CN102815627A - Automatic traction system for large-scale tower-type crane standard-knot removal and installation - Google Patents

Automatic traction system for large-scale tower-type crane standard-knot removal and installation Download PDF

Info

Publication number
CN102815627A
CN102815627A CN2012102756334A CN201210275633A CN102815627A CN 102815627 A CN102815627 A CN 102815627A CN 2012102756334 A CN2012102756334 A CN 2012102756334A CN 201210275633 A CN201210275633 A CN 201210275633A CN 102815627 A CN102815627 A CN 102815627A
Authority
CN
China
Prior art keywords
introduction
trailer
traction
traction system
dolly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102756334A
Other languages
Chinese (zh)
Inventor
周勇
李绍俊
张�浩
杨硕
邹纪钞
袁利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Jincheng Construction Machinery Co Ltd
SICHUAN NO3 CONSTRUCTION ENGINEERING Co
Original Assignee
Sichuan Jincheng Construction Machinery Co Ltd
SICHUAN NO3 CONSTRUCTION ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Jincheng Construction Machinery Co Ltd, SICHUAN NO3 CONSTRUCTION ENGINEERING Co filed Critical Sichuan Jincheng Construction Machinery Co Ltd
Priority to CN2012102756334A priority Critical patent/CN102815627A/en
Publication of CN102815627A publication Critical patent/CN102815627A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses an automatic traction system for large-scale tower-type crane standard-knot removal and installation and relates to the technical field of building construction machinery. The automatic traction system solves the technical problem that the existing traction system for tower-type crane standard-knot removal and installation adopts a manual traction method so that operation carried out by removal and installation operators is difficult and has low efficiency. A traction mechanism (5) of the automatic traction system is installed on a tail of a single-track introduction beam (2). An end of the single-track introduction beam (2) is provided with a leading sheave. The traction mechanism (5) passes through and is wound by a traction steel wire rope (6). A long end (7) of the traction steel wire rope (6) bypasses the leading sheave and then is fixed to an introduction trolley (3) by a rope cappel. A short end (8) of the traction steel wire rope (6) is connected to a rope tensioning device (10) on the introduction trolley (3). An introduction trailer (4) is connected to a standard-knot (9) by steel wire ropes. Two sides of the introduction trailer (4) are respectively provided with lifting lugs (11). Two sides of the introduction trolley (3) are respectively provided with angle steel mount points (13).

Description

Large-scale tower crane peace is torn the automatic traction system of standard knot open
Technical field
Patent of the present invention relates to the constructional engineering machinery technical field, particularly the automatic traction system torn open of the peace of various column crane mast section.
 
Background technology
Referring to accompanying drawing 11, existing general-duty column crane mast section peace is torn introduction system open and is adopted manpower to draw, and this standard knot traction system mainly introduces beam by two and an introduction dolly is formed.The imported unit that now more common tower machine standard knot peace is torn open is made up of jacking suspension hook, introduction beam, introduction dolly three big parts; Need change peace when peace is torn standard knot open and tear the special-purpose jacking suspension hook of standard knot open; The jacking suspension hook tangles the introduction dolly; Introduce to rise after dolly use bolt pin is connected with standard knot and rise to the standard knot introduction Liang Chu that installs with undersetting; Peace is torn personnel open and to introducing on the beam jacking suspension hook and introduction dolly is broken away from, and the disengaging back peace personnel of tearing open stand on the stock upper platform and pull, and standard knot is introduced put in place.
Existing general-duty column crane mast section peace is torn introduction system open and is adopted manpower to draw, and the shortcoming or the weak point of existence have:
1, peace is torn the personnel operation difficulty open;
Aloft work when 2, the operating personal peace is torn operation open has a big risk;
Efficient was low when 3, peace was torn operation open;
Labour intensity was big when 4, peace was torn operation open.
 
Summary of the invention
The present invention is intended to solve existing column crane mast section peace and tears introduction system open and exist and adopt manpower to draw, pacify technical matters such as tear the personnel operation difficulty open, operating risk is big, labour intensity is big and efficient is low, with provide a kind of peace to tear high efficiency open, operating personal is easy to operate, labour intensity is low and safety factor is high large-scale tower crane peace is torn the automatic traction system of standard knot open.
The objective of the invention is to realize through following technical scheme.
Large-scale tower crane peace of the present invention is torn the automatic traction system of standard knot open; Introducing beam 2, introduction dolly 3, introduction trailer 4 and trailer coupling 5 by jacking suspension hook 1, single track constitutes; Wherein trailer coupling 5 is installed on the afterbody that single track is introduced beam 2; Single track introduce beam 2 the position, termination be equiped with leading sheave; Trailer coupling 5 is worn around haulage cable 6, and the long end 7 of haulage cable 6 is walked around behind the leading sheave with introducing dolly 3 and fixed through wire clips, and the short end 8 of haulage cable 6 links to each other with tight rope device 10 on the introduction dolly 3; The steel rope that passes through of introducing trailer 4 is connected with standard knot 9; The both sides of introducing trailer 4 are respectively equipped with hanger 11; The both sides of introducing dolly 3 are respectively equipped with angle steel hanging point 13.
The large-scale tower crane peace of the present invention is torn the beneficial effect of the automatic traction system of standard knot open: improved peace greatly and torn work efficiency open; Labour intensity when having reduced installation exercise; Reduce operating personal, the aloft work risk when having reduced installation exercise has made things convenient for peace to tear operating personnel's operation open.
 
Description of drawings
Fig. 1 the present invention's system architecture scheme drawing
Fig. 2 is that right elevation is amplified in the part of Fig. 1
Fig. 3 haulage cable wiring scheme drawing one
Fig. 4 haulage cable wiring scheme drawing two
Fig. 5 introduces the vehicle structure scheme drawing
Fig. 6 is the right elevation of Fig. 5
Fig. 7 introduces the trailer structure scheme drawing
Fig. 8 is the right elevation of Fig. 7
Fig. 9 jacking suspension hook structural representation
Figure 10 tower machine suspension hook structural representation
Figure 11 tradition column crane mast section peace is torn the introduction system structural representation open
Label declaration among the figure:
1 jacking suspension hook, 2 single tracks are introduced beam, 3 and are introduced dolly, 4 introduction trailers, 5 trailer couplings, 6 haulage cables, 7 long ends, 8 short ends, 9 standard knots, 10 tight rope devices, 11 hangers, 12 operating personal positions, 13 angle steel hanging points, 21 traditional jacking suspension hooks, 22 traditional beam, 23 tradition introduction dollies introduced
The specific embodiment
Detailed structure of the present invention, application principle, effect and effect with reference to accompanying drawing 1-10, are explained through following embodiment.
Introducing beam 2, introduction dolly 3, introduction trailer 4 and trailer coupling 5 by jacking suspension hook 1, single track constitutes; Single track is introduced beam 2 and is installed on the undersetting lower faceplate; Single track is introduced on the beam 2 platform, the railing that the personnel of tearing open pass through is installed; Wherein trailer coupling 5 is installed on the afterbody that single track is introduced beam 2; Single track introduce beam 2 the position, termination be equiped with leading sheave, trailer coupling 5 is worn around haulage cable 6, the long end 7 of haulage cable 6 is walked around behind the leading sheave with introduction dolly 3 and is fixed through wire clips; The short end 8 of haulage cable 6 links to each other with tight rope device 10 on introducing dolly 3 and that hauling rope is carried out actv. is fastening, restricts neatly to guarantee that haulage cable arrange on the reel of trailer coupling 5; Fix 4 steel ropes respectively through shackle on the hole on four jiaos of introduction trailer 4; Another termination of steel rope and the attachment point on the standard knot use shackle to fix; The upper end of jacking suspension hook 1 hangs on the suspension hook of tower machine; The lower end of jacking suspension hook 1 hangs on the hanger 11 of introducing trailer 4 both sides; To introduce trailer 4 through the lifting mechanism of tower machine self hangs on the introduction dolly 3; The peace personnel of tearing open are up on single track introduction beam 2 platforms jacking suspension hook 1 are separated with introduction trailer 4, introduce trailer 4 and hang on the angle steel hanging point 13 of introducing dolly 3 both sides, and the peace personnel that tear open operate trailer coupling 5 on the platform of stock rear operating handle can be introduced moving backward forward of dolly 3.
In sum, the large-scale tower crane peace of the present invention is torn the automatic traction system of standard knot open, has improved peace greatly and has torn work efficiency open; Labour intensity when having reduced installation exercise; Reduce operating personal, the aloft work risk when having reduced installation exercise has made things convenient for peace to tear operating personnel's operation open.

Claims (1)

1. large-scale tower crane peace is torn the automatic traction system of standard knot open; It is characterized in that: introduce beam (2), introduce dolly (3), introduce trailer (4) and trailer coupling (5) formation by jacking suspension hook (1), single track; Wherein trailer coupling (5) is installed on the afterbody that single track is introduced beam (2); Single track introduce beam (2) the position, termination be equiped with leading sheave; Trailer coupling (5) is worn around haulage cable (6), and the long end (7) of haulage cable (6) is walked around behind the leading sheave and fixed through wire clips with introducing dolly (3), and the short end (8) of haulage cable (6) links to each other with tight rope device (10) on the introduction dolly (3); The steel rope that passes through of introducing trailer (4) is connected with standard knot (9); The both sides of introducing trailer (4) are respectively equipped with hanger (11); The both sides of introducing dolly (3) are respectively equipped with angle steel hanging point (13).
CN2012102756334A 2012-08-06 2012-08-06 Automatic traction system for large-scale tower-type crane standard-knot removal and installation Pending CN102815627A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102756334A CN102815627A (en) 2012-08-06 2012-08-06 Automatic traction system for large-scale tower-type crane standard-knot removal and installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102756334A CN102815627A (en) 2012-08-06 2012-08-06 Automatic traction system for large-scale tower-type crane standard-knot removal and installation

Publications (1)

Publication Number Publication Date
CN102815627A true CN102815627A (en) 2012-12-12

Family

ID=47300142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102756334A Pending CN102815627A (en) 2012-08-06 2012-08-06 Automatic traction system for large-scale tower-type crane standard-knot removal and installation

Country Status (1)

Country Link
CN (1) CN102815627A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103058072A (en) * 2012-12-31 2013-04-24 大连理工大学 Large luffing jib tower crane introduction mechanism
CN103407903A (en) * 2012-08-18 2013-11-27 上海庞源机械租赁股份有限公司 Automatic traction system for large-size tower crane mounting and dismounting standard knot and traction method thereof
CN103708360A (en) * 2013-12-19 2014-04-09 中联重科股份有限公司 Movable arm tower crane, and standard knot introduction system and standard knot introduction method thereof
CN103771266A (en) * 2014-01-07 2014-05-07 中联重科股份有限公司 Method for unloading load pulley from tower crane
CN105502179A (en) * 2015-09-30 2016-04-20 徐州建机工程机械有限公司 Auxiliary device for introducing standard sections
CN104555829B (en) * 2013-10-11 2017-03-29 卓越置业集团有限公司 Automatic transmission
CN106744367A (en) * 2016-12-09 2017-05-31 徐州建机工程机械有限公司 A kind of tower crane jacking is from introducing equipment, system and control method
CN108996408A (en) * 2018-10-23 2018-12-14 江苏省送变电有限公司 Standard knot introduction trolley and track
CN110259256A (en) * 2019-05-24 2019-09-20 浙江省建设机械集团有限公司 A kind of electric power pole standard section electric imported unit and its control method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU363318A1 (en) * 1970-11-27 1976-03-05 Центральное Конструкторское Бюро "Строймаш" Traverse for installation of a tower crane
SU1323521A1 (en) * 1986-03-26 1987-07-15 Центральное проектно-конструкторское бюро по лифтам Arrangement for erecting of tower crane
CN2119409U (en) * 1991-12-27 1992-10-21 上海住益建筑机械厂 Crane for floor building blocks
JPH07315766A (en) * 1994-05-20 1995-12-05 Takenaka Komuten Co Ltd Shuttle jib type climbing crane
CN201068371Y (en) * 2007-06-12 2008-06-04 王生银 Self-hoisting tower crane
CN201901539U (en) * 2010-09-27 2011-07-20 中昇建机(南京)重工有限公司 Internal climbing type and external climbing type tower crane with luffing jib
CN202214152U (en) * 2011-07-05 2012-05-09 江苏省特种设备安全监督检验研究院 Trolley walking traction mechanism of bridge crane

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU363318A1 (en) * 1970-11-27 1976-03-05 Центральное Конструкторское Бюро "Строймаш" Traverse for installation of a tower crane
SU1323521A1 (en) * 1986-03-26 1987-07-15 Центральное проектно-конструкторское бюро по лифтам Arrangement for erecting of tower crane
CN2119409U (en) * 1991-12-27 1992-10-21 上海住益建筑机械厂 Crane for floor building blocks
JPH07315766A (en) * 1994-05-20 1995-12-05 Takenaka Komuten Co Ltd Shuttle jib type climbing crane
CN201068371Y (en) * 2007-06-12 2008-06-04 王生银 Self-hoisting tower crane
CN201901539U (en) * 2010-09-27 2011-07-20 中昇建机(南京)重工有限公司 Internal climbing type and external climbing type tower crane with luffing jib
CN202214152U (en) * 2011-07-05 2012-05-09 江苏省特种设备安全监督检验研究院 Trolley walking traction mechanism of bridge crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘佩衡: "塔式起重机安装、拆卸、顶升、附着与内爬", 《工程机械》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103407903A (en) * 2012-08-18 2013-11-27 上海庞源机械租赁股份有限公司 Automatic traction system for large-size tower crane mounting and dismounting standard knot and traction method thereof
CN103058072B (en) * 2012-12-31 2015-04-08 大连理工大学 Large luffing jib tower crane introduction mechanism
CN103058072A (en) * 2012-12-31 2013-04-24 大连理工大学 Large luffing jib tower crane introduction mechanism
CN104555829B (en) * 2013-10-11 2017-03-29 卓越置业集团有限公司 Automatic transmission
CN103708360A (en) * 2013-12-19 2014-04-09 中联重科股份有限公司 Movable arm tower crane, and standard knot introduction system and standard knot introduction method thereof
CN103708360B (en) * 2013-12-19 2015-12-02 中联重科股份有限公司 Movable arm tower crane and standard knot introduction system thereof and standard knot introduction method
CN103771266A (en) * 2014-01-07 2014-05-07 中联重科股份有限公司 Method for unloading load pulley from tower crane
CN105502179A (en) * 2015-09-30 2016-04-20 徐州建机工程机械有限公司 Auxiliary device for introducing standard sections
CN106744367A (en) * 2016-12-09 2017-05-31 徐州建机工程机械有限公司 A kind of tower crane jacking is from introducing equipment, system and control method
CN106744367B (en) * 2016-12-09 2018-07-31 徐州建机工程机械有限公司 A kind of jacking of tower crane is from introducing equipment, system and control method
CN108996408A (en) * 2018-10-23 2018-12-14 江苏省送变电有限公司 Standard knot introduction trolley and track
CN110259256A (en) * 2019-05-24 2019-09-20 浙江省建设机械集团有限公司 A kind of electric power pole standard section electric imported unit and its control method
CN110259256B (en) * 2019-05-24 2024-04-09 浙江省建设机械集团有限公司 Standard electricity-saving electric introduction device for electric pole and control method thereof

Similar Documents

Publication Publication Date Title
CN102815627A (en) Automatic traction system for large-scale tower-type crane standard-knot removal and installation
CN201458596U (en) Crane with self-dismounting device
CN210003305U (en) Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes
CN109973130A (en) Once draw construction system and method in place in a kind of main cable strand realization narrow space of Super Long Tunnel anchor
CN111636313B (en) Installation and maintenance system for bridge inhaul cable brightening engineering and construction method thereof
CN100580182C (en) Soft and hard composite three-level traction technique for stay cables and connecting device thereof
CN109853393A (en) A kind of the hanging cable construction system and its construction method of king-tower vertical transfer cable-stayed bridge
CN103407903B (en) A kind of large-scale derrick crane peace tears the traction method of the automatic trailer system of standard knot open
CN201817208U (en) Simple lifting machine
CN216235734U (en) Vertical transportation hoisting structure for curtain wall unit plate
CN204750193U (en) Automatic decoupling device device in sub -inclined shaft pittop
CN202542743U (en) Auxiliary reeving mechanism for mounting tower crane
CN204967120U (en) Wire exhibition of pulling is put special steel pipe and is strideed across frame
CN113605230A (en) Main cable traction system and method suitable for suspension bridge two-bank tunnel anchor
CN209836818U (en) Large-tonnage cable saddle gliding and mounting system for ultra-long large-inclination-angle tunnel anchor
CN202880710U (en) Automatic traction system of large-sized tower type crane assembling and disassembling standard knot
CN108233275B (en) Auxiliary traction system for cable to pass through CSE cylinder
CN202626985U (en) Hoist traction anchor cable penetration device
CN102704477B (en) Cable threading device and method of chain hoist traction anchor cable
CN202772502U (en) Monorail crane for towing electric cables
CN201473171U (en) Moving and lifting dual-purpose hanging device of cableway device
CN102490758A (en) Emergency braking device for descending mine car
CN202131996U (en) Steel wire rope traction device of rotary drilling machine
CN212174274U (en) Large-span suspension bridge cable crane traction system with combined type sports car and traction tackle
CN205452955U (en) Power line driving

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121212