CN103016010A - 竖井延深一次成井方法 - Google Patents

竖井延深一次成井方法 Download PDF

Info

Publication number
CN103016010A
CN103016010A CN 201210553628 CN201210553628A CN103016010A CN 103016010 A CN103016010 A CN 103016010A CN 201210553628 CN201210553628 CN 201210553628 CN 201210553628 A CN201210553628 A CN 201210553628A CN 103016010 A CN103016010 A CN 103016010A
Authority
CN
China
Prior art keywords
shaft
deepening
construction
section
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201210553628
Other languages
English (en)
Inventor
王成东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Pingdu City Old Shop Gold Mine
Original Assignee
Qingdao Pingdu City Old Shop Gold Mine
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Pingdu City Old Shop Gold Mine filed Critical Qingdao Pingdu City Old Shop Gold Mine
Priority to CN 201210553628 priority Critical patent/CN103016010A/zh
Publication of CN103016010A publication Critical patent/CN103016010A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种竖井延深一次成井方法,竖井延深施工前,将井底积水及杂物进行清理,之后布置延深井筒断面,将原梯子间内的梯子间平台和梯子梁拆除,在生产中段设置人工防护盘,在原梯子间马头门上方安设凿井提升天伦平台,将绞车布置在最低生产中段的调车场,之后依次进行提升间施工和井筒延深施工。竖井延深一次成井方法,利用原有的梯子间安设井筒延深时的掘进提升系统,自上而下直接延深井筒,不会影响上段井筒永久提升,有效解决了上部提升与深部延深的矛盾;施工简单,辅助工程量少、投资少;独立性好,便于集中管理。

Description

竖井延深一次成井方法
技术领域
本发明属于采矿技术领域,具体涉及一种利用原有梯子间延深竖井的方法。
背景技术
在矿石开采中,竖井通常不是一次掘进到底的,而是先掘到上部某一水平,进行采区准备,并达到投产标准后,矿山即可投产使用,在上水平矿体开采完毕以前,为了增加后续资源和生产能力,保证可持续发展,再采取深部开拓方案,延深原有井筒。目前,竖井深部开拓采用较多的延深方案为先掘进施工一小盲竖井,自盲竖井底掘进平巷至竖井底,然后向上返掘天井,与竖井底贯通后,刷大扩帮,然后成井。这种方案虽然避免了上部提升与深部延深之间的矛盾,但是工程量大,工期长,贯通测量要求精度高,施工难度大,同时需要新增一套提升设备系统,后期管理等各项费用都较高。
发明内容
为了克服现有技术领域存在的上述技术问题,本发明的目的在于,提供一种竖井延深一次成井方法,辅助工程量少、投资少,管理集中,独立性好,对生产提升干扰少。
本发明提供的竖井延深一次成井方法,包括以下步骤:
(1)竖井延深施工前,将井底积水及杂物进行清理;
(2)布置延深井筒断面:将原梯子间内的梯子间平台和梯子梁拆除,在生产中段设置人工防护盘,在原梯子间马头门上方安设凿井提升天伦平台,将绞车布置在最低生产中段的调车场;
(3)提升间施工,将原梯子间自上往下掘进到下一段生产水平,作为提升间,所掘矿石由绞车通过提升系统提升到生产中段,通过调车场,运至原竖井提升的罐笼,通过罐笼提升至地表;
(4)在提升间及辅助设备安设好之后,自上往下按井筒设计断面进行延深施工,施工至设计深度时,进行马头门施工和井筒安装工作,之后拆除人工防护盘,竖井延深完成。
本发明提供的竖井延深一次成井方法,其有益效果在于,利用原有的梯子间安设井筒延深时的掘进提升系统,自上而下直接延深井筒,不会影响上段井筒永久提升,有效解决了上部提升与深部延深的矛盾;施工简单,辅助工程量少、投资少;独立性好,便于集中管理。
附图说明
图1是本发明一个实施例的整体布置示意图。
图中标注:
1.原梯子间;2.凿井提升天轮平台;3.地表;4.绞车;5.井筒;6.人工防护盘;7.罐笼。
具体实施方式
下面参照附图,结合一个实施例,对本发明提供的竖井延深一次成井方法
进行详细的说明。
实施例
参照图1,本实施例的竖井延深一次成井方法,包括以下步骤:
(1)竖井延深施工前,将井底积水及杂物进行清理;
(2)布置延深井筒断面:将原梯子间1内的梯子间平台和梯子梁拆除,在生产中段设置人工防护盘6,在原梯子间1马头门上方安设凿井提升天伦平台2,将绞车4布置在最低生产中段的调车场;
(3)提升间施工,将原梯子间1自上往下掘进到下一段生产水平,作为提升间,所掘矿石由绞车4通过提升系统提升到生产中段,通过调车场,运至原竖井提升的罐笼7,通过罐笼提升至地表3;
(4)在提升间及辅助设备安设好之后,自上往下按井筒设计断面进行延深施工,施工至设计深度时,进行马头门施工和井筒5安装工作,之后拆除人工防护盘6,竖井延深完成。
竖井延深一次成井方法,延深辅助工程量小,延深准备工期短,施工成本较低。

Claims (1)

1.一种竖井延深一次成井方法,其特征在于:所述方法包括以下步骤:
(1)竖井延深施工前,将井底积水及杂物进行清理;
(2)布置延深井筒断面:将原梯子间内的梯子间平台和梯子梁拆除,在生产中段设置人工防护盘,在原梯子间马头门上方安设凿井提升天伦平台,将绞车布置在最低生产中段的调车场;
(3)提升间施工,将原梯子间自上往下掘进到下一段生产水平,作为提升间,所掘矿石由绞车通过提升系统提升到生产中段,通过调车场,运至原竖井提升的罐笼,通过罐笼提升至地表;
(4)在提升间及辅助设备安设好之后,自上往下按井筒设计断面进行延深施工,施工至设计深度时,进行马头门施工和井筒安装工作,之后拆除人工防护盘,竖井延深完成。
CN 201210553628 2012-12-19 2012-12-19 竖井延深一次成井方法 Pending CN103016010A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210553628 CN103016010A (zh) 2012-12-19 2012-12-19 竖井延深一次成井方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210553628 CN103016010A (zh) 2012-12-19 2012-12-19 竖井延深一次成井方法

Publications (1)

Publication Number Publication Date
CN103016010A true CN103016010A (zh) 2013-04-03

Family

ID=47965053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210553628 Pending CN103016010A (zh) 2012-12-19 2012-12-19 竖井延深一次成井方法

Country Status (1)

Country Link
CN (1) CN103016010A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470270A (zh) * 2013-09-10 2013-12-25 安徽理工大学 深井马头门支护结构及其施工方法
CN104964625A (zh) * 2015-05-27 2015-10-07 中钢集团马鞍山矿山研究院有限公司 一种竖井延伸时对已有井筒无损害的反掘贯通爆破方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470270A (zh) * 2013-09-10 2013-12-25 安徽理工大学 深井马头门支护结构及其施工方法
CN103470270B (zh) * 2013-09-10 2015-04-08 安徽理工大学 深井马头门支护结构及其施工方法
CN104964625A (zh) * 2015-05-27 2015-10-07 中钢集团马鞍山矿山研究院有限公司 一种竖井延伸时对已有井筒无损害的反掘贯通爆破方法

Similar Documents

Publication Publication Date Title
CN104373125B (zh) 两步骤上向高分层袋装充填采矿法
CN102562065B (zh) 一种分段空场嗣后充填采矿方法
CN105649631B (zh) 一种缓倾斜薄矿体的机械化高效采矿方法
CN103603665B (zh) 矿山采动范围内上盘侧矿体回采方法
CN101881169A (zh) 一种分段留矿崩落阶段空场嗣后充填采矿法
CN101737052A (zh) 一种分段充填采矿方法
CN103790589B (zh) 露天转地下矿山的一种过渡衔接开采方法
CN102926804B (zh) 分布式地下水库群及地下水库群内矿井水的转移方法
CN103696774B (zh) 井上井下平行施工暗井架开拓方法
CN105697021A (zh) 盾构穿越浅覆土河床的预制隧道及施工方法
CN204000830U (zh) 分节接管式砂井机
CN106761758A (zh) 人工混凝土挡墙重构间柱废石充填采矿方法
CN105178330A (zh) 地下结构后浇带换撑方法
CN109751050B (zh) 一种下向凹凸无筋镶嵌连续分层充填采矿法
CN103061767B (zh) 下向水平分层干式充填采矿法
CN103557003A (zh) 一种铁矿体保安矿柱的开采方法
CN103016010A (zh) 竖井延深一次成井方法
CN103982185B (zh) 垂直孔与水平孔协同回采的机械化分段充填采矿法
CN103244121B (zh) 一种有轨与无轨耦合的底部出矿系统
CN105545330A (zh) 一种冶金地下矿山溜破系统施工中的防治水工艺
CN106337687A (zh) 矿山斜溜井便捷式分段支护方法
CN203978442U (zh) 一种公铁合建水下隧道
CN203374282U (zh) 矿山井下落地多绳提升系统天轮硐室布置结构
CN104631465A (zh) 卵石层红砂岩地质条件下的深基坑开挖施工方法
CN104088664B (zh) 一种向上填充采矿的矿井废水处理方法及系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130403