CN103061365A - 一种混凝土基础的扩建方法 - Google Patents

一种混凝土基础的扩建方法 Download PDF

Info

Publication number
CN103061365A
CN103061365A CN2013100384261A CN201310038426A CN103061365A CN 103061365 A CN103061365 A CN 103061365A CN 2013100384261 A CN2013100384261 A CN 2013100384261A CN 201310038426 A CN201310038426 A CN 201310038426A CN 103061365 A CN103061365 A CN 103061365A
Authority
CN
China
Prior art keywords
concrete
foundation
old
new
old concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100384261A
Other languages
English (en)
Inventor
杨彬
王国强
宋富强
杜彦斌
韩红娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinxing Energy Equipment Co Ltd
Original Assignee
Xinxing Energy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinxing Energy Equipment Co Ltd filed Critical Xinxing Energy Equipment Co Ltd
Priority to CN2013100384261A priority Critical patent/CN103061365A/zh
Publication of CN103061365A publication Critical patent/CN103061365A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明涉及一种混凝土基础的扩建方法,包括下列步骤:①将原有基础的旧混凝土四周开挖,将旧混凝土的原基础钢筋凿出;②取与原基础钢筋同直径,同材质的钢筋与原基础钢筋焊接在一起;③将新旧混凝土的接触面凿毛,用清水冲洗干净,刷混凝土界面剂;④建新混凝土模腔,浇筑新混凝土。它解决了基础在上部荷载增大的情况下,通过基础扩建的方式提高承载力的问题,同时避免了清除原有基础造成的施工时间增加,施工难度大的问题。

Description

一种混凝土基础的扩建方法
技术领域
本发明涉及一种属于土木建筑技术领域,特别是涉及一种混凝土基础的扩建方法。
背景技术
目前随着经济的不断发展,经常遇到混凝土建筑改造的问题,处理方法一是将原基础清除,新作基础以满足要求,二是将原基础改造,基础改造可以节省大量投资,减少施工时间。
发明内容
为了克服现有技术的缺点,本发明提供一种混凝土基础的扩建方法,它解决了基础在上部荷载增大的情况下,通过基础扩建的方式提高承载力的问题,同时避免了清除原有基础造成的施工时间增加,施工难度大的问题。
本发明解决其技术问题所采取的技术方案是:包括下列步骤:①、将原有基础的旧混凝土四周开挖,将旧混凝土的原基础钢筋凿出;②、取与原基础钢筋同直径,同材质的钢筋与原基础钢筋焊接在一起;③、将新旧混凝土的接触面凿毛,用清水冲洗干净,刷混凝土界面剂;④、建新混凝土模腔,浇筑新混凝土。
本发明具有下列优点:1)、节省施工时间;2)、避免清除原基础,节省投资;3)、新旧钢筋连接方法简单;4)、新旧混凝土接触面连接可靠,新旧混凝土工作协调。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1为本发明示意图。
具体实施方式
如图1所示,本发明包括下列步骤:①、将原有基础的旧混凝土1四周开挖,将旧混凝土1的原基础钢筋2凿出;②、取与原基础钢筋2同直径,同材质的钢筋4与原基础钢筋2焊接在一起;③、将新旧混凝土的接触面5凿毛,用清水冲洗干净,刷混凝土界面剂;④、建新混凝土模腔6,浇筑新混凝土。
所述的步骤②、③之间增加开槽工序:在新旧混凝土接触面5的旧混凝土上开槽3,以增加新旧混凝土的连接强度。
所述开槽3的横截面为燕尾形。
所述的步骤②、③之间增加锚固工序:在新旧混凝土接触面5的旧混凝土上打锚固杆。

Claims (4)

1.一种混凝土基础的扩建方法,其特征在于:包括下列步骤:①、将原有基础的旧混凝土(1)四周开挖,将旧混凝土(1)的原基础钢筋(2)凿出;②、取与原基础钢筋(2)同直径,同材质的钢筋(4)与原基础钢筋(2)焊接在一起;③、将新旧混凝土的接触面(5)凿毛,用清水冲洗干净,刷混凝土界面剂;④、建新混凝土模腔(6),浇筑新混凝土。
2.根据权利要求1所述的混凝土基础的扩建方法,其特征在于:所述的步骤②、③之间增加开槽工序:在新旧混凝土接触面(5)的旧混凝土上开槽(3)。
3.根据权利要求2所述的混凝土基础的扩建方法,其特征在于:所述开槽(3)的横截面为燕尾形。
4.根据权利要求1所述的混凝土基础的扩建方法,其特征在于:所述的步骤②、③之间增加锚固工序:在新旧混凝土接触面(5)的旧混凝土上打锚固杆。
CN2013100384261A 2013-01-31 2013-01-31 一种混凝土基础的扩建方法 Pending CN103061365A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100384261A CN103061365A (zh) 2013-01-31 2013-01-31 一种混凝土基础的扩建方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100384261A CN103061365A (zh) 2013-01-31 2013-01-31 一种混凝土基础的扩建方法

Publications (1)

Publication Number Publication Date
CN103061365A true CN103061365A (zh) 2013-04-24

Family

ID=48104231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100384261A Pending CN103061365A (zh) 2013-01-31 2013-01-31 一种混凝土基础的扩建方法

Country Status (1)

Country Link
CN (1) CN103061365A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005433A (zh) * 2014-05-16 2014-08-27 上海纺织建筑设计研究院 新型基础加固方法及其构造
CN104695491A (zh) * 2013-12-04 2015-06-10 贵阳铝镁设计研究院有限公司 一种不合格预制柱基础杯口的加固方法及结构
CN109610646A (zh) * 2018-12-19 2019-04-12 广东工业大学 一种新旧混凝土连接结构

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163275A (ja) * 2003-11-28 2005-06-23 Grand Data Kk 布基礎補強構造とその工法
CN101250886A (zh) * 2008-04-09 2008-08-27 武汉大学 一种加固砌体结构建筑物基础的方法
CN101463610A (zh) * 2007-12-20 2009-06-24 上海市基础工程公司 承台大体积砼与内置砼支撑综合处理方法
CN102535536A (zh) * 2012-03-21 2012-07-04 郭猛 一种提高独立基础受弯剪承载力的加固方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163275A (ja) * 2003-11-28 2005-06-23 Grand Data Kk 布基礎補強構造とその工法
CN101463610A (zh) * 2007-12-20 2009-06-24 上海市基础工程公司 承台大体积砼与内置砼支撑综合处理方法
CN101250886A (zh) * 2008-04-09 2008-08-27 武汉大学 一种加固砌体结构建筑物基础的方法
CN102535536A (zh) * 2012-03-21 2012-07-04 郭猛 一种提高独立基础受弯剪承载力的加固方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张永钧等: "《既有建筑地基基础加固工程实例应用手册》", 31 January 2002, 中国建筑工业出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695491A (zh) * 2013-12-04 2015-06-10 贵阳铝镁设计研究院有限公司 一种不合格预制柱基础杯口的加固方法及结构
CN104005433A (zh) * 2014-05-16 2014-08-27 上海纺织建筑设计研究院 新型基础加固方法及其构造
CN104005433B (zh) * 2014-05-16 2016-05-11 上海纺织建筑设计研究院 基础加固方法及其构造
CN109610646A (zh) * 2018-12-19 2019-04-12 广东工业大学 一种新旧混凝土连接结构

Similar Documents

Publication Publication Date Title
CN201981532U (zh) 承重式超深地下连续墙接头
CN105971159B (zh) 一种3d打印配筋砌体剪力墙中的砌体外壳结构
CN203654299U (zh) 一种钢支撑活络端
CN103831507B (zh) 大跨度钢桁梁桥整体桁片全焊节点焊接方法
CN103061365A (zh) 一种混凝土基础的扩建方法
CN104652815A (zh) 一种厨卫间止水反梁浇筑的施工方法
CN103669866A (zh) 地下室钢筋混凝土柱节点连接结构的施工方法
CN101570973B (zh) 外贴止水带内贴防水工艺
CN203846458U (zh) 一种混凝土施工专用模板系统
CN110397074B (zh) 一种通信杆塔地锚加固结构及其施工方法
CN210458914U (zh) 预制桥梁墩柱与盖梁的连接结构
CN102031876B (zh) 建筑物新增立柱的方法
CN105275013B (zh) 一种核心筒逆作叠合地下连续墙及其施工方法
CN206844316U (zh) 一种带套管的装配式钢筋混凝土柱与柱拼接节点
CN205188999U (zh) 一种逆作法竖向支承体系
CN206752693U (zh) 一种箍筋加密的装配式钢筋混凝土柱与柱拼接节点
CN102865083A (zh) 既有地下室结构的无工作井盾构接收工法及其构造
CN210857596U (zh) 一种预制装配式无筋混凝土剪力墙
CN107916625A (zh) 一种宽悬臂箱梁的加宽结构及其方法
CN104594654A (zh) 一种建筑物加固改造方案生成方法
CN104420487A (zh) 一种基础短柱的加固方法及结构
CN105970917A (zh) 一种控制钻孔灌注桩桩顶超灌混凝土的方法
CN108999200A (zh) 一种装配式锚杆框格梁施工方法
CN108301404B (zh) Smw工法桩型钢拔除与高压注浆同步施工方法
CN102797356A (zh) 一种剪力墙接茬模板加固螺栓

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130424