CN102787855A - Excavating and supporting method of roadway containing quicksand layer - Google Patents
Excavating and supporting method of roadway containing quicksand layer Download PDFInfo
- Publication number
- CN102787855A CN102787855A CN2012102865312A CN201210286531A CN102787855A CN 102787855 A CN102787855 A CN 102787855A CN 2012102865312 A CN2012102865312 A CN 2012102865312A CN 201210286531 A CN201210286531 A CN 201210286531A CN 102787855 A CN102787855 A CN 102787855A
- Authority
- CN
- China
- Prior art keywords
- supporting
- roadway
- quicksand layer
- excavating
- sand formation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses an excavating and supporting method of a roadway containing a quicksand layer; the method comprises the following steps that (1) before the roadway is excavated, a slip casting pipe is arranged into the quicksand layer in front of an excavation direction along the design section line of the roadway, cementing slurry is injected into the quicksand layer by a slip casting pump, so that the quicksand layer is cemented together, and then an advanced temporary supporting method is adopted; (2) the roadway is excavated through a conventional excavating method, and anchor mesh spray primary supporting is carried out through a conventional supporting method after safe footage is reached; (3) anchor rope secondary supporting is carried out, a steel strand with the diameter being phi 12mm to 16mm and the length being 5m to 8m is adopted as an anchor rope, and the anchoring length needs to be more than 1m; and (4) U-shaped steel telescopic supports are used for enhancing the supporting, and the spacing between the U-shaped steel telescopic supports is 0.8m to 1.0m. According to the excavating and supporting method of the roadway containing quicksand layer, the problems that the quicksand layer is easy to collapse so that the formation of the roadway is difficult and the construction is unsafe are solved; and in addition, the supporting capability is improved, so that the deformation of the roadway after being supported is greatly improved, and the requirement of long-term stability is met.
Description
Technical field
The present invention relates to the tunnelling supporting method.
Background technology
In colliery underworkings (especially crossdrift) driving, often run into the situation that drift sand formation is passed in the tunnel at present, as adopting common temporary lining measure, drift sand formation collapses easily during tunneling construction, and drift section is difficult to be shaped, and it is also dangerous to construct; And the excavation back adopts common anchor net spray supporting method to be difficult to reach supporting effect as simple; Top board just showed tangible distortion increase phenomenon when supporting was accomplished one month; Deflection reaches more than the 500mm; Two help distortion also at 300mm simultaneously, rate of deformation reaches 11mm/d, has exceeded the ultimate deformation that general bolt support allowed; The pallet phenomenon of caving under bolt support, occurs simultaneously, be difficult to reach supporting effect.
Summary of the invention
For addressing the above problem, the present invention proposes the tunnelling supporting method that a kind of safety is passed drift sand formation.
The technical scheme that the present invention takes is that the laneway support method of glued soft rock and drift sand formation a little less than a kind of safety is passed is characterized in that it may further comprise the steps:
The first step, before tunnelling, along squeezing into Grouting Pipe in the drift sand formation in tunnel design section alignment driving the place ahead, in drift sand formation, inject glued slurries with grouting pump; Making drift sand formation glued is one, takes leading temporary lining method again, promptly on drift section overhead pulley profile, beats spacing 0.3m; Diameter 38mm, the boring of dark 3.0m, 1 inch steel pipe or φ 30 round steel of the long 4m of insertion in the boring; Insert the outer termination of exposing of leaving 1.0m of back boring, and set up the arched frame canopy and hold steel pipe and expose the termination;
Second step, by conventional driving method excavation tunnel, carry out anchor net spray once supporting by conventional supporting method after reaching safe drilling depth;
Behind the 3rd step, the anchor net spray once supporting, carry out the anchor cable secondary supporting again, anchor cable adopts the steel strand of Φ 12-16mm, length 5-8m, and anchorage length should be greater than 1m;
Behind the 4th step, the anchor cable secondary supporting, adopt U-shaped steel collapsible timbering to add strong supporting again, U-shaped steel collapsible timbering spacing 0.8-1.0m.
In order further to strengthen supporting effect, when the anchor cable secondary supporting, can install the reinforcing bar ladder beam at the back position simultaneously; Described reinforcing bar ladder beam is the truss that is welded with reinforcing bar.
The invention solves the roadway forming difficulty that drift sand formation collapses easily and causes, the construction unsafe problems; And increased support capacity, make supporting after roadway deformation obtained bigger improvement, reached the long-time stability requirement.
Description of drawings
Fig. 1 is the sectional schematic diagram of the embodiment of the invention.
The specific embodiment
With reference to accompanying drawing and the described technical scheme of summary of the invention, those skilled in the art can implement.
The first step in the face of technical scheme specifies down.
1, Grouting Pipe employing diameter is that 1 inch, length are the steel pipe of 3.5m, the some apertures of quincuncial arrangement on the steel pipe tube wall, and the aperture is 6mm, and pitch-row is 200mm, and the steel pipe tube head is fined away.
2, the installation of Grouting Pipe also should meet following regulation:
The Grouting Pipe spacing should be confirmed according to the country rock situation.When adopting individual layer to arrange, its spacing is preferably 200~400mm; When adopting double-deck the layout, its spacing is preferably 400~600mm, and levels should be staggeredly arranged.
The outer subtended angle degree of Grouting Pipe should be confirmed according to the thickness of the glued arch of slip casting, be preferably 10 °~25 °.
Grouting pressure should be generally 0.5~1.0MPa according to the decision of stratum compactness extent.
Claims (2)
1. tunnelling supporting method that contains drift sand formation is characterized in that it may further comprise the steps:
The first step, before tunnelling, along squeezing into Grouting Pipe in the drift sand formation in tunnel design section alignment driving the place ahead, in drift sand formation, inject glued slurries with grouting pump; Making drift sand formation glued is one, takes leading temporary lining method again, promptly on drift section overhead pulley profile, beats spacing 0.3m; Diameter 38mm, the boring of dark 3.0m, 1 inch steel pipe or φ 30 round steel of the long 4m of insertion in the boring; Insert the outer termination of exposing of leaving 1.0m of back boring, and set up the arched frame canopy and hold steel pipe and expose the termination;
Second step, by conventional driving method excavation tunnel, carry out anchor net spray once supporting by conventional supporting method after reaching safe drilling depth;
Behind the 3rd step, the anchor net spray once supporting, carry out the anchor cable secondary supporting again, anchor cable adopts the steel strand of Φ 12-16mm, length 5-8m, and anchorage length should be greater than 1m;
Behind the 4th step, the anchor cable secondary supporting, adopt U-shaped steel collapsible timbering to add strong supporting again, U-shaped steel collapsible timbering spacing 0.8-1.0m.
2. the tunnelling supporting method that contains drift sand formation as claimed in claim 1 is characterized in that, when the anchor cable secondary supporting, installs the reinforcing bar ladder beam at the back position simultaneously.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102865312A CN102787855A (en) | 2012-08-13 | 2012-08-13 | Excavating and supporting method of roadway containing quicksand layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102865312A CN102787855A (en) | 2012-08-13 | 2012-08-13 | Excavating and supporting method of roadway containing quicksand layer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102787855A true CN102787855A (en) | 2012-11-21 |
Family
ID=47153416
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012102865312A Pending CN102787855A (en) | 2012-08-13 | 2012-08-13 | Excavating and supporting method of roadway containing quicksand layer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102787855A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061779A (en) * | 2012-12-25 | 2013-04-24 | 中鼎国际工程有限责任公司 | Novel mine tunnel supporting structure and construction method thereof |
CN104100280A (en) * | 2014-07-07 | 2014-10-15 | 中冶交通工程技术有限公司 | Primary double-wing outrigger support structure and tunnel construction method thereof |
CN104879150A (en) * | 2014-12-31 | 2015-09-02 | 龙口矿业集团有限公司 | Anchor cable support method for deep soft rock roadway without stable rock stratum |
CN105484753A (en) * | 2015-12-29 | 2016-04-13 | 龙口矿业集团有限公司 | Tunneling support method for high-water-pressure high-flow fracture zone |
CN105507923A (en) * | 2015-12-29 | 2016-04-20 | 大同煤矿集团有限责任公司 | Bolting-wire mesh-shotcreting support and bolt-cable coupling support integrated supporting method for large-span chamber |
CN105927231A (en) * | 2016-05-24 | 2016-09-07 | 中国矿业大学 | Cyclic induction curtain grouting method for inclined shaft to penetrate through water-enriched compact quicksand stratum |
CN109184747A (en) * | 2018-10-24 | 2019-01-11 | 中南大学 | A kind of method for protecting support of Deep Soft Rock Tunnel |
CN117248915A (en) * | 2023-11-16 | 2023-12-19 | 矿冶科技集团有限公司 | Method for constructing drift sand stratum roadway |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4052860A (en) * | 1974-12-09 | 1977-10-11 | Environmental Engineering Dr. Ing. Alterman Ltd. | Construction of underground tunnels and rock chambers |
CN101498220A (en) * | 2009-03-16 | 2009-08-05 | 煤炭科学研究总院西安研究院 | Vertical shaft working surface artesian flow sand layer slurry protecting rotary spraying grouting process |
-
2012
- 2012-08-13 CN CN2012102865312A patent/CN102787855A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4052860A (en) * | 1974-12-09 | 1977-10-11 | Environmental Engineering Dr. Ing. Alterman Ltd. | Construction of underground tunnels and rock chambers |
CN101498220A (en) * | 2009-03-16 | 2009-08-05 | 煤炭科学研究总院西安研究院 | Vertical shaft working surface artesian flow sand layer slurry protecting rotary spraying grouting process |
Non-Patent Citations (2)
Title |
---|
亓荣强等: "弱胶结软岩巷道支护实践与合理支护形式探讨", 《采矿技术》, vol. 11, no. 1, 31 January 2011 (2011-01-31), pages 28 - 29 * |
周少杰: "谈管棚法穿越暗河沙层段施工过程的监理", <<山西建筑>>, vol. 38, no. 20, 31 July 2012 (2012-07-31), pages 228 - 229 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061779A (en) * | 2012-12-25 | 2013-04-24 | 中鼎国际工程有限责任公司 | Novel mine tunnel supporting structure and construction method thereof |
CN103061779B (en) * | 2012-12-25 | 2014-11-05 | 中鼎国际工程有限责任公司 | Novel mine tunnel supporting structure and construction method thereof |
CN104100280A (en) * | 2014-07-07 | 2014-10-15 | 中冶交通工程技术有限公司 | Primary double-wing outrigger support structure and tunnel construction method thereof |
CN104879150A (en) * | 2014-12-31 | 2015-09-02 | 龙口矿业集团有限公司 | Anchor cable support method for deep soft rock roadway without stable rock stratum |
CN105484753A (en) * | 2015-12-29 | 2016-04-13 | 龙口矿业集团有限公司 | Tunneling support method for high-water-pressure high-flow fracture zone |
CN105507923A (en) * | 2015-12-29 | 2016-04-20 | 大同煤矿集团有限责任公司 | Bolting-wire mesh-shotcreting support and bolt-cable coupling support integrated supporting method for large-span chamber |
CN105484753B (en) * | 2015-12-29 | 2018-01-23 | 龙口矿业集团有限公司 | The Supporting Method for Drifting of high hydraulic pressure big flow crushed zone |
CN105927231A (en) * | 2016-05-24 | 2016-09-07 | 中国矿业大学 | Cyclic induction curtain grouting method for inclined shaft to penetrate through water-enriched compact quicksand stratum |
CN105927231B (en) * | 2016-05-24 | 2018-06-29 | 中国矿业大学 | Inclined shaft passes through rich water densification drifting sand layer circulation-induced curtain-grouting method |
CN109184747A (en) * | 2018-10-24 | 2019-01-11 | 中南大学 | A kind of method for protecting support of Deep Soft Rock Tunnel |
CN117248915A (en) * | 2023-11-16 | 2023-12-19 | 矿冶科技集团有限公司 | Method for constructing drift sand stratum roadway |
CN117248915B (en) * | 2023-11-16 | 2024-02-20 | 矿冶科技集团有限公司 | Method for constructing drift sand stratum roadway |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102787855A (en) | Excavating and supporting method of roadway containing quicksand layer | |
CN104389628B (en) | Landslide location tunnel reinforcement device and reinforced construction method | |
CN103161480B (en) | Initiatively support the method for roadside packing gob side entry retaining | |
CN107762533B (en) | A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel | |
CN109372555A (en) | A kind of fault disruption zone area tunnel 3 D stereo grouting support method | |
CN102322273A (en) | A kind of roadway floor anchor is annotated integrated reinforcement means | |
CN110374600B (en) | Non-offset arrangement method for mining roadway of extremely-close coal seam group | |
CN111119935B (en) | Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure | |
CN104047613B (en) | Baseboard of coal mine roadway anchoring process | |
CN110878696B (en) | Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method | |
CN103993892A (en) | Supporting method for soft broken nonuniform stratum tunnel construction | |
CN105781597A (en) | Method for performing anchoring and grouting reinforcement inside deep well soft rock gob-side entry retaining | |
CN112855223A (en) | Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space | |
CN103216244B (en) | Roadway soft and weak top plate anchoring beam-arch combined structure support system and support method | |
CN212296427U (en) | Double-lane arrangement working face outer lane narrow coal pillar stable supporting structure | |
CN103742158B (en) | The advance support in inclination tunnel and method for digging | |
CN110529151A (en) | A kind of fully mechanized workface Grading And Zoning integrative consolidation passing sunk pillars on full method | |
CN106988760A (en) | Facility-sliding strata tunnel portal reinforcing construction and construction method | |
CN106014443B (en) | A kind of method of the Floor Heave in Roadway for preventing gob side entry retaining and wall sliding | |
CN102704950B (en) | Support method used in passing water guide fracture structure in mine exploration | |
CN104863588A (en) | Advanced pier column pre-arranging gob-side entry retaining method | |
CN103089277A (en) | Space reinforcing construction technology of sand layer roadway | |
CN110273700A (en) | It is a kind of to control red shale tunnel strength bolt-grouting support structure and its construction method | |
CN109578032A (en) | A kind of high stress breaking surrounding rock chamber reinforcement means | |
CN101737078B (en) | Structure and method for preventing gob-side entry retaining filling wall from slipping |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20121121 |