CN102953392A - Pile foundation structure of photovoltaic power station and construction process of pile foundation - Google Patents

Pile foundation structure of photovoltaic power station and construction process of pile foundation Download PDF

Info

Publication number
CN102953392A
CN102953392A CN2012104165254A CN201210416525A CN102953392A CN 102953392 A CN102953392 A CN 102953392A CN 2012104165254 A CN2012104165254 A CN 2012104165254A CN 201210416525 A CN201210416525 A CN 201210416525A CN 102953392 A CN102953392 A CN 102953392A
Authority
CN
China
Prior art keywords
hole
pile
pile foundation
photovoltaic plant
stake hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104165254A
Other languages
Chinese (zh)
Other versions
CN102953392B (en
Inventor
余荣彪
赵小顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU HUAYUAN NEW ENERGY SCIENCE & TECHNOLOGY Co Ltd
Original Assignee
JIANGSU HUAYUAN NEW ENERGY SCIENCE & TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HUAYUAN NEW ENERGY SCIENCE & TECHNOLOGY Co Ltd filed Critical JIANGSU HUAYUAN NEW ENERGY SCIENCE & TECHNOLOGY Co Ltd
Priority to CN201210416525.4A priority Critical patent/CN102953392B/en
Publication of CN102953392A publication Critical patent/CN102953392A/en
Application granted granted Critical
Publication of CN102953392B publication Critical patent/CN102953392B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention provides a pile foundation structure of a photovoltaic power station, which is suitable for construction of the photovoltaic power station in a desolate beach of Gobi with a complex geologic structure. The pile foundation structure of the photovoltaic power station is characterized by comprising a prefabricated steel pile and a pile hole vertical to the horizontal plane. The prefabricated steel pile is installed in the pile hole and inserted into a soil layer at the bottom of the pile hole and the top of the prefabricated steel pile extends out of the ground. A concrete layer is poured between the hole wall of the pile hole and the prefabricated steel pile. A compact pure soil layer is backfilled on the upper part of the concrete layer. The invention further provides a construction process of the pile foundation of the photovoltaic power station. The construction process is simple in process and low in cost, and the ecological environment is not easy to damage. The construction process of the pile foundation of the photovoltaic power station is characterized by comprising the steps of: first, drilling the pile hole by a large excavator; then, inserting the prefabricated steel pile into the soil layer at the bottom of the pile hole through the pile hole; then, pouring concrete into the pile hole and vibrating with a vibrator while pouring the concrete; and finally, backfilling the pure soil and compacting on the upper part of the concrete layer.

Description

A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique
Technical field
The present invention relates to the photovoltaic plant technical field of construction, be specially a kind of pile foundation structure and pile foundation construction technique of photovoltaic plant.
Background technology
The basis of general photovoltaic plant mostly is independently box foundation, its construction is excavation pit at first, then in foundation ditch, foundation forms is assembled into box-shaped, concreting in the box-shaped template again, stripping gets final product after the concrete curing expiration, its construction technology is simple, it is more single that but it is only applicable to geologic structure, the area that soil property is relatively soft, for the NORTHWEST CHINA hinterland, particularly the Gobi desert barren beach is regional, because such regional geology complex structure, soil property is hard, and the stratum contains a large amount of rubbles, so its difficulty of construction is large, efficient is low, cost is high; In addition, carry out large-scale excavation of foundation pit in such area, understand the heavy damage surface vegetation, thereby affect the ecological environment of this area's fragility.
Summary of the invention
For the problems referred to above, the invention provides a kind of pile foundation structure of photovoltaic plant, it is applicable to the construction of the photovoltaic plant in complicated barren beach area, Gobi desert of geologic structure, for this reason, the present invention also provides the construction technology of this kind photovoltaic plant pile foundation, its construction technology is simple, cost is low, survivable ecological environment.
A kind of pile foundation structure of photovoltaic plant, it is characterized in that: it comprises prefabricated piling bar and the stake hole vertical with Earth surface plane, described prefabricated piling bar is installed in the described stake hole and described prefabricated piling bar inserts in described the soil layer bottom the hole, elevate above the soil in the top, built layer of concrete between the hole wall in described stake hole and the described prefabricated piling bar, the top backfill of described layer of concrete has closely knit plain soil layer.
It is further characterized in that:
The buried depth H of described prefabricated piling bar ' be 1.3m~1.4m; Described pre-manufactured steel pile length L is greater than described stake hole depth H 20cm at least; Described prefabricated piling bar upper end is equipped with the support mounting flange; Described pile body surface has the resistance to plucking tongue and groove of annular.
A kind of construction technology of photovoltaic plant pile foundation, it is characterized in that: at first adopt large excavator to drill through a hole, then the soil layer that prefabricated piling bar is inserted bottom, described stake hole by described stake hole is concreting in the described stake hole again, and vibrate with vibrator in concreting limit, limit, at last real the getting final product of layer of concrete top backfill element soil pressure.
It is further characterized in that:
When described large excavator drills through hole, the water filling in the described stake hole while holing;
The digging arm end of described large excavator is equipped with drilling rod, and described drilling rod front end is equipped with drill bit, needs held stationary, not run-off the straight and displacement when described excavator is in place, and keeps drilling rod perpendicular to the ground;
The center deviation in described stake hole, wherein central pile be not more than ± 40mm, skirt piles be not more than ± 30mm stake hole depth allowable variation+100mm, vertical degree of the peg hole allowable variation≤0.01L, sediment thickness≤50mm at the bottom of the stake hole, hole; Described strength grade of concrete C20.
Photovoltaic plant pile foundation structure of the present invention, its prefabricated piling bar passes the stake hole vertical with the ground facial plane, the soil layer of bottom, stake hole is inserted in its bottom, the top concreting is also with plain earthen backfill compacting, photovoltaic power plant bracket directly with the support mounting flange connection at prefabricated piling bar top, it is simple in structure, and supporting is stable; The pile body of prefabricated piling bar has the resistance to plucking tongue and groove of annular, can more effectively guarantee stable support; Its construction does not need to carry out large-area excavation of foundation pit, only by large excavator configuration drilling rod and drill bit vertical drilling is carried out on ground, again prefabricated piling bar is inserted soil layer by this vertical drilling, prefabricated piling bar is fixed in the native closely knit backfill of element by concreting again and guarantees in the vertical drilling that it is reliable and stable, its construction is convenient, efficiency of construction is high, and can not cause large tracts of land to damage to surface vegetation, effectively guarantee environment; The water filling in the stake hole while holing when drilling through hole, can so that the silt particle in the stake hole to meet cement solid, particularly regional for the larger Gobi desert barren beach of gravel content, more be conducive to the shaping in a hole, guarantee the follow-up construction of pile foundation.
Description of drawings
Fig. 1 is photovoltaic plant pile foundation structure schematic diagram among the present invention.
The specific embodiment
See Fig. 1, it comprises stake hole 1 and the prefabricated piling bar 2 vertical with Earth surface plane photovoltaic plant pile foundation structure of the present invention, prefabricated piling bar 2 is installed in the hole 1 and prefabricated piling bar 2 inserts in the soil layer of bottom, hole, elevate above the soil in the top, built layer of concrete 3 between the hole wall in stake hole 2 and the prefabricated piling bar, layer of concrete 3 top backfills have closely knit plain soil layer 4.The buried depth H of prefabricated piling bar ' be 1.3m~1.4m; The length L of prefabricated piling bar 2 is greater than stake hole 1 depth H 20cm at least; Prefabricated piling bar 2 upper ends are equipped with support mounting flange 5, and prefabricated piling bar 2 pile body surfaces have the resistance to plucking tongue and groove 6 of annular.
Photovoltaic plant pile foundation construction technique of the present invention: at first adopt large excavator to drill through a hole, in large excavator drilling rod and drill bit are installed, need held stationary when excavator is in place, not run-off the straight and displacement, and keep drilling rod perpendicular to the ground, stake center, the hole deviation that wherein drills through should satisfy central pile and be not more than ± 40mm, skirt piles are not more than ± 30mm, stake hole depth H allowable variation+100mm, vertical degree of the peg hole allowable variation≤0.01L, sediment thickness≤50mm at the bottom of the stake hole, hole, in the water filling in the stake hole while holing of when boring, so that the silt particle mud in the hole is guaranteed pile hole forming admittedly, then with prefabricated piling bar through being inserted into the soil layer below the hole in the stake hole, building the C20 layer of concrete again between stake hole wall and prefabricated piling bar, vibrates with vibrator in concreting limit, limit, at last backfill element soil on layer of concrete.

Claims (9)

1. the pile foundation structure of a photovoltaic plant, it is characterized in that: it comprises prefabricated piling bar and the stake hole vertical with Earth surface plane, described prefabricated piling bar is installed in the described stake hole and described prefabricated piling bar inserts in described the soil layer bottom the hole, elevate above the soil in the top, built layer of concrete between the hole wall in described stake hole and the described prefabricated piling bar, the top backfill of described layer of concrete has closely knit plain soil layer.
2. the pile foundation structure of a kind of photovoltaic plant according to claim 1 is characterized in that: the buried depth H of described prefabricated piling bar ' be 1.3m~1.4m.
3. the pile foundation structure of a kind of photovoltaic plant according to claim 2 is characterized in that: described pre-manufactured steel pile length L is greater than described stake hole depth H 20cm at least.
4. the pile foundation structure of a kind of photovoltaic plant according to claim 3, it is characterized in that: described prefabricated piling bar upper end is equipped with the support mounting flange.
5. the pile foundation structure of a kind of photovoltaic plant according to claim 4 is characterized in that: described pile body surface has the resistance to plucking tongue and groove of annular.
6. the construction technology of a photovoltaic plant pile foundation, it is characterized in that: at first adopt large excavator to drill through a hole, then the soil layer that prefabricated piling bar is inserted bottom, described stake hole by described stake hole is concreting in the described stake hole again, and vibrate with vibrator in concreting limit, limit, at last real the getting final product of layer of concrete top backfill element soil pressure.
7. the construction technology of a kind of photovoltaic plant pile foundation according to claim 6 is characterized in that: when described large excavator drills through hole, and the water filling in the described stake hole while holing.
8. according to claim 6 or the construction technology of 7 described a kind of photovoltaic plant pile foundations, it is characterized in that: the digging arm end of described large excavator is equipped with drilling rod, described drilling rod front end is equipped with drill bit, need held stationary, not run-off the straight and displacement when described excavator is in place, and keep drilling rod perpendicular to the ground.
9. the construction technology of a kind of photovoltaic plant pile foundation according to claim 8, it is characterized in that: the center deviation in described stake hole, wherein central pile be not more than ± 40mm, skirt piles be not more than ± 30mm, stake hole depth allowable variation+100mm, vertical degree of the peg hole allowable variation≤0.01L, sediment thickness≤50mm at the bottom of the stake hole, hole; Described strength grade of concrete C20.
CN201210416525.4A 2012-10-27 2012-10-27 A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique Active CN102953392B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210416525.4A CN102953392B (en) 2012-10-27 2012-10-27 A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210416525.4A CN102953392B (en) 2012-10-27 2012-10-27 A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique

Publications (2)

Publication Number Publication Date
CN102953392A true CN102953392A (en) 2013-03-06
CN102953392B CN102953392B (en) 2015-12-02

Family

ID=47762734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210416525.4A Active CN102953392B (en) 2012-10-27 2012-10-27 A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique

Country Status (1)

Country Link
CN (1) CN102953392B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695461A (en) * 2015-02-10 2015-06-10 浙江中控太阳能技术有限公司 Upright post-type heliostat mounting base and mounting method thereof
CN110359450A (en) * 2019-07-29 2019-10-22 中铁二院工程集团有限责任公司 Assembled circle pilework and construction method
CN110409480A (en) * 2019-07-26 2019-11-05 北京北控光伏科技发展有限公司 A kind of construction method on the photovoltaic bracket basis in gravel place
CN111719579A (en) * 2020-06-02 2020-09-29 中国电建集团西北勘测设计研究院有限公司 Post-water-injection vibration-compaction construction method for desert photovoltaic support pile foundation
CN113106966A (en) * 2021-04-09 2021-07-13 上海友海建设工程有限公司 High-bearing composite stiffness pile and construction method thereof
CN115977132A (en) * 2023-01-05 2023-04-18 中国电建集团西北勘测设计研究院有限公司 Construction method for non-static pressure type photovoltaic support prefabricated pipe pile foundation

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55159019A (en) * 1979-05-30 1980-12-10 Ohbayashigumi Ltd Method for stabilizing and solidifying sludge having hardening property at pit dug in ground
CN2231275Y (en) * 1994-05-12 1996-07-17 王光明 Reinforced pile with rotary spray composite pile
JP2004092025A (en) * 2002-08-29 2004-03-25 Daia Soil Kk Foundation pile and construction method thereof
CN1609346A (en) * 2003-10-20 2005-04-27 胡柏英 Superposed pile structure and construction method
CN201217801Y (en) * 2007-11-22 2009-04-08 王家毅 Prestressed concrete side-assist pressing enhancement type precast pile
JP4445832B2 (en) * 2004-10-29 2010-04-07 株式会社トーヨーアサノ Friction-enhanced concrete pile
KR20100110224A (en) * 2009-04-02 2010-10-12 주식회사 포스코 Precast pile
CN202954373U (en) * 2012-10-27 2013-05-29 江苏华源新能源科技有限公司 Pile foundation structure of photovoltaic power station

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55159019A (en) * 1979-05-30 1980-12-10 Ohbayashigumi Ltd Method for stabilizing and solidifying sludge having hardening property at pit dug in ground
CN2231275Y (en) * 1994-05-12 1996-07-17 王光明 Reinforced pile with rotary spray composite pile
JP2004092025A (en) * 2002-08-29 2004-03-25 Daia Soil Kk Foundation pile and construction method thereof
CN1609346A (en) * 2003-10-20 2005-04-27 胡柏英 Superposed pile structure and construction method
JP4445832B2 (en) * 2004-10-29 2010-04-07 株式会社トーヨーアサノ Friction-enhanced concrete pile
CN201217801Y (en) * 2007-11-22 2009-04-08 王家毅 Prestressed concrete side-assist pressing enhancement type precast pile
KR20100110224A (en) * 2009-04-02 2010-10-12 주식회사 포스코 Precast pile
CN202954373U (en) * 2012-10-27 2013-05-29 江苏华源新能源科技有限公司 Pile foundation structure of photovoltaic power station

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695461A (en) * 2015-02-10 2015-06-10 浙江中控太阳能技术有限公司 Upright post-type heliostat mounting base and mounting method thereof
CN110409480A (en) * 2019-07-26 2019-11-05 北京北控光伏科技发展有限公司 A kind of construction method on the photovoltaic bracket basis in gravel place
CN110359450A (en) * 2019-07-29 2019-10-22 中铁二院工程集团有限责任公司 Assembled circle pilework and construction method
CN110359450B (en) * 2019-07-29 2024-03-08 中铁二院工程集团有限责任公司 Assembled round pile structure and construction method
CN111719579A (en) * 2020-06-02 2020-09-29 中国电建集团西北勘测设计研究院有限公司 Post-water-injection vibration-compaction construction method for desert photovoltaic support pile foundation
CN113106966A (en) * 2021-04-09 2021-07-13 上海友海建设工程有限公司 High-bearing composite stiffness pile and construction method thereof
CN115977132A (en) * 2023-01-05 2023-04-18 中国电建集团西北勘测设计研究院有限公司 Construction method for non-static pressure type photovoltaic support prefabricated pipe pile foundation

Also Published As

Publication number Publication date
CN102953392B (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN203308470U (en) Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN102953392B (en) A kind of pile foundation structure of photovoltaic plant and pile foundation construction technique
CN102966119B (en) Geogrid reinforced wall and construction method thereof
CN102888834B (en) A kind of construction method of major diameter broken stone pile
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN109488202A (en) A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN107299650B (en) A kind of remote open caisson casting method for correcting error
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN204491624U (en) The synchronous excavation supporting system of the asymmetric deep big foundation pit in soft clay area
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN107700507A (en) Dewatering construction engineering method in steel plate pile water stopping curtain auxiliary tank
CN103938641A (en) Foundation construction technology of large-scale photovoltaic power station in desert
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN201635745U (en) Ribbed-arch multi-arch tunnel
CN104074234B (en) The interior river intake structure of electric power plant circulating water system and construction method thereof
CN202954373U (en) Pile foundation structure of photovoltaic power station
CN205688454U (en) Power transmission tower resistance to plucking well foundation
CN106906829A (en) A kind of horizontal soil body reinforcement means of subway open-cut foundation ditch
CN215441846U (en) Foundation anti-settling structure
CN203007967U (en) Photovoltaic plant component bracket foundation for plateau Gobi sandy soil regions
CN110067205A (en) A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant