CN102968692A - Method and device for adjusting electric power workload - Google Patents
Method and device for adjusting electric power workload Download PDFInfo
- Publication number
- CN102968692A CN102968692A CN2012104742529A CN201210474252A CN102968692A CN 102968692 A CN102968692 A CN 102968692A CN 2012104742529 A CN2012104742529 A CN 2012104742529A CN 201210474252 A CN201210474252 A CN 201210474252A CN 102968692 A CN102968692 A CN 102968692A
- Authority
- CN
- China
- Prior art keywords
- workload
- time
- servant
- power failure
- afternoon
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention discloses a method for adjusting the electric power workload. The method comprises the following steps of: acquiring each power cut plan in a workload adjustment time period; acquiring a first time dividing point, a second time dividing point and a ticket writing advanced hourage in the workload adjustment time period; respectively calculating the time for outage ticket writing, outage operation, recommision ticket writing and recommision operation corresponding to each power cut plan; reckoning the workloads of the outage ticket writing, the outage operation, the recommision ticket writing and the recommision operation corresponding to each power cut plan in morning values or afternoon values of a corresponding working day to obtain the workload corresponding to the morning values and the afternoon values of each working day in the workload adjustment time period; and adjusting and executing each power cut plan in the workload adjustment time period. Moreover, the invention also discloses a device for adjusting the electric power workload. With the adoption of the method and the device, the problem of overlarge working strength in a certain time period caused by too concentrated workload is solved.
Description
Technical field
The present invention relates to the power scheduling technical field, relate in particular to a kind of work about electric power amount adjustment method and a kind of work about electric power amount adjusting apparatus.
Background technology
In the operation of power networks process, to run into inevitably the situation of power failure.Have great significance for the pool collaboration capabilities that improves operation of power networks efficient, saving cost and enhancing electric power dispatching system and formulate targetedly the power failure plan.But in engineering practice, very reasonable even power failure is planned at the beginning of formulating, also often can be because various factors have to be forced to adjustment.Wherein, the most normal situation that runs into be exactly in same working day in addition in certain working day the workload in the morning or afternoon too saturated, and cause lineman Cheng personnel and engineering equipment to consume excessive.This situation can be brought very large potential safety hazard, also is unfavorable for saving cost.Therefore, calculate accurately and effectively power failure and plan the workload brought to business such as scheduling, transmission of electricity, power transformation and pilot scales, and the power failure plan adjusted effectively, avoid causing because workload too concentrates in certain time period working strength excessive, become a problem in the urgent need to address.
Summary of the invention
Based on this, the invention provides a kind of work about electric power amount adjustment method and a kind of work about electric power amount adjusting apparatus.
A kind of work about electric power amount adjustment method may further comprise the steps:
Obtain workload and adjust each interior bar power failure plan of time period;
Obtaining workload adjusts very first time separation, the second time separation in the time period and writes the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
According to start time of described each bar power failure plan, concluding time with describedly write hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation;
According to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
According to the value and be worth corresponding workload afternoon in each that draws, adjust and the execution work amount is adjusted the plan that has a power failure of each bar in the time period in workaday morning.
Compare with general technology, work about electric power amount adjustment method of the present invention is hourage according to start time, the concluding time of each bar power failure plan with before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.In conjunction with very first time separation and the second time separation, draw workload and adjust in the time period value and be worth corresponding workload afternoon in each in workaday morning, adjust at last and each bar power failure that the execution work amount was adjusted in the time period is planned.Avoided workload too to concentrate and cause the excessive problem of working strength in certain time period.
A kind of work about electric power amount adjusting apparatus comprises power failure plan acquisition module, time-obtaining module, Time Calculation module, workload computing module and workload adjusting module;
Described power failure plan acquisition module is used for obtaining workload and adjusts each interior bar power failure plan of time period;
Described time-obtaining module, being used for obtaining workload adjusts very first time separation, the second time separation in the time period and writes the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
Described Time Calculation module is used for the start time, concluding time according to described each bar power failure plan and describedly writes hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates time;
Described workload computing module, be used for according to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
Described workload adjusting module is used for according to the value and be worth corresponding workload afternoon in each that draws in workaday morning, adjusts and each bar power failure that the execution work amount was adjusted in the time period is planned.
Compare with general technology, work about electric power amount adjusting apparatus of the present invention is hourage according to start time, the concluding time of each bar power failure plan with before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.In conjunction with very first time separation and the second time separation, draw workload and adjust in the time period value and be worth corresponding workload afternoon in each in workaday morning, adjust at last and each bar power failure that the execution work amount was adjusted in the time period is planned.Avoided workload too to concentrate and cause the excessive problem of working strength in certain time period.
Description of drawings
Fig. 1 is the schematic flow sheet of work about electric power amount adjustment method of the present invention;
Fig. 2 is the structural representation of work about electric power amount adjusting apparatus of the present invention.
Embodiment
For further setting forth the technological means that the present invention takes and the effect that obtains, below in conjunction with accompanying drawing and preferred embodiment, to technical scheme of the present invention, know and complete description.
See also Fig. 1, be the schematic flow sheet of work about electric power amount adjustment method of the present invention.Work about electric power amount adjustment method of the present invention may further comprise the steps:
S101 obtains workload and adjusts each interior bar power failure plan of time period;
The balanced data of two aspects that need of workload support as basic data: business datum, mainly obtain from master, distribution production system, and contain power failure plan, defect record, patrol plan etc.; Power network topology and equipment account information, from major network EMS system acquisition master network equipment topology information, major network asset system obtain master network equipment account information, the distribution generalized information system is obtained distribution net equipment topology and account information.
S102 obtains workload and adjusts very first time separation, the second time separation in the time period and write the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
As one of them embodiment, described very first time separation is 8 a.m., and described the second time separation is points in afternoons 16, and hourage is 2 hours before the described tickets-raise up of writing.
Very first time separation, the second time separation and write that hourage also can be other numerical value before the tickets-raise up.
S103 is according to start time of described each bar power failure plan, concluding time and describedly write hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation;
Hourage according to start time, the concluding time of each bar power failure plan and before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.For example, take very first time separation as 8 a.m., the second time separation is points in afternoons 16, write before the tickets-raise up hourage and be 2 hours and be example, the start time of certain bar power failure plan is assumed to be point 2 days 9 January in 2011, concluding time is point 3 days 8 January in 2011, the start time reach was 7 points in 2 hours, stop so to use as a servant and write the ticket operational ton and count the afternoon on January 1st, 2011 in the value, start time is 9 points, stop using as a servant the execution work amount and count the morning on January 2nd, 2011 in the value, the concluding time reach was 6 points in 2 hours, so multiple labour is write afternoon that the ticket workload counts on January 2nd, 2011 in the value, and the concluding time is 8 points, uses as a servant so again the execution work amount and counts the morning on January 3rd, 2011 in the value.
S104 is according to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
As one of them embodiment, determine to stop using as a servant according to have a power failure calculated power failure equipments type and electric pressure write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload;
With determine stop using as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload counts relevant work day morning value or afternoon value.
S105 is according to the value and be worth corresponding workload afternoon in each that draws in workaday morning, adjusts and each bar power failure that the execution work amount was adjusted in the time period is planned.
Each that draws value in the workaday morning and being worth afternoon after the corresponding workload can be adjusted workload according to actual conditions and adjust each bar power failure plan in the time period, and carry out the operation that has a power failure according to the power failure plan after adjusting.
As one of them preferred embodiment, obtain workload and adjust the start time of time period and the power failure plan set A in the concluding time scope;
According to workload start time and the concluding time of adjustment time period, form workload set B corresponding to every workday;
Obtain despatching work amount time period configuration D, hourage c before wherein D comprises very first time separation a, the second time separation b and writes the tickets-raise up, with a=8:00, b=16:00, c=2 are example:
Every the plan An that has a power failure in the traversal set A, wherein the start time of An is assumed to be point 2 days 9 January in 2011, concluding time is point 3 days 8 January in 2011, the start time reach was 7 points in c hour, An's stops using as a servant and writes the ticket operational ton and count the afternoon on January 1st, 2011 in the value so, start time is 9 points, so An stop use as a servant the execution work amount and count the morning on January 2nd, 2011 in the value, the concluding time reach was 6 points in c hour, the multiple labour of An is write the ticket workload and is counted the afternoon on January 2nd, 2011 in the value so, concluding time is 8 points, and the multiple labour execution work amount of An is counted the morning on January 3rd, 2011 in the value so.
Draw the every workday in the set B the morning value and afternoon value workload, workload numerical value obtains from the configuration of despatching work amount according to the difference of the power failure equipments type of power failure plan and electric pressure and adds up.
Compare with general technology, work about electric power amount adjustment method of the present invention is hourage according to start time, the concluding time of each bar power failure plan with before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.In conjunction with very first time separation and the second time separation, draw workload and adjust in the time period value and be worth corresponding workload afternoon in each in workaday morning, adjust at last and each bar power failure that the execution work amount was adjusted in the time period is planned.Avoided workload too to concentrate and cause the excessive problem of working strength in certain time period.
See also Fig. 2, be the structural representation of work about electric power amount adjusting apparatus of the present invention.Work about electric power amount adjusting apparatus of the present invention comprises power failure plan acquisition module 201, time-obtaining module 202, Time Calculation module 203, workload computing module 204 and workload adjusting module 205;
Described power failure plan acquisition module 201 is used for obtaining workload and adjusts each interior bar power failure plan of time period;
The balanced data of two aspects that need of workload support as basic data: business datum, mainly obtain from master, distribution production system, and contain power failure plan, defect record, patrol plan etc.; Power network topology and equipment account information, from major network EMS system acquisition master network equipment topology information, major network asset system obtain master network equipment account information, the distribution generalized information system is obtained distribution net equipment topology and account information.
Described time-obtaining module 202, being used for obtaining workload adjusts very first time separation, the second time separation in the time period and writes the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
As one of them embodiment, the very first time separation that the workload that described time-obtaining module is obtained was adjusted in the time period is 8 a.m., and the second time separation is points in afternoons 16, and hourage is 2 hours before the described tickets-raise up of writing.
Described Time Calculation module 203 is used for the start time, concluding time according to described each bar power failure plan and describedly writes hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates time;
Hourage according to start time, the concluding time of each bar power failure plan and before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.
Described workload computing module 204, be used for according to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
As one of them embodiment, described workload computing module comprises that workload acquisition module and workload count module;
Described workload acquisition module, be used for determining to stop using as a servant according to have a power failure calculated power failure equipments type and electric pressure write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload;
Described workload counts module, the workload that be used for determining stop using as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates count relevant work day the morning value or afternoon value.
Described workload adjusting module 205 is used for according to the value and be worth corresponding workload afternoon in each that draws in workaday morning, adjusts and each bar power failure that the execution work amount was adjusted in the time period is planned.
Each that draws value in the workaday morning and being worth afternoon after the corresponding workload can be adjusted workload according to actual conditions and adjust each bar power failure plan in the time period, and carry out the operation that has a power failure according to the power failure plan after adjusting.
Compare with general technology, work about electric power amount adjusting apparatus of the present invention is hourage according to start time, the concluding time of each bar power failure plan with before writing the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation.In conjunction with very first time separation and the second time separation, draw workload and adjust in the time period value and be worth corresponding workload afternoon in each in workaday morning, adjust at last and each bar power failure that the execution work amount was adjusted in the time period is planned.Avoided workload too to concentrate and cause the excessive problem of working strength in certain time period.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to claim of the present invention.Should be pointed out that for the person of ordinary skill of the art without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.
Claims (6)
1. a work about electric power amount adjustment method is characterized in that, may further comprise the steps:
Obtain workload and adjust each interior bar power failure plan of time period;
Obtaining workload adjusts very first time separation, the second time separation in the time period and writes the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
According to start time of described each bar power failure plan, concluding time with describedly write hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, time that multiple labour is write ticket and multiple labour operation;
According to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
According to the value and be worth corresponding workload afternoon in each that draws, adjust and the execution work amount is adjusted the plan that has a power failure of each bar in the time period in workaday morning.
2. work about electric power amount adjustment method according to claim 1, it is characterized in that, described corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and the workload of multiple labour operation count relevant work day the morning value or afternoon value step, may further comprise the steps:
Determine to stop using as a servant according to have a power failure calculated power failure equipments type and electric pressure write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload;
With determine stop using as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload counts relevant work day morning value or afternoon value.
3. work about electric power amount adjustment method according to claim 1, it is characterized in that, described obtain workload and adjust very first time separation, the second time separation in the time period and write the tickets-raise up before in the step of hourage, described very first time separation is 8 a.m., described the second time separation is points in afternoons 16, and hourage is 2 hours before the described tickets-raise up of writing.
4. a work about electric power amount adjusting apparatus is characterized in that, comprises power failure plan acquisition module, time-obtaining module, Time Calculation module, workload computing module and workload adjusting module;
Described power failure plan acquisition module is used for obtaining workload and adjusts each interior bar power failure plan of time period;
Described time-obtaining module, being used for obtaining workload adjusts very first time separation, the second time separation in the time period and writes the front hourage of tickets-raise up, wherein, described very first time separation was worth the morning on the same day and be worth the afternoon day before yesterday for distinguishing, and described the second time separation is used for differentiation value in afternoon on the same day and be worth morning next day;
Described Time Calculation module is used for the start time, concluding time according to described each bar power failure plan and describedly writes hourage before the tickets-raise up, calculate respectively corresponding the stopping of each bar power failure plan use as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates time;
Described workload computing module, be used for according to above-mentioned result of calculation, described very first time separation and described the second time separation, corresponding the stopping of each bar power failure plan used as a servant write ticket, stop using as a servant operation, multiple labour write the workload of ticket and multiple labour operation count relevant work day the morning value or afternoon value, draw value and be worth corresponding workload afternoon in workload adjustment time period in interior each in workaday morning;
Described workload adjusting module is used for according to the value and be worth corresponding workload afternoon in each that draws in workaday morning, adjusts and each bar power failure that the execution work amount was adjusted in the time period is planned.
5. work about electric power amount adjusting apparatus according to claim 1 is characterized in that, described workload computing module comprises that workload acquisition module and workload count module;
Described workload acquisition module, be used for determining to stop using as a servant according to have a power failure calculated power failure equipments type and electric pressure write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates workload;
Described workload counts module, the workload that be used for determining stop using as a servant write ticket, stop using as a servant operation, multiple labour is write ticket and multiple labour operates count relevant work day the morning value or afternoon value.
6. work about electric power amount adjusting apparatus according to claim 1, it is characterized in that, the very first time separation that the workload that described time-obtaining module is obtained was adjusted in the time period is 8 a.m., and the second time separation is points in afternoons 16, and hourage is 2 hours before the described tickets-raise up of writing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012104742529A CN102968692A (en) | 2012-11-20 | 2012-11-20 | Method and device for adjusting electric power workload |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012104742529A CN102968692A (en) | 2012-11-20 | 2012-11-20 | Method and device for adjusting electric power workload |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102968692A true CN102968692A (en) | 2013-03-13 |
Family
ID=47798822
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012104742529A Pending CN102968692A (en) | 2012-11-20 | 2012-11-20 | Method and device for adjusting electric power workload |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102968692A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104504519A (en) * | 2014-12-22 | 2015-04-08 | 国家电网公司 | Power network overhaul work intensity graphical display method based on GIS (geographic information system) technology |
CN104732355A (en) * | 2015-04-07 | 2015-06-24 | 哈尔滨理工大学 | Device drive integrated dispatching method for adjusting devices during idle time period |
CN107766975A (en) * | 2017-10-11 | 2018-03-06 | 广西电网有限责任公司 | A kind of traffic control task preferred allocation method for considering dispatcher's workload |
CN113903099A (en) * | 2021-08-30 | 2022-01-07 | 浙江文谷科技有限公司 | Device monitoring method and system based on scada |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003016374A (en) * | 2001-06-28 | 2003-01-17 | Toshiba Corp | Evaluating method and drawing-up method for power generating facility plan, and program |
-
2012
- 2012-11-20 CN CN2012104742529A patent/CN102968692A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003016374A (en) * | 2001-06-28 | 2003-01-17 | Toshiba Corp | Evaluating method and drawing-up method for power generating facility plan, and program |
Non-Patent Citations (1)
Title |
---|
郇嘉嘉等: "电网停电综合管理与分析决策系统的研究与开发", 《电力系统保护与控制》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104504519A (en) * | 2014-12-22 | 2015-04-08 | 国家电网公司 | Power network overhaul work intensity graphical display method based on GIS (geographic information system) technology |
CN104504519B (en) * | 2014-12-22 | 2017-12-01 | 国家电网公司 | A kind of grid maintenance working strength graphical representation method based on GIS technology |
CN104732355A (en) * | 2015-04-07 | 2015-06-24 | 哈尔滨理工大学 | Device drive integrated dispatching method for adjusting devices during idle time period |
CN104732355B (en) * | 2015-04-07 | 2018-12-21 | 哈尔滨理工大学 | The device drives integrated dispatch method of equipment free time section adjustment |
CN107766975A (en) * | 2017-10-11 | 2018-03-06 | 广西电网有限责任公司 | A kind of traffic control task preferred allocation method for considering dispatcher's workload |
CN107766975B (en) * | 2017-10-11 | 2021-04-13 | 广西电网有限责任公司 | Dispatching work task allocation method considering dispatcher workload |
CN113903099A (en) * | 2021-08-30 | 2022-01-07 | 浙江文谷科技有限公司 | Device monitoring method and system based on scada |
CN113903099B (en) * | 2021-08-30 | 2023-09-08 | 浙江文谷科技有限公司 | Equipment monitoring method and system based on scada |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103197623B (en) | A kind of streamline method for managing and monitoring and device | |
CN102968692A (en) | Method and device for adjusting electric power workload | |
CN103427417A (en) | Power distribution network fault processing method based on multi-source information fusion | |
CN108736465A (en) | A kind of future-state electric network model construction method and device | |
CN102938109B (en) | Grid power blackout method of combination and device | |
CN102930403B (en) | The whole network diagram data system based on WPF technology | |
CN107622342B (en) | MVC (model view controller) architecture-based distribution network area data analysis system | |
CN106295984A (en) | A kind of demand response system and method towards industrial undertaking | |
CN103544652A (en) | Power grid industry classification load automatic statistical method and system | |
CN103208050A (en) | Decision platform for implementing comprehensive power-cut maintenance plan | |
CN105048456A (en) | Loss-reducing and energy-saving management method and system applied to intelligent metering platform | |
CN108183814B (en) | Troubleshooting method and device for communication channel of electricity utilization information acquisition system | |
CN109903185B (en) | Power communication unified resource management system based on cloud computing | |
CN202727583U (en) | Information acquisition system for rotary printing machine | |
CN104156888A (en) | Power system operation risk monitoring method based on comprehensive risk evaluation model | |
CN104253859A (en) | Centralized scheduling resource distributing load balancing device and method | |
CN103760856A (en) | Cold strip steel leveling unit process control method | |
CN110807539A (en) | Fault equipment maintenance path selection method and device | |
CN115951172A (en) | Method, device and equipment for positioning metering point of abnormal unbalanced electric quantity of bus | |
CN104463505A (en) | Operation state on-line monitoring method based on detail data | |
CN201417948Y (en) | Distribution network status and operating mode optimizing system based on DSCADA system | |
CN211928020U (en) | Electric energy acquisition data analysis early warning device | |
CN103606023A (en) | Graph platform-based management method for materials of newly input electric power system | |
CN114118717A (en) | Mine enterprise production state supervision method and system | |
CN102891536B (en) | Integrated electric energy management platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20130313 |