CN103122695A CN2013100413955A CN201310041395A CN103122695A CN 103122695 A CN103122695 A CN 103122695A CN 2013100413955 A CN2013100413955 A CN 2013100413955A CN 201310041395 A CN201310041395 A CN 201310041395A CN 103122695 A CN103122695 A CN 103122695A
Authority
CN
China
Prior art keywords
leg
concrete floor
sleeve
thickness
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100413955A
Other languages
Chinese (zh)
Inventor
王大钢
张伟刚
陈万里
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2013100413955A priority Critical patent/CN103122695A/en
Publication of CN103122695A publication Critical patent/CN103122695A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a tool for controlling pouring thickness of a concrete floor. The tool for controlling the pouring thickness of the concrete floor comprises a flat plate, and a plurality of stand bars which are arranged at the lower end of the flat plate. A sleeve is connected on each stand bar in a sleeved mode, the bottom portion of each sleeve is in a cone-shaped structure, a pull rod is arranged at the upper end of the flat plate, and the lower end of the pull rod and the flat plate are vertically fixed. By applying the technical scheme, each stand bar is connected with the sleeve in a sleeved mode, and then is inserted into concrete, the height which the flat plate is located is the thickness of the concrete floor, a scraping ruler is used for scraping the concrete which is higher than the flat plate, the tool is extracted through the pull rod after completing operation, and the sleeves are kept inside the concrete. The tool for controlling the pouring thickness of the concrete floor has the advantages of being simple in structure, convenient to operate, and small in a thickness error of pouring floors.

Description

A kind of instrument of building thickness for the control concrete floor
Technical field
The present invention relates to technical field of building construction, be specifically related to a kind of instrument of building thickness for the control concrete floor.
Background technology
The control that concrete floor is built thickness is the high identical identification point of bidding on the vertical structure reinforcing bar normally, draws horizon between two identification points, measures the newly placed concrete face with invar tape and controls slab thickness to horizontal distance.This method troublesome poeration, and error is large, inefficiency.
Summary of the invention
For the deficiency that prior art exists, the object of the present invention is to provide a kind of simple in structure, easy to operate, build little being used for of slab thickness error and control the instrument that concrete floor is built thickness.
For achieving the above object, the invention provides following technical scheme: a kind of instrument of building thickness for the control concrete floor, comprise dull and stereotyped a plurality of legs with being arranged on dull and stereotyped lower end, and be socketed with sleeve on each leg, described each tapered structure in sleeve bottom, described dull and stereotyped upper end is provided with pull bar, and described pull bar lower end is vertical with flat board fixing.
By adopting technique scheme, each leg first inserts concrete again with the sleeve socket, the height at dull and stereotyped place is the thickness of concrete floor, the reinforcement of concrete floating rule higher than flat board is wiped off, after complete operation, by the pull bar puller, sleeve is stayed in concrete, and is simple in structure, easy to operate, build the slab thickness error little.
The present invention further is set to: described flat board is steel plate, three leg nuts of welding on described steel plate lower surface, and the straight line at these three leg nut places consists of triangular structure, and described each leg upper end is provided with screw thread, and each leg and corresponding leg nut thread connection.By this setting, each leg is connected reliably with steel plate, and mounting or dismounting are convenient.
The present invention also further is set to: described sleeve upper end is fixed by socket with corresponding leg nut, and each sleeve bottom is conical structure.By this setting, sleeve is connected simply with the leg nut, convenient disassembly.
The present invention also further is set to: middle part, described steel plate upper surface is provided with pull-rod nut, and described pull bar lower end is provided with screw thread, and pull bar is fixing by being threaded with pull-rod nut.By this setting, pull bar and steel plate are fixing reliable, and mounting or dismounting are convenient, and the position arranges rationally.
The present invention also further is set to: the contour setting of described a plurality of legs.By this setting, can better reduce the error of building slab thickness, make work more reliable.
Advantage of the present invention is: structure of the present invention arranges rationally, by in a dull and stereotyped lower end, a plurality of legs being set, and all be socketed with sleeve on each leg, dull and stereotyped upper end arranges pull bar, insert concrete after each leg and sleeve socket, the height at dull and stereotyped place is the thickness of concrete floor, the reinforcement of concrete floating rule higher than flat board is wiped off, pass through the pull bar puller after complete operation, after concrete setting, sleeve can be stayed in concrete, simple in structure, easy to operate, build the slab thickness error little.
The invention will be further described below in conjunction with specification drawings and specific embodiments.
Description of drawings
Fig. 1 is the structural representation of the embodiment of the present invention;
Fig. 2 is the schematic top plan view of the embodiment of the present invention;
Fig. 3 is the elevational schematic view of the embodiment of the present invention.
The specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3, a kind of instrument of building thickness for the control concrete floor disclosed by the invention, comprise flat board 1 and a plurality of legs 2 that are arranged on dull and stereotyped 1 lower end, and be socketed with sleeve 6 on each leg, described each sleeve 6 tapered structure in bottom, described dull and stereotyped 1 upper end is provided with pull bar 3, and described pull bar 3 lower ends are vertical with dull and stereotyped 1 fixing.
As preferably, the present embodiment described dull and stereotyped 1 is steel plate, three leg nuts 4 of welding on described steel plate 1 lower surface, and the straight line at these three leg nut 4 places consists of triangular structure, described each leg 2 upper ends are provided with screw thread, and each leg 2 is threaded with corresponding leg nut 4.Be that the present embodiment arranges 2, three leg 2 distributions triangular in shape of three legs altogether, three leg nuts 4 lay respectively at the summit of the triangular structure of these nut 4 place straight lines formations.
Described sleeve 6 upper ends are fixed by socket with corresponding leg nut 4, and each sleeve pipe 6 bottoms are conical structure.This technical scheme, conical structure is arranged in sleeve 6 bottoms, be convenient to insert concrete, after concrete setting, upwards draw flat board 1 and leg nut 4 and pull bar 3 interlocks by pull bar 3, this moment, leg nut 4 broke away from sleeve 6, sleeve 6 is stayed in concrete, and whole instrument is extracted conveniently, reliable operation.
Described steel plate 1 middle part, upper surface is provided with pull-rod nut 5, and described pull bar 3 lower ends are provided with screw thread, and pull bar 3 is by being threaded fixing with pull-rod nut 5.Pull-rod nut 5 just in time is positioned at the barycenter oftriangle position that three leg nuts, 4 place straight lines consist of.
For making work of the present invention more reliable, described three the contour settings of leg 2 of the present embodiment.And the length of three legs 2 can be changed according to slab thickness.
During practical application, select leg 2 length according to slab thickness, then leg 2 is tightened with corresponding leg nut 4, be socketed with sleeve 6 on each leg 2, then leg 2 and sleeve 6 are inserted concrete on earth, the height of steel plate 1 is the thickness of floor at this moment, floating rule is placed on steel plate surface, concrete surface is scraped to flushing with steel plate surface, by pull bar 3, instrument is extracted after complete operation, be placed into next control point, strike off operation.
Above-described embodiment is to specific descriptions of the present invention; only be used for the present invention is further illustrated; can not be interpreted as the restriction to protection domain of the present invention, the technician of this area according to the content of foregoing invention, the present invention is made some nonessential improvement and adjust all fall into protection scope of the present invention within.

Claims (5)

1. one kind is used for controlling the instrument that concrete floor is built thickness, it is characterized in that: comprise flat board (1) and be arranged on a plurality of legs (2) of flat board (1) lower end, and be socketed with sleeve (6) on each leg, the tapered structure in described each sleeve (6) bottom, described flat board (1) upper end is provided with pull bar (3), and described pull bar (3) lower end is vertical with dull and stereotyped (1) fixing.
2. a kind of instrument for controlling concrete floor and build thickness according to claim 1, it is characterized in that: described flat board (1) is steel plate, welding three leg nuts ((4) on described steel plate (1) lower surface, and the straight line at this three leg nuts (4) place consists of triangular structure, described each leg (2) upper end is provided with screw thread, and each leg (2) is threaded with corresponding leg nut (4).
3. a kind of instrument for controlling concrete floor and build thickness according to claim 2 is characterized in that: described sleeve (6) upper end is fixed by socket with corresponding leg nut (4), and is conical structure bottom each sleeve pipe (6).
4. a kind of instrument for controlling concrete floor and build thickness according to claim 3, it is characterized in that: middle part, described steel plate (1) upper surface is provided with pull-rod nut (5), described pull bar (3) lower end is provided with screw thread, and pull bar (3) is by being threaded fixing with pull-rod nut (5).
5. a kind of instrument of building thickness for the control concrete floor according to claim 4, is characterized in that: the contour setting of described a plurality of legs (2).
CN2013100413955A 2013-02-04 2013-02-04 Tool for controlling pouring thickness of concrete floor Pending CN103122695A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100413955A CN103122695A (en) 2013-02-04 2013-02-04 Tool for controlling pouring thickness of concrete floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100413955A CN103122695A (en) 2013-02-04 2013-02-04 Tool for controlling pouring thickness of concrete floor

Publications (1)

Publication Number Publication Date
CN103122695A true CN103122695A (en) 2013-05-29

Family

ID=48453816

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100413955A Pending CN103122695A (en) 2013-02-04 2013-02-04 Tool for controlling pouring thickness of concrete floor

Country Status (1)

Country Link
CN (1) CN103122695A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615063A (en) * 2013-12-12 2014-03-05 深圳市鹏城建筑集团有限公司 Construction method for pouring pitched roof concrete and steel bar structure used in method
CN106437167A (en) * 2016-08-31 2017-02-22 中冶天工集团天津有限公司 Device with functions of thickness measuring and leveling for concrete and usage method thereof
CN108915269A (en) * 2018-06-29 2018-11-30 中国冶集团有限公司 Concrete thickness control and leveling unit and method
CN110836016A (en) * 2019-10-25 2020-02-25 江苏兴厦建设工程集团有限公司 Floor thickness detector and construction process using same

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1423449A (en) * 1964-02-07 1966-01-03 Device for smoothing solid concrete floors
JPH07331879A (en) * 1994-06-02 1995-12-19 Tetsuya Matsushima Floor level
CN201292673Y (en) * 2008-10-09 2009-08-19 江苏省建筑工程集团有限公司 Floor concrete casting thickness controller
CN102127971A (en) * 2011-03-23 2011-07-20 中天建设集团有限公司 Adjustable leveling stool and method for controlling floorslab thickness by using same
CN202416712U (en) * 2012-01-11 2012-09-05 浙江工程建设监理公司 Concrete thickness control measurer for cast-in-place floorslab
CN203034813U (en) * 2013-02-04 2013-07-03 中天建设集团有限公司 Tool for controlling thickness of pouring of concrete floor slab

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1423449A (en) * 1964-02-07 1966-01-03 Device for smoothing solid concrete floors
JPH07331879A (en) * 1994-06-02 1995-12-19 Tetsuya Matsushima Floor level
CN201292673Y (en) * 2008-10-09 2009-08-19 江苏省建筑工程集团有限公司 Floor concrete casting thickness controller
CN102127971A (en) * 2011-03-23 2011-07-20 中天建设集团有限公司 Adjustable leveling stool and method for controlling floorslab thickness by using same
CN202416712U (en) * 2012-01-11 2012-09-05 浙江工程建设监理公司 Concrete thickness control measurer for cast-in-place floorslab
CN203034813U (en) * 2013-02-04 2013-07-03 中天建设集团有限公司 Tool for controlling thickness of pouring of concrete floor slab

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615063A (en) * 2013-12-12 2014-03-05 深圳市鹏城建筑集团有限公司 Construction method for pouring pitched roof concrete and steel bar structure used in method
CN106437167A (en) * 2016-08-31 2017-02-22 中冶天工集团天津有限公司 Device with functions of thickness measuring and leveling for concrete and usage method thereof
CN108915269A (en) * 2018-06-29 2018-11-30 中国冶集团有限公司 Concrete thickness control and leveling unit and method
CN110836016A (en) * 2019-10-25 2020-02-25 江苏兴厦建设工程集团有限公司 Floor thickness detector and construction process using same

Similar Documents

Publication Publication Date Title
CN103122695A (en) Tool for controlling pouring thickness of concrete floor
CN204530742U (en) A kind of adjustable suspension column
CN103184796A (en) Accurate leveling device for cast-in-situ concrete flooring formed in one step and construction method
CN103669655A (en) Construction technology for pouring concrete of walls on two sides of deformation joint
CN103993736A (en) Fastening bolt for shear wall formwork
CN102296828B (en) Construction method of boom before building ceiling or pipelining
CN102995905A (en) Cast-in-place concrete board elevation control device and construction method
CN102677896A (en) Bathroom settlement plate shaping mould and construction method
CN103122696B (en) Cast-in-place concrete floor gage controller and method thereof
CN204676879U (en) Model sheetinstallat structure
CN203175052U (en) Leveler for building floor beam slab construction
CN203034813U (en) Tool for controlling thickness of pouring of concrete floor slab
CN204571294U (en) Different level concrete support mould tool
CN104047228B (en) The prepared hole die of bridge stone bolt
CN103899076A (en) Method and device for quickly demarcating construction standard of brick wall and plaster layer
CN203891470U (en) Fastening bolt for shear wall formwork
CN105839914A (en) Adjustable steel beam supporting device and adjustable steel beam supporting system
CN202100000U (en) Adjustable bracket girder structure for building template
CN204212418U (en) A kind of primary-secondary beam connector
CN204850478U (en) Controlling means is pour to concrete floor thickness
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN203879014U (en) Cast-in-situ concrete floor thickness control device
CN203878943U (en) Calibration device for brick wall and plaster layer construction standard
CN202509750U (en) Height-adjustable type scaffold
CN204266600U (en) A kind of concrete planeness and height controller

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130529