of later stage.
2.2.3.
Can not install the back in the gypsum plank front portion and agree to carry out the surface layer processing, avoid the later stage that moulding segment space surface layer operational difficulties is arranged.
2.2.4.
When large-scale pendent lamp is arranged built-in fitting is installed in advance, is avoided the later stage load-bearing not enough.
3, safety measure
3.1 the project director must bear the safety responsibility of job site, and signing " safety responsibility book " comprehensively.
3.2 strictly observe relevant labor safety laws and regulations requirement, strengthen Safety Management and safety education, the every safety in production rules and regulations of strict execution.
3.3 the scaffold building of furred ceiling engineering should meet the construction safety standard, must not surpass specified load.
3.4 construction teams and groups must accept once safety education in regular every month, the raising awareness of safety,, must adhere to the fire safety training activity, adhere to that dangerous operations such as welding, paint carry out the fire safety system of confiding a technological secret, and in time eliminate disaster hidden-trouble
3.5 the construction layer scaffold must be by the operation of can putting on the shelf after the acceptance(check).
3.6 the constructor should be equipped with safety helmet, safety belt, kit bag, prevents falling of personnel and object.
3.7 the construction equipment that the installation furred ceiling is used must carry out the strictness check before use.
4, environmental practice
4.1 set up corresponding construction environment administration of health mechanism, in work progress, strictly observe law, the rules of the relevant environmental protection that country and local government issue, reinforcement is to control and the improvement of engineering material, equipment, production rubbish.
4.2 environment-friendly materials are selected in strict raw-material buying.At first select nontoxic, harmless, free of contamination material, raw-material buying must be carried out in strict accordance with the relevant execute file of ISO9001 and ISO14O01 in the construction, and the hazardous substances of control material is in prescribed limit.
4.3 rationally the scheduling job time, avoid carrying out cutting operation with night at noon, construction noise be reduced to a minimum to surrounding environment influence.Should select to use low noise equipment and carry out closure construction adopt an effective measure control noise, airborne dust, waste discharge in construction boundary noise-sensitive zone.
4.4 the workman of Sand paper for polishing and spraying emulsion paint should wear mouth mask, wears caftan, also should be with gloves, prevents from sucking dust, emulsion paint.

Claims (2)

1. a folded level hangs the job practices that Thistle board makes up furred ceiling, and described side comprises step: (1) levelling, snap the line; (2) suspension rod and main joist are installed; (3) limit, inferior, stull keel are installed; (4) the first floor Thistle board is installed; (5) squeegee, paste bandage, local Puttying, upper layer coating; (6) second layer Thistle board is installed; (7) brush rustproof paint; (8) squeegee, paste bandage, local putty levelling; (9) the full Puttying of first pass; (10) second times full Puttying; (11) polishing; (12) subbing; (13) middle coating intermediate; (14) investment precoat.
2. according to the process of claim 1 wherein that each step is specially:
(1) levelling, snap the line
According to the absolute altitude control point that the scene provides, press each regional absolute altitude of construction drawing, eject the absolute altitude control line at metope, cylinder end face, level gauge is adopted in levelling, requires horizon, absolute altitude unanimity, accurate;
(2) suspension rod and main joist are installed
1) suspension rod is installed:
Punch at the cross hairs place that is reserving with jump bit, the degree of depth 60-70mm in hole, determine the length of suspension rod and suspension rod is installed according to the drop of folded level furred ceiling, expansion tube must not exceed flooring, packing ring is arranged behind the nut, and nut must be tightened, and the suspension rod termination protruded length that installs is not less than 3mm, be connected with hanging piece behind the mantle fiber of lower end, when length of boom must arrange anti-support during greater than 1.5 meters;
2) main joist is installed:
With suspender member main joist is installed, tighten the screws, the joint of adjacent main joist should stagger, and answers arch camber simultaneously, and the main joist that main joist is at first installed first floor base plate furred ceiling is installed in the termination in wall 300mm, reserve the main joist of staggered floor part;
(3) limit, inferior, stull keel are installed
According to playing good position in advance, pass through the special-shaped part of folded level successively, install successively from high in the end, secondary joist and keelson junction, the two-sided 20mm of cutting mouth is located for 90 ° in the secondary joist termination, and outwards rolls over 90 °, fix with rivet for three in the time of fixedly, forbid to use the gas nail fixing, for access hole, the position of last manhole ventilation opening, keel corresponding increase keel simultaneously are being installed, when running into large-scale furred ceiling, carry out built-in fitting in advance, after keel are installed, the suspension rod verticality is adjusted, because of the equipment occupation space position, during suspension rod spacing>1200mm, should adjust and additional suspension rod, the channel planeness is adjusted in backguy, camber clamps the secondary joist suspension member with pliers.After main joist of suspended ceiling, secondary joist and reserved opening edge sealing keel installed, backguy checked the secondary joist spacing and plays camber, reserved opening position, after keel spacing, camber are adjusted, with pliers the secondary joist suspension member is clamped;
(4) the first floor Thistle board is installed
Pass through successively according to field condition, middle successively to fixing all around from Thistle board with self-tapping screw from high in the end, should stay 3~5mm between the gypsum plank, the self-tapping screw top will be sunk to about paper 1mm, the self-tapping screw spacing is answered<20mm, Thistle board is wanted all around when mounted, the corresponding fissure of displacement is installed up and down, avoids the later stage cracking;
(5) squeegee, paste bandage, local levelling processing
Do antirust processing in the self-tapping screw corresponding position after installing the first floor Thistle board, with the filleting gypsum self-tapping screw hole for nailing of squeegeeing, paste at all seam crossings with 5mm kraft or corresponding anti-cracking material, the foundation slab part Puttying of second layer Thistle board exposed parts is installed at needs with putty, and be polished flat and look for, gypsum plank and metope junction will be pasted behind the kraft in Puttying, after the polishing levelling, and last respective face coating;
(6) second layer Thistle board is installed
Pass through successively according to field condition, middle successively to fixing all around from Thistle board with self-tapping screw from high in the end, should stay 3~5mm between the gypsum plank, the self-tapping screw top will be sunk to about paper 1mm, the self-tapping screw spacing is answered≤20mm, Thistle board is wanted all around when mounted, the corresponding fissure of displacement is installed up and down, avoids the later stage cracking;
(7) brush rustproof paint
After Thistle board installed, self-tapping screw should carry out antirust processing, and used the putty levelling;
(8) squeegee, paste bandage, local putty levelling
Do antirust processing in the self-tapping screw corresponding position after installing second layer Thistle board, with the filleting gypsum self-tapping screw hole for nailing of squeegeeing, paste with all seam crossings of 5mm kraft or corresponding anti-cracking material;
(9) the full Puttying of first pass
1) all covering with paint positions all should completely be scraped, and metope is horizontal to be scraped, and end face is vertical with available light;
2) scrape as far as possible thin, must not leak and scrape; Joint must not stay stranding;
(10) second times full Puttying
All are covered with paint, lacquer, colour wash, etc. the position and all should completely scrape, and metope is perpendicular to be scraped, and end face is parallel with available light;
(11) polishing
1) polish flat, smooth; Clean out floating dust with row brush;
2) check that the external corner Founder is not more than 2mm, straightness accuracy, flatness 2mm;
(12) subbing
Carry out at drying, cleaning, firm laminar surface, spray one time, coating needs evenly, must not holiday;
(13) middle coating intermediate
As finding to have the out-of-flatness part, mend plain grinding light with putty before the brushing first pass middle coating intermediate.Coating is used portable electric stirring rifle before use and is stirred, and pours coating into pallet then, with coating roller libation at an ancient wedding ceremony material brushing first pass, roller should laterally be brushed, and then longitudinal rolling, and coating is caught up with out, be coated with flatly, roller coating is generally from top to bottom in proper order, from left to right, back far away is near earlier, and big face requires thickness even behind first corner corner angle, the facet, prevent that settling off stream from weighing down, roller is coated with less than the inner corner trim place is arranged, and needs to replenish with hairbrush, must not holiday.To reject the roller hair of being stained with on the wall at any time, one face wall will accomplish without any letup, avoid connecing raft brush mark overlapping phenomenon, stain and in time to clean with clear water to the coating at other positions, after the construction of first pass middle coating intermediate, need drying more than 4 hours, just can descend road polishing operation, then, polish with fine sandpaper, firmly want light during polishing and spare, and must not worn out coating, mill with the surface cleaning totally, second time middle level is coated with product and brushes identical with first pass, but do not repolish, after the brushing, should reach the requirement of the senior swabbing of general emulsion paint;
(14) resin emulsion paint surface layer spraying
Because basic unit's material, tooth phase, alkalescence, degree of drying difference should be tried spray at local metope in advance, with the compatible situation of definite basic unit and coating, and determine suitable coating weight simultaneously; Emulsion paint coating will fully shake container before use, and it is fully mixed, and opens container then, fully stirs with waddy; During spraying, mouth should remain vertical with Decorative watch, and distance is about 0.3-0.5M, nozzle exit pressure is 0.2-0.3N/M2, and spray gun is zigzag pushes ahead, and horizontal vertical intersection is carried out, spray gun moves wants the balance coating weight to want consistent, must not the time stopping time move, bound forward, to avoid windrow, sagging or leak the spray phenomenon, spraying is in proper order: the metope position, the post position, pre-facial position, door and window position.
CN2013101652671A 2013-05-08 2013-05-08 Construction method of laminated suspension gypsum plaster board combinational suspended ceiling Pending CN103206066A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101652671A CN103206066A (en) 2013-05-08 2013-05-08 Construction method of laminated suspension gypsum plaster board combinational suspended ceiling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101652671A CN103206066A (en) 2013-05-08 2013-05-08 Construction method of laminated suspension gypsum plaster board combinational suspended ceiling

Publications (1)

Publication Number Publication Date
CN103206066A true CN103206066A (en) 2013-07-17

Family

ID=48753456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101652671A Pending CN103206066A (en) 2013-05-08 2013-05-08 Construction method of laminated suspension gypsum plaster board combinational suspended ceiling

Country Status (1)

Country Link
CN (1) CN103206066A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652746A (en) * 2015-01-08 2015-05-27 钟利伦 Gypsum plaster board and manufacturing method thereof
CN106013582A (en) * 2016-07-13 2016-10-12 深圳市奇信建设集团股份有限公司 Construction method for gypsum plaster board ceiling
CN107268793A (en) * 2017-07-12 2017-10-20 北京城建深港建筑装饰工程有限公司 A kind of folded level type sets of brackets on top of the columns aluminium sheet connector system and its construction method
CN108170917A (en) * 2017-12-20 2018-06-15 巧夺天宫(深圳)科技有限公司 A kind of furred ceiling threedimensional model drawing system, method, terminal and medium
CN108952179A (en) * 2018-07-16 2018-12-07 深圳市中建南方建设集团有限公司 A kind of bumps mirror surface wall of the moulding and construction method of smallpox
CN108999404A (en) * 2018-09-30 2018-12-14 中建八局装饰工程有限公司 Construction method for grid ceiling in large space
CN112012392A (en) * 2020-08-31 2020-12-01 浙江世润建创科技发展有限公司 Light steel keel gypsum plaster slab suspended ceiling and construction method
CN112502344A (en) * 2020-09-23 2021-03-16 上海美家美沪装饰科技有限公司 Light steel keel gypsum board suspended ceiling construction process
CN112726931A (en) * 2021-01-26 2021-04-30 武汉市华天仑建筑装饰工程有限公司 Green construction method of light steel keel gypsum plasterboard
CN113150584A (en) * 2021-03-22 2021-07-23 境洁环保科技(上海)有限公司 Putty-free direct-coating top paint and preparation method and construction method thereof
CN114704116A (en) * 2022-04-20 2022-07-05 上海天补材料科技有限公司 GRC decorative line repairing and reinforcing method
CN115434471A (en) * 2022-08-19 2022-12-06 鑫源建设科技有限责任公司 Light steel keel gypsum board suspended ceiling construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040213003A1 (en) * 2003-04-23 2004-10-28 Bruce Lauderdale Suspended ceiling lighting system incorporating T-bar component
CN202227559U (en) * 2011-07-22 2012-05-23 中建七局第四建筑有限公司 Edging device for plasterboard furred ceiling

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040213003A1 (en) * 2003-04-23 2004-10-28 Bruce Lauderdale Suspended ceiling lighting system incorporating T-bar component
CN202227559U (en) * 2011-07-22 2012-05-23 中建七局第四建筑有限公司 Edging device for plasterboard furred ceiling

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
XYKE66887799: "新工法.doc1(网址:http://wenku.baidu.com/link?url=kfoU_p83vLwaXjJI0LQBHE_nBnHAZGCmarvE8C8IFAc5AmT2iu4Tq5jkxg6qpIL0Xl8wJgKTBSwc6tW0ewa0jQBiVYHhD4C1Ia8YtjcejlC)", 《百度文库》, 13 September 2012 (2012-09-13), pages 4 - 8 *
刘念华: "《建筑装饰施工技术》", 31 December 2002, article "轻钢龙骨及铝合金龙骨吊顶施工工艺", pages: 34-41 *
刘良军等: "纸面石膏板顶棚质量问题的分析与控制", 《石家庄铁路职业技术学院学报》, vol. 4, 1 September 2005 (2005-09-01), pages 40 - 43 *
庄兴等: "混凝土墙面、天花直接煽灰找平的施工方法", 《广东建材》, no. 4, 13 August 2007 (2007-08-13) *
李冰 等: "《装饰金属工》", 31 December 2002, article "第三单元 石膏板及其它饰面板的安装", pages: 185-190 *
苏晓爽: "装饰施工中轻钢龙骨石膏板吊顶的质量控制", 《中华建设》, no. 2, 28 February 2013 (2013-02-28), pages 140 - 141 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652746A (en) * 2015-01-08 2015-05-27 钟利伦 Gypsum plaster board and manufacturing method thereof
CN104652746B (en) * 2015-01-08 2017-04-12 钟利伦 Manufacturing method for gypsum plaster board
CN106013582A (en) * 2016-07-13 2016-10-12 深圳市奇信建设集团股份有限公司 Construction method for gypsum plaster board ceiling
CN107268793A (en) * 2017-07-12 2017-10-20 北京城建深港建筑装饰工程有限公司 A kind of folded level type sets of brackets on top of the columns aluminium sheet connector system and its construction method
CN108170917A (en) * 2017-12-20 2018-06-15 巧夺天宫(深圳)科技有限公司 A kind of furred ceiling threedimensional model drawing system, method, terminal and medium
CN108952179A (en) * 2018-07-16 2018-12-07 深圳市中建南方建设集团有限公司 A kind of bumps mirror surface wall of the moulding and construction method of smallpox
CN108999404A (en) * 2018-09-30 2018-12-14 中建八局装饰工程有限公司 Construction method for grid ceiling in large space
CN112012392A (en) * 2020-08-31 2020-12-01 浙江世润建创科技发展有限公司 Light steel keel gypsum plaster slab suspended ceiling and construction method
CN112502344A (en) * 2020-09-23 2021-03-16 上海美家美沪装饰科技有限公司 Light steel keel gypsum board suspended ceiling construction process
CN112726931A (en) * 2021-01-26 2021-04-30 武汉市华天仑建筑装饰工程有限公司 Green construction method of light steel keel gypsum plasterboard
CN113150584A (en) * 2021-03-22 2021-07-23 境洁环保科技(上海)有限公司 Putty-free direct-coating top paint and preparation method and construction method thereof
CN113150584B (en) * 2021-03-22 2022-06-17 境洁环保科技(上海)有限公司 Putty-free direct-coating top paint and preparation method and construction method thereof
CN114704116A (en) * 2022-04-20 2022-07-05 上海天补材料科技有限公司 GRC decorative line repairing and reinforcing method
CN115434471A (en) * 2022-08-19 2022-12-06 鑫源建设科技有限责任公司 Light steel keel gypsum board suspended ceiling construction method

Similar Documents

Publication Publication Date Title
CN103206066A (en) Construction method of laminated suspension gypsum plaster board combinational suspended ceiling
CN105569251B (en) Device for split-level ceiling and installation method
CN103375000B (en) A kind of water-soluble metal fluorocarbon coatings is coated with the construction technology on plucking surface in elasticity
CN109797920A (en) A kind of interior covering with paint construction method
CN104110112B (en) Building wall decoration mortar construction technology
CN202090569U (en) Plastering screed strip template
CN103184785A (en) Paint construction process
CN110219371A (en) Assembled furred ceiling and metope Demountable
CN103899072A (en) Hanging member for wet hanging of stone or tiles and wet hanging method
CN203905374U (en) Hanging piece for hanging stones or tiles in wet hanging mode
CN201588390U (en) Screeding die plate for plastering
CN113585594A (en) Construction method of large-span arc-shaped suspended ceiling
CN111576716B (en) Assembly type metal ceiling and installation method thereof
CN210659081U (en) Mounting system of building indoor wall assembled veneer
CN201908415U (en) Wall decorative board layer structure
CN104372877B (en) Tall and big vertical stone material Water curtain wall construction
CN207110334U (en) A kind of magnetic attracting quick-mounting wall board structure renovated for metope with decorating
CN207988307U (en) Facing is in the plaster tablet suspended ceiling structure of metal effect
CN209891611U (en) Cylinder gypsum punching rib structure
US5157884A (en) Solely wall mounted drop ceiling structure
CN204040284U (en) A kind of stone material composite honeycomb board installation of ceiling system
NL1044297B1 (en) Reusable wall tile and method for manufacturing a corresponding reusable wall tile
Everett et al. Drywall joint finishing: productivity and ergonomics
CN205712662U (en) A kind of abnormal curved surface ceiling structure
GB2584718A (en) Refurbishment method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20130717

RJ01 Rejection of invention patent application after publication