CN102926389B - Grouped pile structure for preventing and treating landslide and construction method thereof - Google Patents
Grouped pile structure for preventing and treating landslide and construction method thereof Download PDFInfo
- Publication number
- CN102926389B CN102926389B CN201210389876.0A CN201210389876A CN102926389B CN 102926389 B CN102926389 B CN 102926389B CN 201210389876 A CN201210389876 A CN 201210389876A CN 102926389 B CN102926389 B CN 102926389B
- Authority
- CN
- China
- Prior art keywords
- main
- antislide pile
- piles
- pile
- slide
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种地下基础结构中的桩基础结构,具体的说,是涉及一种防治滑坡的群桩结构及其施工方法,适用于房屋建筑边坡、道路边坡及各种天然边坡。The invention relates to a pile foundation structure in an underground foundation structure, in particular to a pile group structure for preventing landslides and a construction method thereof, which is suitable for building construction slopes, road slopes and various natural slopes.
背景技术 Background technique
受自然动力如地震、强降雨的影响以及因实际工程需要人为开挖边坡坡脚等因素,会造成边坡失稳而发生滑坡。Affected by natural dynamics such as earthquakes and heavy rainfall, as well as artificial excavation of the slope toe due to actual engineering needs, etc., the slope will become unstable and landslides will occur.
目前防治滑坡的抗滑桩主要采用单根大直径的钢筋混凝土桩,该钢筋混凝土桩的的直径上下一致,而抗滑桩桩在实际工作过程中所受的应力呈中间大、顶部和底部小的类抛物线分布,两者不相符造成了部分材料的浪费。另外由于目前抗滑桩的桩距较大,虽整体稳定性可以满足,但桩间土的挤出破坏时有发生,而减少桩距又会大大增加工程造价和施工周期。At present, the anti-slide piles used to prevent landslides mainly use a single large-diameter reinforced concrete pile. The parabolic distribution of the two, the inconsistency between the two caused the waste of some materials. In addition, due to the large pile distance of the current anti-slide piles, although the overall stability can be satisfied, the extrusion damage of the soil between the piles occurs from time to time, and reducing the pile distance will greatly increase the project cost and construction period.
发明内容 Contents of the invention
本发明要解决的是抗滑桩桩间土易发生挤出破坏的技术问题,提供了一种防治滑坡的群桩结构及其施工方法,能够在不减小桩间距离的前提下,有效避免桩间土的挤出破坏,从而节约工程成本。The invention aims to solve the technical problem that the soil between the anti-slide piles is prone to extrusion damage, and provides a pile group structure and construction method for preventing landslides, which can effectively avoid the piles without reducing the distance between piles. Extrusion damage of soil between piles, thus saving engineering cost.
为了解决上述技术问题,本发明通过以下的技术方案予以实现:In order to solve the above technical problems, the present invention is achieved through the following technical solutions:
一种防治滑坡的群桩结构,包括至少一排间隔设置于坡体的主抗滑桩,同排的相邻两个所述主抗滑桩之间浇筑连接有主冠梁;每排所述主抗滑桩下部坡体上设置有直径小于所述主抗滑桩的次抗滑桩,所述次抗滑桩对应于相邻两个所述主抗滑桩之间的中间位置,所述次抗滑桩与相邻两个所述主抗滑桩之间浇筑连接有次冠梁;A pile group structure for preventing landslides, comprising at least one row of main anti-slide piles arranged at intervals on the slope body, and main crown beams are poured and connected between two adjacent main anti-slide piles in the same row; The lower slope of the main anti-slide pile is provided with a secondary anti-slide pile whose diameter is smaller than the main anti-slide pile, and the secondary anti-slide pile corresponds to the middle position between two adjacent main anti-slide piles. A secondary crown beam is poured and connected between the secondary anti-slide pile and the two adjacent primary anti-slide piles;
所述主抗滑桩中部的直径大于上部和下部的直径,所述主抗滑桩设置有纵筋和箍筋,所述主抗滑桩中部的所述箍筋加密;所述次抗滑桩设置有纵筋和箍筋,所述次抗滑桩中部的所述箍筋加密。The diameter of the middle part of the main anti-slide pile is larger than the diameter of the upper part and the lower part, and the main anti-slide pile is provided with longitudinal bars and stirrups, and the stirrups in the middle part of the main anti-slide pile are encrypted; the secondary anti-slide pile Longitudinal bars and stirrups are provided, and the stirrups in the middle of the secondary anti-slide pile are dense.
所述主冠梁和其下部对应的两个所述次冠梁围成的三角形区域内设置有绿化带。A green belt is arranged in the triangular area enclosed by the main crown beam and the two corresponding secondary crown beams below it.
所述主抗滑桩的最小直径为其最大直径的1/2~2/3。The minimum diameter of the main anti-slide pile is 1/2 to 2/3 of its maximum diameter.
所述次抗滑桩的直径为所述主抗滑桩最大直径的1/3,所述次抗滑桩的长度为所述主抗滑桩长度的1/3~1/2。The diameter of the secondary anti-slide pile is 1/3 of the maximum diameter of the main anti-slide pile, and the length of the secondary anti-slide pile is 1/3-1/2 of the length of the main anti-slide pile.
所述次抗滑桩中纵筋的直径小于所述主抗滑桩中纵筋的直径4~6mm,所述次抗滑桩中箍筋的直径小于所述主抗滑桩中箍筋的直径2~4mm。The diameter of the longitudinal reinforcement in the secondary anti-slide pile is 4-6 mm less than the diameter of the longitudinal reinforcement in the main anti-slide pile, and the diameter of the stirrup in the secondary anti-slide pile is smaller than the diameter of the stirrup in the main anti-slide pile 2 ~ 4mm.
所述主抗滑桩和所述次抗滑桩中部加密的所述箍筋间距为其他部分所述箍筋间距的1/2。The distance between the stirrups in the middle of the main anti-slide pile and the secondary anti-slide pile is 1/2 of the distance between the stirrups in other parts.
所述次冠梁的截面边长为所述主冠梁截面边长的40%~60%。The side length of the cross-section of the secondary crown beam is 40% to 60% of the side length of the main crown beam.
一种利用上述防治滑坡的群桩结构的施工方法,包括如下步骤:A construction method utilizing the above-mentioned pile group structure for prevention and control of landslides, comprising the steps of:
(1)精确确定主抗滑桩、次抗滑桩的位置;(1) Accurately determine the positions of the main anti-slide pile and the secondary anti-slide pile;
(2)人工或钻机进行主抗滑桩的挖孔工作,上部与中部的最粗直径相等,下部进行缩孔挖孔;(2) The main anti-slide pile shall be excavated manually or by a drilling rig, the upper part and the middle part shall have the same maximum diameter, and the lower part shall be excavated for shrinkage holes;
(3)进行次抗滑桩的钻孔;(3) Drilling of secondary anti-slide piles;
(4)分别预制主抗滑桩和次抗滑桩的钢筋笼;(4) Prefabricate the reinforcement cages of the main anti-slide pile and the secondary anti-slide pile respectively;
(5)将预制好的主抗滑桩的钢筋笼和次抗滑桩的钢筋笼,分别放入已经钻好的主抗滑桩、次抗滑桩的孔中,浇筑混凝土;其中浇筑到主抗滑桩上部时,进行上部缩径处理,用与主抗滑桩上部形状相同的钢套管将主抗滑桩的钢筋笼套住,钢套管外侧与孔壁之间的间隙用边坡自然土回填,接着继续进行混凝土浇筑,直至完成主抗滑桩的成型;(5) Put the prefabricated steel cage of the main anti-slide pile and the reinforcement cage of the secondary anti-slide pile into the drilled holes of the main anti-slide pile and the secondary anti-slide pile respectively, and pour concrete; For the upper part of the anti-slide pile, the diameter of the upper part shall be reduced, and the steel cage of the main anti-slide pile shall be covered with a steel casing with the same shape as the upper part of the main anti-slide pile. Backfilling with natural soil, followed by concrete pouring until the formation of the main anti-slide pile is completed;
(6)浇筑主冠梁和次冠梁,浇筑完成后主冠梁和次冠梁上部进行浇水养护。(6) Pour the main crown beam and the secondary crown beam. After the pouring is completed, the upper part of the main crown beam and the secondary crown beam will be watered and maintained.
本发明的有益效果是:The beneficial effects of the present invention are:
(一)本发明的主抗滑桩能够确保滑坡的整体稳定性,次抗滑桩能够避免滑坡桩间土的挤出破坏,采用主、次抗滑桩结构体系,可以在保证滑坡稳定的前提下,有效增大主抗滑桩的间距,节约工程成本,避免主抗滑桩之间的土体发生挤出破坏;(1) The main anti-slide pile of the present invention can ensure the overall stability of the landslide, and the secondary anti-slide pile can avoid the extrusion damage of the soil between the landslide piles. The main and secondary anti-slide pile structure system can ensure the stability of the landslide. effectively increase the distance between the main anti-slide piles, save engineering costs, and avoid extrusion damage of the soil between the main anti-slide piles;
(二)本发明根据桩身的受力大小和受力规律,改变了传统桩身上下直径相同的设计方案,采用中间粗两边细的桩体结构,符合桩身的受力规律,能够抵抗相对较大的外力,增强了桩的抗力性能,还可以大大节约工程造价;(2) According to the force of the pile body and the law of force, the present invention changes the traditional design of the pile body with the same diameter at the top and bottom, and adopts a pile body structure with a thick middle and thin sides, which conforms to the force law of the pile body and can resist relative pressure. The larger external force enhances the resistance performance of the pile and can greatly save the project cost;
(三)本发明的主抗滑桩之间通过主冠梁相互连接、主抗滑桩和次抗滑桩之间通过次冠梁相互连接,有利于主抗滑桩和次抗滑桩形成整体受力的优势,从而增强抗滑桩的整体抗滑能力;(3) The main anti-slide piles of the present invention are connected to each other through the main crown beam, and the main anti-slide piles and the secondary anti-slide piles are connected to each other through the secondary crown beam, which is conducive to the formation of the main anti-slide pile and the secondary anti-slide pile The advantages of force, thereby enhancing the overall anti-sliding ability of the anti-slide pile;
(四)本发明的主抗滑桩和次抗滑桩中部的箍筋加密,能够增强抗滑桩的抗剪切能力和抗弯能力,防止抗滑桩发生破坏;(4) The stirrups in the middle of the main anti-slide pile and the secondary anti-slide pile are encrypted, which can enhance the shear resistance and bending resistance of the anti-slide pile, and prevent the anti-slide pile from being damaged;
(五)本发明采用绿化带可以起到美观作用。(5) The green belt used in the present invention can play an aesthetic role.
附图说明 Description of drawings
图1是本发明所提供的群桩结构的平面示意图;Fig. 1 is a schematic plan view of pile group structure provided by the present invention;
图2是本发明所提供的主抗滑桩的结构示意图;Fig. 2 is the structural representation of main anti-slide pile provided by the present invention;
图3是本发明所提供的次抗滑桩的结构示意图。Fig. 3 is a schematic structural view of the secondary anti-slide pile provided by the present invention.
图中:1,主抗滑桩;2,主冠梁;3,次冠梁;4,次抗滑桩;5,绿化带;6,箍筋;7,纵筋。In the figure: 1, the main anti-slide pile; 2, the main crown beam; 3, the secondary crown beam; 4, the secondary anti-slide pile; 5, the green belt; 6, the stirrup; 7, the longitudinal bar.
具体实施方式 Detailed ways
为能进一步了解本发明的内容、特点及效果,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:
如图1所示,本发明公开了一种防治滑坡的群桩结构,由主抗滑桩1、次抗滑桩4、主冠梁2、次冠梁3和绿化带构成。As shown in Fig. 1, the present invention discloses a pile group structure for preventing and controlling landslides, which is composed of a main anti-slide pile 1, a secondary anti-slide pile 4, a main crown beam 2, a secondary crown beam 3 and a green belt.
主抗滑桩1根据滑坡规模和下滑力在坡体上设置一排或多排。如图2所示,主抗滑桩1的形状为中间粗两边细,粗细部分可以是圆滑过渡或阶梯式过渡,即主抗滑桩1中部的直径大于上部和下部的直径,其最小直径为其最大直径的1/2~2/3。The main anti-slide piles 1 are arranged in one or more rows on the slope body according to the scale of the landslide and the sliding force. As shown in Figure 2, the shape of the main anti-slide pile 1 is thick in the middle and thin on both sides, and the thick and thin parts can be a smooth transition or a stepped transition, that is, the diameter of the middle part of the main anti-slide pile 1 is larger than the diameter of the upper and lower parts, and its minimum diameter is 1/2 to 2/3 of its maximum diameter.
主抗滑桩1设置有纵筋7和箍筋6,纵筋7沿主抗滑桩1周向均匀布置,箍筋6通过弯钩与纵筋7相连接。其中,位于主抗滑桩1中部的箍筋6间距小于其上部和下部的箍筋6间距,即中部箍筋6加密;而中部加密的箍筋6间距为其他部分箍筋6间距的一半。The main anti-slide pile 1 is provided with longitudinal bars 7 and stirrups 6, the longitudinal bars 7 are evenly arranged along the circumference of the main anti-slide pile 1, and the stirrups 6 are connected with the longitudinal bars 7 through hooks. Among them, the distance between the stirrups 6 in the middle of the main anti-slide pile 1 is smaller than the distance between the stirrups 6 in the upper and lower parts, that is, the distance between the stirrups 6 in the middle is denser; and the distance between the stirrups 6 in the middle is half of the distance between the stirrups 6 in other parts.
次抗滑桩4设置于主抗滑桩1下部一定距离的坡体上,该距离一般在1~2m范围内,每个次抗滑桩4对应于相邻两个主抗滑桩1之间的中间位置。如图3所示,次抗滑桩4为普通的圆柱形结构,其直径和长度分别小于主抗滑桩1的直径和长度,次抗滑桩4的直径为主抗滑桩1最大直径的1/3,次抗滑桩4的长度为主抗滑桩1长度的1/3~1/2。The secondary anti-slide piles 4 are arranged on the slope body at a certain distance below the main anti-slide piles 1. The distance is generally within the range of 1-2m. middle position. As shown in Figure 3, the secondary anti-slide pile 4 is a common cylindrical structure, and its diameter and length are respectively smaller than the diameter and length of the main anti-slide pile 1, and the diameter of the secondary anti-slide pile 4 is the maximum diameter of the main anti-slide pile 1. 1/3, the length of the secondary anti-slide pile 4 is 1/3-1/2 of the length of the main anti-slide pile 1.
次抗滑桩4设置有纵筋7和箍筋6,纵筋7沿次抗滑桩4周向均匀布置,箍筋6通过弯钩与纵筋7相连接。次抗滑桩4中纵筋的直径小于主抗滑桩1中纵筋的直径4~6mm,次抗滑桩4中箍筋的直径小于主抗滑桩1中箍筋的直径2~4mm。其中,位于次抗滑桩4中部的箍筋6间距小于其上部和下部的箍筋6间距,即中部箍筋6加密;而中部加密的箍筋6间距为其他部分箍筋6间距的一半。The secondary anti-slide pile 4 is provided with longitudinal bars 7 and stirrups 6, the longitudinal bars 7 are evenly arranged along the circumference of the secondary anti-slide pile 4, and the stirrups 6 are connected with the longitudinal bars 7 through hooks. The diameter of the longitudinal reinforcement in the secondary anti-slide pile 4 is 4-6mm smaller than the diameter of the longitudinal reinforcement in the main anti-slide pile 1, and the diameter of the stirrup in the secondary anti-slide pile 4 is 2-4mm smaller than the diameter of the stirrup in the main anti-slide pile 1. Among them, the distance between the stirrups 6 in the middle of the secondary anti-slide pile 4 is smaller than the distance between the stirrups 6 in the upper and lower parts, that is, the distance between the stirrups 6 in the middle is denser; and the distance between the stirrups 6 in the middle is half of the distance between the stirrups 6 in other parts.
同排的相邻两个主抗滑桩1之间浇筑连接有主冠梁2;每个次抗滑桩4与相邻两个主抗滑桩1之间分别浇筑连接有次冠梁3。主冠梁2和次冠梁3通过混凝土浇筑而成,可以是素混凝土梁,也可以是钢筋混凝土梁。每个主冠梁2和其下部对应的两个次冠梁3围成的三角形区域内设置有绿化带,能够起到美观作用。A main crown beam 2 is poured and connected between two adjacent main anti-slide piles 1 in the same row; a secondary crown beam 3 is poured and connected between each secondary anti-slide pile 4 and two adjacent main anti-slide piles 1 . The main crown beam 2 and the secondary crown beam 3 are formed by pouring concrete, which may be plain concrete beams or reinforced concrete beams. A green belt is arranged in the triangular area surrounded by each main crown beam 2 and the corresponding two secondary crown beams 3 below it, which can play an aesthetic role.
上述防治滑坡的群桩结构施工方法,其具体步骤如下:The pile group structure construction method of above-mentioned prevention and control landslide, its concrete steps are as follows:
用经纬仪精确确定主抗滑桩1、次抗滑桩4的位置,精确度需控制在1mm范围内。Use theodolite to accurately determine the positions of the main anti-slide pile 1 and the secondary anti-slide pile 4, and the accuracy must be controlled within the range of 1mm.
人工进行主抗滑桩1的挖孔工作,开始时上部和中部的直径同样大,与中部的最粗直径相等,下部进行缩孔挖孔。主抗滑桩1挖孔方式也可以由人工挖孔替换为钻机钻孔后再进行缩径处理。Manually carry out the digging work of the main anti-slide pile 1. At the beginning, the diameters of the upper part and the middle part are equally large, which are equal to the thickest diameter of the middle part, and the bottom part carries out shrinkage hole digging. The main anti-slide pile 1 digging method can also be replaced by manual digging to drill holes and then reduce the diameter.
用回转钻机进行次抗滑桩4的钻孔。Carry out the drilling of secondary anti-slide pile 4 with rotary drilling rig.
分别预制主抗滑桩1和次抗滑桩4的钢筋笼。The reinforcement cages of the main anti-slide pile 1 and the secondary anti-slide pile 4 are prefabricated respectively.
将预制好的主抗滑桩1和次抗滑桩4的钢筋笼,分别放入已经钻好的主抗滑桩1、次抗滑桩4的孔中,浇筑混凝土,混凝土的强度不低于C15。其中浇筑到主抗滑桩1上部时,应用进行上部缩径处理,具体是用与主抗滑桩1上部形状相同的钢套管将主抗滑桩1的钢筋笼套住,钢套管外侧与孔壁之间的间隙用边坡自然土回填,接着继续进行混凝土浇筑,直至完成主抗滑桩1的成型。Put the prefabricated steel cages of the main anti-slide pile 1 and the secondary anti-slide pile 4 into the drilled holes of the main anti-slide pile 1 and the secondary anti-slide pile 4 respectively, and pour concrete. The strength of the concrete is not less than C15. When pouring to the upper part of the main anti-slide pile 1, the upper part should be reduced in diameter. Specifically, the steel cage of the main anti-slide pile 1 is covered with a steel casing with the same shape as the upper part of the main anti-slide pile 1. The outside of the steel casing The gap between the hole wall and the hole wall is backfilled with slope natural soil, and then concrete pouring is continued until the main anti-slide pile 1 is formed.
浇筑主冠梁2和次冠梁3,混凝土强度不低于C20,浇筑完成后,主冠梁2和次冠梁3上部盖上草席进行浇水养护7天。The main crown beam 2 and the secondary crown beam 3 are poured, and the concrete strength is not lower than C20. After the pouring is completed, the upper parts of the main crown beam 2 and the secondary crown beam 3 are covered with straw mats for watering and curing for 7 days.
尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式的具体变换,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, without departing from the purpose of the present invention and the scope of protection of the claims, personnel can also make specific changes in many forms, and these all belong to the protection scope of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210389876.0A CN102926389B (en) | 2012-10-15 | 2012-10-15 | Grouped pile structure for preventing and treating landslide and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210389876.0A CN102926389B (en) | 2012-10-15 | 2012-10-15 | Grouped pile structure for preventing and treating landslide and construction method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102926389A CN102926389A (en) | 2013-02-13 |
| CN102926389B true CN102926389B (en) | 2014-12-10 |
Family
ID=47641306
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201210389876.0A Expired - Fee Related CN102926389B (en) | 2012-10-15 | 2012-10-15 | Grouped pile structure for preventing and treating landslide and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102926389B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103643686A (en) * | 2013-12-19 | 2014-03-19 | 中南大学 | Retaining structure of water-saturated landslide with gradual slope ratio and construction method |
| CN104404971B (en) * | 2014-11-26 | 2016-05-18 | 重庆大学 | A kind of Anti-sliding stopping structure and high cut slope reinforcement construction method thereof |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100473375B1 (en) * | 2002-07-03 | 2005-03-10 | (주)세일엔지니어링 | Retaining wall using phc pile |
| CN202081419U (en) * | 2011-05-26 | 2011-12-21 | 中国建筑第七工程局有限公司 | Squeezed branch pile |
| CN202323970U (en) * | 2011-11-26 | 2012-07-11 | 山东大学 | Combined reinforcement system for side slope |
| CN202323969U (en) * | 2011-11-25 | 2012-07-11 | 中冶集团武汉勘察研究院有限公司 | Retaining structure of delta-shaped double-row antiskid piles |
| CN202881964U (en) * | 2012-10-15 | 2013-04-17 | 中国建筑第六工程局有限公司 | Pile structure capable of preventing and treating landslide |
-
2012
- 2012-10-15 CN CN201210389876.0A patent/CN102926389B/en not_active Expired - Fee Related
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100473375B1 (en) * | 2002-07-03 | 2005-03-10 | (주)세일엔지니어링 | Retaining wall using phc pile |
| CN202081419U (en) * | 2011-05-26 | 2011-12-21 | 中国建筑第七工程局有限公司 | Squeezed branch pile |
| CN202323969U (en) * | 2011-11-25 | 2012-07-11 | 中冶集团武汉勘察研究院有限公司 | Retaining structure of delta-shaped double-row antiskid piles |
| CN202323970U (en) * | 2011-11-26 | 2012-07-11 | 山东大学 | Combined reinforcement system for side slope |
| CN202881964U (en) * | 2012-10-15 | 2013-04-17 | 中国建筑第六工程局有限公司 | Pile structure capable of preventing and treating landslide |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102926389A (en) | 2013-02-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105041333B (en) | It is a kind of first to fill out the method for digging method processing Tunnel Landslide afterwards | |
| CN102134998B (en) | Construction method for wind-blown sand tunnel | |
| CN107605489A (en) | Three line Large span tunnel inclined shafts enter positive cavity construction method | |
| CN103758123A (en) | Method for constructing protecting wall lining of cast-in-place manual hole digging pile | |
| CN110219671B (en) | Construction method of unloading arch backfill structure penetrating through large filling-free karst cave tunnel | |
| CN204401385U (en) | A kind of road structure processing Deep Thick Soft Ground karst foundation | |
| CN109209389A (en) | Hazy tunnel construction method | |
| CN104532714A (en) | Roadbed structure for treating deep soft soil karst foundation | |
| CN102926389B (en) | Grouped pile structure for preventing and treating landslide and construction method thereof | |
| CN108360535A (en) | Foundation pit supporting construction based on campshed and inner support and its construction method | |
| CN204435407U (en) | A kind of batter post group anchor formula rock foundation | |
| CN104404971B (en) | A kind of Anti-sliding stopping structure and high cut slope reinforcement construction method thereof | |
| CN114233301B (en) | Tunnel hole entering construction method for stabilizing mountain under large-bias terrain | |
| CN202881964U (en) | Pile structure capable of preventing and treating landslide | |
| CN102877473A (en) | Skirt pile and soil coupled slid-resistant structure | |
| CN115595979A (en) | Construction method for treating karst cave by bridge pile foundation under geological condition of strong development of karst | |
| CN201502065U (en) | A type of composite foundation for bolt combined excavation | |
| CN110528540B (en) | Drainage slide-resistant pile structure with embedded pile columns and construction method thereof | |
| CN104480947A (en) | Construction method of prestress cast-in-place pile and soil cement pile engagement support | |
| CN105370306B (en) | The massif tunnel excavation construction method of vertical pre-reinforcement processing | |
| CN218894091U (en) | Utilize integrated cantilever pile supporting construction of hardening road | |
| CN205154205U (en) | A vertical pre -reinforcing handles structure for massif tunnel excavation | |
| CN204080792U (en) | A kind of embedding rock Anchor anti-slide piles of combined type implanting round steel | |
| CN202672165U (en) | Grouting water-blocking cofferdam | |
| CN210086253U (en) | A composite pile structure for water-rich and ultra-thick sand and pebble foundation pits |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141210 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |