CN103021218A - Simulation training device and simulation training method for switching operation of power distribution circuit - Google Patents

Simulation training device and simulation training method for switching operation of power distribution circuit Download PDF

Info

Publication number
CN103021218A
CN103021218A CN2012104480511A CN201210448051A CN103021218A CN 103021218 A CN103021218 A CN 103021218A CN 2012104480511 A CN2012104480511 A CN 2012104480511A CN 201210448051 A CN201210448051 A CN 201210448051A CN 103021218 A CN103021218 A CN 103021218A
Authority
CN
China
Prior art keywords
switching operation
trainee
grid switching
training
display screen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104480511A
Other languages
Chinese (zh)
Inventor
徐惠强
杨晓翔
高旭启
朱训林
别士光
刘春翔
宋立峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Wuhan NARI Ltd
Huzhou Power Supply Bureau
Original Assignee
State Grid Corp of China SGCC
Wuhan NARI Ltd
Huzhou Power Supply Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Wuhan NARI Ltd, Huzhou Power Supply Bureau filed Critical State Grid Corp of China SGCC
Priority to CN2012104480511A priority Critical patent/CN103021218A/en
Publication of CN103021218A publication Critical patent/CN103021218A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a simulation training device and a simulation training method for switching operation of a power distribution circuit. The device comprises an operation platform provided with a fingerprint identifier, a touch screen and a three-dimensional display screen, wherein a handle and a start-up button are respectively arranged at two sides of the fingerprint identifier; a network interface is further formed below the side of the operation platform; and a three-dimensional signal emitter is arranged above the three-dimensional display screen. The method comprises the following steps of: logging in a switching operation simulation system, selecting a switching item and an own character, loading an operation scene, assigning a switching mission to teams, performing the switching operation, and giving out operation scores of trainers. The simulation training device and the simulation training method disclosed by the invention have the beneficial effects of reducing the training cost, achieving a good training effect, and improving the safety performance of the training.

Description

Distribution line grid switching operation emulation training device and Training Methodology thereof
Technical field
The invention belongs to the lation training course for power system field, refer to particularly a kind of distribution line grid switching operation emulation training device and Training Methodology thereof.
Background technology
Along with the good and fast development of China's economic society, electricity needs is day by day vigorous, and closely-related electrical network is also at Quick Extended with it, and this safety and stability to operation of power networks has proposed higher requirement.
Grid switching operation is directly to change the method for operation of electrical equipment and the operative skill of running status, is a not only important but also complicated job.If the generation misoperation fault just may cause the damage of equipment, injures and deaths and the large-area power failure of the person, cause heavy economic losses.For network access operation electrician practitioner, must expertly grasp back brake professional knowledge and operative skill through system, comprehensive, professional training, could be competent at this work.
Present grid switching operation training mainly is the mode by the master worker trains an apprentice, mock-up is lectured or set up in the classroom.But the master worker trains an apprentice and mode is lectured in the classroom, can only watch or pay attention to the class by the trainee aside; Use the mock-up training, although can operate at material object, mock-up can not simulate real duty, and is subject to the condition restriction such as weather, place.The present ubiquitous shortcoming of grid switching operation training is dangerous high in sum, is subject to the condition restriction such as weather, place, and cost is high, and result of training is very undesirable.
Summary of the invention
The objective of the invention is provides a kind of low cost, effective, the reliable distribution line grid switching operation of security performance emulation training device and Training Methodology thereof in order to overcome above-mentioned deficiency.
For achieving the above object, the technical solution used in the present invention is:
A kind of distribution line grid switching operation emulation training device comprises the operator's console that is provided with Fingerprint Identification Unit, touch-screen and stereoscopic display screen, the both sides of described Fingerprint Identification Unit are respectively arranged with handle and start button, the side-lower of described operator's console also is provided with network interface, and the top of described stereoscopic display screen is provided with the three-dimensional signal transmitter.
Also be placed with the 3D glasses on the described operator's console.
A kind of distribution line grid switching operation emulation training method may further comprise the steps:
Step 1: the trainee is by Fingerprint Identification Unit login grid switching operation analogue system;
Step 2: the trainee selects a back brake project by the touch control screen and selects the role of oneself in bulleted list;
Step 3: the system loads working scene also projects on the stereoscopic display screen by the 3D signal of three-dimensional transmitter with working scene, and the trainee wears the working scene that the 3D glasses can be watched 3 D stereo;
Step 4: the trainee receives the grid switching operation order by the handle control role, and assigns the back brake task to teams and groups;
Step 5: the trainee carries out the banister operation by the handle control role according to the working specification of back brake;
Step 6: grid switching operation rules and the safety standard of step 5 with standard compared, judge whether each step operation is correct;
Step 7: if operating mistake, system will record current mistake, and the prompting trainee returns step 5 and again operates;
Step 8: if operation is correct, judge then whether whole operation is finished; If do not finish, then return step 4 and again operate;
Step 9: if whole operation is finished, system will provide trainee's operation achievement, and whole training process finishes.
Wherein, described step 9 system just provides in trainee's the operation achievement and comprises operator error recording.
The invention has the beneficial effects as follows and reduced the training low cost, it is good to have reached result of training, has improved the security performance of training.
Description of drawings
Fig. 1 is distribution line grid switching operation emulation training apparatus structure synoptic diagram of the present invention.
Fig. 2 is distribution line grid switching operation emulation training method flow diagram of the present invention.
Embodiment
Further specify the present invention below in conjunction with drawings and Examples.
Embodiment: distribution line grid switching operation emulation training device of the present invention comprises: Fingerprint Identification Unit 1, touch control screen 2, handle 3, network interface 4, three-dimensional signal transmitter 5, stereoscopic display screen 6, start button 7,3D glasses 8 and operator's console 9.Fingerprint Identification Unit 1 is arranged on middle part, operator's console 9 table top the place aheads, is used for the trainee and logins the grid switching operation simulation training system.Touch-screen 2 is positioned at the right half part of operator's console 9, is used for the trainee and selects grid switching operation emulation training project and setting item parameter.Handle 3 is arranged on the right side of Fingerprint Identification Unit 1, is used for the trainee and sends operational order to training set.Network interface 4 is arranged on the bottom of operator's console 9, is used for training set and is connected with the internet.Three-dimensional signal transmitter 5 is arranged on the top of stereoscopic display screen 6, is used for to stereoscopic display screen 6 emission 3D signals.Stereoscopic display screen 6 is positioned at the left-half of operator's console 9, and what be used for 5 emissions of reception three-dimensional signal transmitter presents the 3D signal of reception to the trainee, and presents the working scene of 3 D stereo to the trainee.Start button 7 is arranged on the left side of Fingerprint Identification Unit 1, is used for the opening and closing training set.3D glasses 8 are placed on the table top of operator's console 9, are used for the trainee watches the 3 D stereo that presents on the stereoscopic display screen 6 with upper rear reception 3D signal working scene.
Distribution line grid switching operation emulation training method of the present invention is:
Step 1: the trainee is by Fingerprint Identification Unit 1 login grid switching operation analogue system;
Step 2: the trainee selects a back brake project by touch control screen 2 and selects the role of oneself in bulleted list;
Step 3: the system loads working scene also projects on the stereoscopic display screen 6 by the 3D signal of three-dimensional transmitter 5 with working scene, and the trainee wears the working scene that 3D glasses 8 can be watched 3 D stereo;
Step 4: the trainee receives the grid switching operation order by handle 3 control roles, and assigns the back brake task to teams and groups;
Step 5: the trainee carries out grid switching operation by the handle control role according to the working specification of back brake;
Step 6: grid switching operation rules and the safety standard of step 5 with standard compared, judge whether each step operation is correct;
Step 7: if operating mistake, system will record current mistake, and the prompting trainee returns step 5 and again operates;
Step 8: if operation is correct, judge then whether whole operation is finished; If do not finish, then return step 4 and again operate;
Step 9: if whole operation is finished, the operation achievement that system will provide the trainee comprises error logging, and whole training process finishes.
Wherein, grid switching operation comprises in the step 5 of the present invention: fill in operation order, then operation order is submitted to virtual guardian or chief operator audit, simulate item by item according to the operation order content and call out the names of those voted for while counting ballot-slips, preview; Then choose Work tool and the material that uses this mission from tool storage room and material depot; Finish assigning a work of on-the-spot fence, security warning etc., and dress working cloth, safety helmet and the insulating glove etc. of good regulation; Carry out item by item grid switching operation according to the operation order content, content of operation carries out according to selecting of task and corresponding grid switching operation security regulations; Operate backward virtual yardman or work area chief operator and simulated report grid switching operation implementation status; Reported rear label pin operation order
The above is the preferred embodiments of the present invention only, is not limited to the present invention.The content that is not described in detail in this instructions belongs to the known prior art of this area professional and technical personnel.

Claims (4)

1. distribution line grid switching operation emulation training device, comprise the operator's console (9) that is provided with Fingerprint Identification Unit (1), touch-screen (2) and stereoscopic display screen (6), it is characterized in that: the both sides of described Fingerprint Identification Unit (1) are respectively arranged with handle (3) and start button (7), the side-lower of described operator's console (9) also is provided with network interface (4), and the top of described stereoscopic display screen (6) is provided with three-dimensional signal transmitter (5).
2. distribution line grid switching operation emulation training device according to claim 1 is characterized in that: also be placed with 3D glasses (8) on the described operator's console (9).
3. distribution line grid switching operation emulation training device according to claim 1 and 2, the concrete steps of its emulation training method are:
Step 1: the trainee is by Fingerprint Identification Unit login grid switching operation analogue system;
Step 2: the trainee selects a back brake project by the touch control screen and selects the role of oneself in bulleted list;
Step 3: the system loads working scene also projects on the stereoscopic display screen by the 3D signal of three-dimensional transmitter with working scene, and the trainee wears the working scene that the 3D glasses can be watched 3 D stereo;
Step 4: the trainee receives the grid switching operation order by the handle control role, and assigns the back brake task to teams and groups;
Step 5: the trainee carries out the banister operation by the handle control role according to the working specification of back brake;
Step 6: grid switching operation rules and the safety standard of step 5 with standard compared, judge whether each step operation is correct;
Step 7: if operating mistake, system will record current mistake, and the prompting trainee returns step 5 and again operates;
Step 8: if operation is correct, judge then whether whole operation is finished; If do not finish, then return step 4 and again operate;
Step 9: if whole operation is finished, system will provide trainee's operation achievement, and whole training process finishes.
4. distribution line grid switching operation emulation training method according to claim 3 is characterized in that: described step 9 system just provides in trainee's the operation achievement and comprises operator error recording.
CN2012104480511A 2012-11-09 2012-11-09 Simulation training device and simulation training method for switching operation of power distribution circuit Pending CN103021218A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104480511A CN103021218A (en) 2012-11-09 2012-11-09 Simulation training device and simulation training method for switching operation of power distribution circuit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104480511A CN103021218A (en) 2012-11-09 2012-11-09 Simulation training device and simulation training method for switching operation of power distribution circuit

Publications (1)

Publication Number Publication Date
CN103021218A true CN103021218A (en) 2013-04-03

Family

ID=47969772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104480511A Pending CN103021218A (en) 2012-11-09 2012-11-09 Simulation training device and simulation training method for switching operation of power distribution circuit

Country Status (1)

Country Link
CN (1) CN103021218A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930755A (en) * 2012-11-28 2013-02-13 湖州电力局 Live-working simulation training device for multi-circuit lines of distribution networks and training method thereof
CN103425846A (en) * 2013-08-27 2013-12-04 国家电网公司 Simulation method oriented towards distribution line operating maintenance process
CN104966425A (en) * 2015-07-13 2015-10-07 国家电网公司 10kV cable live work simulation training device and method
CN109102730A (en) * 2018-08-08 2018-12-28 泰豪科技股份有限公司 Military generating set simulation training method and device
CN110738881A (en) * 2019-11-26 2020-01-31 国网冀北电力有限公司技能培训中心 Power transformation operation simulation training system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4545767A (en) * 1982-11-17 1985-10-08 The Tokyo Electric Power Company Inc. Training operation system and simulator for training in electric power system
CN101097661A (en) * 2006-05-10 2008-01-02 仁安资讯科技股份有限公司 Operations exercitation simulator suitable for CNC toolroom machine
CN201255955Y (en) * 2008-08-28 2009-06-10 浙江天煌科技实业有限公司 Integrated automation experimental system for transforming plant
CN202142208U (en) * 2010-12-06 2012-02-08 山东省电力学校 DC transmission skill training device
CN102723015A (en) * 2012-05-29 2012-10-10 国网电力科学研究院武汉南瑞有限责任公司 Simulation training system and method for operation and maintenance of distribution network

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4545767A (en) * 1982-11-17 1985-10-08 The Tokyo Electric Power Company Inc. Training operation system and simulator for training in electric power system
CN101097661A (en) * 2006-05-10 2008-01-02 仁安资讯科技股份有限公司 Operations exercitation simulator suitable for CNC toolroom machine
CN201255955Y (en) * 2008-08-28 2009-06-10 浙江天煌科技实业有限公司 Integrated automation experimental system for transforming plant
CN202142208U (en) * 2010-12-06 2012-02-08 山东省电力学校 DC transmission skill training device
CN102723015A (en) * 2012-05-29 2012-10-10 国网电力科学研究院武汉南瑞有限责任公司 Simulation training system and method for operation and maintenance of distribution network

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930755A (en) * 2012-11-28 2013-02-13 湖州电力局 Live-working simulation training device for multi-circuit lines of distribution networks and training method thereof
CN103425846A (en) * 2013-08-27 2013-12-04 国家电网公司 Simulation method oriented towards distribution line operating maintenance process
CN104966425A (en) * 2015-07-13 2015-10-07 国家电网公司 10kV cable live work simulation training device and method
CN109102730A (en) * 2018-08-08 2018-12-28 泰豪科技股份有限公司 Military generating set simulation training method and device
CN110738881A (en) * 2019-11-26 2020-01-31 国网冀北电力有限公司技能培训中心 Power transformation operation simulation training system and method

Similar Documents

Publication Publication Date Title
CN102163382B (en) Live working helmet type simulation training system and method
CN106652686A (en) Relay protection VR training system
CN103021218A (en) Simulation training device and simulation training method for switching operation of power distribution circuit
CN101894488B (en) Distributed three-dimensional simulation training system for regional power system transformer station
CN108345709A (en) The safety measure demonstration emulation methods of exhibiting and device of substation's current loop operation
CN201812399U (en) Table type simulation training system for live-wire work
CN104037937B (en) A kind of analog simulation intelligent substation measure and control device
CN103366059A (en) Model data description method for secondary equipment of substation simulation and training system
CN104182906A (en) Substation simulation method and system for realizing multi-role cooperative operation
CN105225566A (en) A kind of electric network emergency rehearsal visual simulating deduction system
CN103559822A (en) Substation simulation training system
CN110706542A (en) Electric power operation somatosensory training system based on immersion virtual technology
CN107591038A (en) A kind of pole transformer stops the simulated operation interactive system of multiple labour
CN111710032B (en) Method, device, equipment and medium for constructing three-dimensional model of transformer substation
CN110942698B (en) Simulation real operation control platform for distribution network uninterrupted operation
CN109542226A (en) 10kV high-voltage metering cubicle final acceptance of construction simulation system and analogy method based on virtual reality technology
CN103149842B (en) A kind of generating plant excitation analogue system based on emulation-control integrated design
CN105405334A (en) Power distribution automation system and simulation method
CN211555173U (en) Intelligent low-voltage distribution network operation and maintenance comprehensive simulation system
CN111754834A (en) Electric power training method based on virtual reality
CN110992761A (en) VR-based pump station operation simulation training and examination system and method
CN104408262A (en) Online evaluation method and system for power grid relay protection constant value
CN103000065A (en) Running, overhauling and measuring operation simulation training device and training method for same
CN202650332U (en) Virtual simulation training system of distributed transformer substation based on province, prefecture and county level networks
CN114357762A (en) Wisdom power equipment high in clouds control automatic system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130403