CN103128896A - Production method for unvulcanized rubber sheet - Google Patents

Production method for unvulcanized rubber sheet Download PDF

Info

Publication number
CN103128896A
CN103128896A CN2012104733623A CN201210473362A CN103128896A CN 103128896 A CN103128896 A CN 103128896A CN 2012104733623 A CN2012104733623 A CN 2012104733623A CN 201210473362 A CN201210473362 A CN 201210473362A CN 103128896 A CN103128896 A CN 103128896A
Authority
CN
China
Prior art keywords
rubber sheet
half finished
finished rubber
unvulcanized rubber
wound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104733623A
Other languages
Chinese (zh)
Other versions
CN103128896B (en
Inventor
大西庆
金屋诚二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Rubber Industries Ltd
Original Assignee
Sumitomo Rubber Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Rubber Industries Ltd filed Critical Sumitomo Rubber Industries Ltd
Publication of CN103128896A publication Critical patent/CN103128896A/en
Application granted granted Critical
Publication of CN103128896B publication Critical patent/CN103128896B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a production method for unvulcanized rubber sheets. The method can inhibit deterioration of width precision when the unvulcanized rubber sheets cut after being wound by a winding roller is wound on a novel winding roller from happening, so that the unvulcanized rubber sheets can be used by the next process without problems and tyre defects of produced tyres can be prevented. The production method for the unvulcanized rubber sheets comprises a rolling process for processing high temperature unvulcanized rubber into the unvulcanized rubber sheets; a cooling process for cooling the unvulcanized rubber sheets; a winding process for winding the cooled unvulcanized rubber sheets on the winding roller; and a cutting process for cutting the wound unvulcanized rubber sheets. A predetermined length at the front end part is wound at a winding speed faster than a usual winding speed when the wound unvulcanized rubber sheets are wound on the next winding roller.

Description

The production method of half finished rubber sheet
Technical field
The present invention relates to use the production method of the half finished rubber sheet that heat insulation calender (イ Application ス レ one シ ヨ Application カ レ Application ダ one) produces.
Background technology
Fig. 3 is the figure that the production method of half finished rubber sheet in the past is described.As shown in Figure 3, in the past the production and application of the half finished rubber sheet device that is called heat insulation calender carries out.
heat insulation calender possesses: calendering section 10, carry-over pinch rolls section 20, cooling end 30, reeling end 40, the production of half finished rubber sheet is carried out through following operation: the calendering procedure that the half finished rubber of high-temperature is processed into the half finished rubber sheet, to after fitting with carry-over pinch rolls, a plurality of half finished rubbers of sheet processing carry out cooling carry-over pinch rolls operation, with the further cooling refrigerating work procedure of the half finished rubber sheet S that fits, chilled half finished rubber sheet S is wound in the coiling operation of takers-in, the cutting action (patent documentation 1) that utilizes cutter 49 to cut the half finished rubber sheet S that reels.
And the end of the half finished rubber sheet S through cutting is wound in takers-in with keeping intact, and on the other hand, the other end is wound in new takers-in and begins new coiling.Like this, do not stop production line ground by exchanging 2 takers-ins and carry out the continuous production of half finished rubber sheet.
In addition, in above-mentioned each operation, set suitable speed so that half finished rubber sheet S does not produce lax, gauffer.In addition, the carry-over pinch rolls operation can be omitted according to goods sometimes.
Patent documentation 1: TOHKEMY 2010-173223 communique
Summary of the invention
Yet in method in the past, with the half finished rubber sheet S after cutting when being wound in new takers-in, the part sheet width in the length of the approximately 10m of volume core broadens sometimes, and width accuracy worsens.Like this, the half finished rubber sheet S that width accuracy has worsened may have problems in the use of the next operations such as automatic moulding, increases the generation of the wheel tyre defect of goods tire.
But, in the past due to this sheet width broaden agnogenio, so can't suitably tackle.
Therefore, problem of the present invention is to provide the production method of following half finished rubber sheet, the generation of the deterioration of the width accuracy when after the method can suppress to utilize takers-in to reel, the half finished rubber sheet of cutting is wound in new takers-in, thereby also use without any problems in next operation, can reduce the generation of the wheel tyre defect of goods tire.
The inventor conducts in-depth research, and found that the invention according to following record can solve above-mentioned problem, until complete the present invention.
The invention of scheme 1 record is a kind of production method of half finished rubber sheet, it is characterized in that, possesses following operation: the calendering procedure that the half finished rubber of high-temperature is processed into the half finished rubber sheet, the refrigerating work procedure of cooling above-mentioned half finished rubber sheet, chilled above-mentioned half finished rubber sheet is wound in the coiling operation of takers-in, the cutting action that the above-mentioned half finished rubber sheet after coiling is finished cuts;
When the above-mentioned half finished rubber sheet after reel finishing is wound in next takers-in, the length of the regulation of leading section is reeled with the winding speed faster than common winding speed.
The invention of scheme 2 records is production methods of the half finished rubber sheet of scheme 1 record, it is characterized in that, the above-mentioned winding speed faster than common winding speed is the winding speed than common winding speed fast 2~3%.
According to the present invention, the production method of following half finished rubber sheet can be provided, the generation of the deterioration of the width accuracy when after the method can suppress to utilize takers-in to reel, the half finished rubber sheet of cutting is wound in new takers-in, thereby also can use without any problems in next operation, can reduce the generation of the wheel tyre defect of goods tire.
Description of drawings
Fig. 1 is the figure of production method of the half finished rubber sheet of explanation embodiments of the present invention.
Fig. 2 is the figure of production method of the half finished rubber sheet of explanation embodiments of the present invention.
Fig. 3 is the figure that the production method of half finished rubber sheet in the past is described.
Symbol description
10 calendering sections
11 first calender devices
12 second calender devices
20 carry-over pinch rolls sections
21 joint rollers
30 cooling ends
31~36 drum coolers
40 reeling ends
41 the 1st rollers
42 the 2nd rollers
43 the 1st takers-ins
44 the 2nd takers-ins
49 cutters
51 the 1st auxiliary material rollers
51a the 1st auxiliary material
52 the 2nd auxiliary material rollers
52a the 2nd auxiliary material
S half finished rubber sheet
S1 the first half finished rubber sheet
S2 the first half finished rubber sheet
The specific embodiment
As can be known in method in the past, when the half finished rubber sheet after cutting is wound in new takers-in, due to cutting, the stretching that is produced by the difference of the speed between refrigerating work procedure and coiling operation is eliminated, thereby the sheet width broadens, the present invention compensates the stretching of this elimination by the speedup of the speed of new takers-in, suppress the expansion of sheet width.
Below, based on embodiment and with reference to accompanying drawing, the present invention is described.
Fig. 1, Fig. 2 are the figure of production method of the half finished rubber sheet of explanation embodiments of the present invention.The production method of the half finished rubber sheet of present embodiment is used and is carried out with in the past identical Fig. 1, heat insulation calender shown in Figure 2.
1. the formation of heat insulation calender
As mentioned above, heat insulation calender possesses: calendering section 10, carry-over pinch rolls section 20, cooling end 30, reeling end 40, cutter 49, control their the outer control part of figure, the driver element of each one (motor) is controlled by above-mentioned control part.
Heat insulation calender usually to the half finished rubber sheet S of thickness 0.3~3.0mm roll, cooling and reel.
The transporting velocity of the half finished rubber sheet S of each one of calendering section 10, carry-over pinch rolls section 20, cooling end 30, reeling end 40 consists of in the mode that can independently set separately, the speed of half finished rubber sheet S in calendering section 10 is 100 o'clock, and the speed in carry-over pinch rolls section 20, cooling end 30 and reeling end 40 can be set as 90~110 separately.
Calendering section 10 is that the half finished rubber to high-temperature rolls and is processed into the device of half finished rubber sheet S, be processed into the first half finished rubber sheet S1 with the first calender device 11 calendering half finished rubbers, coordinate different half finished rubbers and form the second half finished rubber sheet S2 from the first half finished rubber sheet S1 with the second calender device 12 calenderings.
Carry-over pinch rolls section 20 fits the first and second half finished rubber sheet S1, S2 and the device of formation half finished rubber sheet S.Should illustrate, the 21st, engage and use roller.
Cooling end 30 is drum cooler 31~36 is configured to up and down 2 row and consists of, while by being turned back, moves half finished rubber sheet S, thus make the surface of half finished rubber sheet S alternately contact with drum cooler 31~36 and carry out cooling uniformly with the back side.
Should illustrate, consist of cooling end 30 by front cooling end and rear cooling end, also can make carry-over pinch rolls section 20 play the effect of front cooling end.
Reeling end 40 possess respectively the 1st auxiliary material that are wound with the 1st auxiliary material 51a with roller 51 and the 1st takers-in 43, be wound with the 2nd auxiliary material 52a the 2nd auxiliary material with roller 52 and the 2nd takers-in 44.Should illustrate, the 41, the 42nd, for the 1st roller that band is driven and the 2nd roller.
For continuous production, in reeling end 40, when changing to next auxiliary material, when namely restarting to reel with new takers-in (change of the 1st time), as shown in Fig. 2 (a), fall cutter 49 and cut half finished rubber sheet S.Then, as shown in Fig. 2 (b), lift cutter 49, stop the rotation that the 1st auxiliary material are used roller 51 and the 1st takers-in 43, then make the 1st takers-in 43 increase from band.In addition, make the 2nd auxiliary material with roller 52 and the rotation of the 2nd takers-in 44, then the position that makes the 2nd takers-in 44 the drop to band half finished rubber sheet S that reels.
Next change of the 2nd time is to stop the 2nd auxiliary material with the rotation of roller 52 and the 2nd takers-in 44, makes the 1st auxiliary material rotate and reel with the 1st takers-in 43 with roller 51 and the 1st takers-in 43.Should illustrate, later on also alternately change auxiliary material with roller, the takers-in half finished rubber sheet S that reels with identical main points the 3rd time.
2. the production method of half finished rubber sheet
the production method of the half finished rubber sheet of present embodiment is to use above-mentioned heat insulation calender to produce the method for half finished rubber sheet S, possesses following operation: in calendering section 10, the half finished rubber of high-temperature is processed into the first and second half finished rubber sheet S1, the calendering procedure of S2, make the first and second half finished rubber sheet S1 in carry-over pinch rolls section 20, S2 fits and is processed into the operation of half finished rubber sheet S, refrigerating work procedure at the cooling half finished rubber sheet of cooling end 30 S, at reeling end 40, chilled half finished rubber sheet S is wound in the coiling operation of takers-in, the cutting action of the terminal of the half finished rubber sheet S that reels with cutter 49 cuttings in the coiling operation.
The transporting velocity of each one in the production method of half finished rubber sheet is set as calendering section: carry-over pinch rolls sections (front cooling end): cooling end (rear cooling end): the ratio of reeling end=100:102:98:100.
In present embodiment, utilize the coiling of the half finished rubber sheet S that takers-in carries out to finish, the winding speed of the half finished rubber sheet S when being altered to new takers-in changes.Change following carrying out.
(1) until before the coiling of change half finished rubber sheet S, half finished rubber sheet S reels by common winding speed.
When (2) utilizing new takers-in to begin to reel, change to the winding speed faster than common winding speed.Namely, as shown in Fig. 2 (a), after the coiling that utilizes the 1st takers-in 43 to carry out puts down cutter 49 cutting half finished rubber sheet S the finish time, as shown in Fig. 2 (b), utilize next the 2nd takers-in 44 from the cutting top (leading section) of half finished rubber sheet S when beginning to reel, begin from the cutting top of half finished rubber sheet S to reel regulation length (for example, 10m), to reel than the winding speed of the winding speed (common winding speed) fast 2~3% till cutting half finished rubber sheet S.
Thus, by the half finished rubber sheet S of sheet wider width being applied the suitable tensile force of the size more than the tensile force that is caused by common winding speed, thereby while can make the sheet width return to suitable size to reel.
(3) then, return to the common winding speed half finished rubber sheet S that reels.
Embodiment
Use above-mentioned heat insulation calender, by common rolling velocity, carry-over pinch rolls speed, cooling velocity, winding speed carry out the first volume around, then conversion takers-in, as shown in table 1, in comparative example with common winding speed carry out volume Two around, in an embodiment with the 5 kind winding speeds faster than common winding speed carry out volume Two around.
And, measure volume Two around in the coiling starting end near sheet rubber width increment rate (R/ mean value) (%), the rate of breakdown (%) in the automatic moulding machine that uses in next operation, the incidence (%) of wheel tyre defect.Show the result in table 1.
Table 1
Figure BDA00002433354600071
As shown in Table 1, the winding speed of (during cutting) when reeling change has been increased in 2~3% embodiment 3,4 situation, and any in the incidence (%) of the rate of breakdown (%) in the increment rate of the width of sheet rubber (R/ mean value), automatic moulding machine, wheel tyre defect compared all with comparative example and improved widely.
Should illustrate, the speed the when rolling velocity in table, carry-over pinch rolls speed, cooling velocity, winding speed and coiling change is take the relatively recently expression of coiling winding speed before changing as 100 o'clock.In addition, " R " of the R/ mean value (%) of the sheet rubber width in table is the poor of the Breadth Maximum of the half finished rubber sheet S that reels and minimum widith, and " mean value " is the mean breadth of the half finished rubber sheet S that reels.
Above, according to embodiment, the present invention has been described, but has the invention is not restricted to above-mentioned embodiment.In the scope identical and impartial with the present invention, can apply to above-mentioned embodiment various changes.

Claims (2)

1. the production method of a half finished rubber sheet, it is characterized in that, possess: the calendering procedure that the half finished rubber of high-temperature is processed into the half finished rubber sheet, the refrigerating work procedure of cooling described half finished rubber sheet, cooling described half finished rubber sheet is wound in the coiling operation of takers-in, the cutting action that described half finished rubber sheet after coiling is finished cuts
When the described half finished rubber sheet after reel finishing is wound in next takers-in, the length of the regulation of leading section is reeled with the winding speed faster than common winding speed.
2. the production method of half finished rubber sheet according to claim 1, is characterized in that, the described winding speed faster than common winding speed is the winding speed than common winding speed fast 2~3%.
CN201210473362.3A 2011-11-22 2012-11-20 Production method for unvulcanized rubber sheet Active CN103128896B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2011-255367 2011-11-22
JP2011255367A JP5425873B2 (en) 2011-11-22 2011-11-22 Production method of unvulcanized rubber sheet

Publications (2)

Publication Number Publication Date
CN103128896A true CN103128896A (en) 2013-06-05
CN103128896B CN103128896B (en) 2017-04-12

Family

ID=48489665

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210473362.3A Active CN103128896B (en) 2011-11-22 2012-11-20 Production method for unvulcanized rubber sheet

Country Status (2)

Country Link
JP (1) JP5425873B2 (en)
CN (1) CN103128896B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103483819A (en) * 2013-09-22 2014-01-01 苏州市湘园特种精细化工有限公司 Production technology for conductive rubber sheet
CN103525091A (en) * 2013-09-22 2014-01-22 苏州市湘园特种精细化工有限公司 Production technique of conductive nano flame-retardant rubber sheet
CN103602069A (en) * 2013-11-08 2014-02-26 苏州新颖新材料科技股份有限公司 Production technology of conductive anti-bacterial rubber film

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6598134B2 (en) * 2015-07-30 2019-10-30 住友ゴム工業株式会社 Unvulcanized rubber sheet manufacturing apparatus and unvulcanized rubber sheet manufacturing method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02150340A (en) * 1988-11-30 1990-06-08 Sumitomo Rubber Ind Ltd Apparatus for rubber coating and liner connecting
CN101389468A (en) * 2006-02-27 2009-03-18 横滨橡胶株式会社 Method of manufacturing pneumatic tire
JP2010173223A (en) * 2009-01-30 2010-08-12 Sumitomo Rubber Ind Ltd Equipment and process for producing unvulcanized rubber sheet
CN102189691A (en) * 2010-02-05 2011-09-21 住友橡胶工业株式会社 Method for manufacturing raw tyre for automatic bicycle

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3128316B2 (en) * 1992-03-13 2001-01-29 株式会社ブリヂストン Forming and winding device for belt-shaped members
JPH0790564B2 (en) * 1992-04-27 1995-10-04 三ツ星ベルト株式会社 Rubber sheet winding device
JP3293955B2 (en) * 1993-05-28 2002-06-17 三菱電線工業株式会社 Rubber sheet winding device
JP4365732B2 (en) * 2004-06-18 2009-11-18 住友ゴム工業株式会社 Rubber sheet forming device
JP2006225135A (en) * 2005-02-18 2006-08-31 Kao Corp Method of taking up sheet
JP5638233B2 (en) * 2009-12-16 2014-12-10 株式会社ブリヂストン Rubber sheet molding apparatus and molding method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02150340A (en) * 1988-11-30 1990-06-08 Sumitomo Rubber Ind Ltd Apparatus for rubber coating and liner connecting
CN101389468A (en) * 2006-02-27 2009-03-18 横滨橡胶株式会社 Method of manufacturing pneumatic tire
JP2010173223A (en) * 2009-01-30 2010-08-12 Sumitomo Rubber Ind Ltd Equipment and process for producing unvulcanized rubber sheet
CN102189691A (en) * 2010-02-05 2011-09-21 住友橡胶工业株式会社 Method for manufacturing raw tyre for automatic bicycle

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103483819A (en) * 2013-09-22 2014-01-01 苏州市湘园特种精细化工有限公司 Production technology for conductive rubber sheet
CN103525091A (en) * 2013-09-22 2014-01-22 苏州市湘园特种精细化工有限公司 Production technique of conductive nano flame-retardant rubber sheet
CN103525091B (en) * 2013-09-22 2016-08-10 苏州市湘园特种精细化工有限公司 A kind of production technology of conductive nano flame-retardant rubber sheet
CN103602069A (en) * 2013-11-08 2014-02-26 苏州新颖新材料科技股份有限公司 Production technology of conductive anti-bacterial rubber film

Also Published As

Publication number Publication date
JP5425873B2 (en) 2014-02-26
JP2013107337A (en) 2013-06-06
CN103128896B (en) 2017-04-12

Similar Documents

Publication Publication Date Title
EP2569104B1 (en) Method for the production of flat rolled products
RU2531015C2 (en) Method of rolling for manufacture of flat articles and roll train
CN101912874B (en) Production method of preventing from coiling and pulling narrow of hot-rolled low carbon strip steels used for cold-rolled base plates
CN103128896A (en) Production method for unvulcanized rubber sheet
CN110000209B (en) 4-pass rolling method for aluminum foil with thickness of 0.005mm
CN102284555A (en) Coiling method for controlling and leveling marking defects in strip steel coiling
CN205419209U (en) EVA automatic winding machine
KR101067758B1 (en) System and method for endless hot rolling
RU2007119552A (en) METHOD AND PRODUCTION LINE FOR MAKING A HOT ULTRA-THIN STEEL STRIP WITH TWO CASTING LINES FOR ONE LINE OF INFINITE ROLLING
CN108831706A (en) A kind of three-dimensional winding iron core and its method and device using the production of single layer amorphous band
CN108296711A (en) Strip monovolume taking technique and its control method are cutd open in a kind of strip Precise asymptotics
JP4334539B2 (en) Method and equipment for hot-rolling strips with one stickel rolling stand
CN113399460B (en) Coiling tension control method of thin strip steel in loop type continuous longitudinal shearing and recoiling unit
JP2013094798A (en) Winding control method and apparatus for hot rolled steel band
JP4165723B2 (en) Hot rolling method and equipment
CN104044235A (en) Manufacturing Device And Manufacturing Method Of Unvulcanized Rubber Sheets
CN103894416B (en) The operation method of mandrel coiled material case, the continuous rolling method utilizing it and continuous rolling device
JP4192013B2 (en) Manufacturing method of steel plate for striping in hot rolling line
CN216863180U (en) Graphene oxide membrane slicing system
CN108273870A (en) A kind of belt steel flating machine
JP2003211214A (en) Method for cooling material to be rolled in hot endless rolling
JP2016150468A (en) Device for production of rubber strip
CN116532488A (en) Coiling small tension control method and system
JP5447744B1 (en) Manufacturing method of hot rolled steel sheet
CN117225902A (en) Method for controlling coiling flat coil of thin-specification steel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant