CN103132496B - 高桩码头管桩上部混凝土结构施工的夹桩 - Google Patents
高桩码头管桩上部混凝土结构施工的夹桩 Download PDFInfo
- Publication number
- CN103132496B CN103132496B CN201310055720.3A CN201310055720A CN103132496B CN 103132496 B CN103132496 B CN 103132496B CN 201310055720 A CN201310055720 A CN 201310055720A CN 103132496 B CN103132496 B CN 103132496B
- Authority
- CN
- China
- Prior art keywords
- wire rope
- pile
- high strength
- shaped steel
- strength wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种高桩码头管桩上部混凝土结构施工的夹桩,包括两根高强度钢丝绳、两根型钢短梁和设置在型钢短梁一端内的楔块夹紧机构,两根型钢短梁平行设置在管桩上部两侧;高强度钢丝绳两端分别通过钢丝绳压套将第一型钢短梁横置在管桩上端。两根高强度钢丝绳的端头方向相反,楔块夹紧机构包括成对设置的固定斜楔和可移动斜楔以及一块钢垫块。本发明结构紧凑、重量较轻、拆装方便快捷,大大降低了夹桩的制造成本。本发明利用高强度钢丝绳的柔韧性使得两根高强度钢丝绳一正一反地完全贴合在管桩周面上,每根拉紧后的高强度钢丝绳由于两侧的落差小、处于单侧受力的自锁状态,从而大大提高了本发明的垂直承载力,提高了本发明的可靠性。
Description
技术领域
本发明涉及一种梁板式高桩码头平台的建造工装,尤其是一种用于支撑设置在管桩上端混凝土结构的夹桩,属于港口工程技术领域。
背景技术
在沿海或沿江离岸边有一定距离的深水区域建造梁板式高桩码头平台时,需要先将多根管桩沉桩到江底或海底作为码头基础,其上通过现浇混凝土将单桩联成整体。现浇混凝土结构的模板下侧用长条木方支撑,长条木方两端分别通过其下的主梁型钢支撑在管桩上端的夹桩结构上。两个管桩上端的夹桩结构依靠其与管桩之间加压夹紧后的静摩擦力支撑住来自上方主梁型钢、长条方木、模板及混凝土结构的荷载,应根据上部的荷载大小确定夹桩结构短梁和钢丝绳的规格。当用直径30mm的钢丝绳作为承力结构时,单套夹桩结构可承受的竖向荷载可达50吨以上。
如图1和图2所示,现有夹桩的抱箍10两端分别延伸出对接边101,对接边101由三块筋板102支撑,夹桩通过两片抱箍10箍住管桩4,并通过上下排列的多个螺栓螺母组合20将抱箍10对接固定在管桩4上端。为了增大承载力,抱箍10必须具有较大的宽度,并且多个螺栓螺母组合20必须拧得足够紧,才能增大抱箍10与管桩4之间的正压力,增大两者之间的静摩擦力,从而提高夹桩的承载力。这样的结构导致抱箍10十分笨重,多个螺栓螺母组合20的紧固非常费力。由于抱箍10内侧面与管桩4外周面难以保持良好的接触,使得增大前述两者之间的静摩擦力比较困难,从而影响夹桩的承载力。
发明内容
本发明的目的是提供一种结构紧凑、重量较轻、夹桩与管桩之间的静摩擦力较大的高桩码头管桩上部混凝土结构施工的夹桩。
本发明通过以下技术方案予以实现:
一种高桩码头管桩上部混凝土结构施工的夹桩,包括两根高强度钢丝绳、两根型钢短梁和设置在型钢短梁一端内的楔块夹紧机构,所述两根型钢短梁平行且上下错落地设置在管桩上部两侧;第一高强度钢丝绳一端先穿过第一型钢短梁一端,再绕过第一型钢短梁对侧的管桩上端,然后穿过第一型钢短梁另一端,第一高强度钢丝绳两端分别通过钢丝绳压套将第一型钢短梁横置在管桩上端;第二高强度钢丝绳和第二型钢短梁分别设置在第一高强度钢丝绳下侧,第二高强度钢丝绳两端方向与第一高强度钢丝绳两端方向相反,第二高强度钢丝绳中部绕过第二型钢短梁对侧的管桩上端,第二高强度钢丝绳和第二型钢短梁的连接方式与前述第一高强度钢丝绳和第一型钢短梁的连接方式相同,管桩上端横向分别被第一高强度钢丝绳和第二高强度钢丝绳围绕;所述楔块夹紧机构包括成对设置的固定斜楔和可移动斜楔以及一块钢垫块,一对固定斜楔横向并排固定在型钢短梁一端内,一对可移动斜楔分别与对应的固定斜楔斜面贴合,钢垫块设置在一对可移动斜楔外侧,高强度钢丝绳一端先后穿过一对固定斜楔和一对可移动斜楔之间的空隙后,再穿过位于可移动斜楔上侧的钢垫块,通过与其固定连接的钢丝绳压套支撑在钢垫块上。
本发明的目的还可以通过以下技术措施来进一步实现。
前述的高桩码头管桩上部混凝土结构施工的夹桩,其中所述型钢短梁与管桩外周面之间设有楔形垫木;所述型钢短梁采用矩形管型钢制成。
前述的高桩码头管桩上部混凝土结构施工的夹桩,其中所述型钢短梁一端设有横穿矩形管型钢的通孔,型钢短梁另一端设有与端面相通且横穿矩形管型钢的通槽。
前述的高桩码头管桩上部混凝土结构施工的夹桩,其中第一型钢短梁上侧的第一主梁型钢顶面和第二型钢短梁上侧的第二主梁型钢顶面处于同一水平面上;第二主梁型钢与第二型钢短梁之间设有调节楔块。
本发明结构紧凑、重量较轻,大大降低了夹桩的制造成本。本发明利用高强度钢丝绳的柔韧性使得两根高强度钢丝绳一正一反地完全贴合在管桩周面上,再通过正向敲击可移动斜楔即可拉紧高强度钢丝绳,反向敲击可移动斜楔即可使高强度钢丝绳卸载。每根拉紧后的高强度钢丝绳使得管桩处于单侧受力的自锁状态,且增大了高强度钢丝绳与管桩之间的静摩擦力,从而大大提高了本发明的垂直承载力,提高了本发明的可靠性。
本发明的优点和特点,将通过下面优选实施例的非限制性说明进行图示和解释,这些实施例,是参照附图仅作为例子给出的。
附图说明
图1是现有夹桩的主视图;
图2是图1的俯视图;
图3是本发明的主视图;
图4是图3除去第二主梁型钢和调节楔块的右视图;
图5是图4的俯视图;
图6是图5的Ⅰ部剖视放大图。
具体实施方式
下面结合附图和实施例对本发明作进一步说明。
如图3~图6所示,本实施例包括两根高强度钢丝绳1、两根型钢短梁2和分别设置在型钢短梁2两端内的楔块夹紧机构3,两根型钢短梁2平行且上下错落地设置在管桩4上部两侧;第一高强度钢丝绳11一端先穿过第一型钢短梁21一端,再绕过第一型钢短梁21对侧的管桩4上端,然后穿过第一型钢短梁21另一端,第一高强度钢丝绳11两端分别通过钢丝绳压套5将第一型钢短梁21横置在管桩4上端。第二高强度钢丝绳12和第二型钢短梁22分别设置在第一高强度钢丝绳11下侧,第二高强度钢丝绳12两端方向与第一高强度钢丝绳11两端方向相反,第二高强度钢丝绳12中部绕过第二型钢短梁22对侧的管桩4上端,第二高强度钢丝绳12和第二型钢短梁22的连接方式与前述第一高强度钢丝绳11和第一型钢短梁21的连接方式相同,管桩4上端横向分别被第一高强度钢丝绳11和第二高强度钢丝绳12围绕。
楔块夹紧机构3包括成对设置的固定斜楔31和可移动斜楔32以及一块钢垫块33,一对固定斜楔31横向并排固定在型钢短梁2一端内,一对可移动斜楔32分别与对应的固定斜楔31斜面贴合,一对固定斜楔31横向并排固定在型钢短梁2一端内,可移动斜楔32与固定斜楔31斜面贴合,钢垫块33设置在一对可移动斜楔32外侧。高强度钢丝绳2一端先后穿过一对固定斜楔31和一对可移动斜楔32之间的空隙后,再穿过钢垫块33,通过与其固定连接的钢丝绳压套5支撑在钢垫块33上。钢垫块33一侧还设有限位板34,使得在敲击可移动斜楔32时,钢垫块33只能向上移动,而不能向左移动。
型钢短梁2与管桩4外周面之间设有楔形垫木6,可防止型钢短梁2偏转。型钢短梁2采用矩形管型钢制成,便于在型钢短梁2端口内安装楔块夹紧机构3。型钢短梁2一端设有横穿矩形管型钢2的通孔201,另一端设有与端面相通且横穿矩形管型钢2的通槽202,便于调整绕过管桩4一侧的两根高强度钢丝绳1的平行度,确保能拉紧高强度钢丝绳1。
本实施例的主梁型钢采用两根槽钢槽口相对地拼焊而成。其中第二主梁型钢62与第二型钢短梁22之间设有调节楔块7,敲击调节楔块7,第一型钢短梁21上侧的第一主梁型钢61顶面和第二型钢短梁22上侧的第二主梁型钢62顶面处于同一水平面上,从而能通过支撑在第一主梁型钢61和第二主梁型钢62上的长条木方和模板及上部的混凝土结构。
本发明的高强度钢丝绳1拉紧过程如下:
1)根据管桩4直径和型钢短梁2的厚度确定高强度钢丝绳1的下料长度。
2)将高强度钢丝绳1一端穿过型钢短梁2一端的通孔201,再将钢丝绳压套5分别压紧在高强度钢丝绳1两端的端头上。
3)将型钢短梁2挂在管桩4上端,高强度钢丝绳1绕过管桩4,将高强度钢丝绳1另一端的端头的钢丝绳压套5放入矩形管型钢2另一端的通槽202中。
4)高强度钢丝绳1一端的钢丝绳压套5位于钢垫块33相应位置的外侧,将可移动斜楔32插入固定斜楔31和钢垫块33之间,用锤敲击可移动斜楔32,即可拉紧高强度钢丝绳1,增大高强度钢丝绳1与管桩4之间的静摩擦力。
除上述实施例外,本发明还可以有其他实施方式,凡采用等同替换或等效变换形成的技术方案,均落在本发明要求的保护范围内。
Claims (3)
1.一种高桩码头管桩上部混凝土结构施工的夹桩,其特征在于,包括两根高强度钢丝绳、两根型钢短梁和设置在型钢短梁一端内的楔块夹紧机构,所述两根型钢短梁平行且上下错落地设置在管桩上部两侧;第一高强度钢丝绳一端先穿过第一型钢短梁一端,再绕过第一型钢短梁对侧的管桩上端,然后穿过第一型钢短梁另一端,第一高强度钢丝绳两端分别通过钢丝绳压套将第一型钢短梁横置在管桩上端;第二高强度钢丝绳和第二型钢短梁分别设置在第一高强度钢丝绳下侧,第二高强度钢丝绳两端方向与第一高强度钢丝绳两端方向相反,第二高强度钢丝绳中部绕过第二型钢短梁对侧的管桩上端,第二高强度钢丝绳和第二型钢短梁的连接方式与前述第一高强度钢丝绳和第一型钢短梁的连接方式相同,管桩上端横向分别被第一高强度钢丝绳和第二高强度钢丝绳围绕;所述楔块夹紧机构包括成对设置的固定斜楔和可移动斜楔以及一块钢垫块,一对固定斜楔横向并排固定在型钢短梁一端内,一对可移动斜楔分别与对应的固定斜楔斜面贴合,钢垫块设置在一对可移动斜楔外侧,高强度钢丝绳一端先后穿过一对固定斜楔和一对可移动斜楔之间的空隙后,再穿过位于可移动斜楔上侧的钢垫块,通过与其固定连接的钢丝绳压套支撑在钢垫块上。
2.如权利要求1所述的高桩码头管桩上部混凝土结构施工的夹桩,其特征在于,所述型钢短梁与管桩外周面之间设有楔形垫木。
3.如权利要求1所述的高桩码头管桩上部混凝土结构施工的夹桩,其特征在于,第二主梁型钢与第二型钢短梁之间设有调节楔块。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310055720.3A CN103132496B (zh) | 2013-02-22 | 2013-02-22 | 高桩码头管桩上部混凝土结构施工的夹桩 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310055720.3A CN103132496B (zh) | 2013-02-22 | 2013-02-22 | 高桩码头管桩上部混凝土结构施工的夹桩 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103132496A CN103132496A (zh) | 2013-06-05 |
CN103132496B true CN103132496B (zh) | 2015-04-01 |
Family
ID=48492903
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310055720.3A Expired - Fee Related CN103132496B (zh) | 2013-02-22 | 2013-02-22 | 高桩码头管桩上部混凝土结构施工的夹桩 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103132496B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104831698B (zh) * | 2014-02-11 | 2016-06-22 | 天津市海王星海上工程技术股份有限公司 | 一种适用于桩腿与基盘连接的锁环装置 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1480147A (en) * | 1920-06-28 | 1924-01-08 | Brandt & Krell Engineering Com | Stringer clamp |
US3863302A (en) * | 1972-10-16 | 1975-02-04 | Bureau Bbr Ltd | Apparatus for anchoring wires or stranded wires |
US4003209A (en) * | 1972-07-31 | 1977-01-18 | Jackson Gary A | Pier construction |
US5274888A (en) * | 1993-04-05 | 1994-01-04 | Gto, Inc. | Adjustable U-bolt type pipe clamp |
JPH08277514A (ja) * | 1995-04-05 | 1996-10-22 | Taisei Corp | 吊り支保工装置および桟橋の構築方法 |
CN2346761Y (zh) * | 1998-10-01 | 1999-11-03 | 柳州欧维姆建筑机械有限公司 | 单索预紧工具 |
CN201952777U (zh) * | 2011-03-22 | 2011-08-31 | 葛洲坝集团第五工程有限公司 | 高桩码头钢抱箍支撑结构 |
CN202416183U (zh) * | 2011-12-23 | 2012-09-05 | 中铁十九局集团第五工程有限公司 | 一种盖梁抱箍式浇注支架 |
-
2013
- 2013-02-22 CN CN201310055720.3A patent/CN103132496B/zh not_active Expired - Fee Related
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1480147A (en) * | 1920-06-28 | 1924-01-08 | Brandt & Krell Engineering Com | Stringer clamp |
US4003209A (en) * | 1972-07-31 | 1977-01-18 | Jackson Gary A | Pier construction |
US3863302A (en) * | 1972-10-16 | 1975-02-04 | Bureau Bbr Ltd | Apparatus for anchoring wires or stranded wires |
US5274888A (en) * | 1993-04-05 | 1994-01-04 | Gto, Inc. | Adjustable U-bolt type pipe clamp |
JPH08277514A (ja) * | 1995-04-05 | 1996-10-22 | Taisei Corp | 吊り支保工装置および桟橋の構築方法 |
CN2346761Y (zh) * | 1998-10-01 | 1999-11-03 | 柳州欧维姆建筑机械有限公司 | 单索预紧工具 |
CN201952777U (zh) * | 2011-03-22 | 2011-08-31 | 葛洲坝集团第五工程有限公司 | 高桩码头钢抱箍支撑结构 |
CN202416183U (zh) * | 2011-12-23 | 2012-09-05 | 中铁十九局集团第五工程有限公司 | 一种盖梁抱箍式浇注支架 |
Non-Patent Citations (1)
Title |
---|
海上高墩盖梁施工技术;钟领宗等;《公路交通技术》;20031231(第06期);第55页第1段、第55页第2章第2.1节第1段-第56页第2.3.1节末段及图1-3 * |
Also Published As
Publication number | Publication date |
---|---|
CN103132496A (zh) | 2013-06-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103912073B (zh) | 一种内置型钢钢管混凝土边框低屈服点钢板剪力墙结构 | |
CN103306214B (zh) | 一种钢筋混凝土梁与楼板的加固装置 | |
KR20140122724A (ko) | 강제 교각과 콘크리트제 말뚝기초의 접합구조 | |
CN206752312U (zh) | 中承式及下承式拱桥钢‑混凝土组合梁桥面系构造 | |
CN204608592U (zh) | 一种桥梁用耗能减震防落梁装置 | |
CN202519577U (zh) | 桥梁拉索减震限位器 | |
CN103132496B (zh) | 高桩码头管桩上部混凝土结构施工的夹桩 | |
CN203222098U (zh) | 海洋平台 | |
CN201785937U (zh) | 一种h钢梁 | |
CN103334405B (zh) | 锁固式桩基夹桩 | |
CN207109558U (zh) | 一种高墩大跨窄桥高性能抗震连续刚构结构体系 | |
CN202047398U (zh) | 钢索坝 | |
CN205115994U (zh) | 一种多级防御可调节性防落梁装置 | |
CN201254695Y (zh) | 提高桥梁抗震能力的拉接装置 | |
CN210264725U (zh) | 一种小净距隧道中夹岩组合加固装置 | |
CN102776966A (zh) | 一种改进型双层钢板混凝土剪力墙及其施工方法 | |
CN203878771U (zh) | 一种钢结构框架 | |
CN102140787A (zh) | 钢索坝 | |
CN207919594U (zh) | 一种可伸缩的钢管桩水下连接系 | |
CN202248927U (zh) | 楼板负筋悬挂架体结构 | |
CN205223842U (zh) | 斜拉桥结构体系防止主梁出现负反力构造 | |
CN220565449U (zh) | 悬挑钢梁的后锚固装置 | |
CN202519877U (zh) | 组合梁 | |
CN211646757U (zh) | 一种用于连接梁与柱的螺栓连接器 | |
CN202064986U (zh) | 耙矸机回头滑轮固定装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150401 Termination date: 20170222 |