CN102915337A CN2012103481841A CN201210348184A CN102915337A CN 102915337 A CN102915337 A CN 102915337A CN 2012103481841 A CN2012103481841 A CN 2012103481841A CN 201210348184 A CN201210348184 A CN 201210348184A CN 102915337 A CN102915337 A CN 102915337A
Authority
CN
China
Prior art keywords
model
data
information
electrical network
version
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103481841A
Other languages
Chinese (zh)
Other versions
CN102915337B (en
Inventor
王丽敏
杨国生
周泽昕
王晓阳
杜丁香
李清勉
沈晓凡
张烈
王文焕
申华
王珏
吴春亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN201210348184.1A priority Critical patent/CN102915337B/en
Publication of CN102915337A publication Critical patent/CN102915337A/en
Application granted granted Critical
Publication of CN102915337B publication Critical patent/CN102915337B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Abstract

The invention discloses a variation quantity mode-based hierarchical management method for a fine multistage power grid model. The accuracy and the efficiency in generating, maintaining and applying a power grid model are ensured by adopting three different corresponding methods according to three different stages during the interaction process of various stages of power grid models. During the process of generating the fine power grid model, only an equipment model and a network topology structure model within the scheduling authority scope are analyzed by identifying a scheduling authority; during the maintaining stage, the process of generating and analyzing the power grid model and the interaction process of data files based on the variation quantity are accomplished through a multi-version management technique of the databank and the resource end control to the data change; and during the data application stage, the change information of the power grid model is identified, the information about the variation quantity of the fine power grid model is obtained, the process of generating and analyzing the power grid model based on the variation quantity and the interaction process of the data files are accomplished, and application data are generated through the multi-version management technique of the databank. The accuracy and the efficiency in analyzing and splicing the power grid model are improved.

Description

A kind of layer-management method of the multistage electrical network refined model based on the variable quantity pattern
Technical field
The present invention relates to field of power, be specifically related to a kind of layer-management method of the multistage electrical network refined model based on the variable quantity pattern.
Background technology
At present, electric power system dispatching generally adopts the mode of graded dispatching, the electrical network of the thread administration different range of different stage, but fundamentally, which rank of thread is the interconnected attribute of power system delamination and subarea no matter determined again, its target all is the model of same interconnected network, in order to guarantee electric network model data's consistency and sharing, be necessary to set up concentrated the whole network refined model for this unified interconnected network, and can carry out layer-management and maintenance to this whole network refined model.Described electrical network refined model refers to the electric network model without equivalent network that is described according to actual electric network physical topological structure and actual electric network device model in the present invention.
Principle in line with " source is safeguarded; the overall situation is shared ", scheduling institutions at different levels are according to the dispatching of power netwoks compass of competency, be responsible for the basic data of electrical network actual physics object and the maintenance of model, realize the splicing of electric network model between the scheduling institutions at different levels by horizontal and the mutual mode of longitudinal data, after being spliced into the unified interconnected network model of the whole network, threads at different levels all carry out based on the whole network refined model application and the maintenance of data.
The electric network model of thread is based on IEC61970CIM(Commom Information Model at present) model and extended model thereof, based on CIM/XML or CIM/E(electric power system data markup language-E linguistic norm) the file layout statement.The electric network model that is dispersed in dispatching systems at different levels based on the CIM model being carried out effective integration, form the whole network refined model of a detailed complete, is a very complicated job, and it is accurate, efficient to accomplish.At present, for the mutual research work of dispatching system electric network models at different levels mainly for electric network model based on the CIM model splicing, to pay close attention to more the research of accuracy based on the Bonding Problem of the electric network model of CIM model, to in the model splicing process fast, high efficiency research is less, but splicing speed and efficiency are again to guarantee the practical key factor of splicing, thus be necessary to how to improve the whole network model generation, the efficiency in maintenance and application stage is studied.
Summary of the invention
For the deficiencies in the prior art, the invention provides a kind of layer-management method of the multistage electrical network refined model based on the variable quantity pattern, guarantee the accuracy of electric network model, improve parsing and the splicing efficient of electric network model, simultaneously, guarantee the minimum renewal that electric network model changes, thereby reach the formation speed of raising the whole network model and the purpose of high maintenance and efficient application.
The layer-management method of a kind of multistage electrical network refined model based on the variable quantity pattern provided by the invention, its improvements are, according to three different phases in the electric network model reciprocal processes at different levels, be generation phase, maintenance phase and the application stage of electrical network refined model, adopt corresponding three kinds of diverse ways to guarantee the high efficiency of the accuracy of electric network models and model generation, maintenance and application process.
Wherein, at the generation phase of electrical network refined model, by the identification to the scheduling authority, only resolve device model and network topology structure model in this scheduling extent of competence.
Wherein, at the maintenance phase of electrical network refined model, by many version managements technology of database and to the source control that data change, finish electric network model generation, parsing and data file reciprocal process based on variable quantity.
Wherein, in the market demand stage of electrical network refined model, many version managements technology by database, the change information of identification electric network model, obtain the information of electrical network refined model variable quantity, finish electric network model generation, parsing and data file reciprocal process based on variable quantity, and generate application data.
Wherein, described generation phase at the electrical network refined model, by the identification to the scheduling authority, only resolve device model and network topology structure model in this scheduling extent of competence, refer to according to grid equipment " source is safeguarded; the overall situation is shared " principle, all grid equipment models and network topology structure model all are as the criterion with the model data that scheduling institution under the equipment provides, for the data that belong to different scheduling extents of competence in the same transformer station, according to the division of scheduling authority, the model data that adopts respectively the different stage thread to provide; For the interconnection between each zone, the electric network model that adopts its upper level dispatching office to provide.
Wherein, at the generation phase of electrical network refined model, behind the device model in resolving step by step scheduling extents of competence at different levels and the successively splicing generation the whole network refined model, in the database of threads at different levels, generate the basic version of thread device models at different levels.
Wherein, at electrical network refined model maintenance phase, by many version managements technology of database and the source control that data are changed, finish electric network model generation, parsing and data file reciprocal process based on variable quantity and refer to principle according to " source maintenance ", the entrance that maintenance is provided in its scheduling authority compass of competency that is maintained in to grid equipment model and network topology structure, provide the means of interpolation, modification and the deletion of device model data, the instrument that provides network topology structure to revise; Wherein, variable quantity information comprises the change to interpolation operation, retouching operation, deletion action and the network topology structure of grid equipment model data;
After variable quantity generated, the vestige that preservation equipment and topological structure are revised was saved to database by coming into force of model is machine-processed with variable quantity information, generates the database version based on variable quantity information.
Wherein, maintenance phase at the electrical network refined model, for the version management of database take different scheduling jurisdiction scopes as the basis, the version that electric network model in each different scheduling jurisdiction scope is safeguarded unity at the thread of different stage, in the process of database version management, the descriptive information of maintenance release rise time dot information and version.
Wherein, at electrical network refined model maintenance phase, by many version managements technology of database and to the source control that data change, in electric network model generation, parsing and data file reciprocal process, be based on the variable quantity information realization, be not based on the whole network complete model and realize.
Wherein, in the market demand stage of electrical network refined model, the data synchronization applications between subordinate and the higher level's thread is divided into two kinds of patterns:
(1) subordinate's thread is according to business demand, from higher level's thread obtain, the mode of renewal and application data;
(2) higher level's thread generates the data of redaction, automatically is updated to all threads of subordinate, so that the database of all threads remains the redaction of the whole network refined model.
Wherein, in the application process stage of electrical network refined model, in the application model (1), the process of data acquisition, renewal and application is as described below:
For subordinate's dispatcher-controlled territory data base management system (DBMS), the application of obtaining the whole network model is for the first time obtained the whole network refined model information from higher level's thread, preserves the latest version information of dispatcher-controlled territory data at different levels in this electric network model in local data base;
Market demand process next time, at first upload the database latest version information of the thread in the local range of application of preserving, higher level's thread data base management system (DBMS) is according to the comparison of scope and the database latest version information of request of data, judgement requesting party database is no to be present latest edition, if not present latest edition, the data that then record in this scheduling extent of competence need to upgrade;
After database version in all request scheduling extents of competence checked, obtain the latest edition data of all dispatcher-controlled territories that need to upgrade, generation reaches down the dispatcher-controlled territory system of submitting request to based on the CIM/XML of IEC61970CIM model or the electric network model variable quantity data interaction file of CIM/E form;
Obtain in the subdispatch system of the whole network refined model, obtain the up-to-date variable quantity information of required electric network model, and preserve the latest version information (this version is consistent with higher level's thread version information) of respective change amount information.
Obtain the operation system of the subdispatch system of the whole network refined model and use the latest edition variable quantity information that obtains based on the model information in original local data base and this, merge the up-to-date electric network model information of generation, carry out service application.
Wherein, in the application process stage of electrical network refined model, in the application model (2), the process of data acquisition and renewal and application is as described below:
Be responsible for the inspection of database version and the work for the treatment of of Data Update by the data base management system (DBMS) of higher level's thread;
Higher level's data base management system (DBMS) checks the database version information of removing outer other dispatcher-controlled territories of dispatcher-controlled territory to be updated in the dispatcher-controlled territory data base management system (DBMS) to be updated, to dispatch version consistent with the higher level to check version information, if, then ignore, do not do update mark, need to upgrade otherwise be recorded as, after checking out All Ranges, the zone of upgrading based on needs generates based on the CIM/XML of IEC61970CIM model or the electric network model variable quantity data interaction file of CIM/E form, the lower dispatcher-controlled territory system of submitting request to that reaches;
In subordinate's dispatching system, obtain the up-to-date variable quantity information of All Ranges electric network model, and preserve the latest version information (this version is consistent with higher level's thread version information) of respective change.
The operation system of thread is used the latest edition variable quantity information that obtains based on the model information in original local data base and this, merges to generate up-to-date electric network model information, carries out service application.
Wherein, in the application process stage of electrical network refined model, any one application model, equal many version managements technology by database, the file interaction, model analyzing and the market demand that carry out based on the variable quantity information of electric network model.
Compared with the prior art, beneficial effect of the present invention is:
The present invention is at the generation phase of the whole network refined model, by the identification to the scheduling authority, only resolve device model and network topology structure model in this scheduling extent of competence, reduced unnecessary model analyzing work, improved the efficient of model analyzing and the whole network model splicing.
The present invention successively uploads the electric network model file according to dispatching of power netwoks mechanism rank order from low to high, successively resolves splicing, finally forms the whole network refined model.The present invention is take the scheduling authority as guaranteed the accuracy of electric network model according to the parsing electric network model, and accuracy reaches 100%; On the other hand, the method for successively resolving has from bottom to top guaranteed not repeat in the process analysis work that electric network model is resolved, and each equipment is only resolved once, avoids repeated resolution, makes to resolve the workload minimum, reaches the raising resolution speed, increases the purpose of analyzing efficiency.
The present invention is at the whole network refined model maintenance phase, by many version managements technology of database and the source control that data are changed, realization is based on electric network model generation, parsing and the data file reciprocal process of variable quantity, guaranteed that data file mutual between the threads at different levels is minimum, the workload of Data Analysis is minimum, simultaneously, and based on the database version control of variable quantity information, guaranteed the minimum of storage space of database, data query is fastest.
The present invention is in the market demand stage based on the whole network refined model, many version managements technology by database, the change information of identification electric network model, only obtain the information of the up-to-date variable quantity of electric network model, realization reaches the quantity of information that reduces the data interaction file and the effect that improves model analyzing efficient based on electric network model generation, parsing and the data file reciprocal process of variable quantity.
The present invention is in the market demand stage based on the whole network refined model, which kind of pattern no matter, which kind of application mode, many version managements technology by database, the data interaction that can both guarantee electric network model is based on the file interaction that the variable quantity information of electric network model is carried out, in resolving, also just resolve the changing unit of electric network model, guaranteed that data file mutual between the threads at different levels is minimum, the workload of Data Analysis is minimum, simultaneously, and based on the database version control of variable quantity information, guaranteed the minimum of storage space of database, data query is fastest.
Description of drawings
Fig. 1 be three phases provided by the invention three in distinct methods;
Fig. 2 provided by the inventionly transfers, respectively distinguishes the regulation and control center, economizes three grades of dispatching of power netwoks models that are adjusted to example with state;
Fig. 3 is that state provided by the invention transfers, respectively distinguishes the regulation and control center, economizes the procedure chart of transferring three grades of dispatching of power netwoks models to form the whole network refined model from bottom to top;
Fig. 4 is that a certain province provided by the invention transfers electric network model maintenance process figure;
Fig. 5 is the whole network model data maintenance process figure provided by the invention;
Fig. 6 is that certain province provided by the invention transfers the application process based on the whole network model.
Embodiment
Below in conjunction with accompanying drawing the specific embodiment of the present invention is described in further detail.
The present invention proposes a kind of layer-management method of the multistage electrical network refined model based on the variable quantity pattern, according to three different phases in the electric network model reciprocal processes at different levels, adopt three kinds of corresponding distinct methods to guarantee the high efficiency of the accuracy of electric network model and model generation, maintenance and application process, as shown in Figure 1.For making purpose of the present invention, method, technical scheme and advantage clearer and more definite, regulate and control the center, economize and transfer three grades of scheduling models as example take state's accent, the subregion of actual electric network below in conjunction with accompanying drawing, the method for the invention is described in further details.
The present invention transfers three grades of dispatching of power netwoks models as example take state's accent, subregion regulation and control center, province; in conjunction with the integrated business demand of adjusting the computational data platform of the whole network relay protection; the specific implementation process of each method of the present invention is described; described integrated adjusting calculated the calculating of adjusting that refers to based on the whole network refined model in the present invention; in the process of calculating of adjusting, the Value Data such as do not adopt.The integrated computational data platform of adjusting of the whole network relay protection is responsible for the management of the whole network relay protection professional equipment and the computational data of adjusting; generate the refined model of the whole network relay protection specialty relevant device and network topology structure in this data platform, the personnel of threads protection specialties at different levels use this whole network refined model and carry out the calculating of adjusting based on the whole network refined model.
In the initial relay protection specialty electric network model of scheduling at different levels; each provincial thread, subregion regulation and control center and state transfer safeguard respectively own scheduling extent of competence interior with the electric network model relay protection specialty; adopt equivalent method to process to other electrical networks that are attached thereto; this will certainly affect the precision that relay protection setting calculates; so be necessary to generate the whole network refined model; for calculating, relay protection setting provides more meticulous model; improve the precision of adjusting and calculating, satisfy the under the new situation computation requirement of adjusting of interconnected network.
Among this embodiment, state transfers, subregion is regulated and control the center, economize three grades of dispatching of power netwoks models of accent as shown in Figure 2.The generative process of the whole network refined model comprises two parts, a part is the process that is generated longitudinally higher level's electric network model by subordinate's dispatching of power netwoks model splicing, and this process refers to dispatch electric network model and a plurality of process that the complete higher level who comprises subordinate's dispatching of power netwoks model dispatches the whole network model of subordinate's dispatching of power netwoks model splicing generation based on the IEC61970CIM model by a higher level based on the IEC61970CIM model; Another part refers to that horizontal grid model splicing a plurality of at the same level forms the process of the whole network refined model.Generate in the process of the whole network refined model at the electric network model of adjusting a wage scale based on province's accent electric network model, subregion regulation and control center electric network model, state, subregion is regulated and control the center under at first by provinces at different levels accent the relay protection specialty electric network model in its scheduling extent of competence being uploaded to it, be responsible for the electric network model of each provincial scheduling resolves by the integrated computational data platform of adjusting of relay protection of subregion regulation and control centre grade, and resolve one's duty and regulate and control the interior electric network model of central dispatching extent of competence, these models are spliced, form the electrical network refined model in this subregion regulation and control center range; Finish based on behind the electrical network refined model in this subregion regulation and control center range based on said process at each subregion regulation and control center; being uploaded to state transfers in the integrated computational data platform of adjusting of relay protection; state transfers and is responsible for resolving the electrical network refined model that upload at each subregion regulation and control center; and the electric network model in the parsing state key degree extent of competence; these models are spliced; form the electrical network refined model of relay protection specialty in the network-wide basis, for the integrated computing application of adjusting of thread relay protection specialty at different levels.
In the generative process of above-mentioned the whole network refined model, the parsing of model and splicing and method are followed following method:
Belong to the device models in the different scheduling extents of competence in vertical model analyzing process in to same station, the device parameter that the thread of different stage provides may be inconsistent, adopts which parameter just to become one of key factor that guarantees model accuracy; In horizontal model splicing process, processing to interconnection is one of key issue, the parameter information of the described interconnection of electrical network in different zones may be inconsistent, and the parameter accuracy that how to guarantee interconnection also is the key point that guarantees the whole network model accuracy.According to grid equipment " source is safeguarded; the overall situation is shared " principle, namely whose scheduling, the principle of whose maintenance, the present invention all is as the criterion with the model data that scheduling institution under this equipment provides to all grid equipment models in order to guarantee the accuracy of electric network model, for the equipment that belongs to different scheduling extents of competence in the same transformer station, according to the division of scheduling authority, the model data that adopts respectively the different stage thread to provide is ignored the data that are not that affiliated extent of competence provides.For the interconnection between each zone, usually dispatch authority at the upper level thread, the electric network model that adopts the upper level dispatching office to provide neglects the model data that subordinate's thread provides.
According to dispatching of power netwoks mechanism rank order from low to high, the electric network model file is successively uploaded, successively resolve splicing, finally form the whole network refined model, its procedure chart is as shown in Figure 3.
Concrete, after next stage (as economize transferring) electric network model File Upload is to upper level (such as subregion regulation and control center) the integrated computational data platform of adjusting of relay protection, realize the longitudinal spliced of electric network model, in longitudinal spliced process, at first resolve the electric network model of economizing the scheduling authority of adjusting a wage scale, in resolving, only resolve the device model of economizing in the scheduling authority compass of competency of adjusting a wage scale, for the device model in the subregion regulation and control centre grade scheduling authority compass of competency, ignore and will not resolve, but the parsing of the topological relation between reservation and the subregion regulation and control centre grade scheduling extent of competence equipment; Having resolved province adjusts a wage scale behind the electric network model file that scheduling institution provides, resolve again the electric network model file that subregion regulation and control centre grade scheduling institution provides, equally, in the process of resolving, only resolve the device model in the subregion regulation and control centre grade scheduling authority compass of competency, for the adjust a wage scale equipment of scheduling authority compass of competency of province, because in the electric network model that scheduling provides is adjusted a wage scale by province, be parsed, need not to finish at subregion regulation and control centre grade; Equipment for subregion regulation and control centre grade higher level scheduling (state's accents) authority compass of competency need not to resolve, and waits until subregion and regulates and control the resolving that the center higher level dispatches electric network model and finish; For province adjust a wage scale or subregion regulation and control centre grade scheduling institution electric network model between interconnection because its scheduling authority also need not to resolve in separately upper level scheduling, wait until the resolving that higher level separately dispatches electric network model and finish; By that analogy, the grid model splicing process that each subregion regulation and control center to state transfers is also followed said process, forms the whole network refined model.
By the application of above-described embodiment, proved that the present invention can reach assurance electric network model accuracy, improves the purpose of model analyzing speed and efficient.
After the integrated computing platform of adjusting of relay protection generates the whole network refined model, in database, generate the basic version of each device model.To the maintenance phase of the whole network model, the maintenance of relay protection device model in the scheduling extents of competence at different levels is realized based on following method:
Principle in line with " source maintenance ", the maintenance of grid equipment model and network topology structure is only provided the entrance of maintenance in its scheduling authority compass of competency, provide interpolation, the modification of device data, the means of deletion, the instrument that provides network topology structure to revise.In the present invention, to interpolation, modification and the deletion action of grid equipment model data, and the change of network topology structure, all be considered as the variable quantity information of electric network model.Behind the variable quantity Information generation, the vestige that retaining device and topological structure are revised generates the new database version based on all changes amount information.
Concrete, after province transfers the electric network model modification to finish, database latest edition based on all changes amount information, generation is based on the CIM/XML form of IEC61970CIM model (comprising its extended model) or the data interaction file of CIM/E form, is uploaded in the subregion regulation and control centre data platform by province's thread of adjusting a wage scale.Subregion regulation and control center is carried out the Piece file mergence of variable quantity model based on what the electric network model file of variable quantity and subregion regulation and control center generated based on the electric network model file of variable quantity in conjunction with what all provinces adjusted a wage scale that thread uploads, generation is based on the variable quantity message file at subregion regulation and control center, resolve for this variable quantity message file at subregion regulation and control center, generate the database latest edition based on all changes amount information at subregion regulation and control center.With legacy data storehouse versions merging, generated the meticulous electric network model of redaction that comprises in subregion regulation and control center and the each province's key degree authority compass of competency in the subregion regulation and control central dispatching extent of competence.By that analogy, upwards generate the whole network refined model that state more adjusts a wage scale by each subregion regulation and control center, follow equally said process.
In the process that above-mentioned electric network model is safeguarded, the problem of paying special attention to is the consistance in order to guarantee that threads at different levels are described electric network model in the same scheduling jurisdiction scope, version management for database will be take different scheduling jurisdiction scopes as the basis, the version that electric network model in each different scheduling jurisdiction scope is safeguarded unity at the thread of different stage, simultaneously, in the process of database version management, the time point information that maintenance release generates and the brief information of redaction data.
The present invention is in the whole network model maintenance stage, by many version managements technology of database and the source control that data are changed, realization is based on electric network model generation, parsing and the data file reciprocal process of variable quantity, guaranteed that data file mutual between the threads at different levels is minimum, the workload of Data Analysis is minimum, simultaneously, and based on the database version control of variable quantity information, guaranteed the minimum of storage space of database, data query is fastest.
Take a certain provincial power network model as example, the process that electric network model in self scheduling extent of competence is safeguarded is described, as shown in Figure 4.In to this process that electric network model is safeguarded inside the province, take the factory station as unit, safeguard the variable quantity information of this factory's station equipment.In the maintenance process of electric network model, the variable quantity information of initial all electric network models all is kept at buffer zone, before variable quantity information is applied to database, introduce the model mechanism that comes into force, after confirming that model comes into force, with all variable quantity information write into Databasces, generation is based on the database version of up-to-date variable quantity information, when the generating database redaction, preserve the time that version generates, be convenient to differentiate the data model version rise time that different threads at different levels are uploaded according to the time period in the whole network model.The introducing of the model mechanism of coming into force can be avoided the modification process of electric network model arbitrarily is applied in the whole network model.
After the integrated computational data platform of adjusting of threads at different levels is finished the maintenance process of electric network model in self scheduling extent of competence, realize the maintenance process to the whole network refined model, as shown in Figure 5.Judge whether interior all threads of network-wide basis have the latest data storehouse version based on variable quantity information, if having, the variation that electric network model is arranged in network-wide basis are described then, its variable quantity need to be applied to the whole network refined model.The process that is applied to the whole network refined model comprises that province transfers to the step by step application that subregion regulation and control center to state transfers, and the process of uploading is step by step uploaded the file interaction based on CIM/XML or CIM/E form step by step.
After the integrated computational data platform of adjusting of relay protection generates the whole network refined model, the market demand stage of threads at different levels, economize the integrated computing application of adjusting of accent as example take certain, illustrate based on market demand process of the present invention, as shown in Figure 6.Transfer the integrated requirement of adjusting and calculating according to state; in order to adapt to the demand of interconnected network; the calculation requirement of adjusting to relay protection device calculates based on the whole network refined model; can not do equivalent the processing; so when threads at different levels are adjusted calculating to the relay protection device in the affiliated scheduling extent of competence, all need obtain the whole network refined model.Economize adjustment with certain and surely be calculated as example, transfer request based on this province tuning state, the pattern of obtaining the whole network model is example, describes.After state transfers and receives the request of obtaining the whole network model, judge at first whether this province's accent obtains the whole network model for the first time, if obtain the whole network model for the first time, then issue the whole network model data, this province reconciles to analyse removes the electric network model that this province transfers all threads in addition, be saved to the database latest edition, database version was consistent during this version and state transferred.If not obtaining for the first time the whole network model, state transfer judge electric network model database version that this province removes all threads of this province beyond transferring in transferring whether with the state adjusting system in consistent, if inconsistent, be recorded as need to renewal state.Behind completeer all thread database versions, state transfers the up-to-date variable quantity information based on all threads that need to upgrade, generation is based on the CIM/CML of IEC 61970CIM model or the mutual files of CIM/E form, being issued to this province transfers, this province transfers all changes amount information is resolved, and generates the latest edition data that this province transfers, with original edition data storehouse models coupling, generate up-to-date the whole network refined model, carry out the integrated calculating of adjusting.
Should be noted that at last: above embodiment is only in order to illustrate that technical scheme of the present invention is not intended to limit, although with reference to above-described embodiment the present invention is had been described in detail, those of ordinary skill in the field are to be understood that: still can make amendment or be equal to replacement the specific embodiment of the present invention, and do not break away from any modification of spirit and scope of the invention or be equal to replacement, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (13)

1. layer-management method based on the multistage electrical network refined model of variable quantity pattern, it is characterized in that, according to three different phases in the electric network model reciprocal processes at different levels, be generation phase, maintenance phase and the application stage of electrical network refined model, adopt corresponding three kinds of diverse ways to guarantee accuracy and and the high efficiency of model generation, maintenance and application process of electric network models.
2. the layer-management method of multistage electrical network refined model as claimed in claim 1 is characterized in that, at the generation phase of electrical network refined model, by the identification to the scheduling authority, only resolves this scheduling extent of competence interior device model and network topology structure model.
3. the layer-management method of multistage electrical network refined model as claimed in claim 1, it is characterized in that, maintenance phase at the electrical network refined model, by many version managements technology of database and to the source control that data change, finish electric network model generation, parsing and data file reciprocal process based on variable quantity.
4. the layer-management method of multistage electrical network refined model as claimed in claim 1, it is characterized in that, in the market demand stage of electrical network refined model, many version managements technology by database, the change information of identification electric network model, obtain the information of electrical network refined model variable quantity, finish electric network model generation, parsing and data file reciprocal process based on variable quantity, and generate application data.
5. the layer-management method of multistage electrical network refined model as claimed in claim 2, it is characterized in that, described generation phase at the electrical network refined model, by the identification to the scheduling authority, only resolve device model and network topology structure model in this scheduling extent of competence, refer to according to grid equipment " source is safeguarded; the overall situation is shared " principle, all grid equipment models and topological structure model all are as the criterion with the model data that scheduling institution under the equipment provides, for the data that belong to different scheduling extents of competence in the same transformer station, according to the division of scheduling authority, the model data that adopts respectively the different stage thread to provide; For the interconnection between each zone, the electric network model that adopts its upper level dispatching office to provide.
6. the layer-management method of multistage electrical network refined model as claimed in claim 2, it is characterized in that, generation phase at the electrical network refined model, after device model in resolving step by step scheduling extents of competence at different levels and the splicing that successively makes progress generate the whole network refined model, in the database of threads at different levels, generate the basic version of thread electrical network refined models at different levels.
7. the layer-management method of multistage electrical network refined model as claimed in claim 3, it is characterized in that, at electrical network refined model maintenance phase, by many version managements technology of database and the source control that data are changed, the electric network model of finishing based on variable quantity generates, parsing and data file reciprocal process refer to the principle according to " source maintenance ", the entrance that maintenance is provided in its scheduling authority compass of competency that is maintained in to grid equipment model and network topology structure, the interpolation of device model data is provided, the means of revising and deleting, the instrument that provides network topology structure to revise; Wherein, variable quantity information comprises the change to interpolation operation, retouching operation, deletion action and the network topology structure of grid equipment model data;
After variable quantity generated, the vestige that preservation equipment and topological structure are revised was saved to database by coming into force of model is machine-processed with variable quantity information, generates the database version based on variable quantity information.
8. the layer-management method of multistage electrical network refined model as claimed in claim 3, it is characterized in that, maintenance phase at the electrical network refined model, for the version management of database take different scheduling jurisdiction scopes as the basis, the version that electric network model in each different scheduling jurisdiction scope is safeguarded unity at the thread of different stage, in the process of database version management, the descriptive information of maintenance release rise time dot information and version.
9. the layer-management method of multistage electrical network refined model as claimed in claim 3, it is characterized in that, at electrical network refined model maintenance phase, by many version managements technology of database and to the source control that data change, in electric network model generation, parsing and data file reciprocal process, be based on the variable quantity information realization.
10. the layer-management method of multistage electrical network refined model as claimed in claim 4 is characterized in that in the market demand stage of electrical network refined model, the data synchronization applications between subordinate and the higher level's thread is divided into two kinds of patterns:
(1) subordinate's thread is according to business demand, from higher level's thread obtain, the mode of renewal and application data;
(2) higher level's thread generates the data of redaction, automatically is updated to all threads of subordinate, so that the database of all threads remains the redaction of the whole network refined model.
11. the layer-management method of multistage electrical network refined model is characterized in that as claimed in claim 10, in the application process stage of electrical network refined model, in the application model (1), the process of data acquisition, renewal and application is as described below:
For subordinate's dispatcher-controlled territory data base management system (DBMS), the application of obtaining the whole network refined model is for the first time obtained the whole network refined model information from higher level's thread, preserves the latest version information of dispatcher-controlled territory data at different levels in this electric network model in local data base;
Market demand process next time, at first upload the database latest version information of the thread in the local range of application of preserving, higher level's thread data base management system (DBMS) is according to the comparison of the information of the scope of request of data and database version, judgement requesting party database is no to be present latest edition, if not present latest edition, the data that then record in this scheduling extent of competence need to upgrade;
After database version in all request scheduling extents of competence checked, obtain the latest edition data of all dispatcher-controlled territories that need to upgrade, generation reaches down the dispatcher-controlled territory system of submitting request to based on the CIM/XML of IEC61970CIM model or the electric network model variable quantity data interaction file of CIM/E form;
Obtain in the subdispatch system of the whole network refined model, obtain the up-to-date variable quantity information of required electric network model, and preserve the latest version information of respective change amount information.
Obtain the operation system of the subdispatch system of the whole network refined model and use the latest edition variable quantity information that obtains based on the model information in original local data base and this, merge the up-to-date electric network model information of generation, carry out service application.
12. the layer-management method of multistage electrical network refined model is characterized in that as claimed in claim 10, in the application process stage of electrical network refined model, in the application model (2), the process of data acquisition and renewal and application is as described below:
Be responsible for the inspection of database version and the work for the treatment of of Data Update by the data base management system (DBMS) of higher level's thread:
Higher level's data base management system (DBMS) checks the database version information of removing outer other dispatcher-controlled territories of dispatcher-controlled territory to be updated in the dispatcher-controlled territory data base management system (DBMS) to be updated, to dispatch version consistent with the higher level to check version information, if, then ignore, do not do update mark, need to upgrade otherwise be recorded as, after checking out All Ranges, the zone of upgrading based on needs generates based on the CIM/XML of IEC61970CIM model or the electric network model variable quantity data interaction file of CIM/E form, the lower dispatcher-controlled territory system of submitting request to that reaches;
In subordinate's dispatching system, obtain the up-to-date variable quantity information of All Ranges electric network model, and preserve the latest version information of respective change.
The operation system of thread merges the up-to-date electric network model information of generation based on the latest edition variable quantity information of the model information in original local data base and the renewal of this electric network model, carries out service application.
13. as claim 11 or 12 arbitrary as described in the layer-management method of multistage electrical network refined model, it is characterized in that, in the application process stage of electrical network refined model, any one application model, equal many version managements technology by database, the file interaction, model analyzing and the market demand that carry out based on the variable quantity information of electric network model.
CN201210348184.1A 2012-09-18 2012-09-18 A kind of tiered management approach of multistage power grid refined model based on variable quantity pattern Active CN102915337B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210348184.1A CN102915337B (en) 2012-09-18 2012-09-18 A kind of tiered management approach of multistage power grid refined model based on variable quantity pattern

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210348184.1A CN102915337B (en) 2012-09-18 2012-09-18 A kind of tiered management approach of multistage power grid refined model based on variable quantity pattern

Publications (2)

Publication Number Publication Date
CN102915337A true CN102915337A (en) 2013-02-06
CN102915337B CN102915337B (en) 2016-09-21

Family

ID=47613704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210348184.1A Active CN102915337B (en) 2012-09-18 2012-09-18 A kind of tiered management approach of multistage power grid refined model based on variable quantity pattern

Country Status (1)

Country Link
CN (1) CN102915337B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103390118A (en) * 2013-08-13 2013-11-13 南方电网科学研究院有限责任公司 Online model interaction method based on power grid operation service bus and public information model synchronizer
CN103684881A (en) * 2013-12-30 2014-03-26 曙光云计算技术有限公司 Network modeling method and device
CN104391872A (en) * 2014-10-29 2015-03-04 江苏省电力公司苏州供电公司 Logic consistency calibration method for single line diagrams of PMS (plant management system) and error prevention system
CN105447175A (en) * 2015-12-09 2016-03-30 中国电力科学研究院 Power grid model sharing method applicable to distributed computation of power system
CN105912691A (en) * 2016-04-21 2016-08-31 国电南瑞科技股份有限公司 Power grid model multi-version multi-tenant management system and method based on distributed storage
CN107392042A (en) * 2017-06-30 2017-11-24 国家电网公司 Electric network data monitoring method and device
CN111107097A (en) * 2019-12-27 2020-05-05 国网四川省电力公司电力科学研究院 Intelligent substation equipment network node linkage failure risk analysis method based on CML

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101540505A (en) * 2009-01-09 2009-09-23 南京南瑞继保电气有限公司 Building method of multistage multi-region interconnected network data model
CN101699454A (en) * 2009-11-02 2010-04-28 国电南瑞科技股份有限公司 Method for exchanging and merging electric network models between control center of electric power system and substation
CN102521398A (en) * 2011-12-23 2012-06-27 清华大学 Modeling method for substation-dispatching center two-level distributed type power grid

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101540505A (en) * 2009-01-09 2009-09-23 南京南瑞继保电气有限公司 Building method of multistage multi-region interconnected network data model
CN101699454A (en) * 2009-11-02 2010-04-28 国电南瑞科技股份有限公司 Method for exchanging and merging electric network models between control center of electric power system and substation
CN102521398A (en) * 2011-12-23 2012-06-27 清华大学 Modeling method for substation-dispatching center two-level distributed type power grid

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈朝晖等: "大型互联电网继电保护整定计算数据一体化管理系统", 《电力系统自动化》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103390118A (en) * 2013-08-13 2013-11-13 南方电网科学研究院有限责任公司 Online model interaction method based on power grid operation service bus and public information model synchronizer
CN103684881A (en) * 2013-12-30 2014-03-26 曙光云计算技术有限公司 Network modeling method and device
CN103684881B (en) * 2013-12-30 2017-01-25 曙光云计算技术有限公司 Network modeling method and device
CN104391872A (en) * 2014-10-29 2015-03-04 江苏省电力公司苏州供电公司 Logic consistency calibration method for single line diagrams of PMS (plant management system) and error prevention system
CN104391872B (en) * 2014-10-29 2018-08-07 江苏省电力公司苏州供电公司 PMS systems and anti-error system line chart logical consistency method of calibration
CN105447175A (en) * 2015-12-09 2016-03-30 中国电力科学研究院 Power grid model sharing method applicable to distributed computation of power system
CN105912691A (en) * 2016-04-21 2016-08-31 国电南瑞科技股份有限公司 Power grid model multi-version multi-tenant management system and method based on distributed storage
CN105912691B (en) * 2016-04-21 2019-08-16 国电南瑞科技股份有限公司 Electric network model multi version multi-tenant management system and method based on distributed storage
CN107392042A (en) * 2017-06-30 2017-11-24 国家电网公司 Electric network data monitoring method and device
CN111107097A (en) * 2019-12-27 2020-05-05 国网四川省电力公司电力科学研究院 Intelligent substation equipment network node linkage failure risk analysis method based on CML

Also Published As

Publication number Publication date
CN102915337B (en) 2016-09-21

Similar Documents

Publication Publication Date Title
CN102915337A (en) Variation quantity mode-based hierarchical management method for fine multistage power grid model
CN103577936B (en) A kind of distributed maintenance of electric network model and globally shared system and its implementation
US8032563B2 (en) Generating a unique representation of physical assets
CN107665122B (en) Automatic updating method of civil engineering BIM (building information modeling)
CN104616101B (en) A kind of integrated power system resource model and foundation and maintaining method
CN103093024A (en) Web geographic information system (WEBGIS)-based visualized showing method for planning power grid
CN104133953A (en) Secondary design system of intelligent substation
CN103577938A (en) Power grid dispatching automation main-and-standby system model synchronizing method and synchronizing system thereof
US20140358492A1 (en) Systems and methods for synchronizing geographic information system (gis) network models
CN103065217A (en) Digital model splicing method of electric power setting calculating system
CN104407576A (en) Realization method for general type production and manufacturing unit and control system thereof
EP2871598A1 (en) System and method for optimizing the management of a gas transportation network
CN109657816A (en) A kind of online check method of substation equipment monitoring information table
CN105447175A (en) Power grid model sharing method applicable to distributed computation of power system
CN103208050A (en) Decision platform for implementing comprehensive power-cut maintenance plan
CN103458022A (en) Multi-user different-place concurrent collaborative system
CN102360470A (en) Information matching method and system for electric power system
CN102880748A (en) Method for automatically drawing electric diagrams
CN102609520A (en) Method for exporting model data of substation by filtering
CN104820890A (en) Electric power dispatching equipment model and power grid production equipment information integration method
CN101639875A (en) Power construction budget estimate planning method and networking system thereof
CN104915794A (en) Multi-time-state full-service unified modeling method based on model center
CN103455662B (en) Pollution area distributed plotting system and method
CN106096835A (en) Model center construction method between based on the isomery dispatching patcher of agency service
CN101957942A (en) Accident planning expert system applied to steel mill

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant