CN203097247U CN 201320129805 CN201320129805U CN203097247U CN 203097247 U CN203097247 U CN 203097247U CN 201320129805 CN201320129805 CN 201320129805 CN 201320129805 U CN201320129805 U CN 201320129805U CN 203097247 U CN203097247 U CN 203097247U
Authority
CN
China
Prior art keywords
operation platform
connecting rods
temporary construction
reinforcing bar
laid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320129805
Other languages
Chinese (zh)
Inventor
王爱武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUNYOUNG CONSTRUCTION GROUP CO Ltd
Original Assignee
SUNYOUNG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUNYOUNG CONSTRUCTION GROUP CO Ltd filed Critical SUNYOUNG CONSTRUCTION GROUP CO Ltd
Priority to CN 201320129805 priority Critical patent/CN203097247U/en
Application granted granted Critical
Publication of CN203097247U publication Critical patent/CN203097247U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses an operation platform for temporary construction. The operation platform adopts the structure that two connecting rods are processed by reinforcement bars, and one end of each connecting rod is subjected to wire stripping processing; the two connecting rods are connected through a steel sleeve at the ends subjected to the wire stripping processing; and the outer ends of the connected connecting rods are in welded connection with a reinforcement bar support. During reinforcement bar binding, concealed work acceptance, concrete pouring and the like, the operation platform is laid on a formwork surface, then ties are laid, and is used for temporary construction.

Description

A kind of interim construction operation platform
Technical field
] construction operation platform when the utility model relates to a kind of reinforcing bar binding, hidden examination, concreting etc., particularly a kind of interim construction operation platform.
Background technology
Now in reinforcing bar binding, hidden examination, concreting; the negative muscle of appearance reinforcing bar is stepped on distortion, displacement, workman, and disorderly stepping on, throw out without care pump line smashes reinforcing bar on reinforcing bar; reinforcing bar phenomenon such as outside being exposed to has appearred when concreting; influenced the overall appearance aesthetic feeling of reinforcing bar binding on the one hand; the protective layer thickness of floor does not reach designing requirement on the other hand, has had a strong impact on the total quality of floor.
The utility model content
For addressing the above problem, the utility model provides a kind of interim construction operation platform.Its concrete technical scheme is as follows:
Shell the silk processing with two connecting rods of reinforcing bar processing and at an end of connecting rod, two connecting rods connect with steel bushing at a stripping end of handling.The outer end of the connecting rod that connects then is welded to connect with bar chair.When reinforcing bar binding, hidden examination, concreting etc., be laid on the template surface, lay railway sleepers on again, be used for the operating platform of interim construction.
The utility model beneficial effect: guaranteed that steel bar stress is unshift, the protective layer thickness of floor, improved the total quality of floor.
Description of drawings
Below in conjunction with accompanying drawing the utility model is described further.
Fig. 1 is a structural representation of the present utility model.
1. steel bushings, 2. bar chairs, 3. connecting rods among the figure.
The specific embodiment
Shell the silk processing with reinforcing bar processing two connecting rods (3) and at an end of connecting rod (3).
The end that two connecting rods (3) are handled at the stripping silk connects with steel bushing (1).
The outer end of the connecting rod that connects (3) then is welded to connect with bar chair (2).
More than three kinds of members formed interim construction operation platform.

Claims (1)

1. an interim construction operation platform comprises bar chair (2), connecting rod (3), it is characterized in that: construction operation platform is provided with the steel bushing (1) that is used to connect.
CN 201320129805 2013-03-21 2013-03-21 Operation platform for temporary construction Expired - Fee Related CN203097247U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320129805 CN203097247U (en) 2013-03-21 2013-03-21 Operation platform for temporary construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320129805 CN203097247U (en) 2013-03-21 2013-03-21 Operation platform for temporary construction

Publications (1)

Publication Number Publication Date
CN203097247U true CN203097247U (en) 2013-07-31

Family

ID=48848659

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320129805 Expired - Fee Related CN203097247U (en) 2013-03-21 2013-03-21 Operation platform for temporary construction

Country Status (1)

Country Link
CN (1) CN203097247U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223629A (en) * 2016-08-31 2016-12-14 中建四局第三建筑工程有限公司 A kind of concrete placings operating platform and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223629A (en) * 2016-08-31 2016-12-14 中建四局第三建筑工程有限公司 A kind of concrete placings operating platform and preparation method thereof

Similar Documents

Publication Publication Date Title
CN103774754A (en) Prefabricated ECC-RC combination beam column joint component
CN103866866B (en) Super High Core Walls Structure and housing water node after setting a roof beam in place
CN104563103A (en) Composite-reinforcement partially-prestressed concrete solid square pile and production method thereof
CN203097247U (en) Operation platform for temporary construction
CN103628675A (en) Bailey beam type formwork supporting system and construction method thereof for super high-rise transfer story crossbeam
CN205907878U (en) A anti hook assembly that floats that is used for cast -in -place hollow superstructure board
CN201915400U (en) Prestressed solid square pile
CN208777720U (en) Detachable straight thread steel bar base of wall hanging mould inclined strut
CN204040515U (en) Cat ladder
CN102425327A (en) Cement power pole heightening rod
CN201567719U (en) Inner sleeve type reinforced concrete hollow beam
CN203769086U (en) Concrete embedded part
CN104120833B (en) The anti-concrete filled steel tube peeling off damage
CN202969732U (en) Positioning device of upper reinforcement protective cover of cast-in-place slab
CN204252404U (en) Shear force wall reinforcing steel bar topping controls mould
CN204899034U (en) Prefabricated wall post
CN110094015A (en) A kind of complex beam-column structure of construction
CN204357135U (en) multifunctional steel tie hook
CN207686286U (en) A kind of landing slab Construction Support protection structure
CN207003829U (en) Working space concrete filled steel tube cylinder design structure
CN209614067U (en) A kind of bending tool of antidetonation crotch in complexity framework of steel reinforcement structure
CN101892724B (en) Padding block processor
CN202706335U (en) Cushion block of concrete cover
CN208121961U (en) A kind of assembling frame corner node structure
CN203257109U (en) Portable cast-in-place floor concrete pouring overhead walk way

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130731

Termination date: 20210321