CN102926802B - 利用煤矿井下泄水巷减少淤煤的方法 - Google Patents

利用煤矿井下泄水巷减少淤煤的方法 Download PDF

Info

Publication number
CN102926802B
CN102926802B CN201210423154.2A CN201210423154A CN102926802B CN 102926802 B CN102926802 B CN 102926802B CN 201210423154 A CN201210423154 A CN 201210423154A CN 102926802 B CN102926802 B CN 102926802B
Authority
CN
China
Prior art keywords
coal
water
tunnel
travelling belt
belt lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210423154.2A
Other languages
English (en)
Other versions
CN102926802A (zh
Inventor
李树兴
李玉忠
曹守新
梁和平
祝德胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kailuan Group Co Ltd Donghuantuo Mining Branch
Original Assignee
Kailuan Group Co Ltd Donghuantuo Mining Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kailuan Group Co Ltd Donghuantuo Mining Branch filed Critical Kailuan Group Co Ltd Donghuantuo Mining Branch
Priority to CN201210423154.2A priority Critical patent/CN102926802B/zh
Publication of CN102926802A publication Critical patent/CN102926802A/zh
Application granted granted Critical
Publication of CN102926802B publication Critical patent/CN102926802B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种利用煤矿井下泄水巷减少淤煤的方法,在工作面开采前,首先在运输皮带巷下方开拓一条泄水巷道,泄水巷道与井下水仓相通;在运输皮带巷中间隔设立贯通眼,通过贯通眼将运输皮带巷与泄水巷道贯通,并在贯通处的运输皮带巷设挡水结构;在泄水巷道的末端安装振动筛,振动筛以后再开拓一条运煤巷道,运煤巷道与运输皮带巷相通。由于流入井下水仓的水不再含有大量的固体煤炭,成为仅含有微粒的泥水,水仓不会被淤煤填满,泥水对主水泵吸水口的影响减小,保证了主水泵排水能力和排水的畅通,清挖水仓的工作减少,提高了煤炭生产效率和抗水灾能力。

Description

利用煤矿井下泄水巷减少淤煤的方法
技术领域
本发明属于煤矿开采技术领域。
背景技术
我国重点煤矿受水威胁的煤炭储量大约250亿t,其中受地表水体(江、河、湖、海等)、松散含水层、基岩含水层等水体威胁的煤炭储量近100亿t。仅就受河流影响来看,就有200多个矿井受100余条大小河流威胁,而华北、华东、东北地区的煤田普遍被第四系和第三系松散层含水层覆盖。在煤炭开采中,尤其是大采高(5米以上)开采中易引起导水裂隙带高度的增加和分布范围的扩大,使顶板水从导水裂隙带中流入开采工作面,顶板水与部分细小煤炭混在一起形成水煤体直接排入井底水仓,在水仓中经过长时间淤积,水仓的断面就会减小,蓄水能力就会降低。随着淤煤的增多,部分淤煤就会被水流带入主水泵吸水口,严重影响水泵的排水能力。为此,煤矿井底水仓以往都必须采取定期清理淤煤,尤其是对于俯斜开采的矿井,因水煤浓度高,水仓很快就会被淤煤填满,清挖水仓的工作周期很短,势必会增加矿工的劳动强度,降低煤炭生产效率,而且严重影响煤矿的抗水灾能力。因此,在开采期间将水煤体在井下进行有效分离是解决这一问题的关键。
发明内容
本发明的目的是为解决大水煤层开采矿井水仓的淤煤问题,提出一种减少淤煤的方法。
本发明采取的技术方案是:
一种利用煤矿井下泄水巷减少淤煤的方法,其特征在于:
第一步:在工作面开采前,首先沿运输皮带巷开拓一条带有自流坡度的泄水巷道,泄水巷道的标高应低于皮带巷的标高,在运输皮带巷中间隔设立贯通眼,通过贯通眼将运输皮带巷与泄水巷道贯通,并在贯通处的运输皮带巷设挡水结构;在泄水巷道的末端安装振动筛,振动筛以后再开拓一条运煤巷道,运煤巷道与运输皮带巷相通;
第二步:开采时,工作面的水煤体在挡水结构控制下从最近的贯通眼中泄入泄水巷道,水煤体流至振动筛时,粒度大于筛缝间隙的固体颗粒得到过滤,筛上的过滤煤炭装入运输设备从运煤巷道运至运输皮带巷,从运输皮带巷运至煤仓,筛下的泥水继续从泄水巷道流至井下水仓。
本发明的优点是:由于流入井下水仓的水不再含有大量的固体煤炭,成为仅含有微粒的泥水,水仓不会被淤煤填满,泥水对主水泵吸水口的影响减小,保证了主水泵排水能力和排水的畅通,清挖水仓的工作减少,提高了煤炭生产效率和抗水灾能力。
附图说明
下面结合附图说明本发明的实施。
图1是本发明实施例的示意图。
图例说明,1-工作面,2-运输皮带巷,3-贯通眼,4-振动筛,5-泄水巷道,6-煤仓,7-井下水仓,8-挡水结构,9-运煤巷道。
具体实施方式
如图1所示,一种煤矿井下水仓减少淤煤的方法,其特征是:在工作面1开采前,首先沿运输皮带巷2开拓一条泄水巷道5,泄水巷道5的标高应低于皮带巷2的标高,泄水巷道5与井下水仓7相通;在运输皮带巷2中每隔一定距离设立贯通眼3,通过贯通眼3将运输皮带巷2与泄水巷道4贯通,并在贯通处的运输皮带巷设挡水结构8;在泄水巷道5的末端安装振动筛4,振动筛4以后再开拓一条与运输皮带巷相通的运煤巷道9;工作面1的水煤体在挡水结构8控制下从最近的贯通眼3中泄入泄水巷道5,水煤体流至振动筛4时,粒度大于筛缝间隙的固体颗粒得到过滤,筛上的过滤煤炭装入运输设备从运煤巷道9运至煤仓6,筛下的洁水继续从泄水巷道5流至井下水仓7中。

Claims (1)

1.一种利用煤矿井下泄水巷减少淤煤的方法,其特征在于:
第一步:在工作面开采前,首先沿运输皮带巷开拓一条带有自流坡度的泄水巷道,泄水巷道的标高应低于皮带巷的标高,在运输皮带巷中间隔设立贯通眼,通过贯通眼将运输皮带巷与泄水巷道贯通,并在贯通处的运输皮带巷设挡水结构;在泄水巷道的末端安装振动筛,振动筛以后再开拓一条运煤巷道,运煤巷道与运输皮带巷相通;
第二步:开采时,工作面的水煤体在挡水结构控制下从最近的贯通眼中泄入泄水巷道,水煤体流至振动筛时,粒度大于筛缝间隙的固体颗粒得到过滤,筛上的过滤煤炭装入运输设备从运煤巷道运至运输皮带巷,从运输皮带巷运至煤仓,筛下的泥水继续从泄水巷道流至井下水仓。
CN201210423154.2A 2012-10-30 2012-10-30 利用煤矿井下泄水巷减少淤煤的方法 Expired - Fee Related CN102926802B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210423154.2A CN102926802B (zh) 2012-10-30 2012-10-30 利用煤矿井下泄水巷减少淤煤的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210423154.2A CN102926802B (zh) 2012-10-30 2012-10-30 利用煤矿井下泄水巷减少淤煤的方法

Publications (2)

Publication Number Publication Date
CN102926802A CN102926802A (zh) 2013-02-13
CN102926802B true CN102926802B (zh) 2014-12-10

Family

ID=47641714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210423154.2A Expired - Fee Related CN102926802B (zh) 2012-10-30 2012-10-30 利用煤矿井下泄水巷减少淤煤的方法

Country Status (1)

Country Link
CN (1) CN102926802B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401642B (zh) * 2016-11-24 2018-08-10 攀枝花煤业(集团)有限责任公司 溜煤井的排水结构
CN108590754A (zh) * 2018-04-24 2018-09-28 中煤西安设计工程有限责任公司 一种单斜煤层采区集中泄水巷布置方法
CN108643966A (zh) * 2018-04-24 2018-10-12 中煤西安设计工程有限责任公司 一种工作面底板集中泄水巷布置方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101074608A (zh) * 2007-06-13 2007-11-21 暴万林 煤矿水仓煤泥清理运输装置
CN101387204A (zh) * 2007-09-12 2009-03-18 河南理工大学 煤矿水煤井下脱水技术
RU2009145305A (ru) * 2010-01-20 2011-07-27 Общество с ограниченной ответственностью Научно-технический и экспертный центр новых экотехнологий в гидрогеологии и гидротехнике "НО Способ осушения месторождения полезных ископаемых
CN201978546U (zh) * 2011-02-28 2011-09-21 煤炭工业济南设计研究院有限公司 巷道通过式井下水沉淀系统
CN102505963A (zh) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 回采工作面顶板水预疏放施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101074608A (zh) * 2007-06-13 2007-11-21 暴万林 煤矿水仓煤泥清理运输装置
CN101387204A (zh) * 2007-09-12 2009-03-18 河南理工大学 煤矿水煤井下脱水技术
RU2009145305A (ru) * 2010-01-20 2011-07-27 Общество с ограниченной ответственностью Научно-технический и экспертный центр новых экотехнологий в гидрогеологии и гидротехнике "НО Способ осушения месторождения полезных ископаемых
CN201978546U (zh) * 2011-02-28 2011-09-21 煤炭工业济南设计研究院有限公司 巷道通过式井下水沉淀系统
CN102505963A (zh) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 回采工作面顶板水预疏放施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
振动筛在综采工作面的应用;龙学彬;《科技创新导报》;20111230(第35期);第50页 *
龙学彬.振动筛在综采工作面的应用.《科技创新导报》.2011,(第35期), *

Also Published As

Publication number Publication date
CN102926802A (zh) 2013-02-13

Similar Documents

Publication Publication Date Title
CN102926803B (zh) 复杂水文条件下水、煤同采的排水方法
CN107893658B (zh) 强地压环境下极厚大矿体阶段空场嗣后充填采矿方法
CN102913280B (zh) 大水矿井顶板水排出方法
CN101403314B (zh) 煤矿井下钻孔水力压裂增透抽采瓦斯工艺
CN107448176A (zh) 一种海底浅层非成岩天然气水合物机械射流联合开采方法及装置
RU2594912C2 (ru) Способ освоения глубокозалегающего обводненного месторождения бурожелезняковых оолитовых руд
CN103354766B (zh) 用于矿井的地下水管理系统
CN102926802B (zh) 利用煤矿井下泄水巷减少淤煤的方法
CN104074541A (zh) 一种水体下固体充填开采设计方法
CN205977226U (zh) 一种用于泥水平衡盾构机的砾石采石箱系统
CN109339785B (zh) 一种缓倾斜中厚矿体多单元组合集约化采矿方法
CN102162364B (zh) 煤矿井下重介浅槽选煤布置方法
CN102943691B (zh) 大水煤矿井底水仓减少淤煤泥的方法
CN106381405A (zh) 一种稀土矿山集液系统及方法
CN108590754A (zh) 一种单斜煤层采区集中泄水巷布置方法
CN103603666B (zh) 一种尾矿库采砂方法
CN111322111A (zh) 一种矿井涌水泥砂沉淀结构
CN104020505B (zh) 一种煤矿地下水库的淤积监测方法
Kamp Backfilling on gold mines of the Gold Fields group
CN202007665U (zh) 矿用液压挖装机
CN102200013A (zh) 地下金属矿山无排放生产方法
CN113622364B (zh) 一种适用于深度大于100m的贫水区露天矿地下水库的建设方法
CN204002929U (zh) 一种具有应急泄水装置的地下水库
CN104018459B (zh) 一种煤矿地下水库的清淤方法
CN115584957B (zh) 一种块段化、递进式联动开采盐湖矿产的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20151030

EXPY Termination of patent right or utility model