CN103088819A - 预应力锚索施工方法 - Google Patents
预应力锚索施工方法 Download PDFInfo
- Publication number
- CN103088819A CN103088819A CN2013100559957A CN201310055995A CN103088819A CN 103088819 A CN103088819 A CN 103088819A CN 2013100559957 A CN2013100559957 A CN 2013100559957A CN 201310055995 A CN201310055995 A CN 201310055995A CN 103088819 A CN103088819 A CN 103088819A
- Authority
- CN
- China
- Prior art keywords
- anchor cable
- sleeve
- cable
- hole
- stressed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 238000000034 method Methods 0.000 claims abstract description 18
- 238000004873 anchoring Methods 0.000 claims abstract description 10
- 238000009434 installation Methods 0.000 claims abstract description 5
- 238000007569 slipcasting Methods 0.000 claims description 18
- 229910000831 Steel Inorganic materials 0.000 claims description 11
- 239000010959 steel Substances 0.000 claims description 11
- 239000004568 cement Substances 0.000 claims description 10
- 230000008093 supporting effect Effects 0.000 claims description 7
- 238000012546 transfer Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 4
- 238000005516 engineering process Methods 0.000 abstract description 3
- 239000003673 groundwater Substances 0.000 abstract description 2
- 230000001447 compensatory effect Effects 0.000 abstract 1
- 231100000817 safety factor Toxicity 0.000 abstract 1
- 239000002689 soil Substances 0.000 description 10
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 9
- 239000004927 clay Substances 0.000 description 3
- 238000005553 drilling Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 239000000843 powder Substances 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 239000012467 final product Substances 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001141 propulsive effect Effects 0.000 description 1
- -1 silt Substances 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
Images
Abstract
本发明提供一种预应力锚索施工方法,包括以下步骤:钻孔,在套筒保护下进行,所述套筒对锚索孔周边的软弱地层形成支护;成孔后,进行第一次常压注浆,以保证在所述锚索下放的过程中所述套筒不会产生滑动,以及所述锚索安装后能迅速得到固定;安装好所述锚索后,移除所述套筒,然后进行补偿注浆;在所述第一次常压注浆所形成的注浆体的强度达到所需值时,进行第二次劈裂高压注浆,使所述锚索能锚固牢固。本发明有效地弥补了普通预应力锚索施工工艺的不足,能大大提高富含地下水的软弱地层边坡的预应力锚索支护效果,提高工程建设速度,增加边坡安全系数。
Description
技术领域
本发明涉及一种预应力锚索施工方法,具体是一种在基坑边坡支护技术领域中用于淤泥质粘土、粉细砂层等自稳能力较差的富水软弱地层的预应力锚索施工方法。
背景技术
近年来,随着我国基础设施建设的高速发展,高速公路、工业与民用建筑、城市轨道交通、大型公共设施、体育场馆等项目中将涉及到越来越多的边坡工程,其中边坡支护成为工程质量和安全的重难点。在深基坑边坡支护工程中,常常采用桩加预应力锚索或含预应力锚索的复合土钉墙的支护形式。在一般预应力锚索施工中,多采用普通螺旋钻机成孔,下放锚索、注浆,到达一定强度后进行张拉。但是在淤泥、粉细纱等自稳性较差的软弱土层中,如果采用普通锚索施工方法则难以保证成孔质量和获得理想的拉拔力。因此,如何在富水软弱地层进行预应力锚索的施工是目前亟待解决的问题。
发明内容
本发明提供的预应力锚索施工方法采用套筒保护钻孔及两次注浆相结合的方式进行锚索的施工,能确保锚索的有效直径和长度,强化预应力锚索的支护效果。
本发明提供的预应力锚索施工方法包括以下步骤:钻孔,在套筒保护下进行,所述套筒对锚索孔周边的软弱地层形成支护;成孔后,进行第一次常压注浆,以保证在所述锚索下放的过程中所述套筒不会产生滑动,以及所述锚索安装后能迅速得到固定;安装好所述锚索后,移除所述套筒,然后进行补偿注浆;在所述第一次常压注浆所形成的注浆体的强度达到所需值时,进行第二次劈裂高压注浆,使所述锚索能锚固牢固。
所述套筒可以选用钢套筒。
所述锚索可以由钢绞线制成。
本发明有效地弥补了普通预应力锚索施工工艺的不足,能大大提高富含地下水的软弱地层边坡的预应力锚索支护效果,提高工程建设速度,增加边坡安全系数。
附图说明
图1是本发明具体实施方式的施工工艺流程图。
具体实施方式
下面结合附图和具体例子对本发明的预应力锚索施工方法进行说明。
在本例子中,施工地区的主要地质条件为粘土、粉质粘土、粉土、粉细砂,局部夹杂淤泥,地下水丰富,属富水软弱地层。对于此种地层,采用常规锚索施工方法难以保证成孔质量和获得理想的拉拔力。
本发明的发明人在传统预应力锚索施工方法的基础上,采用套筒保护锚索孔,在成孔的过程中套筒跟进,完成注浆及锚索下放后,再拔出套筒,这样可以有效地防止锚索孔坍塌,确保锚索的有效直径和长度。采用两次注浆即第一次常压注浆和第二次高压劈裂注浆的施工工艺,能有效地增加锚索与土体的接触面积,提高锚杆的拉拔力,强化预应力锚索的支护效果。具体施工工艺流程如下。
1、施工准备
施工准备包括场地布置、机械设备安装调试、人员上场和材料购置及储备等工作。
2、钻孔(套筒保护)
钻孔包括钻机就位、成孔和清孔三个步骤。测量放点后,调整钻机的位置和角度。钻进采用套筒跟进水冲法作业,钻机内配置高压泵及可冲击钻头,土壤在高压水冲击及钻头推进力的作用下冲散形成锚索孔,泥浆及水沿套筒周边涌出,反复冲击,形成扩大头锚索,能更有力的保证锚索的支撑作用。随着钻孔深度加深,套筒长度也相应增加,两段套筒采用例如螺纹连接的方式进行连接,以保证锚索孔被套筒保护,同时套筒对锚索孔周边的软弱地层形成一个支护体系,保证了成孔的质量。套筒可以选用钢套筒,也可以是其他材料的套筒。
3、第一次常压注浆
钻孔结束后彻底清理锚索孔,然后立即插入锚索进行注浆。第一次常压注浆采用水泥净浆,由于注入的水泥浆较锚索孔内残留的泥浆、清水比重大,故能依次将泥浆、清水置换出来,从锚索孔的底部开始注浆,当锚索孔内冒出的水泥浆与注入的水泥浆相同时,再继续注浆一段时间即可。套筒与土体之间的间隙处及锚索孔内均需要进行注浆。这样可以保证在锚索下放的过程中,套筒不会因为周边土体的软弱性而产生滑动,从而避免影响预应力锚索的施工质量,同时在锚索下放的过程中,也可以通过锚索孔内的泥浆的压力作用,保证锚索安装后能够迅速得到固定。注浆压力经试验确定,所注浆料根据试验可相应进行调整。
4、锚索的制作与安装
在钻孔的同时,进行锚索的制作。以采用钢绞线制作锚索为例,钢绞线下料长度为锚索设计长度、张拉承台高度、千斤顶长度、张拉操作长度之和。锚索的钢绞线按要求进行绑扎制作成束,编束时要把钢绞线理顺后再进行绑扎,最后在内锚固段端头装上锥形导向帽。钢绞线两端与锚头的嵌固端牢固联结,两个嵌固端之间的每根钢绞线长度保持一致。锚索加工后经检验合格方可下放。锚索束必须顺直地安放在钻孔中心,并在锚索孔外露出足够的张拉长度。
5、套筒拔除及补偿注浆
锚索下放至设计深度后,即逐段拔除和拆除套筒。套筒取出后,及时对锚索孔进行补偿注浆,直至锚索孔口返水泥浆为止。
6、第二次劈裂高压注浆
第二次高压注浆采用水泥净浆,高压注浆在锚固段第一次注浆体强度达到所需值时进行,第二次注浆压力经试验后确定,其目的是再次向锚固区段注浆,使第一次注浆体被劈裂,浆液在高压下被压入孔内壁的土体中,使锚索能牢固地锚固在土层中。在第二次注浆中必须将锚固段完全注满浆,浆液在高压下充分将锚固体与土层间的空隙填充,增强锚固体与土体之间的锚固效果,从而使锚索能更牢固地锚固在土层中。
7、张拉锁定
张拉前,张拉设备必须配套标定,张拉采用液压千斤顶。安放千斤顶时,使锚具底座顶面与钻孔轴线垂直,以确保锚索张拉时千斤顶出力与锚索在同一轴线上。
以上通过具体实施方式对本发明进行了详细的说明,但本发明并不受限于此。在实现本发明目的的前提下,本领域技术人员可对本发明作出各种改变和变型。
Claims (3)
1.一种预应力锚索施工方法,包括以下步骤:
钻孔,在套筒保护下进行,所述套筒对锚索孔周边的软弱地层形成支护;
成孔后,进行第一次常压注浆,以保证在所述锚索下放的过程中所述套筒不会产生滑动,以及所述锚索安装后能迅速得到固定;
安装好所述锚索后,移除所述套筒,然后进行补偿注浆;
在所述第一次常压注浆所形成的注浆体的强度达到所需值时,进行第二次劈裂高压注浆,使所述锚索能锚固牢固。
2.根据权利要求1所述的预应力锚索施工方法,其特征在于,所述套筒是钢套筒。
3.根据权利要求1或2所述的预应力锚索施工方法,其特征在于,所述锚索由钢绞线制成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310055995.7A CN103088819B (zh) | 2013-02-22 | 2013-02-22 | 预应力锚索施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310055995.7A CN103088819B (zh) | 2013-02-22 | 2013-02-22 | 预应力锚索施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103088819A true CN103088819A (zh) | 2013-05-08 |
CN103088819B CN103088819B (zh) | 2016-04-06 |
Family
ID=48201910
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310055995.7A Active CN103088819B (zh) | 2013-02-22 | 2013-02-22 | 预应力锚索施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103088819B (zh) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103698215A (zh) * | 2013-12-31 | 2014-04-02 | 中国地质大学(北京) | 锚索拉拔试验装置 |
CN103911994A (zh) * | 2014-04-18 | 2014-07-09 | 周同和 | 一种预应力锚杆施工工艺 |
CN103911993A (zh) * | 2014-04-18 | 2014-07-09 | 周同和 | 一种pha锚杆及其施工方法 |
CN103924592A (zh) * | 2014-04-18 | 2014-07-16 | 周同和 | 一种压力型pha锚杆及其施工方法 |
CN105297722A (zh) * | 2015-10-24 | 2016-02-03 | 江南水利水电工程公司 | 拉力型无粘接预应力锚索的施工方法 |
CN106149717A (zh) * | 2016-07-22 | 2016-11-23 | 四川大学 | 一种高安全性预应力锚索施工方法 |
CN106223336A (zh) * | 2016-07-22 | 2016-12-14 | 四川大学 | 一种预应力锚索施工方法 |
CN106284342A (zh) * | 2016-08-30 | 2017-01-04 | 中国建筑西南勘察设计研究院有限公司 | 机械搅拌式扩体抗浮锚杆施工方法 |
CN106907167A (zh) * | 2017-05-03 | 2017-06-30 | 刘伟 | 坑内采场上向长锚索分次注浆施工结构及其施工方法 |
CN107165661A (zh) * | 2017-06-09 | 2017-09-15 | 中铁建大桥工程局集团第五工程有限公司 | 一种高地应力软弱围岩大变形隧道超长扩大头锚索施工方法 |
CN109026097A (zh) * | 2018-07-17 | 2018-12-18 | 深圳市工勘岩土集团有限公司 | 一种抗浮锚杆双钻头成孔施工方法 |
CN110306574A (zh) * | 2019-07-18 | 2019-10-08 | 广东厚普建设工程有限公司 | 一种预应力锚索施工方法 |
CN112878322A (zh) * | 2021-03-23 | 2021-06-01 | 北京京能建设集团有限公司 | 一种地下水水位以下锚杆施工方法 |
CN114411778A (zh) * | 2022-02-28 | 2022-04-29 | 广西洪鼎建筑工程有限公司 | 一种边坡锚索及其边坡锚固施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4132498A (en) * | 1977-02-17 | 1979-01-02 | Shigeru Sugimura | Earth anchor and method of setting and removing same |
CN101532292A (zh) * | 2008-03-14 | 2009-09-16 | 上海市基础工程公司 | 旋喷锚杆施工工艺 |
CN102644285A (zh) * | 2011-02-16 | 2012-08-22 | 五冶集团上海有限公司 | 锚索钻孔防塌孔施工方法 |
CN102797256A (zh) * | 2012-09-11 | 2012-11-28 | 中建八局第三建设有限公司 | 一种穿越软土层的锚索施工方法 |
-
2013
- 2013-02-22 CN CN201310055995.7A patent/CN103088819B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4132498A (en) * | 1977-02-17 | 1979-01-02 | Shigeru Sugimura | Earth anchor and method of setting and removing same |
CN101532292A (zh) * | 2008-03-14 | 2009-09-16 | 上海市基础工程公司 | 旋喷锚杆施工工艺 |
CN102644285A (zh) * | 2011-02-16 | 2012-08-22 | 五冶集团上海有限公司 | 锚索钻孔防塌孔施工方法 |
CN102797256A (zh) * | 2012-09-11 | 2012-11-28 | 中建八局第三建设有限公司 | 一种穿越软土层的锚索施工方法 |
Non-Patent Citations (3)
Title |
---|
刘晓东: "对深基坑预应力锚索施工技术方法的探讨", 《城市建设理论研究(电子版)》 * |
杨建国: "复杂地质条件下预应力锚索和注浆联合支护技术", 《煤炭科学技术》 * |
邵东辉: "同心跟管钻孔技术在拱座基坑预应力锚索施工中的应用", 《四川建材》 * |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103698215A (zh) * | 2013-12-31 | 2014-04-02 | 中国地质大学(北京) | 锚索拉拔试验装置 |
CN103698215B (zh) * | 2013-12-31 | 2016-03-02 | 中国地质大学(北京) | 锚索拉拔试验装置 |
CN103911994A (zh) * | 2014-04-18 | 2014-07-09 | 周同和 | 一种预应力锚杆施工工艺 |
CN103911993A (zh) * | 2014-04-18 | 2014-07-09 | 周同和 | 一种pha锚杆及其施工方法 |
CN103924592A (zh) * | 2014-04-18 | 2014-07-16 | 周同和 | 一种压力型pha锚杆及其施工方法 |
CN103911993B (zh) * | 2014-04-18 | 2016-05-04 | 周同和 | 一种pha锚杆及其施工方法 |
CN105297722A (zh) * | 2015-10-24 | 2016-02-03 | 江南水利水电工程公司 | 拉力型无粘接预应力锚索的施工方法 |
CN106223336A (zh) * | 2016-07-22 | 2016-12-14 | 四川大学 | 一种预应力锚索施工方法 |
CN106149717A (zh) * | 2016-07-22 | 2016-11-23 | 四川大学 | 一种高安全性预应力锚索施工方法 |
CN106284342A (zh) * | 2016-08-30 | 2017-01-04 | 中国建筑西南勘察设计研究院有限公司 | 机械搅拌式扩体抗浮锚杆施工方法 |
CN106907167A (zh) * | 2017-05-03 | 2017-06-30 | 刘伟 | 坑内采场上向长锚索分次注浆施工结构及其施工方法 |
CN107165661A (zh) * | 2017-06-09 | 2017-09-15 | 中铁建大桥工程局集团第五工程有限公司 | 一种高地应力软弱围岩大变形隧道超长扩大头锚索施工方法 |
CN109026097A (zh) * | 2018-07-17 | 2018-12-18 | 深圳市工勘岩土集团有限公司 | 一种抗浮锚杆双钻头成孔施工方法 |
CN109026097B (zh) * | 2018-07-17 | 2020-09-01 | 深圳市地质环境研究院有限公司 | 一种抗浮锚杆双钻头成孔施工方法 |
CN110306574A (zh) * | 2019-07-18 | 2019-10-08 | 广东厚普建设工程有限公司 | 一种预应力锚索施工方法 |
CN112878322A (zh) * | 2021-03-23 | 2021-06-01 | 北京京能建设集团有限公司 | 一种地下水水位以下锚杆施工方法 |
CN114411778A (zh) * | 2022-02-28 | 2022-04-29 | 广西洪鼎建筑工程有限公司 | 一种边坡锚索及其边坡锚固施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103088819B (zh) | 2016-04-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103088819B (zh) | 预应力锚索施工方法 | |
CN105781571A (zh) | 一种软岩变形隧道衬砌支护拆换拱施工方法 | |
CN109763483B (zh) | 一种厚第四系深埋采空塌陷破碎地层上行式分段注浆工艺 | |
CN104895072B (zh) | 一种预应力锚索以及预应力锚索一次成型施工方法 | |
CN103774664B (zh) | 地下室抗浮钢锚索的防水构造及施工方法 | |
CN110409461A (zh) | 一种基于装配式大直径管桩的基坑支护施工方法 | |
CN107165661A (zh) | 一种高地应力软弱围岩大变形隧道超长扩大头锚索施工方法 | |
RU83517U1 (ru) | Грунтовый анкер | |
CN106498943A (zh) | 一次性高压旋喷型扩大头预应力土锚杆施工方法 | |
CN109555548A (zh) | 一种利用超长扩大头锚索对高地应力软弱围岩隧道形成的支护结构 | |
CN106968245A (zh) | 预应力锚索人工挖孔抗拔桩及其施工方法 | |
CN110593254A (zh) | 一种在夹有溶洞的节理带地层中的钻孔灌注桩施工方法 | |
CN104372793A (zh) | 采用旋喷桩法预应力锚索用于既有地下室抗浮的方法 | |
CN110644492B (zh) | 陡倾角宽大裂隙地层综合灌浆施工方法 | |
CN205576957U (zh) | 桩底桩结构 | |
CN103883339B (zh) | 一种重复施加预应力的锚索支护方法 | |
CN204199296U (zh) | 基于老旧地下室外墙结构的基坑支护结构 | |
CN203113332U (zh) | 一种工后锚杆施工结构装置 | |
CN102535462A (zh) | 砂层锚索施工方法 | |
CN109555545A (zh) | 高地应力软弱围岩大变形隧道超长扩大头锚索施工方法 | |
CN209260775U (zh) | 锚索可回收压力分散型囊袋扩体抗浮桩 | |
CN205677538U (zh) | 一种可回收锚索的锚杆钻头 | |
CN112963186A (zh) | 一种沿空掘巷窄煤柱加固支护方法 | |
CN107023008B (zh) | 护壁及反力用沉井平台拔桩方法及系统 | |
CN105952381A (zh) | 一种可回收锚索的锚杆钻头 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
C41 | Transfer of patent application or patent right or utility model | ||
GR01 | Patent grant | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20160315 Address after: 100045 Beijing city Xicheng District South Road No. 17 Applicant after: Beijing municipal administration road and bridge limited company Address before: 100068 Fengtai District South Fourth Ring Road, Beijing, No. 163 Applicant before: Beijing Road and Bridge Construction Co., Ltd. |