CN102904287B - Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system - Google Patents
Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system Download PDFInfo
- Publication number
- CN102904287B CN102904287B CN201210369375.6A CN201210369375A CN102904287B CN 102904287 B CN102904287 B CN 102904287B CN 201210369375 A CN201210369375 A CN 201210369375A CN 102904287 B CN102904287 B CN 102904287B
- Authority
- CN
- China
- Prior art keywords
- voltage
- control
- station
- high resistance
- stagewise
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 24
- 230000005540 biological transmission Effects 0.000 title description 7
- 230000009471 action Effects 0.000 claims abstract description 44
- 241000251468 Actinopterygii Species 0.000 claims description 45
- 238000011217 control strategy Methods 0.000 claims description 19
- 230000003068 static effect Effects 0.000 claims description 15
- 230000001052 transient effect Effects 0.000 claims description 11
- 238000012544 monitoring process Methods 0.000 claims description 10
- 230000006855 networking Effects 0.000 claims description 5
- 238000004804 winding Methods 0.000 claims description 4
- 230000005611 electricity Effects 0.000 claims 1
- 230000001105 regulatory effect Effects 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 16
- 230000033228 biological regulation Effects 0.000 description 12
- 230000008859 change Effects 0.000 description 6
- 230000000694 effects Effects 0.000 description 5
- 238000004088 simulation Methods 0.000 description 4
- 238000004364 calculation method Methods 0.000 description 3
- 230000001939 inductive effect Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 2
- 230000001960 triggered effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000001629 suppression Effects 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/12—Circuit arrangements for AC mains or AC distribution networks for adjusting voltage in AC networks by changing a characteristic of the network load
- H02J3/16—Circuit arrangements for AC mains or AC distribution networks for adjusting voltage in AC networks by changing a characteristic of the network load by adjustment of reactive power
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/30—Reactive power compensation
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
本发明提供一种新能源外送系统的FACTS设备协调控制方法,分为内层控制、外层控制和最外层控制,其中,最外层控制优先级高于外层控制,外层控制优先级高于内层控制。内层控制保证变电站电压能精确控制在某个值或某个范围内,外层控制和最外层控制在系统出现大扰动时提供紧急无功支撑,保证变电站电压能够迅速恢复至允许范围内。三层电压控制结合的方法能够高精度、高效地集中协调控制多个FACTS设备动作,工程适应性很强。
The invention provides a FACTS equipment coordination control method for a new energy external delivery system, which is divided into inner layer control, outer layer control and outermost layer control, wherein the outermost layer control has a higher priority than the outer layer control, and the outer layer control has priority The level is higher than the internal control. The inner layer control ensures that the voltage of the substation can be accurately controlled within a certain value or within a certain range. The outer layer control and the outermost layer control provide emergency reactive power support when there is a large disturbance in the system, ensuring that the voltage of the substation can quickly return to the allowable range. The method of combining three-layer voltage control can centrally coordinate and control the actions of multiple FACTS devices with high precision and high efficiency, and has strong engineering adaptability.
Description
技术领域 technical field
本发明属于电力系统技术领域,具体涉及一种新能源外送系统的FACTS设备协调控制方法。The invention belongs to the technical field of power systems, and in particular relates to a FACTS equipment coordination control method of a new energy delivery system.
背景技术 Background technique
随着新疆与西北主网联网第二通道建成,将形成第一通道—第二通道—海西通道总长度接近3000公里的750千伏双环网。该通道上串有酒泉、哈密两个千万千瓦级大型风电基地和海西光伏基地。这些地区的新能源开发呈现大规模、高集中、远距离的特点,发展迅速。随着新能源大规模馈入,风功率大范围、高频度的波动造成新疆与西北联网的两个通道上潮流波动频繁,无功电压控制困难。采用常规的低压无功补偿设备无法满足频繁投切的要求,需要采用动态无功补偿设备。根据规划论证,新疆与西北联网第二通道规划装设多套容量新型FACTS装置。其中,沙州~鱼卡两回线路共配置4组线路分级式可控电抗器,每组容量390Mvar,固定容量39Mvar,可调容量351Mvar,三级可调,单级容量117Mvar;沙州站变压器第三绕组侧配置静止无功补偿器SVC(360Mvar容性,360Mvar感性);鱼卡站母线配置330Mvar磁阀式母线可控高抗,固定容量为16.5Mvar,连续可调。With the completion of the second channel of the main network between Xinjiang and Northwest China, a 750 kV double-ring network with a total length of nearly 3,000 kilometers will be formed from the first channel - the second channel - Hercynian channel. There are two large-scale wind power bases of 10 million kilowatts in Jiuquan and Hami and a photovoltaic base in Haixi on the channel. The development of new energy in these areas is characterized by large-scale, high concentration, and long-distance, and develops rapidly. With the large-scale feed-in of new energy, large-scale and high-frequency fluctuations in wind power have caused frequent power flow fluctuations on the two channels connecting Xinjiang and Northwest China, making it difficult to control reactive power and voltage. Conventional low-voltage reactive power compensation equipment cannot meet the requirements of frequent switching, and dynamic reactive power compensation equipment is required. According to the planning and demonstration, the second channel of the Xinjiang and Northwest interconnection is planned to install multiple sets of capacity new FACTS devices. Among them, the Shazhou-Yuka two-circuit line is equipped with a total of 4 sets of line graded controllable reactors, each with a capacity of 390Mvar, a fixed capacity of 39Mvar, an adjustable capacity of 351Mvar, three-stage adjustable, and a single-stage capacity of 117Mvar; Shazhou station transformer The third winding side is equipped with a static var compensator SVC (360Mvar capacitive, 360Mvar inductive); the busbar of the fish card station is equipped with a 330Mvar magnetic valve busbar with controllable high reactance, a fixed capacity of 16.5Mvar, and is continuously adjustable.
目前,750kV可控电抗器和SVC独立的控制策略国内已有研究,但多FACTS设备之间的协调控制策略在国内尚属空白。中国750kV敦煌站可控高抗示范工程是世界首套750kV风电集中送出系统应用的可控高抗工程,该工程于2012年1月5日成功投运。针对敦煌750kV可控电抗器,中国电科院系统所提出了基于无功需求增量和母线边界电压的可控电抗器内外双层控制策略,控制策略实际中应用良好,对于抑制母线电压波动、降低线路无功损耗、在暂态过程中实现母线电压动态支撑、减少站内低压无功补偿装置的动作次数和减轻站内运行压力方面作用明显。静止无功补偿器SVC作为无功补偿、抑制电压波动的有效手段,目前已广泛地应用于中、高压电网以及超高压电网中,并积累了多年的运行经验。SVC主要用于在故障后暂态过程中为电网提供紧急无功功率补偿以增强电网电压支撑以改善电网的安全稳定性,同时常态运行中提供连续的无功功率调节以抑制电压的波动。SVC一般采用基于电压的控制策略,通过连续的调节,可以维持SVC所在母线电压恒定。At present, the independent control strategy of 750kV controllable reactor and SVC has been studied in China, but the coordinated control strategy among multiple FACTS equipment is still blank in China. China's 750kV Dunhuang Substation Controllable High Resistance Demonstration Project is the world's first controllable high resistance project applied to the centralized transmission system of 750kV wind power. The project was successfully put into operation on January 5, 2012. For the Dunhuang 750kV controllable reactor, the System Institute of China Electric Power Research Institute proposed a double-layer control strategy for the controllable reactor based on the reactive power demand increment and the bus boundary voltage. It has obvious effects in reducing the reactive power loss of the line, realizing the dynamic support of the bus voltage in the transient process, reducing the number of actions of the low-voltage reactive power compensation device in the station, and reducing the operating pressure in the station. Static var compensator SVC, as an effective means of reactive power compensation and voltage fluctuation suppression, has been widely used in medium and high voltage power grids and ultra-high voltage power grids, and has accumulated many years of operating experience. SVC is mainly used to provide emergency reactive power compensation for the grid in the post-fault transient process to enhance the grid voltage support to improve the safety and stability of the grid, and to provide continuous reactive power regulation during normal operation to suppress voltage fluctuations. SVC generally adopts a voltage-based control strategy. Through continuous adjustment, the voltage of the bus where the SVC is located can be maintained constant.
新疆与西北主网联网第二通道共装设5套750kV可控高抗、1套66kV SVC,是世界上首次在750kV输电系统集中应用新型大容量FACTS设备。实现可控高抗群之间的协调优化控制、可控高抗与SVC之间的协调优化控制,对于有效抑制由于新能源波动造成的二通道输电系统无功电压频繁波动非常关键。A total of 5 sets of 750kV controllable high-resistance and 1 set of 66kV SVC were installed in the second channel of Xinjiang and the Northwest main network. Realizing the coordinated optimal control between the controllable high reactance groups and the coordinated optimal control between the controllable high reactance and SVC is very critical to effectively suppress the frequent fluctuation of reactive power and voltage of the two-channel transmission system caused by the fluctuation of new energy.
发明内容 Contents of the invention
为了克服上述现有技术的不足,本发明提供一种新能源外送系统的FACTS设备协调控制方法,分为内层控制、外层控制和最外层控制,其中,最外层控制优先级高于外层控制,外层控制优先级高于内层控制。内层控制保证变电站电压能精确控制在某个值或某个范围内,外层控制和最外层控制在系统出现大扰动时提供紧急无功支撑,保证变电站电压能够迅速恢复至允许范围内。三层电压控制结合的方法能够高精度、高效地集中协调控制多个FACTS设备动作,工程适应性很强。In order to overcome the shortcomings of the above-mentioned prior art, the present invention provides a FACTS equipment coordination control method for a new energy external delivery system, which is divided into inner layer control, outer layer control and outermost layer control, wherein the outermost layer control has a higher priority For outer control, the priority of outer control is higher than that of inner control. The inner layer control ensures that the voltage of the substation can be accurately controlled within a certain value or within a certain range. The outer layer control and the outermost layer control provide emergency reactive power support when there is a large disturbance in the system, ensuring that the voltage of the substation can quickly return to the allowable range. The method of combining three-layer voltage control can centrally coordinate and control the actions of multiple FACTS devices with high precision and high efficiency, and has strong engineering adaptability.
为了实现上述发明目的,本发明采取如下技术方案:In order to realize the above-mentioned purpose of the invention, the present invention takes the following technical solutions:
本发明提供一种新能源外送系统的FACTS设备协调控制方法,所述方法包括内层控制、外层控制和最外层控制;所述内层控制将变电站电压精确控制在电压目标值或电压控制带内;在新能源外送系统出现大扰动时外层控制和最外层控制提供紧急无功支撑,使变电站电压能够迅速恢复至允许范围内。The invention provides a FACTS equipment coordination control method of a new energy external delivery system, the method includes inner layer control, outer layer control and outermost layer control; the inner layer control accurately controls the voltage of the substation to the voltage target value or voltage In the control zone; when there is a large disturbance in the new energy external transmission system, the outer control and the outermost control provide emergency reactive power support, so that the voltage of the substation can be quickly restored to the allowable range.
所述新能源外送系统为新疆与西北主网联网第二通道,风电和太阳能由联网通道外送,所述联网通道上装设FACTS设备;其中,在联网通道沿线的沙州站主变第三绕组侧装设66kV静止无功补偿器,在鱼卡开关站母线侧装设磁控式母线可控高抗,在沙州~鱼卡线路双回线路两侧装设分级式可控高抗。The new energy delivery system is the second channel of Xinjiang and Northwest main grid network, wind power and solar energy are sent out through the network channel, and FACTS equipment is installed on the network channel; among them, the main transformer of Shazhou station along the network channel is the third A 66kV static var compensator is installed on the winding side, a magnetically controlled busbar controllable high reactance is installed on the busbar side of the Yuka switch station, and a graded controllable high reactance is installed on both sides of the double-circuit line of the Shazhou-Yuka line.
所述内层控制中,内层电压控制每隔1分钟循环一次;沙州站和鱼卡站内层控制设置时延30s,以避免沙州站和鱼卡站线路分级式可控高抗同时动作。In the inner layer control, the inner layer voltage control is cycled every 1 minute; the inner layer control of Shazhou station and Yuka station is set with a time delay of 30s to avoid the simultaneous action of hierarchical controllable high resistance lines at Shazhou station and Yuka station .
所述内层电压控制以变电站母线电压为输入量,输入沙州站控制电压目标值V1、鱼卡站控制电压目标值V2、沙州母线电压控制带[V1-ΔV1,V1+ΔV1]和鱼卡母线电压控制带[V2-ΔV2,V2+ΔV2],ΔV1和ΔV2分别为沙州站和鱼卡站允许的母线电压偏差,V1、V2、ΔV1和ΔV2的数值由用户确定。The inner layer voltage control uses the bus voltage of the substation as the input quantity, and inputs the control voltage target value V 1 of the Shazhou station, the control voltage target value V 2 of the Yuka station, and the Shazhou bus voltage control zone [V 1 -ΔV 1 , V 1 +ΔV 1 ] and Yuka bus voltage control belt [V 2 -ΔV 2 , V 2 +ΔV 2 ], ΔV 1 and ΔV 2 are the bus voltage deviation allowed by Shazhou station and Yuka station respectively, V 1 and V 2 , ΔV 1 and ΔV 2 are determined by the user.
内层电压控制时,优先发挥沙州静止无功补偿器、鱼卡磁控式可控高抗的跟随式调节作用,将沙州站电压和鱼卡站电压分别控制在V1和V2;当静止无功补偿器、磁控式可控高抗已达到最大/最小容量,沙州/鱼卡母线电压仍不在电压控制带内,此时站内的线路可控高抗触发动作;为减少设备损耗,可控高抗控制触发时,沙州站线路可控高抗I和Ⅱ交替动作,鱼卡站线路可控高抗I和Ⅱ交替动作,每次动作一级;When the inner layer voltage is controlled, give priority to the follow-up regulation of the Shazhou static var compensator and the Yuka magnetically controlled high-resistance, and control the Shazhou station voltage and the Yuka station voltage at V 1 and V 2 respectively; When the static var compensator and magnetically controlled high-resistance have reached the maximum/minimum capacity, and the Shazhou/Yuka bus voltage is still not within the voltage control band, the line controllable high-resistance in the station will trigger action at this time; in order to reduce equipment Loss, when the controllable high-resistance control is triggered, the controllable high-resistance I and II of the Shazhou station line alternately act, and the controllable high-resistance I and II of the Yuka station line alternately operate, one level at a time;
当站内一组线路可控高抗I动作一级后,若监控母线电压仍不在允许电压控制带内时,则发触发指令给本站另一组线路可控高抗Ⅱ,可控高抗Ⅱ动作一级,若此时可控高抗Ⅱ故障或已达到最大/最小容量,则发触发指令给可控高抗I,可控高抗I再动作一级;When the controllable high resistance I of a group of lines in the station has moved to the first level, if the monitored bus voltage is still not within the allowable voltage control band, a trigger command will be sent to another group of lines in the station. The first level of action, if the controllable high resistance II is faulty or has reached the maximum/minimum capacity at this time, then send a trigger command to the controllable high resistance I, and the controllable high resistance I will act again;
当站内一组线路可控高抗I需要动作,但由于可控高抗I自身故障或者已达到最大/最小容量,则发触发指令给本站另一组线路可控高抗Ⅱ,可控高抗Ⅱ动作一级,可控高抗Ⅱ动作一级后,若监控母线电压仍不在允许电压控制带内时,则可控高抗Ⅱ需要再动作一级。When the controllable high-resistance I of a group of lines in the station needs to act, but because the controllable high-resistance I itself fails or has reached the maximum/minimum capacity, a trigger command is sent to another group of line controllable high-resistance II in the station, and the controllable high Anti-II action level, after the controllable high anti-II action level, if the monitored bus voltage is still not within the allowable voltage control band, the controllable high anti-II needs to act one level again.
所述外层控制以变电站母线电压为输入量,输入外层电压上边界U1和外层电压下边界U2,外层电压上边界U1和外层电压下边界U2由用户确定;外层控制实时监测电压,当新能源外送系统中出现大的扰动,连续5s监测到母线电压在[U2,U1]之外,站内两组线路可控高抗I和可控高抗Ⅱ同时切除或投入一级容量,此时静止无功补偿器和磁控式可控高抗在5s的监测时间之内已经动态调节完毕,达到其最大/最小容量,线路可控高抗动作完毕后,再开始下一次循环计时;The outer layer control takes the bus voltage of the substation as the input quantity, and inputs the upper boundary U 1 of the outer layer voltage and the lower boundary U 2 of the outer layer voltage, and the upper boundary U 1 of the outer layer voltage and the lower boundary U 2 of the outer layer voltage are determined by the user; Layer control monitors the voltage in real time. When there is a large disturbance in the new energy delivery system and the bus voltage is detected to be outside [U 2 , U 1 ] for 5 seconds in a row, the two sets of lines in the station have controllable high-resistance I and controllable high-resistance II At the same time, the first-level capacity is removed or put in. At this time, the static var compensator and the magnetically controlled high-resistance have been dynamically adjusted within the monitoring time of 5s to reach their maximum/minimum capacity. After the line controllable high-resistance action is completed , and then start the next cycle timing;
当发生区内故障时,即沙州~鱼卡线路故障,则优先电磁暂态控制;若5s的监测时间之内,站内协调控制器和线路可控高抗接收到沙州~鱼卡线路继电保出口信号或断路器位置接点信号,则闭锁外层控制,启动电磁暂态控制策略,将两侧线路可控高抗投至最大容量,待电磁暂态控制结束后,转回外层控制。When a fault occurs in the area, that is, the Shazhou-Yuka line is faulty, the electromagnetic transient control is given priority; if within 5s monitoring time, the coordination controller in the station and the line controllable high resistance receive the Shazhou-Yuka line to continue If the electric protection exit signal or the circuit breaker position contact signal, the outer layer control is blocked, the electromagnetic transient control strategy is started, the controllable high resistance of the lines on both sides is switched to the maximum capacity, and after the electromagnetic transient control is completed, it is switched back to the outer layer control .
所述最外层电压控制以变电站母线电压为输入量,输入最外层电压控制上限U',U'的数值由用户确定;最外层电压控制实时监测系统电压,一旦监测到电压高于U',站内两组线路分级式可控高抗立即动作至最大容量,以抑制系统高压。The outermost layer voltage control uses the substation bus voltage as the input quantity, and inputs the outermost layer voltage control upper limit U', and the value of U' is determined by the user; the outermost layer voltage control monitors the system voltage in real time, and once the voltage is detected to be higher than U ', the two groups of lines in the station have graded controllable high resistance and immediately act to the maximum capacity to suppress the high voltage of the system.
所述最外层控制优先级高于外层控制,外层控制优先级高于内层控制。The outermost control has a higher priority than the outer control, and the outer control has a higher priority than the inner control.
与现有技术相比,本发明的有益效果在于:Compared with prior art, the beneficial effect of the present invention is:
1.本发明的方法直接以电压为控制目标,物理意义明确,简单直观。1. The method of the present invention directly takes voltage as the control target, has clear physical meaning, and is simple and intuitive.
2.本发明将连续调压的FACTS设备(包括静止无功补偿器和磁控式母线可控高抗)与分级动作的线路可控高抗有效协调。当风功率波动引起系统电压变化时,连续调压设备优先动作,发挥其跟随调压功能,将电压精确控制在目标值。当连续调压设备已经调整至最大/最小容量,变电站电压仍超出控制范围时,此时分级式线路可控高抗再动作,将电压控制在合理范围内。控制方法充分发挥SVC、磁控式母线可控高抗的连续跟随调压功能,避免了分级式可控高抗的频繁动作,显著提高各FACTS设备的动作精度和利用效率。2. The present invention effectively coordinates the continuous voltage regulation FACTS equipment (including static var compensator and magnetically controlled busbar controllable high reactance) with the step-by-step line controllable high reactance. When the wind power fluctuation causes the system voltage to change, the continuous voltage regulation device will act first, and exert its follow-up voltage regulation function to accurately control the voltage at the target value. When the continuous voltage regulation equipment has been adjusted to the maximum/minimum capacity and the voltage of the substation is still beyond the control range, the graded line can control the high resistance to operate again at this time to control the voltage within a reasonable range. The control method gives full play to the continuous follow-up voltage regulation function of SVC and magnetically controlled busbar controllable high reactance, avoids the frequent action of graded controllable high reactance, and significantly improves the action accuracy and utilization efficiency of each FACTS equipment.
3.本发明采用三层电压控制,最外层控制优先于外层控制,外层控制优先于内层控制,不同的控制层中分级式可控高抗采取不同的动作原则。内层控制中,每次允许变电站内一组分级式可控高抗动作一级;外层控制中,每次允许变电站内两组分级式可控高抗同时动作一级;最外层控制中,每次允许变电站内两组分级式可控高抗同时动作至最大容量。采取不同的分级式可控高抗动作原则,既可以在内层控制时减少可控高抗的动作频度和对系统的冲击,又可以在外层控制和最外层控制时为系统提供紧急无功支撑。三层控制相结合的方法使得可控高抗动作合理性显著提高,为可控高抗在大规模新能源外送的输电系统中发挥作用提供了保障,具有广阔的应用前景。3. The present invention adopts three layers of voltage control, the outermost layer control is prior to the outer layer control, the outer layer control is prior to the inner layer control, and the hierarchical controllable high resistance adopts different action principles in different control layers. In the inner layer control, one group of hierarchical controllable high resistances in the substation is allowed to act one level each time; in the outer layer control, two groups of hierarchical controllable high resistances in the substation are allowed to act one level at the same time; , allowing two groups of graded controllable high resistances in the substation to operate simultaneously to the maximum capacity each time. Adopting different hierarchical controllable high-resistance action principles can not only reduce the action frequency of controllable high-resistance and the impact on the system during inner control, but also provide emergency safety for the system during outer control and outermost control. power support. The method of combining three layers of control makes the operation rationality of the controllable high resistance significantly improved, which provides a guarantee for the controllable high resistance to play a role in the large-scale new energy transmission system, and has broad application prospects.
附图说明 Description of drawings
图1是新能源外送系统的FACTS设备协调控制方法示意图;Figure 1 is a schematic diagram of the FACTS equipment coordination control method of the new energy delivery system;
图2是本发明实施例中沙州站外层控制策略示意图;Fig. 2 is a schematic diagram of the outer layer control strategy of Shazhou station in the embodiment of the present invention;
图3是本发明实施例中鱼卡站外层控制策略示意图;Fig. 3 is a schematic diagram of the outer layer control strategy of the fish card station in the embodiment of the present invention;
图4是本发明实施例中沙州站最外层控制策略示意图;Fig. 4 is a schematic diagram of the outermost layer control strategy of Shazhou station in the embodiment of the present invention;
图5是本发明实施例中鱼卡站最外层控制策略示意图;Fig. 5 is a schematic diagram of the outermost control strategy of the fish card station in the embodiment of the present invention;
图6是本发明实施例中新疆与西北主网联网第二通道示意图;Fig. 6 is a schematic diagram of the second channel of Xinjiang and Northwest main network networking in the embodiment of the present invention;
图7是本发明实施例中2013年夏大方式下风电均匀波动时沙州侧线路可控高抗动作图;Fig. 7 is a controllable high-resistance action diagram of the Shazhou side line when the wind power fluctuates evenly under the summer mode in 2013 in the embodiment of the present invention;
图8是本发明实施例中2013年夏大方式下风电均匀波动时鱼卡侧线路可控高抗动作图;Fig. 8 is an action diagram of the controllable high resistance of the line on the side of the fish card when the wind power fluctuates uniformly in the summer mode in 2013 in the embodiment of the present invention;
图9是本发明实施例中2013年夏大方式下风电均匀波动时沙州SVC动作图;Fig. 9 is an action diagram of SVC in Shazhou when the wind power fluctuates uniformly in the summer mode in 2013 in the embodiment of the present invention;
图10是本发明实施例中2013年夏大方式下风电均匀波动时鱼卡母线可控高抗动作图;Fig. 10 is an action diagram of the controllable high resistance of the fish-card bus when the wind power fluctuates uniformly in the summer mode in 2013 in the embodiment of the present invention;
图11是本发明实施例中2013年夏大方式下风电均匀波动时沙州站和鱼卡站750kV侧电压变化图(kV);Figure 11 is a diagram of the voltage change (kV) at the 750kV side of the Shazhou station and the Yuka station when the wind power fluctuates uniformly in the summer mode in 2013 in the embodiment of the present invention;
图12是本发明实施例中2013年夏大基础方式下敦煌~酒泉线路N-2故障后沙州站电压变化图(kV);Fig. 12 is a diagram of the voltage change (kV) of the Shazhou station after the N-2 fault of the Dunhuang-Jiuquan line under the Xiada basic mode in 2013 in the embodiment of the present invention;
图13是本发明实施例中2013年夏大基础方式下敦煌~酒泉线路N-2故障后鱼卡站电压变化图(kV);Fig. 13 is a diagram of the voltage change (kV) of the fish card station after the N-2 failure of the Dunhuang-Jiuquan line under the basic mode of Xiada in 2013 in the embodiment of the present invention;
图14是本发明实施例中2013年冬大极限方式下甘肃风电脱网后沙州站电压变化图(kV);Fig. 14 is a diagram of the voltage change (kV) of the Shazhou station after the Gansu wind power off-grid in the winter of 2013 under the extreme limit mode in the embodiment of the present invention;
图15是本发明实施例中2013年冬大极限方式下甘肃风电脱网后鱼卡站电压变化图(kV)。Fig. 15 is a diagram of the voltage change (kV) of the Yuka station after the Gansu wind power off-grid in the extreme winter mode of 2013 in the embodiment of the present invention.
具体实施方式 Detailed ways
下面结合附图对本发明作进一步详细说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.
如图1,本发明提供一种新能源外送系统的FACTS设备协调控制方法,所述方法包括内层控制、外层控制和最外层控制;所述内层控制将变电站电压精确控制在电压目标值或电压控制带内;在新能源外送系统出现大扰动时外层控制和最外层控制提供紧急无功支撑,使变电站电压能够迅速恢复至允许范围内。As shown in Figure 1, the present invention provides a FACTS equipment coordination control method for a new energy external transmission system, the method includes inner layer control, outer layer control and outermost layer control; the inner layer control accurately controls the voltage of the substation at the voltage Within the target value or voltage control band; when there is a large disturbance in the new energy external transmission system, the outer control and the outermost control provide emergency reactive power support, so that the voltage of the substation can quickly return to the allowable range.
所述内层控制中,内层电压控制每隔1分钟循环一次;沙州站和鱼卡站内层控制设置时延30s,以避免沙州站和鱼卡站线路分级式可控高抗同时动作。In the inner layer control, the inner layer voltage control is cycled every 1 minute; the inner layer control of Shazhou station and Yuka station is set with a time delay of 30s to avoid the simultaneous action of hierarchical controllable high resistance lines at Shazhou station and Yuka station .
所述内层电压控制以变电站母线电压为输入量,输入沙州站控制电压目标值V1、鱼卡站控制电压目标值V2、沙州母线电压控制带[V1-ΔV1,V1+ΔV1]和鱼卡母线电压控制带[V2-ΔV2,V2+ΔV2],ΔV1和ΔV2分别为沙州站和鱼卡站允许的母线电压偏差,V1、V2、ΔV1和ΔV2的数值由用户确定。The inner layer voltage control uses the bus voltage of the substation as the input quantity, and inputs the control voltage target value V 1 of the Shazhou station, the control voltage target value V 2 of the Yuka station, and the Shazhou bus voltage control zone [V 1 -ΔV 1 , V 1 +ΔV 1 ] and Yuka bus voltage control belt [V 2 -ΔV 2 , V 2 +ΔV 2 ], ΔV 1 and ΔV 2 are the bus voltage deviation allowed by Shazhou station and Yuka station respectively, V 1 and V 2 , ΔV 1 and ΔV 2 are determined by the user.
内层电压控制时,优先发挥沙州静止无功补偿器、鱼卡磁控式可控高抗的跟随式调节作用,将沙州站电压和鱼卡站电压分别控制在V1和V2;当静止无功补偿器、磁控式可控高抗已达到最大/最小容量,沙州/鱼卡母线电压仍不在电压控制带内,此时站内的线路可控高抗触发动作;为减少设备损耗,可控高抗控制触发时,沙州站线路可控高抗I和Ⅱ交替动作,鱼卡站线路可控高抗I和Ⅱ交替动作,每次动作一级;When the inner layer voltage is controlled, give priority to the follow-up regulation of the Shazhou static var compensator and the Yuka magnetically controlled high-resistance, and control the Shazhou station voltage and the Yuka station voltage at V 1 and V 2 respectively; When the static var compensator and magnetically controlled high-resistance have reached the maximum/minimum capacity, and the Shazhou/Yuka bus voltage is still not within the voltage control band, the line controllable high-resistance in the station will trigger action at this time; in order to reduce equipment Loss, when the controllable high-resistance control is triggered, the controllable high-resistance I and II of the Shazhou station line alternately act, and the controllable high-resistance I and II of the Yuka station line alternately operate, one level at a time;
当站内一组线路可控高抗I动作一级后,若监控母线电压仍不在允许电压控制带内时,则发触发指令给本站另一组线路可控高抗Ⅱ,可控高抗Ⅱ动作一级,若此时可控高抗Ⅱ故障或已达到最大/最小容量,则发触发指令给可控高抗I,可控高抗I再动作一级;When the controllable high resistance I of a group of lines in the station has moved to the first level, if the monitored bus voltage is still not within the allowable voltage control band, a trigger command will be sent to another group of lines in the station. The first level of action, if the controllable high resistance II is faulty or has reached the maximum/minimum capacity at this time, then send a trigger command to the controllable high resistance I, and the controllable high resistance I will act again;
当站内一组线路可控高抗I需要动作,但由于可控高抗I自身故障或者已达到最大/最小容量,则发触发指令给本站另一组线路可控高抗Ⅱ,可控高抗Ⅱ动作一级,可控高抗Ⅱ动作一级后,若监控母线电压仍不在允许电压控制带内时,则可控高抗Ⅱ需要再动作一级。When the controllable high-resistance I of a group of lines in the station needs to act, but because the controllable high-resistance I itself fails or has reached the maximum/minimum capacity, a trigger command is sent to another group of line controllable high-resistance II in the station, and the controllable high Anti-II action level, after the controllable high anti-II action level, if the monitored bus voltage is still not within the allowable voltage control band, the controllable high anti-II needs to act one level again.
如图2和图3,所述外层控制以变电站母线电压为输入量,输入外层电压上边界U1和外层电压下边界U2,外层电压上边界U1和外层电压下边界U2由用户确定;外层控制实时监测电压,当新能源外送系统中出现大的扰动,连续5s监测到母线电压在[U2,U1]之外,站内两组线路可控高抗I和可控高抗Ⅱ同时切除或投入一级容量,此时静止无功补偿器和磁控式可控高抗在5s的监测时间之内已经动态调节完毕,达到其最大/最小容量,线路可控高抗动作完毕后,再开始下一次循环计时;As shown in Fig. 2 and Fig. 3, the outer layer control takes the bus voltage of the substation as the input quantity, input the upper boundary of the outer layer voltage U 1 and the lower boundary of the outer layer voltage U 2 , the upper boundary of the outer layer voltage U 1 and the lower boundary of the outer layer voltage U 2 is determined by the user; the outer control monitors the voltage in real time. When there is a large disturbance in the new energy delivery system, the bus voltage is detected to be outside [U 2 , U 1 ] for 5 consecutive seconds, and the two sets of lines in the station can control the high I and controllable high-resistance II are cut off or put into primary capacity at the same time. At this time, the static var compensator and the magnetically controlled high-resistance have been dynamically adjusted within the monitoring time of 5s to reach their maximum/minimum capacity. After the controllable high resistance action is completed, start the next cycle timing;
当发生区内故障时,即沙州~鱼卡线路故障,则优先电磁暂态控制;若5s的监测时间之内,站内协调控制器和线路可控高抗接收到接收到沙州~鱼卡线路继电保出口信号或断路器位置接点信号,则闭锁外层控制,启动电磁暂态控制策略,将两侧线路可控高抗投至最大容量,待电磁暂态控制结束后,转回外层控制。When a fault occurs in the area, that is, the Shazhou-Yuka line fault, the electromagnetic transient control is given priority; if within 5s monitoring time, the coordination controller in the station and the line controllable high-resistance receive the signal received from Shazhou-Yuka If the line relay protects the exit signal or the circuit breaker position contact signal, the outer layer control is blocked, the electromagnetic transient control strategy is started, and the controllable high resistance of the lines on both sides is switched to the maximum capacity. After the electromagnetic transient control is completed, it is switched back to the outer layer layer control.
如图4和图5,所述最外层电压控制以变电站母线电压为输入量,输入最外层电压控制上限U',U'的数值由用户确定;最外层电压控制实时监测系统电压,一旦监测到电压高于U',站内两组线路分级式可控高抗立即动作至最大容量,以抑制系统高压。As shown in Fig. 4 and Fig. 5, the outermost layer voltage control takes the substation bus voltage as the input quantity, and inputs the outermost layer voltage control upper limit U', and the value of U' is determined by the user; the outermost layer voltage control monitors the system voltage in real time, Once it is detected that the voltage is higher than U', the two groups of lines in the station will act immediately to the maximum capacity to suppress the high voltage of the system.
如图6,所述新能源外送系统为新疆与西北主网联网第二通道,风电和太阳能由联网通道外送,所述联网通道上装设FACTS设备;其中,在联网通道沿线的沙州站主变第三绕组侧装设66kV静止无功补偿器,在开关站鱼卡母线侧装设磁控式母线可控高抗,在沙州~鱼卡线路双回线路两侧装设分级式可控高抗。As shown in Figure 6, the new energy delivery system is the second channel of Xinjiang and the Northwest main grid network, wind power and solar energy are sent out through the network channel, and FACTS equipment is installed on the network channel; among them, the Shazhou station along the network channel Install a 66kV static var compensator on the side of the third winding of the main transformer, install a magnetically controlled busbar with controllable high-resistance on the side of the Yuka busbar in the switch station, and install a graded adjustable bus on both sides of the Shazhou-Yuka line double-circuit line. Control high resistance.
基于BPA潮流计算程序进行控制策略仿真计算,考察所提新疆与西北联网第二通道多FACTS设备协调控制策略对于电压的控制效果。第二通道联网示意图如图7所示。Based on the BPA power flow calculation program, the simulation calculation of the control strategy is carried out, and the control effect of the proposed coordinated control strategy for the multi-FACTS equipment of the second channel of the Xinjiang and Northwest Network on the voltage is investigated. The schematic diagram of the second channel networking is shown in FIG. 7 .
首先,考察新疆与西北主网联网第二通道多FACTS设备内层协调控制策略对于电压的控制效果,计算算例采用2013年夏大方式规划数据。设置沙州站、鱼卡站的控制电压目标值V1=775kV,V2=770kV,沙州母线电压控制带为[770kV,780kV],鱼卡母线电压控制带为[765kV,775kV]。考虑敦煌和酒泉风电从0MW均匀波动至3300MW,每300MW一级,风电波动时利用青海水电调峰以维持系统的功率平衡。仿真中,风电初始出力0MW时,二通道各FACTS设备安排发出最大感性无功,即沙州~鱼卡四组线路可控高抗安排在最大容量390Mvar,沙州站SVC安排在感性最大容量360Mvar,鱼卡站磁控式母线可控高抗安排在最大容量330Mvar,感性为“+”,容性为“-”。根据所述内层控制策略,沙州站内部两组线路可控高抗动作情况如图7所示,鱼卡站内部两组线路可控高抗动作情况如图8所示,沙州站SVC动作情况如图9所示,鱼卡站磁控式母线可控高抗动作情况如图10所示。沙州站和鱼卡站750kV侧电压变化情况如图11所示。从图中可以看出,沙州线路可控高抗1、可控高抗2交替动作,鱼卡可控高抗1、可控高抗2交替动作,可控高抗每次只动作一级。当可控高抗动作后,沙州SVC、鱼卡磁控式母线可控高抗将出现反向调节,将电压控制在目标值。图9中,当风电出力2400MW、3000MW、3300MW时,SVC出现反向调节。图10中,当风电出力1800MW、2400MW时,磁控式母线可控高抗出现反向调节。First of all, the control effect of the coordination control strategy on the voltage of the second channel multi-FACTS equipment of the main network in Xinjiang and the Northwest main network is investigated. The calculation example uses the planning data in the summer of 2013. Set the control voltage target values V 1 = 775kV, V 2 = 770kV for Shazhou station and Yuka station, the Shazhou bus voltage control zone is [770kV, 780kV], and the Yuka bus voltage control zone is [765kV, 775kV]. Considering that the wind power in Dunhuang and Jiuquan fluctuates uniformly from 0MW to 3300MW, every 300MW, Qinghai sea power peak regulation is used to maintain the power balance of the system when the wind power fluctuates. In the simulation, when the initial output of wind power is 0MW, the FACTS equipment of the second channel is arranged to generate the maximum inductive reactive power, that is, the controllable high-resistance of the four groups of lines from Shazhou to Yuka is arranged at the maximum capacity of 390Mvar, and the SVC of Shazhou Station is arranged at the maximum inductive capacity of 360Mvar , The controllable high-resistance arrangement of the magnetically controlled busbar at the fish card station is arranged at a maximum capacity of 330Mvar, the inductance is "+", and the capacitance is "-". According to the inner layer control strategy, the controllable high-resistance actions of the two groups of lines inside the Shazhou station are shown in Figure 7, and the controllable high-resistance actions of the two groups of lines inside the Yuka station are shown in Figure 8, and the SVC of the Shazhou station The action is shown in Figure 9, and the controllable high-resistance action of the magnetically controlled bus at the fish card station is shown in Figure 10. The voltage changes on the 750kV side of Shazhou Station and Yuka Station are shown in Figure 11. It can be seen from the figure that the controllable high resistance 1 and controllable high resistance 2 alternate actions of the Shazhou line, the controllable high resistance 1 and the controllable high resistance 2 alternate actions of the fish card, and the controllable high resistance only moves one level at a time . When the controllable high reactance is activated, the controllable high reactance of Shazhou SVC and Yuka magnetically controlled bus will be adjusted in reverse to control the voltage at the target value. In Fig. 9, when the wind power output is 2400MW, 3000MW and 3300MW, the SVC reversely adjusts. In Fig. 10, when the wind power output is 1800MW and 2400MW, the controllable high-resistance of the magnetically controlled busbar is reversely adjusted.
当风电出力0MW~1500MW时,仅依靠沙州站SVC和鱼卡站磁控式母线可控高抗的跟随调压,能够将沙州站、鱼卡站电压控制在目标值。当风电出力1800MW,沙州电压在控制范围内,而鱼卡电压低于765kV,鱼卡一组可控高抗动作一级。当风电出力2100MW、2700MW时,沙州一组线路可控高抗动作一级,沙州和鱼卡电压都能恢复到控制范围内,鱼卡线路可控高抗无需动作。当风电出力2400MW、3300MW时,沙州可控高抗动作一级后,但鱼卡电压低于765kV,鱼卡可控高抗动作一级。当风电出力3000MW时,沙州一组线路可控高抗动作一级后,沙州电压仍低于770kV,沙州另一组线路可控高抗再动作一级,沙州电压恢复至控制范围内,鱼卡电压仍低于765kV,鱼卡一组可控高抗动作一级。采取所述多FACTS设备内层协调控制策略,沙州电压能精确控制在775kV,鱼卡电压在风电波动0~2400MW时能精确控制在770kV,鱼卡电压在风电波动2700MW~3300MW时能控制在[765kV,770kV]范围内。When the wind power output is 0MW~1500MW, the voltage of Shazhou Station and Yuka Station can be controlled at the target value only by relying on the controllable high-resistance follow-up voltage regulation of the SVC of Shazhou Station and the magnetically controlled busbar of Yuka Station. When the wind power output is 1800MW, the voltage in Shazhou is within the control range, and the voltage of the fish card is lower than 765kV, a group of fish cards can control the high resistance to operate at the first level. When the wind power output is 2100MW and 2700MW, the controllable high-resistance of a group of lines in Shazhou operates at the first level, and the voltage of Shazhou and Yuka can be restored to the control range, and the controllable high-resistance of the Yuka line does not need to be activated. When the wind power output is 2400MW and 3300MW, the controllable high-resistance operation of Shazhou is after the first level, but the voltage of the fish card is lower than 765kV, and the controllable high-resistance operation of the fish card is the first level. When the wind power output is 3000MW, the voltage of Shazhou is still lower than 770kV after one group of lines in Shazhou has a controllable high-resistance action of one level, and the other group of lines in Shazhou has a controllable high-resistance action of one level, and the voltage of Shazhou returns to the control range Inside, the voltage of the fish card is still lower than 765kV, and a group of fish cards can control the high resistance to operate at the first level. By adopting the multi-FACTS equipment inner layer coordinated control strategy, the Shazhou voltage can be accurately controlled at 775kV, the fish card voltage can be accurately controlled at 770kV when the wind power fluctuation is 0~2400MW, and the fish card voltage can be controlled at 2700MW~3300MW when the wind power fluctuation is 2700MW~3300MW. [765kV, 770kV] range.
其次,考察新疆与西北主网联网第二通道多FACTS设备外层协调控制策略对于电压的控制效果,计算算例采用2013年夏大基础方式规划数据。设置外层电压控制的上下边界为默认值,取U1=803kV,U2=745kV。仿真中,沙州~鱼卡线路两侧四组可控高抗均投入最大容量390Mvar,沙州SVC容量为0Mvar,鱼卡磁控式母线可控高抗投入最大容量330Mvar。敦煌~酒泉N-2故障后,沙州站、鱼卡站母线电压变化如图12、13所示。新疆与西北联网第二通道沿线各站的电压变化如下表1所示。故障后沙州电压为736kV,鱼卡电压为709kV。考虑SVC的跟随调压作用,沙州电压恢复至750kV,鱼卡电压恢复至720kV,鱼卡电压仍低于外层电压控制下限745kV,启动外层控制,鱼卡侧两组线路可控高抗都切除一级,鱼卡电压恢复至734kV,仍低于745kV,启动下一轮外层控制,鱼卡侧两组线路可控高抗再切除一级,鱼卡电压恢复至748kV。Secondly, the control effect of the outer layer coordination control strategy of multi-FACTS equipment on the second channel of the main network network in Xinjiang and Northwest China is investigated. The calculation example uses the planning data of the summer university in 2013. Set the upper and lower boundaries of the outer layer voltage control as the default value, U 1 =803kV, U 2 =745kV. In the simulation, the four groups of controllable high-resistance on both sides of the Shazhou-Yuka line are all invested with a maximum capacity of 390Mvar, the Shazhou SVC capacity is 0Mvar, and the maximum capacity of the controllable high-resistance input of the Yuka magnetically controlled bus is 330Mvar. After the Dunhuang-Jiuquan N-2 fault, the bus voltage changes at Shazhou Station and Yuka Station are shown in Figures 12 and 13. The voltage changes of the stations along the second channel of the Xinjiang-Northwest Interconnection are shown in Table 1 below. After the fault, the voltage in Shazhou was 736kV, and that in Yuka was 709kV. Considering the follow-up voltage regulation function of SVC, the Shazhou voltage returns to 750kV, the fish card voltage returns to 720kV, the fish card voltage is still lower than the outer layer voltage control lower limit of 745kV, the outer layer control is started, and the two groups of lines on the fish card side can control the high resistance Cut off one level, the fish card voltage returns to 734kV, still lower than 745kV, start the next round of outer layer control, the two groups of lines on the fish card side can control the high resistance and then cut off one level, the fish card voltage returns to 748kV.
表1Table 1
最后,考察新疆与西北主网联网第二通道多FACTS设备最外层协调控制策略对于电压的控制效果,计算算例采用2013年冬大极限方式规划数据。其中,敦煌风电接入3200MW,酒泉风电接入1000MW。设置最外层电压控制的上边界为默认值,取U'=830kV。仿真中,沙州SVC容量为0Mvar,沙州~鱼卡线路两侧四组可控高抗均投入容量156Mvar(固定容量39Mvar+1级可控容量117Mvar)。设置酒泉风电场汇集侧玉门~嘉峪关三永N-1故障,模拟故障后甘肃4200MW风电全部脱网,沙州站和鱼卡站的电压变化情况如图14和图15所示。风电脱网后,考虑SVC跟随调压作用,沙州和鱼卡最高电压仍达到830kV之上,启动最外层控制策略,沙州站和鱼卡站两组线路可控高抗均投至最大容量390Mvar。可控高抗动作后电压能够恢复至合理范围内,沙州电压恢复至790kV,鱼卡电压恢复至790kV。动态无功补偿设备动作后引起的脱网故障后各站电压变化如下表2所示。Finally, the control effect of the coordinated control strategy of the outermost layer of multi-FACTS equipment on the second channel of the main network in Xinjiang and Northwest China is investigated. Among them, Dunhuang wind power access 3200MW, Jiuquan wind power access 1000MW. Set the upper boundary of the outermost voltage control as the default value, and take U'=830kV. In the simulation, the SVC capacity in Shazhou is 0Mvar, and the four groups of controllable high resistance on both sides of the Shazhou-Yuka line have an average input capacity of 156Mvar (fixed capacity 39Mvar+level 1 controllable capacity 117Mvar). The Yumen-Jiayuguan Sanyong N-1 fault on the confluence side of the Jiuquan Wind Farm is set up. After the fault is simulated, the 4200MW wind power in Gansu is all disconnected from the grid. The voltage changes at Shazhou Station and Yuka Station are shown in Figure 14 and Figure 15. After the wind power is disconnected from the grid, the maximum voltage of Shazhou and Yuka is still above 830kV considering the function of SVC to follow the voltage regulation. The outermost control strategy is activated, and the controllable high resistance of the two lines of Shazhou Station and Yuka Station are both turned on to the maximum. Capacity 390Mvar. After the controllable high-resistance operation, the voltage can be restored to a reasonable range, the Shazhou voltage has recovered to 790kV, and the Yuka voltage has recovered to 790kV. The voltage changes of each station after the off-grid fault caused by the action of the dynamic reactive power compensation equipment are shown in Table 2 below.
表2Table 2
最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制,尽管参照上述实施例对本发明进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本发明的具体实施方式进行修改或者等同替换,而未脱离本发明精神和范围的任何修改或者等同替换,其均应涵盖在本发明的权利要求范围当中。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them. Although the present invention has been described in detail with reference to the above embodiments, those of ordinary skill in the art should understand that: the present invention can still be Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention shall be covered by the scope of the claims of the present invention.
Claims (6)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210369375.6A CN102904287B (en) | 2012-09-27 | 2012-09-27 | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system |
PCT/CN2013/084261 WO2014048336A1 (en) | 2012-09-27 | 2013-09-26 | Coordination control method for facts devices of new energy delivery system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210369375.6A CN102904287B (en) | 2012-09-27 | 2012-09-27 | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102904287A CN102904287A (en) | 2013-01-30 |
CN102904287B true CN102904287B (en) | 2015-06-10 |
Family
ID=47576392
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210369375.6A Active CN102904287B (en) | 2012-09-27 | 2012-09-27 | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN102904287B (en) |
WO (1) | WO2014048336A1 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102904287B (en) * | 2012-09-27 | 2015-06-10 | 中国电力科学研究院 | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system |
CN105610175B (en) * | 2016-01-22 | 2020-06-30 | 国家电网公司 | A wide-area reactive power coordination control method for FACTS equipment |
CN105958503A (en) * | 2016-06-13 | 2016-09-21 | 成都欣维保科技有限责任公司 | Operation method for reactive intelligent adjustment power transmission system |
CN105958502A (en) * | 2016-06-13 | 2016-09-21 | 成都欣维保科技有限责任公司 | Reactive automatic regulation method for intelligent power transmission system |
CN106208096B (en) * | 2016-07-21 | 2018-09-21 | 国网河北省电力公司电力科学研究院 | A kind of Substation Reactive-power Compensation grading method |
CN112162509B (en) * | 2020-09-25 | 2024-01-02 | 中国直升机设计研究所 | Active control rotor real-time control system based on FPGA+CPU architecture |
CN112653156B (en) * | 2021-01-05 | 2024-03-12 | 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 | Coordination control method between line controllable high reactance and static synchronous compensator |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102064554A (en) * | 2010-12-20 | 2011-05-18 | 中国电力科学研究院 | Method for controlling controllable high-voltage parallel reactors in power transmission system |
CN102074961A (en) * | 2010-12-30 | 2011-05-25 | 中电普瑞科技有限公司 | Leveled controllable parallel reactor device configured by series public reactor |
EP2325716A1 (en) * | 2009-10-06 | 2011-05-25 | General Electric Company | Reactive power regulation and voltage support for renewable energy plants |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101521381B (en) * | 2008-02-26 | 2011-06-15 | 上海纳杰电气成套有限公司 | Composite device for active dynamic reactive power compensation and filtering |
CN201611785U (en) * | 2010-04-07 | 2010-10-20 | 孙勇 | On-line dynamic electric energy quality integrated control apparatus |
CN102611118B (en) * | 2012-03-14 | 2014-04-16 | 清华大学 | Method for comprehensively controlling reactive voltage of wind farm with imported prediction method |
CN102904287B (en) * | 2012-09-27 | 2015-06-10 | 中国电力科学研究院 | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system |
-
2012
- 2012-09-27 CN CN201210369375.6A patent/CN102904287B/en active Active
-
2013
- 2013-09-26 WO PCT/CN2013/084261 patent/WO2014048336A1/en active Application Filing
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2325716A1 (en) * | 2009-10-06 | 2011-05-25 | General Electric Company | Reactive power regulation and voltage support for renewable energy plants |
CN102064554A (en) * | 2010-12-20 | 2011-05-18 | 中国电力科学研究院 | Method for controlling controllable high-voltage parallel reactors in power transmission system |
CN102074961A (en) * | 2010-12-30 | 2011-05-25 | 中电普瑞科技有限公司 | Leveled controllable parallel reactor device configured by series public reactor |
Non-Patent Citations (1)
Title |
---|
丁剑,张文朝等.大规模风电接入下的河西走廊远距离大容量输电.《高电压技术》.2009,第35卷(第8期),第2027-2041页. * |
Also Published As
Publication number | Publication date |
---|---|
CN102904287A (en) | 2013-01-30 |
WO2014048336A1 (en) | 2014-04-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102904287B (en) | Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system | |
CN102801170B (en) | Reactive-voltage control method and system of regional power-grid substations | |
CN104281977A (en) | Hybrid microgrid application platform and control method theref | |
CN103094911B (en) | Method for optimizing direct current weak receiving terminal power grid static var compensator (SVC) dynamic reactive power compensation configuration measures | |
CN102214917A (en) | Intelligent fault current limiter | |
CN108736500A (en) | Machine method and apparatus are cut in the optimization of regional power grid affluence electric power direct current delivery system | |
CN102195294A (en) | A comprehensive reactive power optimization control method for wind farms | |
CN103746389A (en) | Reactive compensation configuration method based on reactive voltage feature for wind power 500kV collecting transformer substation | |
CN110854870B (en) | A bus voltage automatic correction control method considering static synchronous compensator | |
CN103094912B (en) | A kind of implementation method of 750kV controllable magnetic control shunt reactor excitation system | |
CN106936140A (en) | The reactive-load adjusting device and method coordinated based on flexible direct current and high-voltage parallel electric capacity | |
CN104348162B (en) | 330kV wind energy turbine set collects control method of transformer station voltage | |
Opana et al. | STATCOM Application for Grid Dynamic Voltage Regulation: A Kenyan Case Study | |
CN106712068A (en) | Parallel hybrid DC power transmission system and reactive power regulation optimization method thereof | |
CN102593842A (en) | Distributive flexible reactive compensation configuration method of provincial power grid | |
CN102842920A (en) | AC (alternating current) /DC (direct current) coordinating and control method for restraining large-scale wind turbine tripping | |
CN110994624B (en) | Voltage control method to avoid voltage over-limit caused by failure of UHV DC converter station | |
CN105610175B (en) | A wide-area reactive power coordination control method for FACTS equipment | |
CN102074961A (en) | Leveled controllable parallel reactor device configured by series public reactor | |
Chen-chen et al. | Study of the effect of AC system strength on the HVDC startup characteristics | |
CN110011320B (en) | Reactive voltage optimization control method and system for extra-high voltage alternating current transformer substation | |
CN104022514B (en) | Classification is adjustable high voltage reactor and Static Var Compensator optimistic coordinated control method | |
WO2012126271A1 (en) | Electrified railway traction substation reactive power compensation apparatus | |
CN102074958B (en) | Thyristor valve controlled type controllable paralleling reactor device configured with parallel valve branches | |
CN207664626U (en) | Dynamic voltage adjusting device of power distribution network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |