CN103043572A - Foldable maintenance platform - Google Patents
Foldable maintenance platform Download PDFInfo
- Publication number
- CN103043572A CN103043572A CN2012105704666A CN201210570466A CN103043572A CN 103043572 A CN103043572 A CN 103043572A CN 2012105704666 A CN2012105704666 A CN 2012105704666A CN 201210570466 A CN201210570466 A CN 201210570466A CN 103043572 A CN103043572 A CN 103043572A
- Authority
- CN
- China
- Prior art keywords
- platform
- support arm
- foldable
- movable railing
- digonal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention provides a foldable maintenance platform comprising two guide rails, two connecting plates, two foldable lifting rods, and a platform. Each foldable lifting rod comprises at least one scissors structure with the uppermost end connected with the connecting plates rotationally and the lowermost end connected with the platform rotationally. When not used, the foldable maintenance platform can be folded to the top of a shaftway so as to occupy quite small shaftway space. When used, the foldable maintenance platform can be unfolded by a lifting device, an operator can enter the unfolded maintenance platform for debugging, maintaining and the like through a car top, and can stand on the maintenance platform to observe running condition of elevator parts and measure relevant data of the same when an elevator runs normally, and the maintenance platform cannot affect normal running of the elevator.
Description
[technical field]
The present invention relates to the elevator field, refer in particular to a kind of overhauling elevator platform for debugging, maintenance.
[background technology]
The machine-roomless lift of present main frame inhead type, the parts such as its towing machine, drg, control housing and velocity limiter all are installed in well headroom.The operating personnel must stand in the operation of sedan-chair jacking row when the elevator components of debugging, maintenance well headroom in the past.But, when need in the debug process to move elevator detect, when debugging, the operating personnel is owing to the sedan-chair top is left in the requirement of safety, and the operating personnel can't observe, debug the parts (towing machine, drg, control housing and velocity limiter etc.) on hoistway top so.This causes great inconvenience to debugging/upkeep operation personnel.
Therefore, provide the inspection platform of a kind of convenient debugging, upkeep operation real in necessary.
[summary of the invention]
The object of the present invention is to provide the inspection platform of a kind of convenient debugging, upkeep operation.
For realizing the object of the invention, provide following technical scheme:
The invention provides a kind of Foldable overhaul platform, it comprises two guide rails, be installed in two connecting panels on the guide rail, connect respectively two folding suspension rods, the platform of these two connecting panels, these two folding suspension rods comprise respectively at least one scissor construction, this at least one scissor construction is topmost realized being rotatably connected with connecting panel, and this at least one scissor construction is realized being rotatably connected with platform bottom.
The present invention proposes a kind of novel Foldable overhaul platform.This inspection platform is not when using, and the collapsible well headroom that is retracted into takies hoistway space seldom; Open inspection platform by jacking system during use, the work such as the operating personnel can debug by the inspection platform that the sedan-chair jacking enters open configuration, maintenance, elevator normally moves, the operating personnel can stand in and observe the running condition of surveying elevator components on the inspection platform and measure its relevant data, and inspection platform does not affect the normal operation of elevator.
In some embodiments, this scissor construction comprises two digonal links, and these two digonal link upper ends are rotatably connected with the digonal link lower end of previous scissor construction, or are rotatably connected with connecting panel; The digonal link upper end of these two digonal link lower ends and a rear scissor construction is rotatably connected, or is rotatably connected with platform; Two digonal links middle part mutually intersects and is rotationally connected into scissor-shaped.In some embodiments, a plurality of scissor constructions connect, and realize double-layer staggered connection, can make this folding hanging rod structure more firm, more flexible.
In some embodiments, being rotationally connected between the described scissor construction, and being rotatably connected between scissor construction and connecting panel or the platform is to be connected realization by bearing pin.
In some embodiments, this digonal link upper end has circular hole, and middle part and lower end have long slot bore.The setting of long slot bore makes folding suspension rod realize better the folding and retraction function.
In some embodiments, it also comprises pull bar reinforcement structure, this pull bar is strengthened structure and is comprised at least two the first short digonal links, at least two the second short digonal links, at least one cross bar, hinged in the middle part of the hinged place, two digonal links middle part of scissor construction and the cross bar, or upper and lower digonal link hinged place and cross bar two ends are hinged; The upper end of these at least two the first short digonal links is rotationally connected by bearing pin with the middle part of connecting panel simultaneously, and the lower end is rotationally connected by bearing pin with the two ends of cross bar respectively; These at least two the second short digonal links, its upper end and two mother rib lateral rotundums of cross bar and the lower end of the first short digonal link or the lower end of digonal link are rotationally connected by bearing pin, and the circular hole of its lower end while with the platform middle part is rotationally connected.The Joint strenght that pull bar has been strengthened structural strengthening between the scissor construction.
In some embodiments, the upper end of this first short digonal link and the second short digonal link has circular hole, and the lower end has long slot bore.The setting of long slot bore makes folding suspension rod realize better the folding and retraction function.
In some embodiments, it also comprises roller devices, and this roller devices comprises at least two roller rods, the connecting panel of both sides is passed respectively at the two ends of this roller rod, and the end of roller rod is equipped with the band shaft roller, and this guide rail is provided with guide groove, and this band shaft roller places guide groove.Roller devices can implementation platform along the sway of guide rail, make things convenient for the practical operation of service personnel.
In some embodiments, it further comprises electromagnetic locking device, this electromagnetic locking device comprises electromagnet, magnet coil, the first support arm, the second support arm, the 3rd support arm, the first sleeve, the second sleeve, spring, elastic axis consists of, this first support arm and the second support arm are fixed on the guide rail two ends simultaneously, and the other end of the first support arm and the second support arm reaches the guide way opening part, the on-fixed end of this second support arm successively with elastic axis, spring, the socket of the second sleeve rubber cradle, and described elastic axis can be axially movable in the second sleeve, also overlap in this first support arm first sleeve that can be socketed elastic axis is arranged, described the 3rd support arm one end is fixed on the second support arm, the other end and electromagnet are connected and fixed, and are also twining magnet coil on this electromagnet.Electromagnetic locking device can be realized locking behind platform movement, improve safety performance and stability.
In some embodiments, this first support arm and the second support arm are fixed on the guide rail both sides by the bolt group respectively.
In some embodiments, it also comprises jacking system, this jacking system comprises at least one variable-frequency motor, at least one interlock round bar, at least one first rope sheave, at least one second rope sheave and at least two steel ropes, this variable-frequency motor is fixed on the connecting panel of a side, variable-frequency electric arbor one end passes connecting panel and connects the first rope sheave, the other end becomes to be rigidly connected with an end of interlock round bar, the described interlock round bar other end passes side connecting plate, and connect the second rope sheave, described at least two steel ropes upper end is also fixed on the first rope sheave and the second rope sheave respectively, and the lower end is fixed with the fag end axle that passes the platform both sides respectively.Jacking system can make the lifting of platform realize automation mechanized operation, raises the efficiency.
In some embodiments, this variable-frequency motor is with auto-lock function, can automatically not descend after platform is packed up, and improves safety performance.
In some embodiments, it also comprises the protection railing that is connected between the folding suspension rod in both sides, the safety that further improves operating personal.
In some embodiments, it also comprises the movable railing assembly, this movable railing assembly comprises at least two anchor shafts, at least one the first movable railing, at least one the second movable railing, at least one threaded line pipe, cross bar one end of this first movable railing one end and pull bar reinforcement structure is hinged, the other end of this first movable railing and the socket of threaded line pipe one end; This second movable railing one end is hinged with cross bar one end of lateral bracing strut being strengthened structure, and the other end of the second movable railing is realized being threaded with the threaded line pipe other end.The movable railing assembly is convenient to the operating personnel and climbs up platform and leave platform.When platform drops to assigned address, by turning on threaded line pipe, the first movable railing and the second movable railing are disconnected, remove its safeguard function, this moment, the operating personnel can climb up platform smoothly; Before the operation, the first movable railing is reconnected into rigidity with the second movable railing, recover its safeguard function.When leaving platform, operating process is the contrary operation process of climbing up platform.
In some embodiments, the anchor shaft of cross bar one end of this first movable railing one end and pull bar reinforcement structure is hinged by bearing pin, and this second movable railing one end is hinged by bearing pin with the cross bar one end anchor shaft of lateral bracing strut being strengthened structure.
In some embodiments, the other end of this first movable railing is provided with boss, this threaded line pipe is the little tubular of the large other end opening of an end opening, and the other end of the second movable railing has been attacked outside thread, and the large open end of threaded line pipe is attacked the negative thread that cooperates with the second movable railing outside thread; The little open end of threaded line pipe and the socket of the boss of the first movable railing.
The present invention also provides a kind of elevator device, and this system comprises elevator hoistways, elevator, and it also comprises aforesaid Foldable overhaul platform, and this Foldable overhaul platform is fixed in the hoisting beam of well headroom or well headroom by guide rail.
In some embodiments, the track of this Foldable overhaul platform is fixed in well headroom by holding-down bolt or expansion bolt or is bolted/is weldingly fixed on the hoisting beam.
The contrast prior art, the present invention has the following advantages:
1. Foldable overhaul platform of the present invention can satisfy operating personnel's the requirements of one's work such as debugging, maintenance, make things convenient for its in the platform debugging, detect the elevator components such as towing machine, drg, control housing and velocity limiter, improved operating personnel's work efficiency.
2. the present invention's collapsible packing up when not using takies hoistway space seldom.
3. the present invention is provided with jacking system, and the operating personnel opens, packs up inspection platform easily and safely by control variable-frequency electric function, has improved the utilization ratio of inspection platform.
4. the present invention upper end is provided with guide rail and roller devices, makes the inspection platform can be along the track sway, thereby when satisfying job requirements, can reduce the overall dimensions of platform, alleviates the weight of platform.
5. the present invention is provided with electromagnetic locking device in rail end, can be after inspection platform move to the end of guide rail, and the band bearing roller of pair roller device locks, and improves the safety that inspection platform uses.
6. inspection platform body of the present invention front side, rear side are provided with the protection railing structure, can further improve the safety of inspection platform, wherein the guard rail of a side is the movable protective railing, and the position can be taken protection railing apart therebetween, makes things convenient for personnel to enter inspection platform.
[description of drawings]
Fig. 1 is that Foldable overhaul platform of the present invention is applied to put on the machine room main frame schematic diagram when opening;
Fig. 2 is that Foldable overhaul platform of the present invention is applied to put on the machine room main frame schematic diagram after packing up;
Fig. 3 is the block diagram of Foldable overhaul platform open mode of the present invention;
Fig. 4 is the block diagram of Foldable overhaul platform collapsed state of the present invention;
Fig. 5 is the enlarged view of the calutron of Foldable overhaul platform of the present invention;
Fig. 6 is the cross sectional view of the calutron open mode of Fig. 5;
Fig. 7 is the cross sectional view of the calutron lock-out state of Fig. 5;
Fig. 8 is the enlarged view of the movable guard rail of Foldable overhaul platform of the present invention;
Fig. 9 is the partial view of the I part of Fig. 8.
[specific embodiment]
Below in conjunction with accompanying drawing embodiments of the invention are elaborated:
As depicted in figs. 1 and 2, a kind of novel Foldable overhaul platform is installed on well headroom or the well headroom hoisting beam, has and opens and folding two states.
As shown in Figure 3 and Figure 4, described novel Foldable overhaul platform, it comprises at least two guide rails 7, be fixed on close elevator components (such as towing machine, drg, the control housing etc.) side of the hoisting beam of well headroom or well headroom by at least four holding-down bolts or expansion bolt, and described guide rail 7 is provided with guide groove.
As shown in Figure 4, described novel Foldable overhaul platform top is provided with roller devices, and it comprises at least two roller rods 12, two connecting panels 6 and at least 4 band bearing rollers 8.Described every roller rod 12 all passes the connecting panel 6 of platform both sides, forms " well " font; And at the place, close end of every roller rod 12 a band bearing roller 8 is installed all.Outer end with bearing roller 8 also has axle to carry out spacing with 19 pairs of band bearings of trip ring roller 8.
As shown in Figure 3 and Figure 4, described roller devices, it is installed in the guide groove of guide rail 7 with bearing roller 8, and band bearing roller 8 can roll in guide way, and about driving inspection platform and doing or move forward and backward.
As shown in Figure 3 and Figure 4, the folding suspension rod of described inspection platform body both sides also comprises at least one scissor construction, at least one pull bar is strengthened structure and is connected with platform 1.Described scissor construction is made of at least two digonal links 5 and five bearing pins 15 at least.Described two digonal link 5 upper ends are rotationally connected by bearing pin 15 with the two ends of connecting panel 6 respectively, and two digonal link 5 middle parts mutually intersect and are rotationally connected into scissor-shaped by bearing pin 15; The lower end of described two digonal links 5 is rotationally connected by bearing pin 15 with platform 1 two ends circular hole respectively.
As shown in Figure 3 and Figure 4, preferably, described oblique railing 5 upper ends have circular hole, and middle part and lower end all have long slot bore.
As shown in Figure 3 and Figure 4, described pull bar reinforcement structure is made of with at least one piece cross bar 4 at least two the first short digonal links 20, two the second short digonal links 3 at least.Hinged place, described two digonal link 5 middle parts, also hinged in the lump with cross bar 4 middle part circular holes between two digonal links 5.The described upper end that has two the first short digonal links 20 at least is rotationally connected by bearing pin 15 with the middle part circular hole of connecting panel 6 simultaneously, and the lower end is rotationally connected by bearing pin 15 with the two ends circular hole of cross bar 4 respectively.Have two the described second short digonal links 3 at least, the two mother rib lateral rotundums while of its upper end and cross bar 4 is rotationally connected by bearing pin 15 with the lower end of the described first short digonal link 20.The lower end while of described two the second short digonal links 3 is rotationally connected by fag end axle 18 with the circular hole at platform 1 middle part.
As shown in Figure 3 and Figure 4, preferably, the upper end of the described first short oblique railing 20 and the second short digonal link 3 has circular hole, and the lower end has long slot bore.
As shown in Figure 4 and Figure 5, preferably, described novel Foldable overhaul platform, its every guide rail 7 both sides also are fixed with at least one electromagnetic locking device 13.Described electromagnetic locking device 13 is made of electromagnet 13-9, magnet coil 13-8, the first support arm 13-1, the second support arm 13-3, the 3rd support arm 13-10, the first sleeve 13-2, the second sleeve 13-4, spring 13-5, elastic axis 13-7, rubber cradle 13-6 and bolt group 13-11.Described the first support arm 13-1 and the second support arm 13-3 are fixed on guide rail 7 two ends by bolt group 13-11 respectively, and the other end of the first support arm 13-1 and the second support arm 13-3 reaches guide rail 7 tappings.
As shown in Figure 5, the on-fixed end of described the second support arm 13-3 is socketed with elastic axis 13-7, spring 13-5, the second sleeve 13-4 and rubber cradle 13-6 successively, and described elastic axis 13-7 can be axially movable in the second sleeve 13-4.Also overlapping in described the first support arm 13-1 has the first sleeve 13-2, the location of elastic axis 13-7 when being used for locking.Described the 3rd support arm 13-10 one end is fixedly welded on the second support arm 13-3, and the other end and electromagnet 13-9 are connected and fixed.Also twining magnet coil 13-8 on the described electromagnet 13-9.
Figure as 6 and shown in Figure 7, when magnet coil 13-8 switches on, the on-fixed end of the 3rd support arm 13-10 will make electromagnet 13-9 band magnetic, and overcome spring force and hold elastic axis 13-7, move in the circle that is surrounded by the first support arm 13-1, the second support arm 13-3 and elastic axis 13-7 with bearing roller 8, i.e. the end of guide rail; When magnet coil 13-8 cut off the power supply, electromagnet 13-9 lost magnetism, and under the effect of spring 13-5 spring force, elastic axis 13-7 was restored, and was locked in the end of guide rail by spring shaft 13-7 with bearing roller 8.
As shown in Figure 3 and Figure 4, preferably, described inspection platform body also is provided with jacking system.Described jacking system is made of at least one variable-frequency motor 9, at least one interlock round bar 11, at least one first rope sheave 10, at least one second rope sheave 21 and two steel ropes 17 at least.9 of described variable-frequency motors are fixed on the connecting panel 6 of a side, and described variable-frequency electric arbor one end passes connecting panel 6 and is connected with the first rope sheave 10, and the other end connects into rigidity with an end of interlock round bar 11.Described interlock round bar 11 other ends pass side connecting plate 6, and are connected with the second rope sheave 21.Described two steel rope 17 upper ends are respectively around at the first rope sheave 10 and the second rope sheave 21 upper-level thresholds and fixing, and circular hole that the fag end axle 18 of platform 1 both sides is provided with and fixing is passed respectively in the lower end.Not during the use and maintenance platform, variable-frequency motor 9 backward rotation, the first rope sheave 10 and the second rope sheave 21 are packed up steel rope 17 simultaneously, and pulling platform 1 upward movement makes that inspection platform is folding to be packed up; During usage platform, variable-frequency motor 9 forward rotation, folding suspension rod opens under the Action of Gravity Field of platform 1, and variable-frequency motor 9 is controlled the descending speed of platform 1 by control steel rope 17.Preferably, described variable-frequency motor is also with auto-lock function, can automatically not descend after platform is packed up.
Such as Fig. 4 and Fig. 8, shown in Figure 9, preferably, the front side of described flexible inspection platform body or rear side (installation side of disconnected plate 6, guide rail 7) also are provided with movable railing 22.Described movable railing 22 is made of at least two anchor shaft 22-1, at least one the first movable railing 22-2, at least one the second movable railing 22-4, at least one threaded line pipe 22-3 and two bearing pin 22-5 at least.The anchor shaft 22-1 of described the first movable railing 22-2 one end and cross bar 4 one ends are hinged by bearing pin 22-5.The other end of described the first movable railing 22-2 also is provided with boss.One end anchor shaft 22-1 of described the second movable railing 22-4 one end and offside cross bar 4 are hinged by bearing pin 22-5.And the other end of described the second movable railing 22-4 has been attacked outside thread and has been served as with threaded line pipe 22-3 and be threaded.Described threaded line pipe 22-3 is pre-large post-small tubular, and large open end is attacked the negative thread that cooperates with the second movable railing 22-4 outside thread in the cylinder; After the boss socket of the small end of described threaded line pipe 22-3 and the first movable railing 22-2, connect into rigidity with the second movable railing 22-4 by helicitic texture.When platform 1 drops to assigned address, by turning on threaded line pipe 22-3, the first movable railing 22-2 and the second movable railing 22-4 are disconnected, remove its safeguard function, this moment, the operating personnel can climb up platform 1 smoothly.Before the operation, the first movable railing 22-2 is reconnected into rigidity with the second movable railing 22-4, recover its safeguard function.When leaving platform 1, operating process is the contrary operation process of climbing up platform.
The operating process of Foldable overhaul platform of the present invention is:
When using this Foldable overhaul platform, after the operating personnel enters sedan-chair top, and cage top overhauling is gone upward to the assigned address on hoistway top.The operating personnel is installed in the control button of the platform lifting device of sedan-chair top electric box by startup, make variable-frequency motor 9 forwards that are installed on the inspection platform and put down platform.After the Awaiting Overhaul platform was finished and opened, the operating personnel removed the threaded line pipe 22-3 on the movable railing 22, and movable rail is disconnected; The operating personnel climbs up inspection platform 1.
Before the operation, the operating personnel needs first movable rail 22 to be recovered safeguard function, and then elevator can normally move.
During operation, if the operating personnel need traveling overhaul platform to opposite side (as originally at host computer side, need move to control housing, velocity limiter then) operation, the operating personnel can be by being installed in the unlock button of the electromagnetic locking device on the inspection platform, make band bearing roller 8 recover to roll, can move to target side this moment with platform.After roller moved to target side, electromagnetic locking device can automatically recover lock-out state, and locking strip bearing roller again.
After the operation, before the operating personnel leaves inspection platform, first overhauling elevator to be up to the position of hoistway top appointment, dismantle again movable railing 22; After leaving inspection platform and entering into sedan-chair top, the operating personnel locks movable railing 22 again, and packs up inspection platform by the push button control jacking system of sedan-chair top electric box.
The above is preferred embodiment of the present invention only, and protection scope of the present invention is not limited to this, anyly all belongs within the protection domain of the present invention based on the equivalent transformation on the technical solution of the present invention.
Claims (17)
1. Foldable overhaul platform, it is characterized in that, it comprises two guide rails, be installed in two connecting panels on the guide rail, connect respectively two folding suspension rods, the platform of these two connecting panels, these two folding suspension rods comprise respectively at least one scissor construction, this at least one scissor construction is topmost realized being rotatably connected with connecting panel, and this at least one scissor construction is realized being rotatably connected with platform bottom.
2. Foldable overhaul platform as claimed in claim 1 is characterized in that, this scissor construction comprises two digonal links, and these two digonal link upper ends are rotatably connected with the digonal link lower end of previous scissor construction, or are rotatably connected with connecting panel; The digonal link upper end of these two digonal link lower ends and a rear scissor construction is rotatably connected, or is rotatably connected with platform; Two digonal links middle part mutually intersects and is rotationally connected into scissor-shaped.
3. Foldable overhaul platform as claimed in claim 2 is characterized in that, being rotationally connected between the described scissor construction, and being rotatably connected between scissor construction and connecting panel or the platform is to be connected realization by bearing pin.
4. Foldable overhaul platform as claimed in claim 3 is characterized in that, this digonal link upper end has circular hole, and middle part and lower end have long slot bore.
5. Foldable overhaul platform as claimed in claim 4, it is characterized in that, it also comprises pull bar reinforcement structure, this pull bar is strengthened structure and is comprised at least two the first short digonal links, at least two the second short digonal links, at least one cross bar, hinged in the middle part of the hinged place, two digonal links middle part of scissor construction and the cross bar, or upper and lower digonal link hinged place and cross bar two ends are hinged; The upper end of these at least two the first short digonal links is rotationally connected by bearing pin with the middle part of connecting panel simultaneously, and the lower end is rotationally connected by bearing pin with the two ends of cross bar respectively; These at least two the second short digonal links, its upper end and two mother rib lateral rotundums of cross bar and the lower end of the first short digonal link or the lower end of digonal link are rotationally connected by bearing pin, and the circular hole of its lower end while with the platform middle part is rotationally connected.
6. Foldable overhaul platform as claimed in claim 5 is characterized in that, the upper end of this first short digonal link and the second short digonal link has circular hole, and the lower end has long slot bore.
7. Foldable overhaul platform as claimed in claim 4, it is characterized in that, it also comprises roller devices, this roller devices comprises at least two roller rods, the connecting panel of both sides is passed respectively at the two ends of this roller rod, and the end of roller rod is equipped with the band shaft roller, and this guide rail is provided with guide groove, and this band shaft roller places guide groove.
8. Foldable overhaul platform as claimed in claim 7, it is characterized in that, it further comprises electromagnetic locking device, this electromagnetic locking device comprises electromagnet, magnet coil, the first support arm, the second support arm, the 3rd support arm, the first sleeve, the second sleeve, spring, elastic axis consists of, this first support arm and the second support arm are fixed on the guide rail two ends simultaneously, and the other end of the first support arm and the second support arm reaches the guide way opening part, the on-fixed end of this second support arm successively with elastic axis, spring, the socket of the second sleeve rubber cradle, and described elastic axis can be axially movable in the second sleeve, also overlap in this first support arm first sleeve that can be socketed elastic axis is arranged, described the 3rd support arm one end is fixed on the second support arm, the other end and electromagnet are connected and fixed, and are also twining magnet coil on this electromagnet.
9. Foldable overhaul platform as claimed in claim 8 is characterized in that, this first support arm and the second support arm are fixed on the guide rail both sides by the bolt group respectively.
10. Foldable overhaul platform as claimed in claim 4, it is characterized in that, it also comprises jacking system, this jacking system comprises at least one variable-frequency motor, at least one interlock round bar, at least one first rope sheave, at least one second rope sheave and at least two steel ropes, this variable-frequency motor is fixed on the connecting panel of a side, variable-frequency electric arbor one end passes connecting panel and connects the first rope sheave, the other end becomes to be rigidly connected with an end of interlock round bar, the described interlock round bar other end passes side connecting plate, and connect the second rope sheave, described at least two steel ropes upper end is also fixed on the first rope sheave and the second rope sheave respectively, and the lower end is fixed with the fag end axle that passes the platform both sides respectively.
11. Foldable overhaul platform as claimed in claim 10 is characterized in that, this variable-frequency motor is with auto-lock function.
12. Foldable overhaul platform as claimed in claim 4 is characterized in that, it also comprises protection railing and the movable railing assembly that is connected between the folding suspension rod in both sides.
13. Foldable overhaul platform as claimed in claim 12, it is characterized in that, this movable railing assembly comprises at least two anchor shafts, at least one the first movable railing, at least one the second movable railing, at least one threaded line pipe, cross bar one end of this first movable railing one end and pull bar reinforcement structure is hinged, the other end of this first movable railing and the socket of threaded line pipe one end; This second movable railing one end is hinged with cross bar one end of lateral bracing strut being strengthened structure, and the other end of the second movable railing is realized being threaded with the threaded line pipe other end.
14. Foldable overhaul platform as claimed in claim 13, it is characterized in that, the anchor shaft of cross bar one end of this first movable railing one end and pull bar reinforcement structure is hinged by bearing pin, and this second movable railing one end is hinged by bearing pin with the cross bar one end anchor shaft of lateral bracing strut being strengthened structure.
15. Foldable overhaul platform as claimed in claim 14, it is characterized in that, the other end of this first movable railing is provided with boss, this threaded line pipe is the little tubular of the large other end opening of an end opening, the other end of the second movable railing has been attacked outside thread, and the large open end of threaded line pipe is attacked the negative thread that cooperates with the second movable railing outside thread; The little open end of threaded line pipe and the socket of the boss of the first movable railing.
16. elevator device, this system comprises elevator hoistways, elevator, it is characterized in that, it comprises that also this Foldable overhaul platform is fixed in the hoisting beam of well headroom or well headroom by guide rail such as each described Foldable overhaul platform of claim 1~15.
17. elevator device as claimed in claim 16 is characterized in that, the track of this Foldable overhaul platform is fixed in well headroom by holding-down bolt or expansion bolt or is bolted/is weldingly fixed on the hoisting beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210570466.6A CN103043572B (en) | 2012-12-25 | 2012-12-25 | Foldable overhaul platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210570466.6A CN103043572B (en) | 2012-12-25 | 2012-12-25 | Foldable overhaul platform |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103043572A true CN103043572A (en) | 2013-04-17 |
CN103043572B CN103043572B (en) | 2015-10-14 |
Family
ID=48056467
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210570466.6A Active CN103043572B (en) | 2012-12-25 | 2012-12-25 | Foldable overhaul platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103043572B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612427A (en) * | 2014-12-24 | 2015-05-13 | 广西大学 | Coordinated type non-avoiding stereo garage |
CN106365069A (en) * | 2016-09-21 | 2017-02-01 | 大连爱渥特机器人科技有限公司 | Scissor-fork lifting stabilization mechanism |
CN112610042A (en) * | 2020-12-03 | 2021-04-06 | 温州职业技术学院 | Computer room maintenance and repair operation device |
CN113883957A (en) * | 2020-07-03 | 2022-01-04 | 北京机械设备研究所 | Can dismantle operating floor in pit |
US11427441B2 (en) * | 2020-07-23 | 2022-08-30 | Otis Elevator Company | Elevator car with foldable working platform |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6202801B1 (en) * | 1999-05-07 | 2001-03-20 | Inventio Ag | Equipment for carrying out operations in an elevator shaft |
CN2900447Y (en) * | 2006-04-05 | 2007-05-16 | 倪既民 | Drawing driven side type attached frame combined shear fork jacking lift |
CN101066733A (en) * | 2006-12-13 | 2007-11-07 | 上海永大电梯设备有限公司 | Foldable overhaul platform |
CN102092610A (en) * | 2009-12-15 | 2011-06-15 | 株式会社日立制作所 | Elevator overhaul stand |
US8038110B2 (en) * | 2008-10-31 | 2011-10-18 | William Karl Talbott | Article holding device for aerial work platform |
CN102515000A (en) * | 2011-12-22 | 2012-06-27 | 江南嘉捷电梯股份有限公司 | Elevator ceiling device |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1664662A1 (en) * | 1988-07-18 | 1991-07-23 | Брянский Институт Транспортного Машиностроения | Mechanism for vertical movement of load-bearing platform |
-
2012
- 2012-12-25 CN CN201210570466.6A patent/CN103043572B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6202801B1 (en) * | 1999-05-07 | 2001-03-20 | Inventio Ag | Equipment for carrying out operations in an elevator shaft |
CN2900447Y (en) * | 2006-04-05 | 2007-05-16 | 倪既民 | Drawing driven side type attached frame combined shear fork jacking lift |
CN101066733A (en) * | 2006-12-13 | 2007-11-07 | 上海永大电梯设备有限公司 | Foldable overhaul platform |
US8038110B2 (en) * | 2008-10-31 | 2011-10-18 | William Karl Talbott | Article holding device for aerial work platform |
CN102092610A (en) * | 2009-12-15 | 2011-06-15 | 株式会社日立制作所 | Elevator overhaul stand |
CN102515000A (en) * | 2011-12-22 | 2012-06-27 | 江南嘉捷电梯股份有限公司 | Elevator ceiling device |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612427A (en) * | 2014-12-24 | 2015-05-13 | 广西大学 | Coordinated type non-avoiding stereo garage |
CN106365069A (en) * | 2016-09-21 | 2017-02-01 | 大连爱渥特机器人科技有限公司 | Scissor-fork lifting stabilization mechanism |
CN113883957A (en) * | 2020-07-03 | 2022-01-04 | 北京机械设备研究所 | Can dismantle operating floor in pit |
CN113883957B (en) * | 2020-07-03 | 2023-05-23 | 北京机械设备研究所 | Detachable underground operation table |
US11427441B2 (en) * | 2020-07-23 | 2022-08-30 | Otis Elevator Company | Elevator car with foldable working platform |
CN112610042A (en) * | 2020-12-03 | 2021-04-06 | 温州职业技术学院 | Computer room maintenance and repair operation device |
CN112610042B (en) * | 2020-12-03 | 2022-03-04 | 温州职业技术学院 | Computer room maintenance and repair operation device |
Also Published As
Publication number | Publication date |
---|---|
CN103043572B (en) | 2015-10-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103043572B (en) | Foldable overhaul platform | |
CN102797222B (en) | Hanging bracket hinge joint type bridge maintenance vehicle capable of avoiding bridge-side obstacles | |
CN103306200B (en) | Elevated bridge of high speed railway beam detects and rescue operation vehicle | |
CN105507640B (en) | A kind of drawer type lifting three-dimensional garage | |
CN112282462B (en) | Method for storing and taking vehicles by using transverse trolley with leveling device and rotation function | |
CN102912726A (en) | Combined type multifunctional bridge inspection trolley | |
CN106639447A (en) | Lifting anti-falling device | |
CN101929258A (en) | Hydraulic leveling safety catcher | |
CN205603095U (en) | Engineering work crane | |
CN103253579A (en) | Gear-and-rack elevator | |
CN112081439A (en) | Method for storing and taking vehicles by using transverse moving trolley with telescopic automatic leveling device | |
CN106193728A (en) | A kind of Multi-storey up-down & translation formula hydraulic three-dimensional garage | |
CN105293278A (en) | Electric block type double-rail and single-main-beam crane | |
CN203334180U (en) | High-speed railway overhead bridge detection and rescue working truck | |
CN111041982B (en) | Double-width bridge double-suspension-point bridge inspection vehicle | |
CN212316704U (en) | Bridge construction hanging basket capable of passing pier | |
CN205476727U (en) | Drawer type lift stereo garage | |
CN104671119A (en) | Hammer type gantry crane for collaborative slipway operation | |
CN104164988A (en) | Stereoscopic garage with high-rise mobile lifter and vehicle moving process thereof | |
CN205873697U (en) | Control hoist rise to rise with differential actuating mechanism of mixture of dolly sideslip | |
CN207829536U (en) | A kind of two layers of rear cantilever type parking equipment | |
CN208378237U (en) | A kind of heavy type rail roadway stakcer crane | |
CN113443535A (en) | Down extending type lifting equipment for well construction and mounting method thereof | |
CN202730646U (en) | Bridge maintenance car with articulated type hanging bracket and capable of avoiding bridge-side barriers | |
CN206569924U (en) | A kind of route-variable height beam for crane room is driven a vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |