CN103177402A CN2013101196397A CN201310119639A CN103177402A CN 103177402 A CN103177402 A CN 103177402A CN 2013101196397 A CN2013101196397 A CN 2013101196397A CN 201310119639 A CN201310119639 A CN 201310119639A CN 103177402 A CN103177402 A CN 103177402A
Authority
CN
China
Prior art keywords
information
operator
equipment
operation order
order information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101196397A
Other languages
Chinese (zh)
Inventor
葛伟军
魏华明
王灿
彭家从
王骁
王猛
杨跃平
王鑫国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ninghai county power supply bureau
State Grid Corp of China SGCC
Zhejiang Electric Power Co
Ningbo Electric Power Bureau
Original Assignee
Ninghai county power supply bureau
State Grid Corp of China SGCC
Zhejiang Electric Power Co
Ningbo Electric Power Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ninghai county power supply bureau, State Grid Corp of China SGCC, Zhejiang Electric Power Co, Ningbo Electric Power Bureau filed Critical Ninghai county power supply bureau
Priority to CN2013101196397A priority Critical patent/CN103177402A/en
Publication of CN103177402A publication Critical patent/CN103177402A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a power dispatching error prevention method. The method comprises the steps of receiving equipment information and operation information of equipment, generating operation order information according to the equipment information, the operation information and operation regulations of a power distribution network, and executing an operational command of the operation order information executed by a first operator after receiving a permission order of a second operator. According to the method provided by the invention, at least two operators need to log in a system through different computers before the execution of the operation order, wherein the operational command of one operator only can be executed after the permission command of the other operator is received. According to the power dispatching error prevention method, the manner of executing the operational command of one operator after receiving the permission command of the other operator is used, so that the dispatching accidents caused by the staff negligence in the execution link are prevented. The invention also discloses a power dispatching error prevention device.

Description

A kind of power scheduling anti-misoperation method and device
Technical field
The present invention relates to the power technology field, relate in particular to a kind of power scheduling anti-misoperation method and device.
Background technology
Along with electrical network scale expanding day, administration equipment constantly increases, and power supply reliability requires more and more higher, makes the despatching work task day by day heavy, and safety responsibility is also great all the more.In electric system, along with county's key degree compass of competency enlarges, County Level Regional 110kV substation facilities jurisdiction is substantially transferred to each county and is transferred, after the regulation and control model of integration is implemented, the scheduling operation flow process is more numerous and diverse, in the power scheduling operation, if make out an invoice, examine or carry out the link personnel, carelessness is arranged slightly, just might cause the generation of mistuning degree accident, and then have influence on power grid security.Transfer to say to possess a cover and prevent that effectively the method and system of the generation of mistuning degree accident from seeming particularly urgent as the county, it has very important realistic meaning to the safe and stable operation that ensures electrical network.
Summary of the invention
In view of this, the invention provides a kind of power scheduling anti-misoperation method, in order to solve the generation of neglecting the scheduling accident that causes because carrying out the link personnel, the method comprises:
The facility information of receiving equipment, and the operation information of described equipment;
According to described facility information, described operation information and power distribution network working specification generating run ticket information;
After the allowance instruction that receives the second operator, carry out the operational order of the described operation order information of first operator's execution.
Preferably, in above-mentioned power scheduling anti-misoperation method, the facility information of described receiving equipment, and before the operation information of described equipment, also comprise:
The equipment that relates to during power scheduling is operated shows on screen with the form of electric network wiring scheme, select the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
Preferably, in above-mentioned power scheduling anti-misoperation method, after described allowance instruction receiving the second operator, after the operational order of the described operation order information that execution the first operator carries out, also comprise:
Identify the operation order information of having completed on described electric network wiring scheme, and show the operation order information of follow-up needs operation;
Go out executable operation order information with a kind of colour code, go out the operation order information that to carry out with the colour code that is different from described color.
Preferably, in above-mentioned power scheduling anti-misoperation method, described operation order information comprises a plurality of sub-information;
After described allowance instruction receiving the second operator, carry out the operational order of the described operation order information of first operator's execution, comprising:
After receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
Preferably, in above-mentioned power scheduling anti-misoperation method, described equipment comprises primary equipment, and/or, secondary device.
The embodiment of the present invention also provides a kind of power scheduling error-proof device, comprising:
Receiving element, for the facility information of receiving equipment, and the operation information of described equipment;
The operation order generation unit is used for according to described facility information, described operation information and power distribution network working specification generating run ticket information;
Performance element is used for after the allowance instruction that receives the second operator, carries out the operational order of the described operation order information of first operator's execution.
Preferably, in above-mentioned power scheduling error-proof device, described device also comprises:
Display unit shows on screen for the form of the equipment that the power scheduling operation is related to electric network wiring scheme, selects the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
Preferably, in above-mentioned power scheduling error-proof device, described device also comprises:
The first identify unit is used for identifying the operation order information of having completed on described electric network wiring scheme, and shows the operation order information of follow-up needs operation;
The second identify unit is used for going out executable operation order information with a kind of colour code, goes out the operation order information that can not carry out with the colour code that is different from described color.
Preferably, in above-mentioned power scheduling error-proof device, described operation order information comprises a plurality of sub-information;
Described performance element comprises:
Carry out subelement, after being used for receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
Preferably, in above-mentioned power scheduling error-proof device, described equipment comprises primary equipment, and/or, secondary device.
The method that this programme provides is before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
Description of drawings
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, the below will do to introduce simply to the accompanying drawing of required use in embodiment or description of the Prior Art, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain according to these accompanying drawings other accompanying drawing.
A kind of schematic flow sheet of the power scheduling anti-misoperation method that Fig. 1 provides for the embodiment of the present invention;
Another schematic flow sheet of the power scheduling anti-misoperation method that Fig. 2 provides for the embodiment of the present invention;
Another schematic flow sheet of the power scheduling anti-misoperation method that Fig. 3 provides for the embodiment of the present invention;
A kind of structural representation of the power scheduling error-proof device that Fig. 4 provides for the embodiment of the present invention;
Another structural representation of the power scheduling error-proof device that Fig. 5 provides for the embodiment of the present invention;
Another structural representation of the power scheduling error-proof device that Fig. 6 provides for the embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Based on the embodiment in the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that obtains under the creative work prerequisite.
Referring to Fig. 1, the embodiment of the present invention provides a kind of power scheduling anti-misoperation method, comprising:
S110: the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Reception need to be intended the information of equipment of ticket and the operation information of equipment operating, be that the operator selects to intend the primary equipment of ticket and/or secondary device and to the operation information of the said equipment operation, as selecting switch in primary equipment and the closed procedure of selector switch.
S120: according to facility information, operation information and power distribution network working specification generating run ticket information.
According to facility information, operation information and power distribution network working specification generating run ticket information; wherein; facility information comprises all exercisable primary equipment and secondary devices in power distribution network; all operations that circuit and equipment are carried out in operation information assignment electrical network, the standard that should follow when the power distribution network working specification refers to carry out some operation need to combine closely with real-time electric equipment operation situation and power network wiring mode, protection.
S130: after the allowance instruction that receives the second operator, carry out the operational order of the operation order information of first operator's execution.
Wherein, operation order information can comprise a plurality of operation paper money information, after the allowance instruction that receives the second operator, the operational order of carrying out the operation order information of first operator's execution can comprise: after the allowance instruction that receives the second operator, carry out the operational order of the operation paper money information of first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
Referring to Fig. 2, the embodiment of the present invention provides a kind of power scheduling anti-misoperation method, comprising:
S210: the equipment that relates to during power scheduling is operated shows on screen with the form of electric network wiring scheme, select the operation information of equipment needed thereby and equipment needed thereby on electric network wiring scheme.
For improve the operator work efficiency, during generating run ticket information, the equipment that relates in power scheduling can being operated shows on screen with the form of electric network wiring scheme, the operator is the operation information of selecting equipment needed thereby and equipment needed thereby directly perceived on electric network wiring scheme, and the directly perceived man-machine plan ticket of uniting can make the formation of operation order and examine fast.
S220: the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Reception need to be intended the information of equipment of ticket and the operation information of equipment operating, be that the operator selects to intend the primary equipment of ticket and/or secondary device and to the operation information of the said equipment operation, as selecting switch in primary equipment and the closed procedure of selector switch.
S230: according to facility information, operation information and power distribution network working specification generating run ticket information.
According to facility information, operation information and power distribution network working specification generating run ticket information; wherein; facility information comprises all exercisable primary equipment and secondary devices in power distribution network; all operations that circuit and equipment are carried out in operation information assignment electrical network, the standard that should follow when the power distribution network working specification refers to carry out some operation need to combine closely with real-time electric equipment operation situation and power network wiring mode, protection.
S240: after the allowance instruction that receives the second operator, carry out the operational order of the operation order information of first operator's execution.
Wherein, operation order information can comprise a plurality of operation paper money information, after the allowance instruction that receives the second operator, the operational order of carrying out the operation order information of first operator's execution can comprise: after the allowance instruction that receives the second operator, carry out the operational order of the operation paper money information of first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
Referring to Fig. 3, the embodiment of the present invention provides a kind of power scheduling anti-misoperation method, comprising:
S310: the equipment that relates to during power scheduling is operated shows on screen with the form of electric network wiring scheme, select the operation information of equipment needed thereby and equipment needed thereby on electric network wiring scheme.
For improving operator's work efficiency, during generating run ticket information, the equipment that relates in power scheduling can being operated shows on screen with the form of electric network wiring scheme, the operator is the operation information of selecting equipment needed thereby and equipment needed thereby directly perceived on electric network wiring scheme, and the directly perceived man-machine plan ticket of uniting can make the formation of operation order and examine fast.
S320: the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Reception need to be intended the information of equipment of ticket and the operation information of equipment operating, be that the operator selects to intend the primary equipment of ticket and/or secondary device and to the operation information of the said equipment operation, as selecting switch in primary equipment and the closed procedure of selector switch.
S330: according to facility information, operation information and power distribution network working specification generating run ticket information.
According to facility information, operation information and power distribution network working specification generating run ticket information; wherein; facility information comprises all exercisable primary equipment and secondary devices in power distribution network; all operations that circuit and equipment are carried out in operation information assignment electrical network, the standard that should follow when the power distribution network working specification refers to carry out some operation need to combine closely with real-time electric equipment operation situation and power network wiring mode, protection.
S340: after the allowance instruction that receives the second operator, carry out the operational order of the operation order information of first operator's execution.
Wherein, operation order information can comprise a plurality of operation paper money information, after the allowance instruction that receives the second operator, the operational order of carrying out the operation order information of first operator's execution can comprise: after the allowance instruction that receives the second operator, carry out the operational order of the operation paper money information of first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
S350: identify the operation order information of having completed on electric network wiring scheme, and show the operation order information of follow-up needs operation.
S360: go out executable operation order information with a kind of colour code, go out the operation order information that to carry out with the colour code that is different from above-mentioned color.
electric network wiring scheme is original state before operation, after each operational order is completed, identify the operation order information of having completed on electric network wiring scheme, and show the operation order information of follow-up needs operation, as making hook in " simulation change " hurdle of operation order, electric network wiring scheme can show the operation order information of rear five needs operation automatically after changing, go out executable operation order information with a kind of colour code, go out the operation order information that to carry out with the colour code that is different from described color, identify with green as executable operation order information, the operation order information that can not carry out marks with redness, so that the operator can see intuitively operating result and carry out fast follow-up operational order.
Provide a kind of power scheduling error-proof device referring to Fig. 4, the embodiment of the present invention, comprising:
Receiving element U110, for the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Operation order generation unit U120 is used for according to described facility information, described operation information and power distribution network working specification generating run ticket information.
Performance element U130 is used for after the allowance instruction that receives the second operator, carries out the operational order of the described operation order information of first operator's execution.
Wherein, described operation order information can comprise a plurality of sub-information, and described performance element can comprise:
Carry out subelement, after being used for receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
Provide a kind of power scheduling error-proof device referring to Fig. 5, the embodiment of the present invention, comprising:
Display unit U210 shows on screen for the form of the equipment that the power scheduling operation is related to electric network wiring scheme, selects the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
Receiving element U220, for the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Operation order generation unit U230 is used for according to described facility information, described operation information and power distribution network working specification generating run ticket information.
Performance element U240 is used for after the allowance instruction that receives the second operator, carries out the operational order of the described operation order information of first operator's execution.
Wherein, described operation order information can comprise a plurality of sub-information, and described performance element can comprise:
Carry out subelement, after being used for receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
Provide a kind of power scheduling error-proof device referring to Fig. 6, the embodiment of the present invention, comprising:
Display unit U310 shows on screen for the form of the equipment that the power scheduling operation is related to electric network wiring scheme, selects the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
Receiving element U320, for the facility information of receiving equipment, and the operation information of described equipment.
The said equipment comprises the primary equipment in the power scheduling operation; and/or, secondary device, wherein; primary equipment comprises switch, plug-in strip, main-transformer, bus, circuit, capacitor, pressure change, arc suppression coil, lists etc., and secondary device comprises relay protection, aut.eq., prepared auto restart etc.
Operation order generation unit U330 is used for according to described facility information, described operation information and power distribution network working specification generating run ticket information.
Performance element U340 is used for after the allowance instruction that receives the second operator, carries out the operational order of the described operation order information of first operator's execution.
Wherein, described operation order information can comprise a plurality of sub-information, and described performance element can comprise:
Carry out subelement, after being used for receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
Before operation order is carried out, at least need two operators by different computer login systems, wherein, after the operational order of carrying out one of them operator must receive another operator's allowance instruction, executable operations could be implemented, and that is to say, an operator must obtain another operator's allowance before carrying out each step operational order, if another operator disapproves this operation and carries out, this operator's operational order can't be carried out.The embodiment of the present invention is just carried out the mode of this operator operational order after by the allowance instruction that receives another operator, prevents the scheduling accident that causes because carrying out link personnel carelessness.
The first identify unit U350 is used for identifying the operation order information of having completed on described electric network wiring scheme, and shows the operation order information of follow-up needs operation;
The second identify unit U360 is used for going out executable operation order information with a kind of colour code, goes out the operation order information that can not carry out with the colour code that is different from described color.
In this instructions, each embodiment adopts the mode of going forward one by one to describe, and what each embodiment stressed is and the difference of other embodiment that between each embodiment, identical similar part is mutually referring to getting final product.For the disclosed device of embodiment, because it is corresponding with the disclosed method of embodiment, so description is fairly simple, relevant part partly illustrates referring to method and gets final product.
At last, also need to prove, in this article, relational terms such as first, second grade only is used for an entity or operation are separated with another entity or operational zone, and not necessarily requires or hint and have the relation of any this reality or sequentially between these entities or operation.And, term " comprises ", " comprising " or its any other variant are intended to contain comprising of nonexcludability, thereby make the process, method, article or the equipment that comprise a series of key elements not only comprise those key elements, but also comprise other key elements of clearly not listing, or also be included as the intrinsic key element of this process, method, article or equipment.In the situation that not more restrictions, the key element that is limited by statement " comprising ... ", and be not precluded within process, method, article or the equipment that comprises described key element and also have other identical element.
For the convenience of describing, be divided into various unit with function when describing above device and describe respectively.Certainly, can realize the function of each unit in same or a plurality of softwares and/or hardware when implementing the application.
To the above-mentioned explanation of the disclosed embodiments, make this area professional and technical personnel can realize or use the present invention.Multiple modification to these embodiment will be apparent concerning those skilled in the art, and General Principle as defined herein can be in the situation that do not break away from the spirit or scope of the present invention, realization in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (10)

1. a power scheduling anti-misoperation method, is characterized in that, comprising:
The facility information of receiving equipment, and the operation information of described equipment;
According to described facility information, described operation information and power distribution network working specification generating run ticket information;
After the allowance instruction that receives the second operator, carry out the operational order of the described operation order information of first operator's execution.
2. method according to claim 1, is characterized in that, the facility information of described receiving equipment, and before the operation information of described equipment, also comprise:
The equipment that relates to during power scheduling is operated shows on screen with the form of electric network wiring scheme, select the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
3. method according to claim 2, is characterized in that, after described allowance instruction receiving the second operator, after the operational order of the described operation order information that execution the first operator carries out, also comprises:
Identify the operation order information of having completed on described electric network wiring scheme, and show the operation order information of follow-up needs operation;
Go out executable operation order information with a kind of colour code, go out the operation order information that to carry out with the colour code that is different from described color.
4. method according to claim 1, is characterized in that, described operation order information comprises a plurality of sub-information;
After described allowance instruction receiving the second operator, carry out the operational order of the described operation order information of first operator's execution, comprising:
After receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
5. according to claim 1-4 described methods of any one, is characterized in that, described equipment comprises primary equipment, and/or, secondary device.
6. a power scheduling error-proof device, is characterized in that, comprising:
Receiving element, for the facility information of receiving equipment, and the operation information of described equipment;
The operation order generation unit is used for according to described facility information, described operation information and power distribution network working specification generating run ticket information;
Performance element is used for after the allowance instruction that receives the second operator, carries out the operational order of the described operation order information of first operator's execution.
7. device according to claim 6, is characterized in that, described device also comprises:
Display unit shows on screen for the form of the equipment that the power scheduling operation is related to electric network wiring scheme, selects the operation information of equipment needed thereby and equipment needed thereby on described electric network wiring scheme.
8. device according to claim 7, is characterized in that, described device also comprises:
The first identify unit is used for identifying the operation order information of having completed on described electric network wiring scheme, and shows the operation order information of follow-up needs operation;
The second identify unit is used for going out executable operation order information with a kind of colour code, goes out the operation order information that can not carry out with the colour code that is different from described color.
9. device according to claim 6, is characterized in that, described operation order information comprises a plurality of sub-information;
Described performance element comprises:
Carry out subelement, after being used for receiving described the second operator's allowance instruction, carry out the operational order of the described sub-information of described first operator's execution.
10. according to claim 5-9 described devices of any one, is characterized in that, described equipment comprises primary equipment, and/or, secondary device.
CN2013101196397A 2013-04-08 2013-04-08 Power dispatching error prevention method and power dispatching error prevention device Pending CN103177402A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101196397A CN103177402A (en) 2013-04-08 2013-04-08 Power dispatching error prevention method and power dispatching error prevention device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101196397A CN103177402A (en) 2013-04-08 2013-04-08 Power dispatching error prevention method and power dispatching error prevention device

Publications (1)

Publication Number Publication Date
CN103177402A true CN103177402A (en) 2013-06-26

Family

ID=48637235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101196397A Pending CN103177402A (en) 2013-04-08 2013-04-08 Power dispatching error prevention method and power dispatching error prevention device

Country Status (1)

Country Link
CN (1) CN103177402A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104851052A (en) * 2015-04-02 2015-08-19 国网山东省电力公司青岛供电公司 Intelligent error preventing method and system used for outputting dispatching operation ticket
CN105279588A (en) * 2014-06-16 2016-01-27 国家电网公司 Power grid dispatching operation associated monitoring system
CN109376353A (en) * 2018-09-04 2019-02-22 国家电网公司华东分部 A kind of power grid start-up operation ticket generating means and method based on natural language processing

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030009347A1 (en) * 2001-07-09 2003-01-09 Yasushi Iwai Method and system for surveillance and operation services of power generating equipment
CN101719690A (en) * 2009-11-30 2010-06-02 宁波市鄞州天灵信息科技有限公司 Dispatching method of electric network
CN102064611A (en) * 2011-01-06 2011-05-18 国电南瑞科技股份有限公司 Transformer substation sequentialization control system with visualization and interactivity

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030009347A1 (en) * 2001-07-09 2003-01-09 Yasushi Iwai Method and system for surveillance and operation services of power generating equipment
CN101719690A (en) * 2009-11-30 2010-06-02 宁波市鄞州天灵信息科技有限公司 Dispatching method of electric network
CN102064611A (en) * 2011-01-06 2011-05-18 国电南瑞科技股份有限公司 Transformer substation sequentialization control system with visualization and interactivity

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279588A (en) * 2014-06-16 2016-01-27 国家电网公司 Power grid dispatching operation associated monitoring system
CN104851052A (en) * 2015-04-02 2015-08-19 国网山东省电力公司青岛供电公司 Intelligent error preventing method and system used for outputting dispatching operation ticket
CN104851052B (en) * 2015-04-02 2017-03-01 国网山东省电力公司青岛供电公司 A kind of intelligent error preventing method and system for output scheduling operation order
CN109376353A (en) * 2018-09-04 2019-02-22 国家电网公司华东分部 A kind of power grid start-up operation ticket generating means and method based on natural language processing
CN109376353B (en) * 2018-09-04 2022-09-16 国家电网公司华东分部 Natural language processing-based power grid starting operation ticket generation device and method

Similar Documents

Publication Publication Date Title
CN101923346B (en) Method and system for automatically generating anti-sabotage, anti-blocking, water irrigation, breathing, fire burning logic rules of substation
CN103593742A (en) Secondary circuit configuration controlling method and system for intelligent substation
CN106445506A (en) Business flow chart generation method, device and system
CN101901492A (en) Automatic generating method of electric network station wiring diagram
CN102436241A (en) Intelligent substation switching operation ticket system
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN102957205A (en) Method and system for establishing distribution network model
CN108494089B (en) Rapid, safe and reliable batch remote control method for limited-circuit pull circuits
CN102317900A (en) Method and module of performance threshold value setting
CN103177402A (en) Power dispatching error prevention method and power dispatching error prevention device
CN102968096A (en) Safe error proof verifying method for master station type comprehensive intelligent error proof system
CN104953707A (en) Intelligent error prevention method and system for monitoring operation order
CN112650808A (en) Transformer substation anti-error logic visualization method capable of realizing real-time verification and simulation verification
CN110232450A (en) A kind of security control method of station, system and terminal device
CN202512789U (en) Practice training device of relay protection device
CN104050546A (en) Scheduling operation monitoring method and system for scheduling operation ticket
CN103026306B (en) For method and the configuration computing machine of configuration energy automation equipment
CN103077479B (en) Method for temporarily changing electric network topology structure in pattern dispatching operation ticket system
KR101513983B1 (en) SOP scenario executing system and providing method thereof
JP2009153270A (en) Power system monitor control system
CN111754834A (en) Electric power training method based on virtual reality
CN102968087B (en) A kind of Aptitude Operation Order Sheet System preventing maloperation
JP2011166895A (en) Device and method for analysis of power system data
CN110376944B (en) Sequence control abnormal interrupt processing method
CN113708501A (en) Method and system for improving scheduling operation ticket standard rate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130626