CN102936968B - Construction method of inner steel frame reinforced structure of pseudo-classic architecture - Google Patents

Construction method of inner steel frame reinforced structure of pseudo-classic architecture Download PDF

Info

Publication number
CN102936968B
CN102936968B CN201210468611.XA CN201210468611A CN102936968B CN 102936968 B CN102936968 B CN 102936968B CN 201210468611 A CN201210468611 A CN 201210468611A CN 102936968 B CN102936968 B CN 102936968B
Authority
CN
China
Prior art keywords
steel
column
roof
new
edged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210468611.XA
Other languages
Chinese (zh)
Other versions
CN102936968A (en
Inventor
董有
鞠树森
谢建明
甄进平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YADU CONSTRUCTION GROUP Co.,Ltd.
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201210468611.XA priority Critical patent/CN102936968B/en
Publication of CN102936968A publication Critical patent/CN102936968A/en
Application granted granted Critical
Publication of CN102936968B publication Critical patent/CN102936968B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention provides an inner steel frame reinforced structure of pseudo-classic architecture and a construction method thereof. The steel frame reinforced structure comprises novel edge steel columns, novel angle steel columns, novel edge steel beams, novel horizontal steel beams and roof steel inner ring beams, the novel edge steel columns are attached to the inner walls of original walls and arranged oppositely to the novel edge steel columns of wall bodies correspondingly, the novel angle steel columns are arranged at corners of the original walls and attached to the inner walls of the original walls, the roof steel inner ring beams are arranged on the top surfaces of the novel edge steel columns and the novel angle steel columns and butt against a roof to form a novel supporting steel frame of the roof, the novel edge steel beams are arranged between two adjacent novel edge steel columns or between the novel edge steel columns and the novel angle steel columns and attached to the original walls, and the novel edge steel beams are connecting with the original walls in drawing mode through bolts. A novel inner steel structure device replaces the wall bodies to bear all vertical load of the original architecture. The inner steel frame reinforced structure of the pseudo-classic architecture improves anti-seismic property of the pseudo-classic architecture, does not influence internal space and external sensory effect, and can be widely applied to anti-seismic and reinforcing reconstruction of the pseudo-classic architecture.

Description

The construction method of steelframe ruggedized construction in a kind of building in the style of the ancients
Technical field
The present invention relates to a kind of old building ruggedized construction and construction method thereof of structural engineering, particularly a kind of ruggedized construction of building in the style of the ancients and construction method thereof.
Background technology
Qin brick and Han tile, the building types of the unique distinct Chinese characteristics such as carved beams and painted rafter, make Chinese ancient architecture in international building history, occupy unique historical role and realistic meaning, therefore, the building in the style of the ancients (or local-style dwelling houses) showing national characters is had in China, in the majority greatly mainly with post and panel structure form of building in the style of the ancients, along with improving constantly of social production and living standard, in city, the seismic hardening of building in the style of the ancients (or local-style dwelling houses) has become the weak link of urban renewal engineering.Building in the style of the ancients (or local-style dwelling houses) also exists the potential safety hazards such as structural seismic is low, structure bad connection, globality difference, show according to related data, post and panel structure is when earthquake, due to the strenuous vibration of earthquake, below making, blockwork is askew splits or the distortion that is distorted, or recurring structure side horizontal displacement is excessive, when not bearing upper load, total will be collapsed.At present, the Shockproof reinforcing method conventional to post and panel structure mainly contains: ring beam and construction column reinforcing pull rod, steel concrete board wall, exterior wall pastes steel, the reinforcement measures such as outer wall pasting carbon fiber, above-mentioned reinforcement measure can reach good consolidation effect for common building, if these building in the style of the ancientss of monofilament reinforcement means traditionally carries out seismic hardening, the alien invasion of existing building will be destroyed, due to the emphasis of going sightseeing that building in the style of the ancients is all often a city, affect the overall visual effect of building in the style of the ancients, the economy and social image loss that cannot estimate will be caused to city.Therefore; for elevation of building, existing seismic strengthening technology requires that stricter historical protective building cannot be satisfied the demand; this just needs to find a kind of new reinforcement means, makes these building in the style of the ancientss can play the effect of seismic hardening, can accomplish again the effect of the alien invasion protecting original building.
Summary of the invention
In order to overcome the problems referred to above, the present invention proposes steelframe ruggedized construction and construction method thereof in a kind of building in the style of the ancients, solve the technical problem of existing building in the style of the ancients poor seismic behavior, also solve existing reinforcement means and form of structure, damage building in the style of the ancients outer the inside sensory effects when applying in building in the style of the ancients, weaken the problems such as its sight.
To achieve these goals, this invention takes following technical scheme:
Steelframe ruggedized construction in a kind of building in the style of the ancients, comprise new edged steel column, newly add the column of angles, new edged girder steel, newly add horizontal girder steel and roof steel inner ring beam, described new edged steel column is close to former inner wall and is arranged and the corresponding setting of the new edged steel column of body of wall relatively, describedly newly add the bight that the column of angles is arranged on former wall, and be adjacent to former inner wall, described roof steel inner ring beam is arranged on the end face of new edged steel column and the Xin Jia column of angles, and hold out against with roof and form the new supporting steel frame in roof, described new edged girder steel to be arranged between adjacent two new edged steel columns or new edged steel column and newly adding between the column of angles, and be close to former wall, simultaneously by bolt and former wall drawknot, describedly newly add horizontal girder steel and be arranged between the new edged steel column of the correspondence between relative body of wall.
Describedly newly add horizontal girder steel middle position and be equipped with Xin Jia center steel column, describedly newly add the side that horizontal girder steel is connected to Xin Jia center steel column, meanwhile, be provided with between the steel column of described Xin Jia center and newly add longitudinal girder steel.
Described new edged steel column, newly add the column of angles, new edged girder steel, newly add horizontal girder steel, roof steel inner ring beam, newly add longitudinal girder steel and Xin Jia center steel column is i iron, channel-section steel, H profile steel or above-mentioned any combination.
Together with described new edged girder steel is at least with the horizontal girder steel of Xin Jia.
Billet is lined with between the nut of described bolt and former wall.
The construction method of steelframe ruggedized construction in described building in the style of the ancients, is characterized in that: step is as follows:
Step one, according to design drawing, installs the position well in advance steel-column foundation of new edged steel column, Xin Jia center steel column and the Xin Jia column of angles at the first floor of original building;
Step 2, the position correspondence of installing new edged steel column, Xin Jia center steel column and the Xin Jia column of angles at original building every floor plate opens installing hole;
Step 3, roof steel inner ring beam is set bottom the roof of original building, confirm that the position of roof steel inner ring beam all can be contained and bear the whole load on roof, roof steel inner ring beam and roof are close to simultaneously, and in carry out roof steel system, collar tie beam pre-fixes simultaneously;
Step 4, according to design drawing, be close to the new edged steel column of the former inner wall installation first floor, Xin Jia center steel column and the Xin Jia column of angles, and be connected bottom all steel columns with steel-column foundation, all steel column tops are being passed in the installing hole that the every floor plate of original building is offered in advance;
Step 5, according to design drawing, new edged steel column, Xin Jia center steel column are successively installed, newly add the column of angles and new edged girder steel is set on demand between each layer steel column, newly adds the longitudinal girder steel of horizontal girder steel and Xin Jia, on described new edged girder steel, interval is welded with screw rod, and described screw rod runs through former wall and exposes former wall;
Step 6, by using metal wedge key jam-pack between the column cap of the new edged steel column of top layer, Xin Jia center steel column and the Xin Jia column of angles and roof steel inner ring beam, makes roof load all drop in new bearing wall and frame structure system;
Step 7, the new edged steel column of top layer, Xin Jia center steel column are fixedly connected with roof steel inner ring beam with the column cap of the Xin Jia column of angles, so far, former wall no longer bears the vertical load on roof, is only the peripheral structure of new structural system;
Step 8, on the screw rod exposing former wall nutting by the former wall of each layer and, what the former wall of each layer and nut 10 carried out is fastenedly connected.So just make former wall 7 and new edged girder steel drawknot be integrated, between described nut and former wall, be lined with billet.
In described step 5, the length at least 20cm larger than former wall thickness of screw rod.
The present invention and traditional ruggedized construction and method have following beneficial effect:
Establish new edged steel column, Xin Jia center steel column in the present invention passes through, newly add the column of angles, newly add horizontal girder steel and roof steel inner ring beam forms new structure-bearing system---steel structure device, the whole vertical load of existing building can be born.Using the body of wall of existing building only as the peripheral structure of new architecture.The change of this form of structure, by original body of wall load-bearing, be converted into globality and bearing capacity interior steelframe load-bearing all preferably, both reduced the requirement to age original structure body of wall for a long time, and do not affected the inside usage space of building in the style of the ancients and outside sensory effects simultaneously.
Load system after the present invention transforms; steel frame construction in adopting; because steel work has good ductility, plasticity and toughness; intensity is high; anti-seismic performance is good, and makes the advantages such as simple, the construction period is short, is tightly linked together by bolt with steel frame construction in stylish adding and former wall; make building in the style of the ancients can play the effect of seismic hardening, the effect of the alien invasion protecting original building can be accomplished again.It is little that this technology implements difficulty, can be effectively cost-saving, can not produce destruction simultaneously, have significant economic benefit and social benefit to original building exterior wall.
Accompanying drawing explanation
Fig. 1 is ruggedized construction floor map of the present invention.
Fig. 2 is the A-A sectional view of Fig. 1.
Fig. 3 is Yuan Qiang and new edged girder steel drawknot detail drawing.
Fig. 4 is a direction view of Fig. 3.
In figure, 1: new edged steel column; 2: newly add horizontal girder steel; 3: Xin Jia center steel column; 4: new edged girder steel; 5: newly add the column of angles; 6: newly add longitudinal girder steel; 7: former wall; 8: roof; 9: screw rod; 10: nut; 11: billet; 12: roof steel inner ring beam.
Detailed description of the invention
As Figure 1-4, steelframe ruggedized construction in a kind of building in the style of the ancients, comprise new edged steel column 1, newly add the column of angles 5, new edged girder steel 4, newly add horizontal girder steel 2 and roof steel inner ring beam 12, described new edged steel column 1 is close to former wall 7 inwall and is arranged and the corresponding setting of the new edged steel column 1 of body of wall relatively, describedly newly add the bight that the column of angles 5 is arranged on former wall 7, and be adjacent to former wall 7 inwall, described roof steel inner ring beam 12 is arranged on the end face of new edged steel column 1 and the Xin Jia column of angles 5, and hold out against with roof 8 and form the new supporting steel frame in roof 8, described new edged girder steel 4 to be arranged between adjacent two new edged steel columns 1 or new edged steel column 1 and newly add between the column of angles 5, and be close to former wall 7, simultaneously by bolt and former wall 7 drawknot, describedly newly add horizontal girder steel 2 and be arranged between the new edged steel column 1 of the correspondence between relative body of wall.
Describedly newly add horizontal girder steel 2 middle position and be equipped with Xin Jia center steel column 3, describedly newly add the side that horizontal girder steel 2 is connected to Xin Jia center steel column 3, meanwhile, be provided with between described Xin Jia center steel column 3 and newly add longitudinal girder steel 6.
Described new edged steel column 1, newly add the column of angles 5, new edged girder steel 4, newly add horizontal girder steel 2, roof steel inner ring beam 12, newly add longitudinal girder steel 6 and Xin Jia center steel column 3 is i iron, channel-section steel, H profile steel or above-mentioned any combination.
Together with described new edged girder steel 4 is at least with the horizontal girder steel 2 of Xin Jia.
Billet 11 is lined with between the nut 10 of described bolt and former wall 7.
The construction method of steelframe ruggedized construction in described building in the style of the ancients, step is as follows:
Step one, according to design drawing, installs the position well in advance steel-column foundation of new edged steel column 1, Xin Jia center steel column 3 and the Xin Jia column of angles 5 at the first floor of original building;
Step 2, the position correspondence of installing new edged steel column 1, Xin Jia center steel column 3 and the Xin Jia column of angles 5 at original building every floor plate opens installing hole;
Step 3, roof steel inner ring beam 12 is set bottom the roof 8 of original building, confirm that the position of roof steel inner ring beam 12 all can be contained and bear the whole load on roof 8, roof steel inner ring beam 12 and roof 8 are close to simultaneously, and in carry out roof steel system, collar tie beam 12 pre-fixes simultaneously;
Step 4, according to design drawing, be close to the new edged steel column 1 of the former wall 7 inwall installation first floor, Xin Jia center steel column 3 and the Xin Jia column of angles 5, and be connected bottom all steel columns with steel-column foundation, all steel column tops are being passed in the installing hole that the every floor plate of original building is offered in advance;
Step 5, according to design drawing, new edged steel column 1, Xin Jia center steel column 3 are successively installed, newly add the column of angles 5 and new edged girder steel 4 is set on demand between each layer steel column, newly adds the longitudinal girder steel 6 of horizontal girder steel 2 and Xin Jia, on described new edged girder steel 4, interval is welded with screw rod 9, and described screw rod 9 runs through former wall 7 and exposes former wall 7; The length at least 20cm larger than former wall 7 thickness of screw rod 9.
Step 6, by using metal wedge key jam-pack between the column cap of the new edged steel column 1 of top layer, Xin Jia center steel column 3 and the Xin Jia column of angles 5 and roof steel inner ring beam 12, makes roof load all drop in new bearing wall and frame structure system;
Step 7, the new edged steel column 1 of top layer, Xin Jia center steel column 3 are fixedly connected with roof steel inner ring beam 12 with the column cap of the Xin Jia column of angles 5, so far, former wall 7 no longer bears the vertical load on roof 8, is only the peripheral structure of new structural system;
Step 8, on the screw rod 9 exposing former wall 7, nutting 10 is by former wall 7 He of each layer, and what the former wall 7 of each layer and nut 10 carried out is fastenedly connected.So just make former wall 7 and new edged girder steel 4 drawknot be integrated, between described nut 10 and former wall 7, be lined with billet 11.
Be more than an exemplary embodiments of the present invention, enforcement of the present invention is not limited thereto.

Claims (6)

1. the construction method of steelframe ruggedized construction in a building in the style of the ancients, comprise new edged steel column (1), newly add the column of angles (5), new edged girder steel (4), newly add horizontal girder steel (2) and roof steel inner ring beam (12), described new edged steel column (1) is close to former wall (7) inwall and is arranged and the corresponding setting of the new edged steel column (1) of body of wall relatively, describedly newly add the bight that the column of angles (5) is arranged on former wall (7), and be adjacent to former wall (7) inwall, described roof steel inner ring beam (12) is arranged on new edged steel column (1) and newly adds the end face of the column of angles (5), and hold out against with roof (8) and form the new supporting steel frame in roof (8), described new edged girder steel (4) to be arranged between adjacent two new edged steel columns (1) or new edged steel column (1) and newly add between the column of angles (5), and be close to former wall (7), simultaneously by bolt and Yuan Qiang (7) drawknot, the described horizontal girder steel (2) that newly adds is arranged between the new edged steel column (1) of the correspondence between relative body of wall, it is characterized in that: step is as follows:
Step one, according to design drawing, installs new edged steel column (1), Xin Jia center steel column (3) at the first floor of original building and newly adds the position well in advance steel-column foundation of the column of angles (5);
Step 2, the position correspondence of installing new edged steel column (1), Xin Jia center steel column (3) at original building every floor plate and newly adding the column of angles (5) opens installing hole;
Step 3, in bottom, the roof (8) of original building, roof steel inner ring beam (12) is set, confirm that the position on roof steel inner ring beam (12) all can be contained and bear the whole load of roof (8) simultaneously, roof steel inner ring beam (12) and roof (8) are close to simultaneously, and in carry out roof steel system, collar tie beam (12) pre-fixes;
Step 4, according to design drawing, be close to the new edged steel column (1) of former wall (7) the inwall installation first floor, Xin Jia center steel column (3) and newly adding the column of angles (5), and be connected bottom all steel columns with steel-column foundation, all steel column tops are passed in the installing hole that the every floor plate of original building is offered in advance;
Step 5, according to design drawing, new edged steel column (1), Xin Jia center steel column (3) are successively installed, newly add the column of angles (5) and new edged girder steel (4) is set on demand between each layer steel column, newly adds horizontal girder steel (2) and newly add longitudinal girder steel (6), the upper interval of described new edged girder steel (4) is welded with screw rod (9), and described screw rod (9) runs through Yuan Qiang (7) and exposes former wall (7);
Step 6, by new edged steel column (1), Xin Jia center steel column (3) of top layer with newly to add between the column cap of the column of angles (5) and roof steel inner ring beam (12) with metal wedge key jam-pack, roof load is made all to drop in new bearing wall and frame structure system;
Step 7, the new edged steel column (1) of top layer, Xin Jia center steel column (3) are fixedly connected with roof steel inner ring beam (12) with the column cap newly adding the column of angles (5), so far, former wall (7) no longer bears the vertical load of roof (8), is only the peripheral structure of new structural system;
Step 8, at the upper nutting (10) of the screw rod (9) exposing former wall (7), the former wall (7) of each layer and the new edged girder steel (4) of each layer are fastenedly connected with nut (10), so just make former wall (7) and new edged girder steel (4) drawknot be integrated, between described nut (10) He Yuanqiang (7), be lined with billet (11).
2. the construction method of steelframe ruggedized construction in building in the style of the ancients according to claim 1, it is characterized in that: described horizontal girder steel (2) middle position that newly adds is equipped with Xin Jia center steel column (3), describedly newly add the side that horizontal girder steel (2) is connected to Xin Jia center steel column (3), meanwhile, be provided with between described Xin Jia center steel column (3) and newly add longitudinal girder steel (6).
3. the construction method of steelframe ruggedized construction in building in the style of the ancients according to claim 2, is characterized in that: described new edged steel column (1), newly add the column of angles (5), new edged girder steel (4), newly add horizontal girder steel (2), roof steel inner ring beam (12), newly add longitudinal girder steel (6) and Xin Jia center steel column (3) be i iron, channel-section steel, H profile steel or above-mentioned any combination.
4. the construction method of steelframe ruggedized construction in building in the style of the ancients according to claim 1, is characterized in that: described new edged girder steel (4) and newly add horizontal girder steel (2) and be at least together.
5. the construction method of steelframe ruggedized construction in building in the style of the ancients according to claim 1, is characterized in that: be lined with billet (11) between the nut (10) of described bolt and former wall (7).
6. the construction method of steelframe ruggedized construction in building in the style of the ancients according to claim 1, it is characterized in that: in described step 5, the length of screw rod (9) is than former wall (7) thickness greatly at least 20cm.
CN201210468611.XA 2012-11-15 2012-11-15 Construction method of inner steel frame reinforced structure of pseudo-classic architecture Active CN102936968B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210468611.XA CN102936968B (en) 2012-11-15 2012-11-15 Construction method of inner steel frame reinforced structure of pseudo-classic architecture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210468611.XA CN102936968B (en) 2012-11-15 2012-11-15 Construction method of inner steel frame reinforced structure of pseudo-classic architecture

Publications (2)

Publication Number Publication Date
CN102936968A CN102936968A (en) 2013-02-20
CN102936968B true CN102936968B (en) 2015-06-03

Family

ID=47695887

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210468611.XA Active CN102936968B (en) 2012-11-15 2012-11-15 Construction method of inner steel frame reinforced structure of pseudo-classic architecture

Country Status (1)

Country Link
CN (1) CN102936968B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103526952B (en) * 2013-10-12 2015-09-09 北京筑福国际工程技术有限责任公司 Masonry residence adjustable slipper block cant beam steelframe protects roof construction and construction method thereof
CN103993751B (en) * 2014-05-20 2016-01-13 东南大学 A kind of wall reinforcement structure and method strengthening ancient building globality
CN104895346B (en) * 2015-06-30 2017-03-08 郑州大学 Hardened system and its construction technology that the anti-local soil body of crude cave house vault caves in
CN105926975B (en) * 2016-06-28 2017-12-19 辽宁工程技术大学 A kind of anti-vibration reinforced device of rock cave column rock historical relic
CN106592995B (en) * 2016-11-01 2018-10-26 中国建筑第八工程局有限公司 Open the installation method of overarm steel construction stress system
CN107460972A (en) * 2017-09-15 2017-12-12 江苏省建筑科学研究院有限公司 A kind of assembled steel support frame Strengthened Masonry Walls load bearing wall and reinforced construction method
CN109505420A (en) * 2018-10-12 2019-03-22 北京筑福建筑科学研究院有限责任公司 A kind of old local-style dwelling houses uses interior steelframe ruggedized construction and its construction method
CN112081249B (en) * 2020-08-03 2021-11-12 上海建工一建集团有限公司 Roof integral jacking system and roof integral jacking method
CN112081248B (en) * 2020-08-03 2021-11-12 上海建工一建集团有限公司 Roof integral lifting system and roof integral lifting method
CN112081250B (en) * 2020-08-03 2021-11-12 上海建工一建集团有限公司 House integral lifting system and house integral lifting method
CN112081251B (en) * 2020-08-03 2021-12-03 上海建工一建集团有限公司 Integral house jacking system and integral house jacking method
CN112696042A (en) * 2020-12-11 2021-04-23 华南理工大学 Repairing method for Hakka soil building structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05141118A (en) * 1991-11-21 1993-06-08 Mitsubishi Steel Mfg Co Ltd Earthquake-proof structure of steel frame system prefabricated house
JPH09242183A (en) * 1996-03-11 1997-09-16 Tomoe Corp Earthquake-resistant frame structure
JPH09302952A (en) * 1996-05-10 1997-11-25 Shimizu Corp Earthquake-resistant reinforcing method and earthquake-resistant reinforcing structure of existing building
JP2815331B2 (en) * 1995-11-13 1998-10-27 株式会社山菱 Reinforcement structure of wooden building
CN101798877A (en) * 2009-03-09 2010-08-11 吕西林 Novel earthquake-proof skeleton system of masonry structure
CN202945820U (en) * 2012-11-15 2013-05-22 北京筑福国际工程技术有限责任公司 Inner steel frame reinforced structure of pseudo-classic architecture

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6931804B2 (en) * 2001-06-21 2005-08-23 Shear Force Wall Systems Inc. Prefabricated shearwall having improved structural characteristics

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05141118A (en) * 1991-11-21 1993-06-08 Mitsubishi Steel Mfg Co Ltd Earthquake-proof structure of steel frame system prefabricated house
JP2815331B2 (en) * 1995-11-13 1998-10-27 株式会社山菱 Reinforcement structure of wooden building
JPH09242183A (en) * 1996-03-11 1997-09-16 Tomoe Corp Earthquake-resistant frame structure
JPH09302952A (en) * 1996-05-10 1997-11-25 Shimizu Corp Earthquake-resistant reinforcing method and earthquake-resistant reinforcing structure of existing building
CN101798877A (en) * 2009-03-09 2010-08-11 吕西林 Novel earthquake-proof skeleton system of masonry structure
CN202945820U (en) * 2012-11-15 2013-05-22 北京筑福国际工程技术有限责任公司 Inner steel frame reinforced structure of pseudo-classic architecture

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
民国老礼堂加固设计方案;敬登虎等;《建筑技术》;20070615;第38卷(第6期);432-434 *
钢结构支撑在某框架结构厂房抗震加固设计中的应用;王东等;《建筑设计》;20060215;第35卷(第1期);127-129 *

Also Published As

Publication number Publication date
CN102936968A (en) 2013-02-20

Similar Documents

Publication Publication Date Title
CN102936968B (en) Construction method of inner steel frame reinforced structure of pseudo-classic architecture
CN108560719A (en) The support installation method of super large span double-layer Bidirectional hanging rope structure
CN202945820U (en) Inner steel frame reinforced structure of pseudo-classic architecture
CN102691266B (en) Construction method for ultrahigh combined support for bridge side span cast-in-situ section
CN204920210U (en) Dysmorphism spar template reinforced structure
CN107217747A (en) A kind of novel fabricated connector for building
CN203213591U (en) Beam-free turbinate column cap structure template system
CN105544372A (en) Magnetic levitation encircled track traffic double-line track beam
CN207277363U (en) Assembling type base for construction elevator
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN210420862U (en) Stay cable tower end anchoring device
CN203200745U (en) Underground continuous wall's reinforcement support in reverse construction method construction
CN104141317A (en) Basement tower crane foundation construction method and structure adopting reverse construction method
CN206503233U (en) Assembled architecture beam-to-column joint structure and steel building
CN103061408B (en) Powerful confined concrete core wall with obvious columns and hidden beams
CN105568789A (en) Two-line rail girder of maglev rail-holding rail transit
CN211081110U (en) Reinforced concrete beam plate structure of rear steel structure continuous beam
CN210421983U (en) Steel frame reinforced structure in old house
CN211368420U (en) Main tower lower beam bracing support system
CN204000562U (en) The compound rigid frame bridge of a kind of vertical prestressing steel-concrete
CN109505420A (en) A kind of old local-style dwelling houses uses interior steelframe ruggedized construction and its construction method
CN207363065U (en) Curtain skeleton connects system
CN203034377U (en) Construction template of cable bent tower of cable-stayed bridge
CN112267575A (en) Prefabricated steel-encased concrete column and steel beam connecting joint and construction process
CN105937291A (en) Steel-reinforced concrete column with stud structure and high length-width ratio and installation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, two floor, Chak Yang Building

Applicant after: Beijing Aeido International Engineering Technology Co., Ltd.

Address before: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, two floor, Chak Yang Building

Applicant before: Beijing Zhufu Construction Engineering Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: BEIJING AEIDO CONSTRUCTION ENGINEERING CO., LTD. TO: BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Du Lihong

Inventor before: Dong You

Inventor before: Ju Shusen

Inventor before: Xie Jianming

Inventor before: Zhen Jinping

TR01 Transfer of patent right

Effective date of registration: 20171030

Address after: 102600, room 2, building 2212, center 3, 2 Xinghua street, Daxing District, Beijing

Patentee after: Beijing Yong Bo Science and Technology Ltd.

Address before: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, two floor, Chak Yang Building

Patentee before: Beijing Aeido International Engineering Technology Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171227

Address after: 401220 Chongqing City longevity zone, saddle saddle Green square 1 unit 2-4

Patentee after: Li Wenkang

Address before: 102600, room 2, building 2212, center 3, 2 Xinghua street, Daxing District, Beijing

Patentee before: Beijing Yong Bo Science and Technology Ltd.

TR01 Transfer of patent right
CP02 Change in the address of a patent holder

Address after: 210024 1 Xikang Road, Gulou District, Nanjing, Jiangsu

Patentee after: Li Wenkang

Address before: 401220 1 unit 2-4, riding saddle Green square, Changshou District, Chongqing

Patentee before: Li Wenkang

CP02 Change in the address of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190529

Address after: 202172 Room 1260, No. 495 Yuejin South Road, Xinhai Town, Chongming District, Shanghai (Guangming Rice Industry Economic Park)

Patentee after: Advocating Creation (Shanghai) Consulting Management Firm

Address before: 210024 1 Xikang Road, Gulou District, Nanjing, Jiangsu

Patentee before: Li Wenkang

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210104

Address after: No. 68, Zhenxing Road, Tudian Town, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: YADU CONSTRUCTION GROUP Co.,Ltd.

Address before: Room 1260, building 5, No. 495, Yuejin South Road, Xinhai Town, Chongming District, Shanghai 202172

Patentee before: Advocating Creation (Shanghai) Consulting Management Firm