CN103046747B - Use the inclination concrete structure pouring technique that spiral protective sheath carries out - Google Patents

Use the inclination concrete structure pouring technique that spiral protective sheath carries out Download PDF

Info

Publication number
CN103046747B
CN103046747B CN201310020357.1A CN201310020357A CN103046747B CN 103046747 B CN103046747 B CN 103046747B CN 201310020357 A CN201310020357 A CN 201310020357A CN 103046747 B CN103046747 B CN 103046747B
Authority
CN
China
Prior art keywords
protective sheath
spiral protective
inclination
concrete structure
main muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310020357.1A
Other languages
Chinese (zh)
Other versions
CN103046747A (en
Inventor
胡诗珠
许海峰
吴欣之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201310020357.1A priority Critical patent/CN103046747B/en
Publication of CN103046747A publication Critical patent/CN103046747A/en
Application granted granted Critical
Publication of CN103046747B publication Critical patent/CN103046747B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a kind of spiral protective sheath and inclination concrete structure pouring technique; described inclination concrete structure pouring technique adopt scene everywhere visible reinforcing bar as material; its shape of simple change and make spiral protective sheath; and be fixedly welded on the main muscle of incline structure; make the pump line of oscillating column pump can along spiral protective sheath; namely any position in incline structure is inserted into along the direction of main muscle tilted; avoid in prior art the generation of the situations such as leakiness of vibrating, substantially increase pouring quality and the efficiency of inclination concrete structure.

Description

Use the inclination concrete structure pouring technique that spiral protective sheath carries out
Technical field
The present invention relates to the casting craft of concrete structure, particularly relate to a kind of spiral protective sheath and inclination concrete structure pouring technique.
Background technology
Along with the progress of construction technology, novel structure is more and more applied at building field, large volume concrete structural is combined rigidity and the stability that effectively can strengthen steel work with steel work, the usual scale of construction of this concrete structure is large and special-shaped, such component exists builds complex procedures, compactness is difficult to the features such as guarantee, carrying out in casting and compacting of concrete process, because oscillating column pump can not when inserting in this structure insert along the incline direction of incline structure and fix well, do not go deep into the bottom of incline structure, therefore water the process of smashing to be difficult to make concrete compaction, greatly reduce the pouring quality of concrete structure.
Summary of the invention
The object of this invention is to provide a kind of spiral protective sheath and inclination concrete structure pouring technique, with solve exist in prior art medium dip concrete structure pouring process water to smash and be difficult to the problems such as closely knit.
For solving the problems of the technologies described above; the invention provides a kind of spiral protective sheath; be applied in inclination concrete structure pouring technique, described spiral protective sheath is twisted into spiral helicine reinforcing bar by one and forms, and described reinforcing bar material therefor is identical with the main muscle in inclination concrete structure.
The present invention also provides a kind of inclination concrete structure pouring technique using above-mentioned spiral protective sheath, and its method comprises:
Step one: select unnecessary described reinforcing bar on building sites, and according to the pump tube length of oscillating column pump and the operating position of operating personnel, be made into the described spiral protective sheath of some designated length;
Step 2: arrange described some spiral protective sheaths in plum blossom-shaped in the inclination of putting up main muscle structure, described spiral protective sheath and described main muscle are welded to connect, the angle of inclination of described spiral protective sheath is consistent with the angle of inclination of described main muscle;
Step 3: the insertion depth marking the pump line of described oscillating column pump according to concreting lift height on described spiral protective sheath, and the pump line inserting described oscillating column pump along described spiral protective sheath is to this degree of depth;
Step 4: concreting in the main muscle structure of inclination, and carry out by described oscillating column pump work of vibrating.
Compared with prior art, the present invention has following beneficial effect:
Inclination concrete structure pouring technique provided by the invention adopt scene everywhere visible reinforcing bar as material; its shape of simple change and make spiral protective sheath; and be fixedly welded on the main muscle of incline structure; make the pump line of oscillating column pump can along spiral protective sheath; namely any position in incline structure is inserted into along the direction of main muscle tilted; avoid in prior art the generation of the situations such as leakiness of vibrating, substantially increase pouring quality and the efficiency of inclination concrete structure.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the invention will be further described:
The structural representation of the spiral protective sheath that Fig. 1 provides for the embodiment of the present invention;
The position figure of the spiral protective sheath that Fig. 2 provides for the embodiment of the present invention;
Fig. 3 is structural representation when spiral protective sheath that the embodiment of the present invention provides is connected with main muscle;
The structural representation of inclination concrete structure when building that Fig. 4 provides for the embodiment of the present invention.
In Fig. 1 to Fig. 4,
1: spiral protective sheath; 2: inclination concrete structure; 3: main muscle; 4: pump line.
Detailed description of the invention
The spiral protective sheath proposed the present invention below in conjunction with the drawings and specific embodiments and inclination concrete structure pouring technique are described in further detail.According to the following describes and claims, advantages and features of the invention will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, the aid illustration embodiment of the present invention lucidly.
Core concept of the present invention is, a kind of spiral protective sheath and inclination concrete structure pouring technique are provided, described inclination concrete structure pouring technique adopt scene everywhere visible reinforcing bar as material, its shape of simple change and make spiral protective sheath, and be fixedly welded on the main muscle of incline structure, make the pump line of oscillating column pump can along spiral protective sheath, namely any position in incline structure is inserted into along the direction of main muscle tilted, avoid in prior art the generation of the situations such as leakiness of vibrating, substantially increase pouring quality and the efficiency of inclination concrete structure.
Please refer to Fig. 1 to Fig. 4, the structural representation of the spiral protective sheath that Fig. 1 provides for the embodiment of the present invention; The position figure of the spiral protective sheath that Fig. 2 provides for the embodiment of the present invention; Fig. 3 is structural representation when spiral protective sheath that the embodiment of the present invention provides is connected with main muscle; The structural representation of inclination concrete structure when building that Fig. 4 provides for the embodiment of the present invention.
Please emphasis with reference to figure 1; as shown in Figure 1; the embodiment of the present invention provides a kind of spiral protective sheath 1; be applied in the casting craft of inclination concrete structure 2; described spiral protective sheath 1 is twisted into spiral helicine reinforcing bar by one and forms, and described reinforcing bar material therefor is identical with the main muscle 3 in inclination concrete structure 2.
Please emphasis referring to figs. 2 to Fig. 4, and composition graphs 1, as shown in Figures 1 to 4, the embodiment of the present invention also provides a kind of casting craft using the inclination concrete structure 2 of above-mentioned spiral protective sheath 1, and its method comprises:
Step one: select unnecessary described reinforcing bar on building sites, and according to pump line 4 length of oscillating column pump and the operating position of operating personnel, be made into the described spiral protective sheath 1 of some designated length;
Step 2: arrange described some spiral protective sheaths 1 in plum blossom-shaped in the inclination of putting up main muscle structure, be welded to connect with described main muscle 3 by described spiral protective sheath 1, the angle of inclination of described spiral protective sheath 1 is consistent with the angle of inclination of described main muscle 3;
Step 3: the insertion depth marking the pump line 4 of described oscillating column pump according to concreting lift height on described spiral protective sheath 1, and insert the pump line 4 of described oscillating column pump to this degree of depth along described spiral protective sheath 1;
Step 4: concreting in the main muscle structure of inclination, and carry out by described oscillating column pump work of vibrating.
Inclination concrete structure pouring technique provided by the invention adopt scene everywhere visible reinforcing bar as material; its shape of simple change and make spiral protective sheath 1; and be fixedly welded on the main muscle 3 of incline structure; make the pump line 4 of oscillating column pump can along spiral protective sheath 1; namely any position in incline structure is inserted into along the direction of main muscle 3 tilted; avoid in prior art the generation of the situations such as leakiness of vibrating, substantially increase pouring quality and the efficiency of inclination concrete structure 2.
Obviously, those skilled in the art can carry out various change and distortion to the present invention and not depart from the spirit and scope of the present invention.Like this, if these amendments of the present invention and modification belong within the scope of the claims in the present invention and equivalent technologies thereof, then the present invention is also intended to comprise these change and modification.

Claims (1)

1. the inclination concrete structure pouring technique using spiral protective sheath to carry out, is characterized in that, comprising:
Step one: select unnecessary reinforcing bar on building sites, and according to the pump tube length of oscillating column pump and the operating position of operating personnel, be made into the spiral protective sheath of some designated length, described spiral protective sheath is twisted into spiral helicine reinforcing bar by one and forms, and described reinforcing bar material therefor is identical with the main muscle in inclination concrete structure;
Step 2: arrange described some spiral protective sheaths in plum blossom-shaped in the inclination of putting up main muscle structure, described spiral protective sheath and described main muscle are welded to connect, the angle of inclination of described spiral protective sheath is consistent with the angle of inclination of described main muscle;
Step 3: the insertion depth marking the pump line of described oscillating column pump according to concreting lift height on described spiral protective sheath, and the pump line inserting described oscillating column pump along described spiral protective sheath is to this degree of depth;
Step 4: concreting in the main muscle structure of inclination, and carry out by described oscillating column pump work of vibrating.
CN201310020357.1A 2013-01-18 2013-01-18 Use the inclination concrete structure pouring technique that spiral protective sheath carries out Expired - Fee Related CN103046747B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310020357.1A CN103046747B (en) 2013-01-18 2013-01-18 Use the inclination concrete structure pouring technique that spiral protective sheath carries out

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310020357.1A CN103046747B (en) 2013-01-18 2013-01-18 Use the inclination concrete structure pouring technique that spiral protective sheath carries out

Publications (2)

Publication Number Publication Date
CN103046747A CN103046747A (en) 2013-04-17
CN103046747B true CN103046747B (en) 2015-08-19

Family

ID=48059578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310020357.1A Expired - Fee Related CN103046747B (en) 2013-01-18 2013-01-18 Use the inclination concrete structure pouring technique that spiral protective sheath carries out

Country Status (1)

Country Link
CN (1) CN103046747B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104746878B (en) * 2015-03-23 2017-03-08 浙江臻泰建设有限公司 Concrete energy-saving vibrator

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06146394A (en) * 1992-11-11 1994-05-27 Shimizu Corp Structure of reinforced concrete column and construction method thereof
CN1657710A (en) * 2005-01-11 2005-08-24 北京市机械施工公司 Method of vibration and extrusion for cast-in-place concrete in pile hole and its vibration rod device
CN201172968Y (en) * 2008-04-17 2008-12-31 河南泰宏房屋营造有限公司 Grid conductor for slant concrete placement
CN201221203Y (en) * 2008-07-02 2009-04-15 易朝全 Circular ring-shaped narrow slit vibrator of drain pipe sleeve floor drain concrete
CN201695697U (en) * 2010-05-25 2011-01-05 中建三局建设工程股份有限公司 Beating and vibrating construction structure of special-shaped reinforced concrete member

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06146394A (en) * 1992-11-11 1994-05-27 Shimizu Corp Structure of reinforced concrete column and construction method thereof
CN1657710A (en) * 2005-01-11 2005-08-24 北京市机械施工公司 Method of vibration and extrusion for cast-in-place concrete in pile hole and its vibration rod device
CN201172968Y (en) * 2008-04-17 2008-12-31 河南泰宏房屋营造有限公司 Grid conductor for slant concrete placement
CN201221203Y (en) * 2008-07-02 2009-04-15 易朝全 Circular ring-shaped narrow slit vibrator of drain pipe sleeve floor drain concrete
CN201695697U (en) * 2010-05-25 2011-01-05 中建三局建设工程股份有限公司 Beating and vibrating construction structure of special-shaped reinforced concrete member

Also Published As

Publication number Publication date
CN103046747A (en) 2013-04-17

Similar Documents

Publication Publication Date Title
CN203200771U (en) Connection structure for pile extension top and bearing platform
CN103046747B (en) Use the inclination concrete structure pouring technique that spiral protective sheath carries out
CN103031848B (en) Concrete grouting construction method and device for implementing same
CN204676525U (en) High strength rigidity soil compaction composite pile
CN203818291U (en) Template used for reversing holes in precast concrete unit
CN203947570U (en) A kind of reinforced concrete structure of printing based on 3D
CN207711438U (en) A kind of hydraulic forming machine
CN204252543U (en) For culvert, foot bridge abutment body construction the U-shaped card of positive and negative silk to drawing push rod
CN202298565U (en) Template
CN204178936U (en) A kind of electric capacity bent angle tool
CN208137479U (en) A kind of reinforcement type building transformational structure
CN203383212U (en) Big diameter thin-wall steel protective cylinder
CN205024573U (en) Concrete trowelling machine that vibrates fast
CN204040301U (en) The building block of a kind of loop beam forms
CN206844636U (en) Wall and the cast-in-place aluminum alloy pattern plate support system of superstructure
CN204023574U (en) Assembly type draws a core mud device
CN104526843A (en) Forming machine for fast splicing modules of concrete water channels
CN204530684U (en) Cement-soil stirring pile construction is with lengthening shaft
CN203126348U (en) Interior reinforcement structure of single mountains and rockeries
CN203118761U (en) Pressing tool for three-phase elliptical coil
CN204125939U (en) Intensity adjustable strength core composite pile
CN202672106U (en) Pouring template
CN203403417U (en) Sedimentation auxiliary device for steel cofferdam
CN203097247U (en) Operation platform for temporary construction
CN201962673U (en) Cast-in-place concrete thin wall pipe pile shoe capable of reducing or avoiding squeezing effect

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 200072 Luochuan Middle Road, Shanghai, No. 701, No.

Applicant after: SHANGHAI MECHANIZED CONSTRUCTION GROUP Co.,Ltd.

Address before: 200072 Luochuan Middle Road, Shanghai, No. 701, No.

Applicant before: SHANGHAI MECHANIZED CONSTRUCTION Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD. TO: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150819

Termination date: 20220118