CN103606023A - Graph platform-based management method for materials of newly input electric power system - Google Patents

Graph platform-based management method for materials of newly input electric power system Download PDF

Info

Publication number
CN103606023A
CN103606023A CN201310334962.6A CN201310334962A CN103606023A CN 103606023 A CN103606023 A CN 103606023A CN 201310334962 A CN201310334962 A CN 201310334962A CN 103606023 A CN103606023 A CN 103606023A
Authority
CN
China
Prior art keywords
equipment
data
platform
wiring diagram
newly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310334962.6A
Other languages
Chinese (zh)
Inventor
王瑞欣
程伦
高圣源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING YONGSHANG POWERSOFT Ltd
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Original Assignee
BEIJING YONGSHANG POWERSOFT Ltd
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING YONGSHANG POWERSOFT Ltd, State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd filed Critical BEIJING YONGSHANG POWERSOFT Ltd
Priority to CN201310334962.6A priority Critical patent/CN103606023A/en
Publication of CN103606023A publication Critical patent/CN103606023A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention relates to a graph platform-based management method for materials of a newly input electric power system. According to an IEC61970 protocol, the management method uses a graph multi-section principle to build a graphic topological platform, data carriers cime file and g file of a power grid main wiring diagram derived from an EMS are analyzed to obtain graphic data, model data and real-time measurement data of the power grid, and a real-time operation mode of the power grid is imported into the graph platform. By virtue of Active X widget technology, the graph platform is correlated with a new input flow of equipment, thereby providing materials of the power grid wiring diagram, topological relation and equipment parameters for new input of the equipment, greatly reducing the workload of a material preparation stage in the new input flow of the equipment, and improving the work efficiency and the accuracy of wiring diagram drawing. In an electric power system, the graph platform-based management method for materials of the newly input electric power system applies graph platform technology to the new input business process of the equipment, provides a new solution for graphic model library integrated management and index of data of the parameters, the wiring diagram, and the topological relation of the newly input equipment, and can be applied to the technical field of management of electric power system dispatching operation modes.

Description

The management method of a kind of power system device new investment material based on graphic platform
Technical field
Present technique relates to electric power system dispatching method of operation administrative skill, is specifically related to the management method of a kind of power system device new investment material based on graphic platform.
Background technology
Equipment is newly thrown flow process as one of seven large core processes of dispatching system; the complicacy with height; relate to all specialized departments such as scheduling in scheduling institution, plan, mode, protection, communication, robotization; also relate to network regulation, the cooperatively interacting of different stage scheduling institution such as adjust; and there is close interface with a plurality of specialized service flow processs, comprise that power failure plan, communication automation system are exchanged, database and EMS frame updating, protection fixed value adjusting, scheduling operation etc.Equipment is newly thrown the data that needs collection in flow process, and as device parameter, transforming plant primary wiring diagram etc., kind is complicated, and simple craft is compiled difficult, and easily makes mistakes.Although use at present conventional AutoCAD software and Visio can draw wiring diagram, but can not be in figure defined parameters and carry out simulated operation, can not carry out safety check to its mode of connection, so need to build a special grid graph topology platform.On this platform, can draw electric network wiring scheme, management equipment parameter, by graph topology relation, butted line mode is carried out safety check, and then forms rational wiring diagram and device parameter, increases work efficiency, and reduces economic loss, avoids personnel to injure.
Equipment is newly thrown flow process at present not combine with electrical network real time operation mode, can not judge accurately and fast rationality and the accuracy of new throwing equipment electrical network main wiring diagram and device parameter thereof.
Summary of the invention
Of the present invention goal of the inventionjust be to provide the management method of a kind of power system device new investment material based on graphic platform, for above-mentioned prior art problem, the inventive method utilizes the principle of multibreak of figure to build graph topology platform, and with energy management system (Energy Management System, EMS) docking, regularly the main wiring diagram in EMS is imported in graph topology platform, to guarantee graphic platform dynamically state and the real time data of display device.The ActiveX control technology of employing based on the Component Object Model is embedded into graphical application in new equipment flow process, for the new data of throwing of equipment is prepared to provide convenience, support efficiently.
Of the present invention technical schemebe:
The management method of power system device new investment material based on graphic platform, the steps include:
Step 1, according to IEC61970 stipulations, adopt multibreak principle of figure to build power network topology graphic platform:
(1), in database, build table.In table, record the section information of electrical network, mainly contained wiring diagram, figure layer, equipment component, topological relation, device parameter and state etc.
(2), a series of table in each section correspondence database, and by section number, these tables are connected.While showing section, according to section number, find the database table that this section is corresponding, import corresponding data.
(3), during map releasing, section and current section after safeguarding can be analyzed, data merging, to guarantee refreshing in time of current profile data.
Modification to figure on graphic platform, is all to carry out on a certain section, can avoid like this figure in revising to impact the wiring diagram in real time execution.Revise complete, the content of modification can be submitted to other people audit.Examine errorless after, revised context merges to real-time section, for other users.
Step 2, electrical network real time operation mode import.Described electrical network real time operation mode imports, and is that this graphic platform builds according to IEC61970 stipulations, can with energy management system slitless connection; The primary connection figure using in graphic platform derives in EMS, by regularly obtain grid graph data, model data and real-time measuring data, the dynamically state of display device and real time data thereof from EMS; Performing step is:
(1), in EMS, derive electrical network main wiring diagram:
The electrical network main wiring diagram of being derived by EMS is usingd cime and g file as data carrier, the topological connection relation, plant stand relation and the device measuring data that wherein in cime file, are recording electrical network, recording redirect relation between feature, Word message and the figure under equipment voltage color, different conditions in g file.
(2), electric network wiring scheme is imported in graph topology platform:
By the parsing to cime file and g file, form primary connection graph model, imported in graphic platform, by real-time importing grid graph data, model data and real-time measuring data, the dynamically real-time status of display device and data.
Step 3, graphic platform are newly thrown flow process with equipment and are docked.It is to adopt ActiveX control technology based on the Component Object Model that graphical application is embedded into equipment newly to throw in flow process that described graphic platform and equipment newly throw that flow process docks, when equipment is newly thrown requirements of process while calling figure, can activate figure application controls, open graphic platform; Performing step is as follows:
(1), graphical application control embedded equipment is newly thrown flow process:
The ActiveX control technology of employing based on the Component Object Model (Component Object Model, COM) is embedded into equipment by graphical application and newly throws in flow process.COM is a kind of scale-of-two and network standard, allows any two assemblies to communicate by letter mutually.ActiveX control technology is followed COM rules, the Tlibmp.exe instrument that graphical application is carried by programming tool is packaged into the metadata in procedure set, during operation by RCW (Runtime Callable Wrapper, RCW) at any time in state of activation to process solicited message.When equipment, newly throw while needing to call figure in flow process, can activate figure application controls, open graphic platform.
(2), in graphic platform, rendering apparatus is newly thrown main wiring diagram:
Before new equipment starts, can drag pel by graphic platform and draw electrical network main wiring diagram, by analogue simulation, operate, graphic platform carries out Security Checking according to topological relation to its mode of connection automatically, and assisted user is modified to figure.The figure of drawing and the device parameter of definition are kept in database in real time automatically.Before map releasing, the new new throwing equipment wiring diagram of drawing, can not have any impact to the method for operation of the wiring diagram moving; After map releasing, can merge with the real-time section of system, formally come into operation.
Compared with prior art, of the present invention beneficial effectbe embodied in:
The technology of the present invention method has solved power system device new investment material and has prepared difficult problem, greatly surmounted the method that original craft is collected, arrayed data, can by graph topology platform, draw electrical network main wiring diagram define equipment parameter fast, for equipment is new, throw the preparation of giving information., dock with the real-time of power system operating mode meanwhile, can check easily equipment state and real time data in operation of power networks, can help scheduling mode personnel to grasp in time electrical network real time operation mode.The present invention has realized equipment and newly throws flow process and can combine with electrical network real time operation mode in a word, can judge accurately and fast rationality and the accuracy of new throwing equipment electrical network main wiring diagram and device parameter thereof.
Accompanying drawing explanation
Accompanying drawing 1 is newly thrown flow process docking concept figure for graphic platform of the present invention and equipment.
Embodiment
Below in conjunction with instantiation, the present invention is described in more detail.
For making object, technical scheme and the advantage of present technique clearer, be further described below.
first,be according to IEC61970 stipulations, adopt multibreak principle of figure to build power network topology graphic platform.Specific implementation step is as follows:
1, in database, build table.In table, record the section information of electrical network, mainly contained wiring diagram, figure layer, equipment component, topological relation, device parameter and state etc.
2, a series of table in each section correspondence database, and by section number, these tables are connected.While showing section, according to section number, find the database table that this section is corresponding, import corresponding data.
3,, during map releasing, section and current section after safeguarding can be analyzed, data merging, to guarantee refreshing in time of current profile data.
Modification to figure on graphic platform, is all to carry out on a certain section, can avoid like this figure in revising to impact the wiring diagram in real time execution.Revise complete, the content of modification can be submitted to other people audit.Examine errorless after, revised context merges to real-time section, for other users.
This graphic platform has reached component-level to the control of figure, can comparative analysis go out all operations such as the element that certain section is carried out adds, deletion, modification attribute, shift position, thereby when can support many people to same figure, revise, issue respectively, improved the efficiency of the aspect of changing plan.
The figure of drawing in graphic platform is preserved in real time automatically, without worrying, because unscheduled event causes graph data, loses.
secondly, electrical network real time operation mode imports, and takes following steps to realize:
1, in EMS, derive electrical network main wiring diagram.
The electrical network main wiring diagram of being derived by EMS is usingd cime and g file as data carrier, the topological connection relation, plant stand relation and the device measuring data that wherein in cime file, are recording electrical network, recording redirect relation between feature, Word message and the figure under equipment voltage color, different conditions in g file.
2, electric network wiring scheme is imported in graph topology platform
By the parsing to cime file and g file, form primary connection graph model, imported in graphic platform, by real-time importing grid graph data, model data and real-time measuring data, the dynamically real-time status of display device and data.
finally, graphic platform is newly thrown flow process with equipment and is docked, and adopts following steps to realize:
1, graphical application control embedded equipment is newly thrown flow process
The ActiveX control technology of employing based on the Component Object Model (Component Object Model, COM) is embedded into equipment by graphical application and newly throws in flow process.COM is a kind of scale-of-two and network standard, allows any two assemblies to communicate by letter mutually.ActiveX control technology is followed COM rules, the Tlibmp.exe instrument that graphical application is carried by programming tool is packaged into the metadata in procedure set, during operation, pass through RCW (Runtime Callable Wrapper, RCW) at any time in state of activation to process solicited message, telescopiny is as shown in Figure 1.When equipment, newly throw while needing to call figure in flow process, can activate figure application controls, open graphic platform.
2, in graphic platform, rendering apparatus is newly thrown main wiring diagram
Before new equipment starts, can drag pel by graphic platform and draw electrical network main wiring diagram, by analogue simulation, operate, graphic platform carries out Security Checking according to topological relation to its mode of connection automatically, and assisted user is modified to figure.The figure of drawing and the device parameter of definition are kept in database in real time automatically.Before map releasing, the new new throwing equipment wiring diagram of drawing, can not have any impact to the method for operation of the wiring diagram moving; After map releasing, can merge with the real-time section of system, formally come into operation.
The inventive method practical applicationin Hebei Electric Power Corporation, economize in ground one scheduling mode management system, new equipment is put into operation to manage to combine with graphic platform, has realized the drafting of electrical network primary connection figure, makes power system operating mode more reasonable, avoid the modification repeatedly of primary connection figure, saved the drawing time; Direct recording device parameter on figure, and preserve into equipment library.When equipment is newly thrown, directly by graphic platform, import primary connection figure and the device parameter of drawing, accelerated the speed of putting into operation, greatly improved work efficiency.

Claims (1)

1. the management method of power system device new investment material based on graphic platform, is characterized in that, the step of described management method is:
Step 1, according to IEC61970 stipulations, adopt multibreak principle of figure to build power network topology graphic platform:
(1), in database, build table, in table, recorded the section information of electrical network;
(2), a series of table in each section correspondence database, and by section number, these tables are connected; While showing section, according to section number, find the database table that this section is corresponding, import corresponding data;
(3), during map releasing, section and current section after safeguarding can be analyzed, data merging, to guarantee refreshing in time of current profile data;
Step 2, electrical network real time operation mode import: described electrical network real time operation mode imports, and are that this graphic platform builds according to IEC61970 stipulations, can with energy management system slitless connection; The primary connection figure using in graphic platform derives in EMS, by regularly obtain grid graph data, model data and real-time measuring data, the dynamically state of display device and real time data thereof from EMS; Performing step is:
(1), in EMS, derive electrical network main wiring diagram:
The electrical network main wiring diagram of being derived by EMS is usingd cime and g file as data carrier, the topological connection relation, plant stand relation and the device measuring data that wherein in cime file, are recording electrical network, recording redirect relation between feature, Word message and the figure under equipment voltage color, different conditions in g file;
(2), electric network wiring scheme is imported in graph topology platform:
By the parsing to cime file and g file, form primary connection graph model, imported in graphic platform, by real-time importing grid graph data, model data and real-time measuring data, the dynamically real-time status of display device and data;
Step 3, graphic platform are newly thrown flow process with equipment and are docked: it is to adopt ActiveX control technology based on the Component Object Model that graphical application is embedded into equipment newly to throw in flow process that described graphic platform and equipment newly throw that flow process docks, when equipment is newly thrown requirements of process while calling figure, can activate figure application controls, open graphic platform; Performing step is as follows:
(1), graphical application control embedded equipment is newly thrown flow process:
The ActiveX control technology of employing based on the Component Object Model (Component Object Model, COM) is embedded into equipment by graphical application and newly throws in flow process; When equipment, newly throw while needing to call figure in flow process, can activate figure application controls, open graphic platform;
(2), in graphic platform, rendering apparatus is newly thrown main wiring diagram:
Before new equipment starts, can drag pel by graphic platform and draw electrical network main wiring diagram, by analogue simulation, operate, graphic platform carries out Security Checking according to topological relation to its mode of connection automatically, and assisted user is modified to figure; The figure of drawing and the device parameter of definition are kept in database in real time automatically; Before map releasing, the new new throwing equipment wiring diagram of drawing, can not have any impact to the method for operation of the wiring diagram moving; After map releasing, can merge with the real-time section of system, formally come into operation.
CN201310334962.6A 2013-12-19 2013-12-19 Graph platform-based management method for materials of newly input electric power system Pending CN103606023A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310334962.6A CN103606023A (en) 2013-12-19 2013-12-19 Graph platform-based management method for materials of newly input electric power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310334962.6A CN103606023A (en) 2013-12-19 2013-12-19 Graph platform-based management method for materials of newly input electric power system

Publications (1)

Publication Number Publication Date
CN103606023A true CN103606023A (en) 2014-02-26

Family

ID=50124243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310334962.6A Pending CN103606023A (en) 2013-12-19 2013-12-19 Graph platform-based management method for materials of newly input electric power system

Country Status (1)

Country Link
CN (1) CN103606023A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750934A (en) * 2015-04-06 2015-07-01 国网河南禹州市供电公司 Method and system for shortening power grid operation mode changing scheduling operation time
CN105701271A (en) * 2015-12-29 2016-06-22 中国电力科学研究院 Creating and deleting method for device in electric power system graph/model hybrid simulation modeling
CN105843737A (en) * 2016-03-21 2016-08-10 南京国电南自美卓控制系统有限公司 ActiveX control technology based method for defining and debugging generator-transformer unit protection apparatus

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750934A (en) * 2015-04-06 2015-07-01 国网河南禹州市供电公司 Method and system for shortening power grid operation mode changing scheduling operation time
CN105701271A (en) * 2015-12-29 2016-06-22 中国电力科学研究院 Creating and deleting method for device in electric power system graph/model hybrid simulation modeling
CN105701271B (en) * 2015-12-29 2021-04-06 中国电力科学研究院 Method for creating and deleting equipment in graph-model hybrid simulation modeling of power system
CN105843737A (en) * 2016-03-21 2016-08-10 南京国电南自美卓控制系统有限公司 ActiveX control technology based method for defining and debugging generator-transformer unit protection apparatus

Similar Documents

Publication Publication Date Title
CN104809932B (en) A kind of nuclear power plant's digital safety level Control system simulation device
CN108847994A (en) Alarm localization method, device, equipment and storage medium based on data analysis
CN103761624A (en) Implementing method of integrated power grid dispatching operation intelligent mistaken-early-warning preventing system
CN106960103A (en) The automatic generation method and device of a kind of grid graph
CN108345739B (en) Method for identifying CIME and SVG model file information to realize protection fixed value on-line check function and obtain model
CN103617760A (en) Power distribution network DTS (Dispatcher Training Simulation) simulation system and simulation method thereof
CN109145362A (en) A kind of power network modeling method and system
CN105701271B (en) Method for creating and deleting equipment in graph-model hybrid simulation modeling of power system
CN108520163A (en) Three-dimensional net rack method for automatic modeling based on CIM model and SVG figures
CN109146253A (en) A kind of intelligent automatic interactive operating system for making out an invoice and protecting locking
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN106356850B (en) The generation method of safety and stability control device failure Off-line control Policy model
CN105807749A (en) Test platform and test method for power dispatching automatic master station system
CN103678815A (en) Mechanical product collaborative simulation platform system and simulation method thereof
CN108320104B (en) Method for realizing protection fixed value on-line verification function obtaining model based on RelayCAC relay protection setting software
CN102222982A (en) Method and device for realizing programmed operation of transformer station based on SVG (Scalable Vector Graphics) technology
CN102983594A (en) Control method of grid closed loop operation impact current
CN108134690A (en) Network service deployment flow control method, apparatus and system
CN102968096A (en) Safe error proof verifying method for master station type comprehensive intelligent error proof system
CN105808880A (en) Relay protection setting method and system based on graphical power distribution network
CN103545917A (en) Scheduling-automation sub-station simulation system
CN202221628U (en) Simulation system for power grid of hybrid transformer substation
CN103606023A (en) Graph platform-based management method for materials of newly input electric power system
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN105373008A (en) Full physics model simulation method for electric power system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140226