CN102817372A - 地下深基础混凝土反模施工方法 - Google Patents

地下深基础混凝土反模施工方法 Download PDF

Info

Publication number
CN102817372A
CN102817372A CN2011101531432A CN201110153143A CN102817372A CN 102817372 A CN102817372 A CN 102817372A CN 2011101531432 A CN2011101531432 A CN 2011101531432A CN 201110153143 A CN201110153143 A CN 201110153143A CN 102817372 A CN102817372 A CN 102817372A
Authority
CN
China
Prior art keywords
concrete
foundation
reverse
formworks
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101531432A
Other languages
English (en)
Inventor
李刚
于淼
周煜源
苏元洪
陈顺华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN2011101531432A priority Critical patent/CN102817372A/zh
Publication of CN102817372A publication Critical patent/CN102817372A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种地下深基础混凝土反模施工方法,其特征在于包括以下步骤:a、施工支护桩;b、基坑开挖支反模,其中包括以下步骤:(1)支护桩达到养生强度进行开挖基坑;(2)开挖到基坑底标高打垫层;(3)在垫层上对基础精确定位放线;(4)根据放线支设反模;其中:当基础埋深>-5米时,在模板与基坑壁之间用∮6~∮12mm的边角余料钢筋进行焊接和绑扎成钢筋网片,支反模所用的木模是7层以上的夹层板,支模高度与基础砼等高;c、浇注反模混凝土,d、施工混凝土基础。本发明的地下深基础混凝土反模施工方法具有在相邻的建构筑物中间增建新的深基础,开挖施工时能保证邻近建构筑物不发生位移和破坏的优点。

Description

地下深基础混凝土反模施工方法
技术领域
本发明属于建筑施工技术领域,涉及一种地下深基础混凝土的施工方法,具体地说,是一种地下深基础混凝土反模施工方法。
背景技术
对于埋深至-5.0米左右的地下混凝土基础施工,为了满足支设模板的操作空间需要,基坑开挖后的大小必须大于基础混凝土边距800mm以上,但有些特殊情况下基坑却很狭窄,例如基坑与其他原有建、构筑物相邻,在一些技术改造项目或改扩建项目中,经常要在原有建、构物中间新建基础,又如在新近回填的疏松土体或砂质土层地基上开挖,如果水位较高且又无足够的放坡空间情况下,可采取在基坑周围先施工支护桩(如钻孔灌注桩等),然后开挖。
在基坑狭窄无法支模的情况下,常用方法是砌筑砖胎膜,但只适用于较浅的基础。其原因一是砌砖速度慢,地下水很快涌上来,遇到雨季更抵挡不了泥砂,二是砖胎膜超过一定的高度不能承受浇注混凝土时的侧向压力(混凝土本身静压和振捣产生的动压),有变型、倒塌的风险。
因此使用已知的支模方法在地下深基础和基坑狭窄的情况下施工存在着上述种种不便和问题。
发明内容
本发明的目的,在于提出一种适用于多雨季节,疏松砂质土层进行安全、可靠、快捷、方便、经济施工的地下深基础混凝土反模施工方法。
本发明的另一目的,在于提出一种适用于在原有建、构筑物之间进行技术改扩建项目的地下深基础混凝土反模施工方法。
本发明的又一目的,在于提出一种适用于在狭窄的基坑内进行的地下深基础混凝土反模施工方法。
为实现上述目的,本发明的技术解决方案是:
一种地下深基础混凝土反模施工方法,其特征在于包括以下步骤:
a、施工支护桩
根据图纸坐标尺寸进行基础定位放线,然后靠近基础周边施工混凝土支护桩,使边距为300~500mm,所述混凝土支护桩为混凝土灌注桩,或者混凝土连续挡土墙;
b、基坑开挖支反模,其中包括以下步骤:
(1)支护桩达到养生强度进行开挖基坑;
(2)开挖到基坑底标高打垫层;
(3)在垫层上对基础精确定位放线;
(4)根据放线支设反模;
其中:当基础埋深>-5米时,在模板与基坑壁之间用∮6~∮12mm的边角余料钢筋进行焊接和绑扎成钢筋网片,支反模所用的木模是7层以上的夹层板,支模高度与基础砼等高;
c、浇注反模混凝土
浇注反模混凝土,浇筑完成后24小时拆模;
d、施工混凝土基础
利用反模砼墙作为基础的正式模板,施工基础钢筋,浇筑混凝土基础。
本发明的地下深基础混凝土反模施工方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述步骤b基坑开挖支反模中,用拉杆固定模板:在基坑支护桩上凿出钢筋,焊接拉杆用以固定木模板。
前述的方法,其中所述步骤b基坑开挖支反模中,用脚手架钢管支撑模板:在基础内侧用木方、脚手架钢管、扣件等搭设支撑体系。
前述的方法,其中所述步骤c浇注反模混凝土中,反模混凝土的标号为C10。
采用上述技术方案后,本发明的地下深基础混凝土反模施工方法具有以下优点:
1、在相邻的建构筑物中间增建新的深基础,开挖施工时能保证邻近建构筑物不发生位移和破坏;
2、在大面积新回填的疏松土质及粉砂土质,又遇暴雨季节的最不利状况下,能以最快的速度完成基坑的模板支护,防止流砂和土体坍塌;
3、在其他所有无法放坡的狭窄基坑中,勘称最快捷、最安全、质量最可靠,也是比较经济的施工方法。
附图说明
图1为本发明实施例的反模的支撑方式的示意图;
图2为本发明实施例的另一反模的支撑方式的示意图;
图3为本发明实施例的反模成型后示意图;
图4为本发明实施例的用反模砼代替模板施工基础示意图。
图中:1支护桩,2碎石基层,3模板,4垫层,5拉杆螺栓,6钢筋网片,7模板支撑,8木方,9反模,10钢筋,11模板支撑。
具体实施方式
以下结合实施例及其附图对本发明作更进一步说明。
实施例1
本发明的一种地下深基础混凝土反模施工方法,其特征在于包括以下步骤:
a、施工支护桩
根据图纸坐标尺寸进行基础定位放线,然后靠近基础周边施工混凝土支护桩,使边距为300~500mm,所述混凝土支护桩为混凝土灌注桩,或者混凝土连续挡土墙。
b、基坑开挖支反模,其中包括以下步骤:
(1)支护桩达到养生强度进行开挖基坑;
(2)开挖到基坑底标高打垫层;
(3)在垫层上对基础精确定位放线;
(4)根据放线支设反模;
其中:当基础埋深>-5米时,在模板与基坑壁之间用∮6~∮12mm的边角余料钢筋进行焊接和绑扎成钢筋网片,支反模所用的木模可用7层以上的夹层板,均为废旧利用;支模高度与基础砼等高;图1为本发明实施例的反模的支撑方式的示意图,其中反模的支撑方式用拉杆固定模板:在基坑支护桩上凿出钢筋,焊接拉杆用以固定木模板。
c、浇注反模混凝土
图3为本发明实施例的反模成型后示意图,浇注反模混凝土,反模混凝土的标号为C10,浇筑完成后24小时拆模。
d、施工混凝土基础
图4为本发明实施例的用反模砼代替模板施工基础示意图,利用反模砼墙作为基础的正式模板,施工基础钢筋,浇筑混凝土基础。
实施例2
图2为本发明实施例的另一反模的支撑方式的示意图,其中除反模的支撑方式用脚手架钢管支撑模板:在基础内侧用木方、脚手架钢管、扣件等搭设支撑体系外,其余同实施例1。
本发明的地下深基础混凝土反模施工方法在首钢迁钢二冷轧四、六区取向硅钢工程中大范围使用,该工程地下电缆隧道共有40多条,基坑深度均在-5m~-7m之间,纵横交织、布置紧凑、设备基础密布其间,造成基坑狭窄、无支模的操作空间;土建施工阶段又正赶上该地区罕见的暴雨期,挖好的基坑一遇下雨就涌入流砂。应用本发明的地下深基础混凝土反模施工方法,以反模的支撑方式采取了先打支护桩再开挖后支反模的方法,由于支反模速度快,能迅速封闭土体避免雨水侵蚀,使工期提前半个月完成。
本发明的地下深基础混凝土反模施工方法,预先在基础面内侧支护简易的反向模板,在此反模板与基坑壁之间预浇注C10标号的混凝土,达到一定强度后拆除简易的反模模板,成型的混凝土墙,就可代替基础正式模板,待基础施工完毕也无需凿除,直接埋入回填土即可。这种反模支护简单、效率极高,绝无塌方和流砂等安全隐患,模板全为废旧利用因而也非常经济适用。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。

Claims (4)

1.一种地下深基础混凝土反模施工方法,其特征在于包括以下步骤:
a、施工支护桩:
根据图纸坐标尺寸进行基础定位放线,然后靠近基础周边施工混凝土支护桩,使边距为300~500mm,所述混凝土支护桩为混凝土灌注桩,或者混凝土连续挡土墙;
b、基坑开挖支反模,其中包括以下步骤:
(1)支护桩达到养生强度进行开挖基坑;
(2)开挖到基坑底标高打垫层;
(3)在垫层上对基础精确定位放线;
(4)根据放线支设反模;
其中:当基础埋深>-5米时,在模板与基坑壁之间用∮6~∮12mm的边角余料钢筋进行焊接和绑扎成钢筋网片,支反模所用的木模是7层以上的夹层板,支模高度与基础砼等高;
c、浇注反模混凝土:
浇注反模混凝土,浇筑完成后24小时拆模;
d、施工混凝土基础:
利用反模砼墙作为基础的正式模板,施工基础钢筋,浇筑混凝土基础。
2.如权利要求1所述的地下深基础混凝土反模施工方法,其特征在于,所述步骤b基坑开挖支反模中,用拉杆固定模板:在基坑支护桩上凿出钢筋,焊接拉杆用以固定木模板。
3.如权利要求1所述的地下深基础混凝土反模施工方法,其特征在于,所述步骤b基坑开挖支反模中,用脚手架钢管支撑模板:在基础内侧用木方、脚手架钢管、扣件搭设支撑体系。
4.如权利要求1所述的地下深基础混凝土反模施工方法,其特征在于,所述步骤c浇注反模混凝土中,反模混凝土的标号为C10。
CN2011101531432A 2011-06-09 2011-06-09 地下深基础混凝土反模施工方法 Pending CN102817372A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101531432A CN102817372A (zh) 2011-06-09 2011-06-09 地下深基础混凝土反模施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101531432A CN102817372A (zh) 2011-06-09 2011-06-09 地下深基础混凝土反模施工方法

Publications (1)

Publication Number Publication Date
CN102817372A true CN102817372A (zh) 2012-12-12

Family

ID=47301786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101531432A Pending CN102817372A (zh) 2011-06-09 2011-06-09 地下深基础混凝土反模施工方法

Country Status (1)

Country Link
CN (1) CN102817372A (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669368A (zh) * 2013-12-26 2014-03-26 上海建工二建集团有限公司 逆作板施工结构及其施工方法
CN104131576A (zh) * 2014-07-31 2014-11-05 中建一局集团第三建筑有限公司 一种止水帷幕抗渗构造及其施工方法
CN105544561A (zh) * 2016-02-25 2016-05-04 中铁十八局集团有限公司 抗滑桩护壁混凝土快速浇注的施工方法
CN105625435A (zh) * 2014-10-30 2016-06-01 五冶集团上海有限公司 海积岛屿多截面、多层次异型设备深基坑快速成型方法
CN105821885A (zh) * 2015-01-05 2016-08-03 五冶集团上海有限公司 海积岛屿复杂地质中超长基坑的组合式支护和维护方法
CN108252324A (zh) * 2018-02-01 2018-07-06 浙江水利水电学院 一种河床底部混凝土挡土墙固定装置及施工方法
CN109989408A (zh) * 2019-05-23 2019-07-09 中铁城市规划设计研究院有限公司 一种城市轻轨超深基坑混凝土浇筑支护施工方法
CN111576444A (zh) * 2020-06-01 2020-08-25 范春青 一种基坑地下支护结构及其施工工艺
CN111794265A (zh) * 2020-05-29 2020-10-20 五冶集团上海有限公司 一种通过隔离淤泥进行设备基础施工的方法
CN111794266A (zh) * 2020-05-29 2020-10-20 五冶集团上海有限公司 一种滩涂回填区域淤泥地质条件下设备基础的施工方法
CN114737570A (zh) * 2022-05-07 2022-07-12 中建八局第二建设有限公司 一种基于单侧模板的山体边坡深基坑支护施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126240A (zh) * 2006-08-16 2008-02-20 上海电力设计院有限公司 深基坑开挖过程中利用时差效应控制基坑变形的方法
CN101328713A (zh) * 2008-07-18 2008-12-24 华丰建设股份有限公司 圆形深基坑支护的施工方法
CN201212150Y (zh) * 2008-06-06 2009-03-25 中铁十四局集团有限公司 地铁明挖车站大模板衬砌台车
JP4382625B2 (ja) * 2004-10-12 2009-12-16 株式会社ピーエス三菱 コンクリート土留壁及びその施工方法
CN101761092A (zh) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 大跨度深基坑可移动整体大模板侧墙施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4382625B2 (ja) * 2004-10-12 2009-12-16 株式会社ピーエス三菱 コンクリート土留壁及びその施工方法
CN101126240A (zh) * 2006-08-16 2008-02-20 上海电力设计院有限公司 深基坑开挖过程中利用时差效应控制基坑变形的方法
CN201212150Y (zh) * 2008-06-06 2009-03-25 中铁十四局集团有限公司 地铁明挖车站大模板衬砌台车
CN101328713A (zh) * 2008-07-18 2008-12-24 华丰建设股份有限公司 圆形深基坑支护的施工方法
CN101761092A (zh) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 大跨度深基坑可移动整体大模板侧墙施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨国俊: "单侧墙体大钢模模板施工技术", 《重庆建筑》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669368A (zh) * 2013-12-26 2014-03-26 上海建工二建集团有限公司 逆作板施工结构及其施工方法
CN103669368B (zh) * 2013-12-26 2016-05-11 上海建工二建集团有限公司 逆作板施工结构及其施工方法
CN104131576A (zh) * 2014-07-31 2014-11-05 中建一局集团第三建筑有限公司 一种止水帷幕抗渗构造及其施工方法
CN104131576B (zh) * 2014-07-31 2016-01-20 中建一局集团第三建筑有限公司 一种止水帷幕抗渗构造的施工方法
CN105625435A (zh) * 2014-10-30 2016-06-01 五冶集团上海有限公司 海积岛屿多截面、多层次异型设备深基坑快速成型方法
CN105821885A (zh) * 2015-01-05 2016-08-03 五冶集团上海有限公司 海积岛屿复杂地质中超长基坑的组合式支护和维护方法
CN105544561A (zh) * 2016-02-25 2016-05-04 中铁十八局集团有限公司 抗滑桩护壁混凝土快速浇注的施工方法
CN105544561B (zh) * 2016-02-25 2017-10-13 中铁十八局集团有限公司 抗滑桩护壁混凝土快速浇注的施工方法
CN108252324A (zh) * 2018-02-01 2018-07-06 浙江水利水电学院 一种河床底部混凝土挡土墙固定装置及施工方法
CN108252324B (zh) * 2018-02-01 2020-09-11 浙江水利水电学院 一种河床底部混凝土挡土墙固定装置及施工方法
CN109989408A (zh) * 2019-05-23 2019-07-09 中铁城市规划设计研究院有限公司 一种城市轻轨超深基坑混凝土浇筑支护施工方法
CN111794265A (zh) * 2020-05-29 2020-10-20 五冶集团上海有限公司 一种通过隔离淤泥进行设备基础施工的方法
CN111794266A (zh) * 2020-05-29 2020-10-20 五冶集团上海有限公司 一种滩涂回填区域淤泥地质条件下设备基础的施工方法
CN111576444A (zh) * 2020-06-01 2020-08-25 范春青 一种基坑地下支护结构及其施工工艺
CN114737570A (zh) * 2022-05-07 2022-07-12 中建八局第二建设有限公司 一种基于单侧模板的山体边坡深基坑支护施工方法

Similar Documents

Publication Publication Date Title
CN102817372A (zh) 地下深基础混凝土反模施工方法
CN107542108B (zh) 一种建筑物地下室结构的逆向施工方法
CN205742213U (zh) 基坑支护结构
EP2761098B1 (en) Retaining wall construction using site compaction and excavation
CN101691751B (zh) 超长人工挖孔桩穿越溶洞施工方法及穿越溶洞的超长桩
CN106958256A (zh) 一种分层浇筑、多次下沉的沉井施工工艺
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN104264688A (zh) 人工挖孔变截面桩支护施工工艺
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN106049505A (zh) 一种深基坑支撑支护体系的施工方法
CN112554198B (zh) 紧邻高层建筑物的深基坑防护结构的施工方法
CN110939303B (zh) 一种旋流池半逆作法施工方法
Godavarthi et al. Contiguous pile wall as a deep excavation supporting system
CN206070508U (zh) 一种加固地基基础的装置
CN109706952A (zh) 大型沉井施工方法
CN104264683A (zh) 三面环绕文保建筑凹字形超深基坑分区支护方法
CN110055973B (zh) 施工空间受限时的高铁桥下基坑围护结构与止水方法
CN101994314A (zh) 深孔矩形联排抗滑桩不跳桩开挖施工
CN105484270B (zh) 一种毗邻深基坑高陡老旧毛石挡土墙加固保护施工方法
CN110306989B (zh) 一种非明挖装配式管沟开挖支护加固方法
CN104480945A (zh) 一种基坑逆作施工方法
CN114922195A (zh) 一种紧邻保护对象的软土深大基坑施工方法
CN114232602A (zh) 地下连续桩施工工艺
CN114837455B (zh) 一种沉陷水工建筑物的复建方法
CN112609706B (zh) 填海区基坑对撑角撑混凝土水平支护结构施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121212