CN103031848B - Concrete grouting construction method and device for implementing same - Google Patents

Concrete grouting construction method and device for implementing same Download PDF

Info

Publication number
CN103031848B
CN103031848B CN201210556576.7A CN201210556576A CN103031848B CN 103031848 B CN103031848 B CN 103031848B CN 201210556576 A CN201210556576 A CN 201210556576A CN 103031848 B CN103031848 B CN 103031848B
Authority
CN
China
Prior art keywords
concrete
underwater concrete
dreg
underwater
drawing pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210556576.7A
Other languages
Chinese (zh)
Other versions
CN103031848A (en
Inventor
林朝庆
彭小林
陈锦云
许建得
李龙送
李才波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foundation Design Group Co., Ltd of Guangdong Province
Original Assignee
GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG PROV FOUNDATION ENGINEERING Co filed Critical GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority to CN201210556576.7A priority Critical patent/CN103031848B/en
Publication of CN103031848A publication Critical patent/CN103031848A/en
Application granted granted Critical
Publication of CN103031848B publication Critical patent/CN103031848B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a concrete grouting construction method and a device for implementing the same. The device comprise a plurality of tremies of which one ends extend into underwater concrete in a grouting slot; a blanking hopper is arranged at the top end of each tremie; a slag pumping pipe is arranged in the grouting slot; and the bottom end of the slag pumping pipe is positioned at a position which is 1-2 meters away from the surface of the underwater concrete. According to the concrete grouting construction method and the construction device, slurry above the surface of the underwater concrete is pumped through the slag pumping pipe in a concrete pouring process, and concrete is poured in the pumping process, so that the quality of underwater concrete is prevented from being damaged by the slurry above the surface of the underwater concrete, and the piling quality of the underwater concrete is effectively ensured; and the method and the device can be applied to the field of building construction.

Description

The device of filling concrete construction method and enforcement the method
Technical field
The present invention relates to the realm of building construction, particularly relate to the device of a kind of filling concrete construction method and enforcement the method.
Background technology
After general construction pile body or diaphragm wall pore-forming, start pouring underwater concrete through clear hole, in this filling process, only removed conduit and controlled pipe laying depth, and mud has not been carried out to circular treatment, easily cause the pile defect after pile.
Summary of the invention
For addressing the above problem, the invention provides a kind of can effective guarantee pile quality filling concrete construction method and implement the device of the method.
The technical solution adopted for the present invention to solve the technical problems is:
Filling concrete construction method, is characterized in that, comprises the following steps:
1), in filling concrete slotted eye, pour into a mould one section of underwater concrete;
2), detect the hyperscaling of described underwater concrete raised floor mud index;
3), extract the body refuse apart from underwater concrete face 1~2m place by dreg-drawing pipe, mend slurry simultaneously, then continue to build underwater concrete;
4), promote dreg-drawing pipe, make dreg-drawing pipe be positioned at gradually on the underwater concrete surface of rising 1~2m place until concreting is complete always.
Be further used as the improvement of technical solution of the present invention, the mud amount extracting by dreg-drawing pipe in step 3) equates with benefit slurry amount.
Being further used as the improvement of technical solution of the present invention, step 2) front underwater concrete height of having built is 10m~20m.
Implement the filling concrete construction equipment of said method, comprise that in perfusion slotted eye, the some tremies in underwater concrete are stretched in one end, the top of each tremie is equipped with lower funnel, in perfusion slotted eye, be also provided with dreg-drawing pipe, the bottom of dreg-drawing pipe is positioned at the position of 1~2m on underwater concrete surface.
Be further used as the improvement of technical solution of the present invention, in perfusion slotted eye, be also provided with and mend slurry pipe, the grout outlet of mending slurry pipe is positioned under slurry face.
Beneficial effect of the present invention: this filling concrete construction method and construction equipment are carrying out in concreting process, by dreg-drawing pipe, mud more than underwater concrete surface is extracted, and carry out concrete cast in the process extracting, can prevent the quality of the mud infringement underwater concrete of underwater concrete face top, thus the pile quality of effective guarantee underwater concrete.
Brief description of the drawings
Below in conjunction with accompanying drawing, the invention will be further described:
Fig. 1 is embodiment of the present invention overall structure schematic diagram.
Detailed description of the invention
With reference to Fig. 1, the present invention is a kind of filling concrete construction method, it is characterized in that, comprises the following steps:
1), in filling concrete slotted eye, pour into a mould one section of underwater concrete;
2), detect the hyperscaling of described underwater concrete raised floor mud index;
3), extract the body refuse apart from underwater concrete face 1~2m place by dreg-drawing pipe, mend slurry simultaneously, then continue to build underwater concrete;
4), promote dreg-drawing pipe, make dreg-drawing pipe be positioned at gradually on the underwater concrete surface of rising 1~2m place until concreting is complete always.
Implement the filling concrete construction equipment of said method, comprise that in perfusion slotted eye, the some tremies 1 in underwater concrete are stretched in one end, the top of each tremie 1 is equipped with lower funnel 2, in perfusion slotted eye, be also provided with dreg-drawing pipe 3, the bottom of dreg-drawing pipe 3 is positioned at the position of 1~2m on underwater concrete surface.
This filling concrete construction method and construction equipment are carrying out in concreting process, by dreg-drawing pipe 3, mud more than underwater concrete surface is extracted, and carry out concrete cast by tremie 1 in the process extracting, can prevent the quality of the mud infringement underwater concrete of underwater concrete face top, thus the pile quality of effective guarantee underwater concrete.
As the preferred embodiment of the present invention, the mud amount extracting by dreg-drawing pipe in step 3) equates with benefit slurry amount.
As the preferred embodiment of the present invention, step 2) front underwater concrete height of having built is 10m~20m.
As the preferred embodiment of the present invention, when underwater concrete difference in height 10m that underwater concrete identity distance is built from needs, stop step 4).
As the preferred embodiment of the present invention, in perfusion slotted eye, be also provided with and mend slurry pipe 4, the grout outlet of mending slurry pipe 4 is positioned under slurry face.
Mend slurry pipe 4 and in work progress, constantly supplement solidifying slurry, so that perfusion slotted eye is carried out to retaining wall, prevent from pouring into slotted eye and cave in, ensure construction safety.
For super deeply, in the drilled pile or construction of diaphragm wall process that dark or geological conditions is poor, along with the continuous uphill process of pouring underwater concrete slurry face, in perfusion slotted eye with several meters, underwater concrete raised floor place within the scope of mud index can produce obvious variation.The indexs such as the proportion of mud, sand factor, viscosity have larger variation can start to build than just time, affect the quality of underwater concrete.In pouring underwater concrete process, by anti-circular treatment mode, the above mud of underwater concrete raised floor is carried out to continuous circular treatment, make the indices of mud substantially meet technological requirement, can effectively ensure underwater concrete construction quality.
Certainly, the invention is not limited to above-mentioned embodiment, those of ordinary skill in the art also can make equivalent variations or replacement under the prerequisite without prejudice to spirit of the present invention, and the modification that these are equal to or replacement are all included in the application's claim limited range.

Claims (5)

1. filling concrete construction method, is characterized in that, comprises the following steps:
1), in filling concrete slotted eye, pour into a mould one section of underwater concrete;
2), detect the hyperscaling of described underwater concrete raised floor mud index;
3), extract the body refuse apart from underwater concrete face 1~2m place by dreg-drawing pipe, mend slurry simultaneously, continue to build underwater concrete by tremie;
4), promote dreg-drawing pipe, make dreg-drawing pipe be positioned at gradually on the underwater concrete surface of rising 1~2m place until concreting is complete always.
2. filling concrete construction method according to claim 1, is characterized in that: the mud amount extracting by dreg-drawing pipe in described step 3) equates with benefit slurry amount.
3. filling concrete construction method according to claim 1, is characterized in that: described step 2) front underwater concrete height of having built is 10m~20m.
4. implement the claims the filling concrete construction equipment of method described in 1, it is characterized in that: comprise that in perfusion slotted eye, the some tremies (1) in underwater concrete are stretched in one end, the top of described each tremie (1) is equipped with lower funnel (2), in described perfusion slotted eye, be also provided with dreg-drawing pipe (3), the bottom of described dreg-drawing pipe (3) is positioned at the position of 1~2m on underwater concrete surface.
5. filling concrete construction equipment according to claim 4, is characterized in that: in described perfusion slotted eye, be also provided with and mend slurry pipe (4), the grout outlet of described benefit slurry pipe (4) is positioned under slurry face.
CN201210556576.7A 2012-12-19 2012-12-19 Concrete grouting construction method and device for implementing same Active CN103031848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210556576.7A CN103031848B (en) 2012-12-19 2012-12-19 Concrete grouting construction method and device for implementing same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210556576.7A CN103031848B (en) 2012-12-19 2012-12-19 Concrete grouting construction method and device for implementing same

Publications (2)

Publication Number Publication Date
CN103031848A CN103031848A (en) 2013-04-10
CN103031848B true CN103031848B (en) 2014-10-29

Family

ID=48019207

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210556576.7A Active CN103031848B (en) 2012-12-19 2012-12-19 Concrete grouting construction method and device for implementing same

Country Status (1)

Country Link
CN (1) CN103031848B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032742B (en) * 2014-05-16 2016-04-06 陕西建工机械施工集团有限公司 A kind of Placement of Underwater Concrete for Casting technique based on DLC four hopper
CN104141308B (en) * 2014-07-21 2016-08-17 杭州华能大坝安全工程技术有限公司 A kind of boring rises concrete grout construction method
JP6693090B2 (en) * 2015-11-05 2020-05-13 株式会社大林組 Management method for secondary slime treatment
CN106498935B (en) * 2016-11-09 2018-10-16 中冶建工集团有限公司 A kind of bored pile underwater concrete casting method
CN108978737A (en) * 2018-07-04 2018-12-11 中国二十冶集团有限公司 A kind of construction method for bored concrete pile sound detecting pipe slip casting

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58185824A (en) * 1982-04-23 1983-10-29 Ohbayashigumi Ltd Mud water-solidification work reusing good-quality excavated soil
KR100422216B1 (en) * 2001-05-23 2004-03-30 주식회사유신코퍼레이션 The method of construction prevening a waterflow of cassion basis for a bridge
CN1233903C (en) * 2003-01-21 2005-12-28 上海市第二建筑有限公司 Construction method for structure of reinforced concrete underwater
CN102041811A (en) * 2009-10-22 2011-05-04 罗红 Bottom tube for processing conduit water feeding accidents in process of pouring concrete in cast-in-situ bored pile
CN202220340U (en) * 2011-08-24 2012-05-16 中交二航局第三工程有限公司 Underwater concreting conduit
CN102691294B (en) * 2012-05-15 2013-08-21 安宜建设集团有限公司 Construction method of underground continuous wall

Also Published As

Publication number Publication date
CN103031848A (en) 2013-04-10

Similar Documents

Publication Publication Date Title
CN103031848B (en) Concrete grouting construction method and device for implementing same
CN103437348B (en) Construction device and method of pile peripheral cemented soil cast-in-place stiffness core pile
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN103382722B (en) Concrete foundation slab restoring method for preformed water collecting well for higher underground hydraulic pressure
CN103628575A (en) Large-altitude-difference variable-section concrete structure construction joint and construction method thereof
CN102912789A (en) Mechanical hole forming technology applied to karst landform
CN107268599A (en) A kind of embedded large-scale filling solution cavity ruggedized construction of substrate and reinforcement means
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN203625883U (en) Steel sheet support pile with pipes for foundation pit construction
CN105332511A (en) Huge concrete filled steel tubular column core grouting pouring and tamping device and method
CN102704478A (en) Building anchor rod construction technology
CN203049588U (en) Pit-in-pit cylindrical mould
CN202108039U (en) Cylindrical compound concrete macadam placepile
CN204370426U (en) A kind of retaining wall construction equipment based on multilayer template
CN204780928U (en) Major diameter bored concrete pile concrete first set groundwater increment controlling means
CN204343327U (en) A kind of construction equipment of retaining wall
CN102561389B (en) Construction method of underground diaphragm wall joint pipes
CN103774643A (en) Digging pile non-water underwater pouring construction method
CN106351240A (en) Shut-in method for dewatering well arranged below building or structure foundation
CN204326065U (en) Drilled pile secondary pouring pile making device
CN205189421U (en) Huge steel core concrete column is irritated core and is watered and smash device
CN202730767U (en) Basement top-down-method steel pipe column core concrete pouring device
CN203919342U (en) The casting waste materials recovery structure of air-entrained concrete building block
CN204370472U (en) A kind of retaining wall construction equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUANGDONG FOUNDATION ENGINEERING GROUP CO., LTD.

Free format text: FORMER NAME: GUANGDONG PROV. FOUNDATION ENGINEERING CO.

CP01 Change in the name or title of a patent holder

Address after: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Patentee after: Foundation Design Group Co., Ltd of Guangdong Province

Address before: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Patentee before: Guangdong Prov. Foundation Engineering Co.