CN103018067A - 换流阀器件冷却试验系统 - Google Patents

换流阀器件冷却试验系统 Download PDF

Info

Publication number
CN103018067A
CN103018067A CN2012105182933A CN201210518293A CN103018067A CN 103018067 A CN103018067 A CN 103018067A CN 2012105182933 A CN2012105182933 A CN 2012105182933A CN 201210518293 A CN201210518293 A CN 201210518293A CN 103018067 A CN103018067 A CN 103018067A
Authority
CN
China
Prior art keywords
valve
electric
test system
main circulation
converter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105182933A
Other languages
English (en)
Other versions
CN103018067B (zh
Inventor
冷明全
卢志敏
吴安兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Goaland Energy Conservation Tech Co Ltd
Original Assignee
Guangzhou Goaland Energy Conservation Tech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Goaland Energy Conservation Tech Co Ltd filed Critical Guangzhou Goaland Energy Conservation Tech Co Ltd
Priority to CN201210518293.3A priority Critical patent/CN103018067B/zh
Publication of CN103018067A publication Critical patent/CN103018067A/zh
Application granted granted Critical
Publication of CN103018067B publication Critical patent/CN103018067B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

本发明公开了一种换流阀器件冷却试验系统,包括主循环泵、第一电动三通阀、空气散热器、机械过滤器、第二电动三通阀、试验阀组及电加热器,所述电加热器、主循环泵、第一电动三通阀、空气散热器、机械过滤器及第二电动三通阀通过管道依次连接,试验阀组通过第一球阀与电加热器连接,通过第二球阀与第二电动三通阀连接形成主循环回路。通过该试验系统可以获得换流阀器件的压差—流量特性、热运行特性、耐压性能、高低温热循环性能以及高电压电腐蚀特性,还可以完成PVDF配水管道流量匹配设计和验证试验,判断换流阀中与散热有关的器件是否满足相应技术要求,该试验系统可以作为直流换流阀配套产品,降低工程成本,创造巨大的经济效益。

Description

换流阀器件冷却试验系统
技术领域
本发明涉及换流阀器件的测试,特别涉及换流阀器件冷却试验系统。
背景技术
换流阀由晶闸管、阻尼电容、均压电容、阻尼电阻、均压电阻、饱和电抗器、晶闸管控制单元等零部件组成。换流阀在运行过程中会产生大量的热量,水冷是目前广泛采用的冷却方式,换流阀在投入使用前,需要对换流阀内部水冷器件包括水冷散热器、水冷电阻、水冷电抗器以及与外部冷却冷却系统连接的PVDF配水管道进行试验,确保其可靠运行,包括其压力流量特性、热运行热性、耐水压性能、高低温热循环性能以及高电压电腐蚀性能试验。
发明内容
本发明的目的在于克服上述现有技术的缺点,提供一种换流阀器件冷却试验系统,所述换流阀器件包括水冷散热器、水冷电阻、水冷电抗器、与外部冷却冷却系统连接的PVDF配水管道及其它与散热有关的器件。
为解决上述问题,本发明采用的技术方案是:
一种换流阀器件冷却试验系统,包括主循环泵、第一电动三通阀、空气散热器、机械过滤器、第二电动三通阀、试验阀组及电加热器,所述电加热器、主循环泵、第一电动三通阀、空气散热器、机械过滤器及第二电动三通阀通过管道依次连接,试验阀组通过第一球阀与电加热器连接,通过第二球阀与第二电动三通阀连接形成主循环回路,通过控制第一电动三通阀调节流经空气散热器的冷却介质流量,用于冬天温度低及试验阀组低负荷运行时的冷却介质温度调节,避免冷却介质温度过低,通过控制第二电动三通阀调节流经试验阀组的冷却介质流量。
为了更好的实现本发明,所述试验阀组并联有低温循环旁路,所述低温循环旁路包括通过管道依次连接的常闭第一电动阀、第一过滤器、低温循环泵、缓冲罐及常闭第二电动阀。
为了更好的实现本发明,所述电加热器与试验阀组之间设置有常开第三电动阀,低温模式下第一电动三通阀、第二电动三通阀及第三电动阀关闭,第一电动阀及第二电动阀打开,所述主循环泵、第一电动三通阀及第二电动三通阀形成回路,低温循环旁路及试验阀组形成回路。
为了更好的实现本发明,所述主循环回路并联有去离子支路,所述去离子支路包括通过管道依次连接的第四电动阀、离子罐、第二过滤器及缓冲罐,还包括补水装置及稳压装置,稳压装置与缓冲罐连接,通过控制第四电动阀调节主循环回路中冷却介质的电导率。
为了更好的实现本发明,所述换流阀器件冷却试验系统还包括由试压水箱、过滤器、电动试压泵及手动试压泵组成的移动试压装置,需要试压时,关闭第一球阀及第二球阀,移动试压装置与试验阀组形成试压通路。
为了更好的实现本发明,所述主循环回路安装有流量变送器,用于监测主循环回路中冷却介质的流量。
为了更好的实现本发明,所述试验阀组进口安装有进阀温度变送器,出口安装有出阀温度变送器,用于监测冷却介质进出阀温度。
为了更好的实现本发明,所述主循环回路并联电导率测量旁路,包括通过管道依次连接的第三球阀、电导率变送器、压力表及第四球阀,用于监测主循环回路中冷却介质的电导率。设置旁路有两个作用,第一是对电导率变送器进行压力保护,通过设定旁路的管径及球阀的开度控制旁路的压力,防止压力过大损坏电导率变送器,第二是仪表需要检修时,只需关闭第三球阀及第四球阀,不影响整个系统的正常运行。
为了更好的实现本发明,所述试验阀组进口安装有进阀压力变送器,出口安装有出阀压力变送器,用于监测主循环回路中冷却介质的压力以及试验阀组进出口的压差。
为了更好的实现本发明,所述主循环回路安装有压力表,用于监测试压通路的压力。
本发明的原理如下:本发明换流阀器件冷却试验系统,分为2种运行模式。
常规运行模式:恒定压力和流速的冷却介质源源不断流经空气散热器进行热交换,散热后再进入换流阀带走热量。根据热负荷的变化以及供水温度的变化来控制进入换热器的冷却介质流量比例和散热器的转速,从而达到精确控制温度的要求。常规试验模式下,进入换流阀冷却介质的流量通过第二电动三通阀进行调节,进入换流阀冷却介质的电导率通过第四电动阀进行调节。常规试验模式下,还可对小流量测试元件和阀组散热器进行独立测试。
高低温运行模式:高温模式时启动电加热器,冷却介质上升到目标温度后停止,并关闭第一电动三通阀,主循环回路运行,完成高温加热时间后切换至低温模式,低温模式下关闭第一电动三通阀、第二电动三通阀及第三电动阀,打开第一电动阀及第二电动阀,主循环泵、第一电动三通阀及第二电动三通阀形成回路,低温循环旁路及试验阀组形成回路,完成低温运行时间后,再次进行高温模式,打开第二电动三通阀及第三电动阀,关闭第一电动阀及第二电动阀,如此进行高温模式及低温模式的循环,直至试验结束。
为适应换流阀在高电压条件下的使用要求,防止在高电压环境下产生漏电流,冷却介质必须具备极低的电导率。因此在主循环回路上并联了去离子支路。预设一定流量的冷却介质流经离子罐,不断净化管路中可能析出的离子,然后通过缓冲罐,与主循环回路冷却介质在主循环泵入口合流,与缓冲罐连接的氮气稳压系统保持系统管路中冷却介质的充满及隔绝空气。
本发明与现有技术相比,具有如下优点及有益效果:通过该试验系统可以获得换流阀器件的压差—流量特性、热运行特性、耐压性能、高低温热循环性能以及高电压电腐蚀特性,还可以完成PVDF配水管道流量匹配设计和验证试验,判断换流阀中与散热有关的器件是否满足相应技术要求,该试验系统可以作为直流换流阀配套产品,降低工程成本,创造巨大的经济效益。
附图说明
图1是本发明实施例1所述换流阀器件冷却试验系统原理结构图。
具体实施方式
下面结合实施例及附图对本发明的实施方式作进一步详细的描述,但本发明的实施方式不限于此。
实施例1
如图1所示,一种换流阀器件冷却试验系统,电加热器1、主循环泵2、第一电动三通阀3、空气散热器4、机械过滤器5及第二电动三通阀6通过管道依次连接,试验阀组7通过第一球阀8与电加热器1连接,通过第二球阀9与第二电动三通阀6连接形成主循环回路,通过控制第一电动三通阀3调节流经空气散热器4的冷却介质流量,用于冬天温度低及试验阀组低负荷运行时的冷却介质温度调节,避免冷却介质温度过低,通过控制第二电动三通阀6调节流经试验阀组4的冷却介质流量。
为了更好的实现本发明,所述试验阀组4并联有低温循环旁路10,所述低温循环旁路5包括通过管道依次连接的常闭第一电动阀10-1、第一过滤器10-2、低温循环泵10-3、缓冲罐10-4及常闭第二电动阀10-5。
为了更好的实现本发明,所述电加热器1与试验阀组7之间设置有常开第三电动阀11,所述换流阀器件冷却试验系统在高温模式下启动电加热器1,冷却介质上升到目标温度后停止,并关闭第一电动三通阀3,主循环回路运行,完成高温加热时间后切换至低温模式,低温模式下关闭第一电动三通阀3、第二电动三通阀6及第三电动阀11,打开第一电动阀10-1及第二电动阀10-5,所述主循环泵2、第一电动三通阀3及第二电动三通阀6形成回路,低温循环旁路10及试验阀组7形成回路,完成低温运行时间后,再次进行高温模式,打开第二电动三通阀6及第三电动阀11,关闭第一电动阀10-1及第二电动阀10-5,如此进行高温模式及低温模式的循环,直至试验结束。
为了更好的实现本发明,所述主循环回路并联有去离子支路12,所述去离子支路包括通过管道依次连接的第四电动阀12-1、离子罐12-2、第二过滤器12-3及缓冲罐12-4,还包括补水装置12-5及稳压装置12-6,稳压装置12-6与缓冲罐12-4连接,通过控制第四电动阀12-1调节主循环回路中冷却介质的电导率,当主循环回路冷却介质进出阀温度高于树脂能承受的最高温度时,第四电动阀12-1关闭。
为了更好的实现本发明,所述换流阀器件冷却试验系统还包括由试压水箱13-1、过滤器13-2、电动试压泵13-3及手动试压泵13-4组成的移动试压装置13,需要试压时,关闭第一球阀8及第二球阀9,移动试压装置13与试验阀组7形成通路。
为了更好的实现本发明,所述主循环回路安装有流量变送器14,用于监测主循环回路中冷却介质的流量。
为了更好的实现本发明,所述试验阀组进口安装有进阀温度变送器15,出口安装有出阀温度变送器16,用于监测冷却介质进出阀温度。
为了更好的实现本发明,所述主循环回路并联电导率测量旁路17,包括通过管道依次连接的第三球阀17-1、电导率变送器17-3、压力表17-3及第四球阀17-4,设置旁路有两个作用,第一是对电导率变送器进行压力保护,通过设定旁路的管径及球阀的开度控制旁路的压力,防止压力过大损坏电导率变送器,第二是仪表需要检修时,只需关闭第三球阀及第四球阀,不影响整个系统的正常运行。
为了更好的实现本发明,所述试验阀组进口安装有进阀压力变送器18,出口安装有出阀压力变送器17,用于监测主循环回路中冷却介质的压力,以及试验阀组进出口的压差。
为了更好的实现本发明,所述主循环回路安装有压力表19,用于监测试压通路的压力。
上述实施例为本发明较佳的实施方式,但本发明的实施方式并不受上述实施例的限制,其他的任何未背离本发明的精神实质与原理下所作的改变、修饰、替代、组合、简化,均应为等效的置换方式,都包含在本发明的保护范围之内。

Claims (10)

1.一种换流阀器件冷却试验系统,其特征在于:包括主循环泵、第一电动三通阀、空气散热器、机械过滤器、第二电动三通阀、试验阀组及电加热器,所述电加热器、主循环泵、第一电动三通阀、空气散热器、机械过滤器及第二电动三通阀通过管道依次连接,试验阀组通过第一球阀与电加热器连接,通过第二球阀与第二电动三通阀连接形成主循环回路,通过控制第一电动三通阀调节流经空气散热器的冷却介质流量,通过控制第二电动三通阀调节流经试验阀组的冷却介质流量。
2.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述试验阀组并联有低温循环旁路,所述低温循环旁路包括通过管道依次连接的常闭第一电动阀、第一过滤器、低温循环泵、缓冲罐及常闭第二电动阀。
3.根据权利要求2所述一种换流阀器件冷却试验系统,其特征在于:所述电加热器与试验阀组之间设置有常开第三电动阀,第一电动三通阀、第二电动三通阀及第三电动阀关闭,第一电动阀及第二电动阀打开,所述主循环泵、第一电动三通阀及第二电动三通阀形成回路,低温循环旁路及试验阀组形成回路。
4.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述主循环回路并联有去离子支路,所述去离子支路包括通过管道依次连接的第四电动阀、离子罐、第二过滤器及缓冲罐,还包括补水装置及稳压装置,稳压装置与缓冲罐连接,通过控制第四电动阀调节主循环回路中冷却介质的电导率。
5.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述换流阀器件冷却试验系统还包括由试压水箱、过滤器、电动试压泵及手动试压泵组成的移动试压装置,需要试压时,关闭第一球阀及第二球阀,移动试压装置与试验阀组形成通路。
6.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述主循环回路安装有流量变送器。
7.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述试验阀组进口安装有进阀温度变送器,出口安装有出阀温度变送器。
8.根据权利要求4所述一种换流阀器件冷却试验系统,其特征在于:所述主循环回路并联电导率测量旁路,包括通过管道依次连接的第三球阀、电导率变送器、压力表及第四球阀。
9.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述试验阀组进口安装有进阀压力变送器,出口安装有出阀压力变送器。
10.根据权利要求1所述一种换流阀器件冷却试验系统,其特征在于:所述主循环回路安装有压力表。
CN201210518293.3A 2012-12-05 2012-12-05 换流阀器件冷却试验系统 Active CN103018067B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210518293.3A CN103018067B (zh) 2012-12-05 2012-12-05 换流阀器件冷却试验系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210518293.3A CN103018067B (zh) 2012-12-05 2012-12-05 换流阀器件冷却试验系统

Publications (2)

Publication Number Publication Date
CN103018067A true CN103018067A (zh) 2013-04-03
CN103018067B CN103018067B (zh) 2015-09-16

Family

ID=47966924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210518293.3A Active CN103018067B (zh) 2012-12-05 2012-12-05 换流阀器件冷却试验系统

Country Status (1)

Country Link
CN (1) CN103018067B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103674594A (zh) * 2013-12-08 2014-03-26 合肥天鹅制冷科技有限公司 液冷源设备测试装置及测试方法
CN104953794A (zh) * 2015-06-25 2015-09-30 常州博瑞电力自动化设备有限公司 高压直流换流阀水冷却系统
CN106053118A (zh) * 2016-07-21 2016-10-26 北京国电富通科技发展有限责任公司 一种过流组件测试装置
CN107178540A (zh) * 2017-06-29 2017-09-19 广州市日森机械股份有限公司 一种液压系统风冷却器散热性能测试装置
CN107748076A (zh) * 2017-12-01 2018-03-02 新乡市豫新航空工业制品有限公司 一种散热器燃滑油检验转换管路系统
CN107960043A (zh) * 2017-10-30 2018-04-24 全球能源互联网研究院 一种换流阀及其水冷系统
CN110646194A (zh) * 2019-08-29 2020-01-03 中国南方电网有限责任公司超高压输电公司广州局 一种换流阀冷却能力多维度分析预警方法及系统
CN111357093A (zh) * 2017-11-22 2020-06-30 宝惹株式会社 粉末防护三向阀
CN112362297A (zh) * 2020-10-19 2021-02-12 中国科学院合肥物质科学研究院 一种偏滤器吹扫试验环路数据采集系统及方法
CN112539931A (zh) * 2020-12-14 2021-03-23 沈阳盛世五寰科技有限公司 一种阀门用高压冷热态试验系统

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06102392A (ja) * 1992-09-18 1994-04-15 Toshiba Corp 原子炉圧力容器付属配管第一次耐圧試験加圧装置
US20070089548A1 (en) * 2002-10-15 2007-04-26 Florida Turbine Technologies, Inc. Process and apparatus for testing a material under a high temperature and pressure environment
CN102394551A (zh) * 2011-09-30 2012-03-28 广州高澜节能技术股份有限公司 一种直流输电换流阀冷却系统
CN102566623A (zh) * 2012-01-04 2012-07-11 广州高澜节能技术股份有限公司 直流输电换流阀纯水冷却装置控制系统
CN202364101U (zh) * 2011-11-29 2012-08-01 广州高澜节能技术股份有限公司 一种削峰型直流输电换流阀冷却系统
CN202565148U (zh) * 2012-04-27 2012-11-28 广州高澜节能技术股份有限公司 一种直流输电换流阀复合外冷却系统
CN203024989U (zh) * 2012-12-05 2013-06-26 广州高澜节能技术股份有限公司 换流阀器件冷却试验系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06102392A (ja) * 1992-09-18 1994-04-15 Toshiba Corp 原子炉圧力容器付属配管第一次耐圧試験加圧装置
US20070089548A1 (en) * 2002-10-15 2007-04-26 Florida Turbine Technologies, Inc. Process and apparatus for testing a material under a high temperature and pressure environment
CN102394551A (zh) * 2011-09-30 2012-03-28 广州高澜节能技术股份有限公司 一种直流输电换流阀冷却系统
CN202364101U (zh) * 2011-11-29 2012-08-01 广州高澜节能技术股份有限公司 一种削峰型直流输电换流阀冷却系统
CN102566623A (zh) * 2012-01-04 2012-07-11 广州高澜节能技术股份有限公司 直流输电换流阀纯水冷却装置控制系统
CN202565148U (zh) * 2012-04-27 2012-11-28 广州高澜节能技术股份有限公司 一种直流输电换流阀复合外冷却系统
CN203024989U (zh) * 2012-12-05 2013-06-26 广州高澜节能技术股份有限公司 换流阀器件冷却试验系统

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103674594A (zh) * 2013-12-08 2014-03-26 合肥天鹅制冷科技有限公司 液冷源设备测试装置及测试方法
CN104953794A (zh) * 2015-06-25 2015-09-30 常州博瑞电力自动化设备有限公司 高压直流换流阀水冷却系统
CN106053118A (zh) * 2016-07-21 2016-10-26 北京国电富通科技发展有限责任公司 一种过流组件测试装置
CN107178540A (zh) * 2017-06-29 2017-09-19 广州市日森机械股份有限公司 一种液压系统风冷却器散热性能测试装置
CN107960043A (zh) * 2017-10-30 2018-04-24 全球能源互联网研究院 一种换流阀及其水冷系统
CN111357093B (zh) * 2017-11-22 2023-04-07 宝惹株式会社 粉末防护三向阀
CN111357093A (zh) * 2017-11-22 2020-06-30 宝惹株式会社 粉末防护三向阀
CN107748076A (zh) * 2017-12-01 2018-03-02 新乡市豫新航空工业制品有限公司 一种散热器燃滑油检验转换管路系统
CN107748076B (zh) * 2017-12-01 2023-09-12 河南新航航空设备科技有限公司 一种散热器燃滑油检验转换管路系统
CN110646194A (zh) * 2019-08-29 2020-01-03 中国南方电网有限责任公司超高压输电公司广州局 一种换流阀冷却能力多维度分析预警方法及系统
CN112362297A (zh) * 2020-10-19 2021-02-12 中国科学院合肥物质科学研究院 一种偏滤器吹扫试验环路数据采集系统及方法
CN112362297B (zh) * 2020-10-19 2023-11-28 中国科学院合肥物质科学研究院 一种偏滤器吹扫试验环路数据采集系统及方法
CN112539931A (zh) * 2020-12-14 2021-03-23 沈阳盛世五寰科技有限公司 一种阀门用高压冷热态试验系统

Also Published As

Publication number Publication date
CN103018067B (zh) 2015-09-16

Similar Documents

Publication Publication Date Title
CN103018067A (zh) 换流阀器件冷却试验系统
CN105301047B (zh) 一种超临界氟利昂换热实验系统及其实验方法
CN202260470U (zh) 一种svc密闭式循环纯水冷却系统
CN107145175B (zh) 一种蒸汽发生器给水温度控制模拟系统
CN102368615A (zh) 一种svc密闭式循环纯水冷却系统
CN212902022U (zh) 一种输出温度连续可调的导热油换热系统
CN106895950B (zh) 一种用于汽车散热器风洞试验台的辅助低温冷却水系统
CN203024989U (zh) 换流阀器件冷却试验系统
CN103574954B (zh) 一种能量回馈型热交换系统
CN203733005U (zh) 一种发动机中冷模拟温度控制装置
CN103323358A (zh) 热循环试验设备及试验方法
CN205317441U (zh) 一种用于汽车散热器风洞试验台的辅助低温冷却水系统
CN204854097U (zh) 水冷式冷水机组测试系统
CN103217058A (zh) 一种冰水机热交换量控制系统
CN208254049U (zh) 一种冷却水集中供冷多温区恒温处理装置
CN103241802B (zh) 一种脉冲式纯水维持系统
CN102539191A (zh) 具有表冷盘管调节功能的风冷冷(热)水机组试验装置
CN203248911U (zh) 用于纺丝生产线熔体管道的保温系统
CN207473437U (zh) 一种蒸汽控制与电加热控制的双模式切换控制系统
CN204099046U (zh) 一种发动机中冷温度控制装置
CN205135941U (zh) 一种可输出多种温度热水的空压机余热回收系统
CN207163011U (zh) 一种冷热联供系统
CN204646623U (zh) 一种核电站主给水泵气蚀性能试验系统
CN107787162B (zh) 采用纯水介质的循环冷却装置及其使用方法
CN215203402U (zh) 紧凑型大流量余弦曲线温控装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Geng Man

Inventor after: Leng Mingquan

Inventor after: Lu Zhimin

Inventor after: Wu Anbing

Inventor before: Leng Mingquan

Inventor before: Lu Zhimin

Inventor before: Wu Anbing

COR Change of bibliographic data
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Cooling test system of converter valve

Effective date of registration: 20201103

Granted publication date: 20150916

Pledgee: Bank of China Limited Guangzhou Pearl River Branch

Pledgor: GUANGZHOU GOALAND ENERGY CONSERVATION TECH Co.,Ltd.

Registration number: Y2020440000348

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220726

Granted publication date: 20150916

Pledgee: Bank of China Limited Guangzhou Pearl River Branch

Pledgor: GUANGZHOU GOALAND ENERGY CONSERVATION TECH Co.,Ltd.

Registration number: Y2020440000348

PC01 Cancellation of the registration of the contract for pledge of patent right