CN102127971A - Adjustable leveling stool and method for controlling floorslab thickness by using same - Google Patents
Adjustable leveling stool and method for controlling floorslab thickness by using same Download PDFInfo
- Publication number
- CN102127971A CN102127971A CN 201110071931 CN201110071931A CN102127971A CN 102127971 A CN102127971 A CN 102127971A CN 201110071931 CN201110071931 CN 201110071931 CN 201110071931 A CN201110071931 A CN 201110071931A CN 102127971 A CN102127971 A CN 102127971A
- Authority
- CN
- China
- Prior art keywords
- stool
- levelling
- thickness
- control
- regulate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses an adjustable leveling stool, which comprises a panel, wherein an upper plane of the panel is provided with a handle; and a lower plane of the panel is provided with three telescopic supporting legs. The invention also provides a method for controlling floorslab thickness by using the adjustable leveling stool, which comprises the following steps of: adjusting the length of the supporting legs according to the thickness of the floorslab, and making the length of the supporting legs equal to the thickness of the floorslab; and arranging the adjustable leveling stool on a floorslab template, and controlling the thickness of the floorslab according to a point-line-plane control method. The leveling stool with the telescopic supporting legs is designed aiming at the problem in the traditional floorslab thickness control; moreover, the thickness of the floorslab is controlled by the leveling stool through the point-line-plane control method; the leveling stool provides convenience for the construction personnel to control the thickness of the floorslab, is easy to operate, low in processing cost and high in control accuracy, can be repeatedly used and can solve the problem of long-span arched floorslab thickness control.
Description
Technical field
The present invention relates to the levelling stool and use the levelling stool to control the method for slab thickness.
Background technology
The method of tradition control slab thickness is an absolute altitude control method, promptly on post, wall reinforcing bar, be ferreted out with respect to floor face+the 50cm relief, backguy control panel face absolute altitude then, thus control slab thickness indirectly.There is the link of many generation deviations in this control method, and as the deviation that template is installed absolute altitude, five zero levels are copied the deviation of survey, the deviation of institute's backguy rope, and deviation that leveling work produced or the like is difficult to so want to control in the deviation range that standard allows; If structural span is big, beam-slab template needs arch camber, and the deviation of slab thickness is just bigger.
Summary of the invention
Technical problem to be solved by this invention just provides a kind of levelling stool of regulating, and is convenient to the control of constructor to slab thickness, and is simple to operate, processing cost is low, but repetitive cycling is used, and the control accuracy height can solve large span arch camber slab thickness control problem.
For solving the problems of the technologies described above, the present invention adopts following technical scheme: can regulate the levelling stool, it is characterized in that: comprise flat board, the plane is provided with the leader on the described flat board, and described dull and stereotyped lower plane is provided with three flexible feets.
Preferably, described flat board is the triangle steel plate, and described three flexible feets are located at the below, three angles of triangle steel plate.
Preferably, described feet comprises the sleeve that is provided with internal thread, and the indented bars head that is threadedly connected in the described sleeve is formed.
The present invention also provides a kind of above-mentioned method of regulating levelling stool control slab thickness of using, and it is characterized in that:
At first according to the thickness of floor, regulate the length of flexible feet, make feet length equal slab thickness, can regulate the levelling stool then places on the slab form, thickness according to point-line-surface control method control floor, concrete enforcement is whole floor face to be resolved into several facets control, each faceted control utilization and concrete thickness of slab can be regulated the levelling stool as one " point " with high one, can regulate the levelling stool with the concrete thickness of slab with high two is that basic point is controlled as one " line ", can regulate the levelling stool can be with using with putting, after a control point uses up, can mention handle, move to next control point, the leveling on plane, a zonule, need three and can regulate the levelling stool, after this zone leveling, the levelling stool can be moved to next zone, all zonules are all after the levelling, just can realize the leveling of whole floor plate, control panel face absolute altitude is controlled slab thickness indirectly effectively.
This problem of the present invention at existence in traditional slab thickness control, design the levelling stool of three flexible feets, and use this levelling stool by point-line-surface control method control slab thickness, be convenient to the control of constructor to slab thickness, simple to operate, processing cost is low, but repetitive cycling is used, the control accuracy height can solve large span arch camber slab thickness control problem.
Description of drawings
Below in conjunction with the drawings and specific embodiments the present invention is further described:
Fig. 1 is the structural representation of levelling stool of the present invention;
The levelling stool was arranged schematic diagram when Fig. 2 can regulate levelling stool control slab thickness for utilizing.
The specific embodiment
As shown in Figure 1, for the present invention can regulate the embodiment of levelling stool, comprise dull and stereotypedly 2, the plane is provided with one 3 hand on the described flat board, and described dull and stereotyped lower plane is provided with three flexible feets.Described dull and stereotyped 2 is the triangle steel plate, and described three flexible feets are located at the below, three angles of triangle steel plate.Described feet comprises the sleeve 4 that is provided with internal thread, and the indented bars head 5 that is threadedly connected in the described sleeve is formed.
As shown in Figure 2, during use, at first according to the thickness of floor, regulate the length of spike, make slab thicknesses such as spike length, can regulate levelling stool 1 then places on the slab form 6, thickness according to point-line-surface control method control floor, also promptly control a plane by one one line, concrete enforcement is whole floor face to be resolved into several facets control, each faceted control utilization and concrete thickness of slab with high one " point " (can regulate the levelling stool for one) and with the concrete thickness of slab with high one " line " (with two can regulate the levelling stool be basic point towards concrete muscle line or the good floor face of levelling) control, be similar to the operation of plastering of pasting the cake floating screed.Can regulate the levelling stool can after a control point uses up, can mention handle with using with putting, and moves to next control point.The leveling on plane, a zonule needs three and can regulate the levelling stool, after this zone leveling, the levelling stool can be moved to next zone.The leveling of whole floor plate all after the levelling, just can be realized in all zonules, and control panel face absolute altitude is controlled slab thickness indirectly effectively.After can regulating the levelling stool and using up, the reinforcing bar spike should be split out, residual cement paste and fine sand on the steel bar end screw thread and in the sleeve cleaned out, and the maintenance that oils, in order to use next time.
Claims (4)
1. can regulate the levelling stool, it is characterized in that: comprise flat board (2), the plane is provided with (a 3) hand on the described flat board, and described dull and stereotyped lower plane is provided with three flexible feets.
2. the levelling stool of regulating according to claim 1 is characterized in that: described flat board (2) is the triangle steel plate, and described three flexible feets are located at the below, three angles of triangle steel plate.
3. the levelling stool of regulating according to claim 2 is characterized in that: described feet comprises the sleeve (4) that is provided with internal thread and is threadedly connected to the interior indented bars head (5) of described sleeve.
4. use the method that to regulate levelling stool control slab thickness, it is characterized in that: at first according to the thickness of floor, regulate the length of flexible feet, make feet length equal slab thickness, can regulate levelling stool (1) then places on the slab form (6), thickness according to point-line-surface control method control floor, concrete enforcement is whole floor face to be resolved into several facets control, each faceted control utilization and concrete thickness of slab can be regulated the levelling stool as one " point " with high one, can regulate the levelling stool with the concrete thickness of slab with high two is that basic point is controlled as one " line ", can regulate the levelling stool with using with putting, after a control point uses up, mention handle, move to next control point, the leveling on plane, a zonule needs three and can regulate the levelling stool, after this zone leveling, the levelling stool can be moved to next zone, the leveling of whole floor plate all after the levelling, has just been realized in all zonules, control panel face absolute altitude is controlled slab thickness indirectly effectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110071931 CN102127971A (en) | 2011-03-23 | 2011-03-23 | Adjustable leveling stool and method for controlling floorslab thickness by using same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110071931 CN102127971A (en) | 2011-03-23 | 2011-03-23 | Adjustable leveling stool and method for controlling floorslab thickness by using same |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102127971A true CN102127971A (en) | 2011-07-20 |
Family
ID=44266224
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110071931 Pending CN102127971A (en) | 2011-03-23 | 2011-03-23 | Adjustable leveling stool and method for controlling floorslab thickness by using same |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102127971A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103122695A (en) * | 2013-02-04 | 2013-05-29 | 中天建设集团有限公司 | Tool for controlling pouring thickness of concrete floor |
CN106437167A (en) * | 2016-08-31 | 2017-02-22 | 中冶天工集团天津有限公司 | Device with functions of thickness measuring and leveling for concrete and usage method thereof |
CN108979155A (en) * | 2018-09-14 | 2018-12-11 | 中铁建设集团有限公司 | A kind of construction operation platform |
CN110485682A (en) * | 2019-08-05 | 2019-11-22 | 中国建筑第八工程局有限公司 | Finished product ash cake and its installation method |
CN110836016A (en) * | 2019-10-25 | 2020-02-25 | 江苏兴厦建设工程集团有限公司 | Floor thickness detector and construction process using same |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2103346A1 (en) * | 1971-01-26 | 1972-08-17 | Adomeit, Heinz, 5800 Hagen | Jig stands for setting the height of leveling gauges for concrete ceiling surfaces |
FR2904996A1 (en) * | 2006-08-17 | 2008-02-22 | Alain Baudry | Low-level supporting tripod for use by e.g. floor coverer, has rod with handle at its upper part and low level support at its lower part, level fixation screw provided below support, and cleats locking feet in open or closed position |
CN101169000A (en) * | 2007-11-16 | 2008-04-30 | 通州建总集团有限公司 | Concrete Thickness Control Device |
CN101260740A (en) * | 2008-04-16 | 2008-09-10 | 江西省第三建筑有限责任公司 | Cast-in-situ floor leveling equipment |
CN201292673Y (en) * | 2008-10-09 | 2009-08-19 | 江苏省建筑工程集团有限公司 | Floor concrete casting thickness controller |
CN101619611A (en) * | 2009-08-04 | 2010-01-06 | 刘贤 | Controller capable of controlling thickness of steel hogging moment steel bar protecting layer of bar concrete cast-in-situ plate and thickness of bar concrete cast-in-situ plate |
CN201972409U (en) * | 2011-03-23 | 2011-09-14 | 中天建设集团有限公司 | Adjustable leveling bench |
-
2011
- 2011-03-23 CN CN 201110071931 patent/CN102127971A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2103346A1 (en) * | 1971-01-26 | 1972-08-17 | Adomeit, Heinz, 5800 Hagen | Jig stands for setting the height of leveling gauges for concrete ceiling surfaces |
FR2904996A1 (en) * | 2006-08-17 | 2008-02-22 | Alain Baudry | Low-level supporting tripod for use by e.g. floor coverer, has rod with handle at its upper part and low level support at its lower part, level fixation screw provided below support, and cleats locking feet in open or closed position |
CN101169000A (en) * | 2007-11-16 | 2008-04-30 | 通州建总集团有限公司 | Concrete Thickness Control Device |
CN101260740A (en) * | 2008-04-16 | 2008-09-10 | 江西省第三建筑有限责任公司 | Cast-in-situ floor leveling equipment |
CN201292673Y (en) * | 2008-10-09 | 2009-08-19 | 江苏省建筑工程集团有限公司 | Floor concrete casting thickness controller |
CN101619611A (en) * | 2009-08-04 | 2010-01-06 | 刘贤 | Controller capable of controlling thickness of steel hogging moment steel bar protecting layer of bar concrete cast-in-situ plate and thickness of bar concrete cast-in-situ plate |
CN201972409U (en) * | 2011-03-23 | 2011-09-14 | 中天建设集团有限公司 | Adjustable leveling bench |
Non-Patent Citations (1)
Title |
---|
《山西建筑》 20040630 牛俊平 楼板混凝土浇筑板面标高控制技术 第30卷, 第11期 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103122695A (en) * | 2013-02-04 | 2013-05-29 | 中天建设集团有限公司 | Tool for controlling pouring thickness of concrete floor |
CN106437167A (en) * | 2016-08-31 | 2017-02-22 | 中冶天工集团天津有限公司 | Device with functions of thickness measuring and leveling for concrete and usage method thereof |
CN108979155A (en) * | 2018-09-14 | 2018-12-11 | 中铁建设集团有限公司 | A kind of construction operation platform |
CN110485682A (en) * | 2019-08-05 | 2019-11-22 | 中国建筑第八工程局有限公司 | Finished product ash cake and its installation method |
CN110836016A (en) * | 2019-10-25 | 2020-02-25 | 江苏兴厦建设工程集团有限公司 | Floor thickness detector and construction process using same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102127971A (en) | Adjustable leveling stool and method for controlling floorslab thickness by using same | |
CN203924349U (en) | A kind of prefabricated panel and superposed beam rapid installing connection structure | |
CN202520003U (en) | Device for adjusting wall-in type masonry horizontal line | |
CN201424810Y (en) | Supporting head of concrete molding board | |
CN206512996U (en) | A kind of leveling structure | |
CN205804904U (en) | A kind of leveling unit | |
CN106812310A (en) | A kind of building template supporting construction | |
CN201972409U (en) | Adjustable leveling bench | |
CN204174898U (en) | A kind of ceramic tile smoother for building | |
CN203097300U (en) | Guide rail type concrete terrace leveling device | |
CN203296379U (en) | Formwork beam supporting device convenient to clamp and adjustable in height | |
CN207847122U (en) | Construction has with adjustable combined type marked rod | |
CN205713112U (en) | A kind of shear wall formwork adjustable base device | |
CN205822723U (en) | New terrestrial ceramic tile is laid mortar and is spread out and put on Levelling Controller | |
CN204311711U (en) | A kind of flexible nose bar for levelling tile paste face | |
CN203514740U (en) | Rib filling device | |
CN203346897U (en) | Foundation raft embedded steel column positioning support | |
CN208934358U (en) | One kind being used for the compound floating screed device of plastering on inner walls gypsum | |
CN204475877U (en) | Infilled wall mortar joint flatness control device | |
CN100543151C (en) | Tamping material leveling unit | |
CN205134896U (en) | Novel infrared ray lining mud foam | |
CN203334524U (en) | Concrete heat-preservation brickwork used for civil engineering | |
CN204040315U (en) | A kind of multi-functional bar concrete structural slab plate muscle bracing or strutting arrangement | |
CN203783129U (en) | Width-retractable formwork device | |
CN110424228A (en) | Construction site temporary road height controller and control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20110720 |