CN102912802B - 一种用于处理后筑式高陡填方边坡的方法 - Google Patents
一种用于处理后筑式高陡填方边坡的方法 Download PDFInfo
- Publication number
- CN102912802B CN102912802B CN201210376973.6A CN201210376973A CN102912802B CN 102912802 B CN102912802 B CN 102912802B CN 201210376973 A CN201210376973 A CN 201210376973A CN 102912802 B CN102912802 B CN 102912802B
- Authority
- CN
- China
- Prior art keywords
- slope
- face
- rammer
- region
- compacting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
一种用于处理后筑式高陡填方边坡的RDCP技术,包括:表层土分区分层换填碾压、中部坡体夯实减少抗剪强度、下部坡体砼面板护坡等技术问题。针对后筑式高陡填土边坡自身的特殊性及其失稳根本原因,以大气降雨临界下渗深度为切入点,提出一种自上而下采用“表层土分区分层换填碾压+中部坡体夯实+下部坡体砼面板护坡”进行高陡填土边坡加固的立体组合处理技术。其优点是:分区分批地对填土区域进行碾压、夯实,避免了边坡碾压边缘效应问题,保证碾压质量,增强了抗剪强度,解决了浅表层及深层整体的局部稳定性问题;在技术方面具有针对性强、可靠性高等优点,在施工方面具有工艺简单、工期短、造价低等优点。
Description
技术领域
本发明涉及后筑式高陡填方边坡的一种加固技术,具体的说是一种自上而下采用“表层土分区分层换填碾压+中部坡体夯实+下部坡体砼面板护坡”联合处理后筑式高陡填方边坡的立体组合加固技术。
背景技术
山区、丘陵地带新建建设工程时,为满足场地平整需要,将会形成大量的高陡填方边坡。填方边坡由于物质成分复杂、结构松散,在大气降雨、地震等不利诱发因素作用下极易产生失稳,造成巨大经济损失。
根据高陡填方边坡加固实施阶段的不同,可分为前筑式和后筑式两种,其中前筑式是指在填方过程中进行边坡加固,主要加固措施有强夯、土工格栅等;后筑式是指在填方完成后进行边坡加固,主要加固措施有挡土墙、抗滑桩、格构锚固等。对于后筑式高陡填方边坡而言,采用单一的抗滑支挡措施加固时,由于填土自身强度低、自稳能力差,达到设计安全标准常需大截面的抗滑桩或多排抗滑桩,且桩间土容易挤出造成治理工程失效;采用单一的锚固措施加固时,由于填土与锚固体的粘结强度较低,达到设计安全标准常需大直径的长预应力锚索,且当填土碎块石含量较高时,成孔难度大、预应力易损失。由此可见,传统加固措施不仅施工工艺复杂、成本高、周期长,而且技术可靠度不高,难以从根源上解决填土边坡的永久稳定性问题,为此有必要从填土边坡自身的特殊性及其变形失稳机理角度来建立该类边坡的治理体系。
发明内容
本发明的目的是针对填土自身的特殊性及其变形失稳根本原因,以大气降雨临界下渗深度为切入点,提出一种自上而下的分层立体组合加固技术,从根源上阻隔导致填土边坡产生变形失稳的通道,提高治理可靠度,降低施工成本,缩短施工工期。
本发明一种用于处理后筑式高陡填方边坡的方法,其步骤如下:
①表层土分区分层换填碾压:将潜在滑移面以上且坡顶面以下3.0m深度范围内的填土采用三七灰土进行换填,并以距坡面3m为界采用不同吨位的振动压路机进行分区分层碾压,即在距离坡面3米以外的区域用14t振动压路机进行碾压,在距离坡面3米以内的区域用2t振动压路机进行碾压;采用此技术来解决大气降雨地表下渗问题;
②中部坡体夯实:对强夯面以下的B区即坡顶面以下3.0~12.0m范围内采用点夯与满夯相结合的强夯方式对该区域内填土进行夯实,形成中部夯实体,同时为避免强夯边缘效应问题,采用H100型夯实机对坡体夯实面进行夯实,以此来增强大气降雨临界下渗深度范围内填土的抗剪强度;
③下部坡体砼面板护坡:对下部砼面板护坡区C(坡顶面以下12.0m深度范围外)采用H100型夯实机对坡体夯实面进行夯实,并顺坡体夯实面砌筑C25砼面板进行护坡,以此解决大气降雨临界下渗深度外填土的稳定性问题。
所述的中部夯实体是按下列方式完成的:首先在强夯面与潜在滑移面交线以下的强夯区铺设10~20cm厚碎石,采用6000KN·m夯击能,按3.5×3.5m间距呈等边三角形布置,对强夯面与潜在滑移面交线的坡体进行点夯,一直到强夯面与坡面交线处且点夯夯点的夯击数不少于6击,并以点夯最后两击平均夯沉量小于0.1m为收踵标准;然后采用1000KN·m夯击能对坡体进行满夯,满夯夯击遍数不少于2遍,夯迹搭接1/4踵印。
本发明一种用于处理后筑式高陡填方边坡的方法,其优点是:分区分批地对填土区域进行碾压、夯实,避免了边坡碾压边缘效应问题,保证碾压质量,增强了抗剪强度,解决了浅表层及深层整体的局部稳定性问题;在技术方面具有针对性强、可靠性高等优点,在施工方面具有工艺简单、工期短、造价低等优点。
附图说明
图1为用于处理后筑式高陡填方边坡的方法处理后筑式高陡填方边典型剖面图。
图2为用于处理后筑式高陡填方边坡的方法中部坡体夯实平面布置图。
图中,1–填方坡面线,2–潜在滑移面,3–强夯面,4–坡体夯实面,5–C25砼面板,6–强夯面与潜在滑移面交线,7–点夯夯点,8–强夯面与坡面交线,A1–距离坡面3米以外的区域,A2–距离坡面3米以内的区域,B–中部坡体夯实区,C–下部砼面板护坡区。
具体实施方式
根椐图1、图2所示:一种用于处理后筑式高陡填方边坡的方法,具体实施步骤如下:
①、表层土分区分层换填碾压:将潜在滑移面2以上且坡顶面以下3.0m深度范围内的填土采用三七灰土进行换填,灰土配合比生石灰:粘性土=3:7,单层换填厚度20~30cm;然后将距坡面3m以外的A1区的换填土采用14t振动压路机进行分层碾压,碾压压实系数不小于0.95;最后将距坡面3m以内的A2区的换填土采用2t振动压路机进行分层碾压,碾压压实系数不小于0.92。
②、中部坡体夯实:对强夯面3以下的B区即坡顶面以下3.0~12.0m范围内,首先采用点夯与满夯相结合的强夯方式对该区域内填土进行夯实,形成中部夯实体;然后采用H100型夯实机对坡体夯实面4进行夯实,夯击数不少于2击,夯迹搭接长度不小于10cm。
③、下部坡体砼面板护坡:对下部砼面板护坡区C区(坡顶面以下12.0m深度范围外),首先采用H100型夯实机对坡体夯实面4进行夯实,夯击数不少于3击,夯迹搭接长度不小于15cm;然后垂直于夯实后坡面,按4.0×4.0m间距呈正方形布置3.0m长土钉;最后在坡体夯实面4上铺设200×200mm间距的钢筋网,并喷射厚150mm的C25砼面板5形成砼面板。
Claims (1)
1.一种用于处理后筑式高陡填方边坡的方法,其特征在于:其步骤如下:
①、表层土分区分层换填碾压:将潜在滑移面(2)以上且坡顶面以下3.0m深度范围内的填土采用三七灰土进行换填,并以距坡面3m为界采用不同吨位的振动压路机进行分区分层碾压,即在距离坡面3米以外的区域用14t振动压路机进行碾压,在距离坡面3米以内的区域用2t振动压路机进行碾压;采用此技术来解决大气降雨地表下渗问题;
②、中部坡体夯实:对强夯面(3)以下的B区即坡顶面以下3.0~12.0m范围内采用点夯与满夯相结合的强夯方式对该区域内填土进行夯实,形成中部夯实体,同时为避免强夯边缘效应问题,采用H100型夯实机对坡体夯实面(4)进行夯实,以此来增强大气降雨临界下渗深度范围内填土的抗剪强度;
③、下部坡体砼面板护坡:对下部砼面板护坡区C即坡顶面以下12.0m深度范围外采用H100型夯实机对坡体夯实面(4)进行夯实,并顺坡体夯实面(4)砌筑C25砼面板(5)进行护坡,以此解决大气降雨临界下渗深度外填土的稳定性问题;
其中,所述的中部夯实体是按下列方式完成的:首先在强夯面与潜在滑移面交线(6)以下的强夯区铺设10~20cm厚碎石,采用6000KN·m夯击能,按3.5×3.5m间距呈等边三角形布置,对强夯面与潜在滑移面交线(6)的坡体进行点夯,一直到强夯面与坡面交线(8)处且点夯夯点(7)的夯击数不少于6击,并以点夯最后两击平均夯沉量小于0.1m为收踵标准;然后采用1000KN·m夯击能对坡体进行满夯,满夯夯击遍数不少于2遍,夯迹搭接1/4踵印。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210376973.6A CN102912802B (zh) | 2012-10-08 | 2012-10-08 | 一种用于处理后筑式高陡填方边坡的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210376973.6A CN102912802B (zh) | 2012-10-08 | 2012-10-08 | 一种用于处理后筑式高陡填方边坡的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102912802A CN102912802A (zh) | 2013-02-06 |
CN102912802B true CN102912802B (zh) | 2015-09-16 |
Family
ID=47611352
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210376973.6A Active CN102912802B (zh) | 2012-10-08 | 2012-10-08 | 一种用于处理后筑式高陡填方边坡的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102912802B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114439020A (zh) * | 2022-01-10 | 2022-05-06 | 中冶华成(武汉)工程有限公司 | 一种强夯边坡及强夯边坡施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101575835A (zh) * | 2009-05-25 | 2009-11-11 | 铁道第三勘察设计院集团有限公司 | 隐式支挡路基结构 |
CN201390968Y (zh) * | 2009-04-15 | 2010-01-27 | 中铁二院工程集团有限责任公司 | 岩土边坡微型桩抗滑构造 |
CN101787689A (zh) * | 2010-03-26 | 2010-07-28 | 中冶实久建设有限公司 | 昔格达土高边坡填方的强夯施工方法 |
CN201908313U (zh) * | 2010-11-26 | 2011-07-27 | 中国水电顾问集团成都勘测设计研究院 | 边坡加固结构 |
CN102704497A (zh) * | 2012-05-31 | 2012-10-03 | 中冶集团武汉勘察研究院有限公司 | 一种用于处理高填方边坡的rpw法技术 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3653551B2 (ja) * | 2001-06-28 | 2005-05-25 | 独立行政法人港湾空港技術研究所 | 裏込土の吸出防止工法 |
-
2012
- 2012-10-08 CN CN201210376973.6A patent/CN102912802B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201390968Y (zh) * | 2009-04-15 | 2010-01-27 | 中铁二院工程集团有限责任公司 | 岩土边坡微型桩抗滑构造 |
CN101575835A (zh) * | 2009-05-25 | 2009-11-11 | 铁道第三勘察设计院集团有限公司 | 隐式支挡路基结构 |
CN101787689A (zh) * | 2010-03-26 | 2010-07-28 | 中冶实久建设有限公司 | 昔格达土高边坡填方的强夯施工方法 |
CN201908313U (zh) * | 2010-11-26 | 2011-07-27 | 中国水电顾问集团成都勘测设计研究院 | 边坡加固结构 |
CN102704497A (zh) * | 2012-05-31 | 2012-10-03 | 中冶集团武汉勘察研究院有限公司 | 一种用于处理高填方边坡的rpw法技术 |
Non-Patent Citations (2)
Title |
---|
水利部建设与管理司等.面板堆石坝打夯机斜坡及边角夯实施工工法.《2009-2010年度水利水电工程建设工法汇编》.黄河水利出版社,2011,第524页. * |
水利部长江水利委员会等.武汉市堤工程地质勘察.《长江年鉴 2000》.水利部长江水利委员会长江年鉴社,2000,第337页. * |
Also Published As
Publication number | Publication date |
---|---|
CN102912802A (zh) | 2013-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203741868U (zh) | 一种带组合锚索的钢筋混凝土挡墙结构 | |
CN103410167A (zh) | 一种立体加筋刚柔复合生态挡土墙及施工方法 | |
CN105155558A (zh) | 一种组合支挡结构及其施工方法 | |
CN203320549U (zh) | 机场工程高边坡加筋格宾挡墙 | |
CN201158826Y (zh) | 土工格栅加筋挡土墙 | |
CN101949153B (zh) | 地基排水控制法 | |
CN104389320B (zh) | 桩基础锚索预应力高挡墙施工方法 | |
CN105240018B (zh) | 竖井施工装置及方法 | |
CN210315102U (zh) | 复合式生态装饰面板护坡加筋路基结构 | |
CN203429660U (zh) | 一种立体加筋刚柔复合生态挡土墙 | |
CN202298648U (zh) | 自嵌式花阶墙的挡土防冲刷系统 | |
CN102704497B (zh) | 一种用于处理高填方边坡的方法 | |
CN102912800B (zh) | 一种用于处理后筑式高陡填方边坡的立体组合加固方法 | |
CN204356788U (zh) | 柔性减胀生态护坡构造 | |
CN206902734U (zh) | 一种软基地区的地面结构 | |
CN206844132U (zh) | 超高轻型支挡结构 | |
CN102912802B (zh) | 一种用于处理后筑式高陡填方边坡的方法 | |
CN107604940A (zh) | 一种钢管格栅膨胀土挡墙及其施工方法 | |
CN107100179B (zh) | 轻型组合支挡结构及治理大范围高填方边坡工程的方法 | |
CN206667263U (zh) | 一种基坑支护结构 | |
CN105113350A (zh) | 桥墩台路基结构及施工方法 | |
CN204940310U (zh) | 一种组合支挡结构 | |
CN202055251U (zh) | 大于安息角园林高填土地形堆筑结构 | |
CN102912803B (zh) | 一种用于处理后筑式高陡填方边坡的ltbd方法 | |
CN102912801B (zh) | 一种用于处理后筑式高陡填方边坡的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |