CN102767181A - 用钻孔护壁法进行预应力混凝土管桩静压施工方法 - Google Patents
用钻孔护壁法进行预应力混凝土管桩静压施工方法 Download PDFInfo
- Publication number
- CN102767181A CN102767181A CN2012102900903A CN201210290090A CN102767181A CN 102767181 A CN102767181 A CN 102767181A CN 2012102900903 A CN2012102900903 A CN 2012102900903A CN 201210290090 A CN201210290090 A CN 201210290090A CN 102767181 A CN102767181 A CN 102767181A
- Authority
- CN
- China
- Prior art keywords
- pile
- clay
- concrete pipe
- borehole wall
- prestressed concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Piles And Underground Anchors (AREA)
Abstract
用钻孔护壁法进行预应力混凝土管桩静压施工方法。自从上世纪八十年代,我国引进预应力钢筋砼管桩以来,在工业与民用建筑、市政、桥梁、港口、公路等领域得到广泛应用。一种用钻孔护壁法进行预应力混凝土管桩静压施工方法,本方法首先测设桩点,在压桩之前先用长螺旋钻机钻孔,然后向孔内压灌粘土水泥砂浆护壁,再清理桩孔周围浮土,压机就位压桩并经复压成桩。本发明用于混凝土管桩。
Description
技术领域:
本发明涉及一种用钻孔护壁法进行预应力混凝土管桩静压施工方法。
背景技术:
自从上世纪八十年代,我国引进预应力钢筋砼管桩以来,在工业与民用建筑、市政、桥梁、港口、公路等领域得到广泛应用。
管桩施工主要有两种方法:锤击法、静压法。锤击法穿透力较强,但当桩端落于砂层时,同等桩长较静压法单桩承载力低。静压法因其施工过程中对桩底基土压实,桩侧基土挤密的“挤土效应|”获得较高的承载能力和较高的经济性。截止目前,静压管桩可用于杂填土、粘土、砂土、风化岩等地质条件。
在一般杂填土、粘土、稍密或中密状态的砂层比较容易压入,但遇到密实的中粗砂、砾砂,圆砾层、风化岩层时,常规压桩法很难穿透或压入。最近几年,对在以上地质状况下工程施工中,先后采用了引孔法、中掘法等多种辅助方法,但效果均不理想,压入深度无法满足要求。
发明内容:
本发明的目的是提供一种采用钻孔护壁法使预应力混凝土管桩能够穿透或进入坚硬土层静压施工方法。
上述的目的通过以下的技术方案实现:
一种用钻孔护壁法进行预应力混凝土管桩静压施工方法,本方法首先测设桩点,在压桩之前先用长螺旋钻机钻孔,然后向孔内压灌粘土水泥砂浆护壁,再清理桩孔周围浮土,压机就位压桩并经复压成桩。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的钻孔是桩点测设完成后,先用长螺旋钻机钻孔,孔径为预应力管桩直径+100mm;钻孔深度为孔底高出设计桩底标高0.3m——0.6m,所述的钻孔深度根据桩端持力层类型、密实程度进行调整。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压灌流态粘土水泥砂浆是钻孔至预定深度后,用砼输送泵从钻杆中心压灌流态粘土水泥砂浆,粘土水泥砂浆具有一定的可以用泵输送的流动性和粘稠度;所述的粘土水泥砂浆中的粘土和中砂的重量比为1:0.8—1.2,并掺入15%--20%的普通硅酸盐水泥。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压桩是在泥浆压灌完成后,移走桩机,清理干净钻出的土方;静压机就位,开始压入管桩,泥浆一部分被挤入桩周土体,一部分将从管芯及管侧向外返出;将管桩桩端送至引孔底部后,加大压力值,将桩端压入原土层,达到设计终压值后,反复复压4—5次,保证端部的承载力,成桩。
有益效果:
1.本发明在泥浆中加入粘土保证了浆液具有一定的粘稠度,防止了周围土体塌落和泥浆中砂子沉淀,同时具有流动性,保证了管桩压入过程中,泥浆能从桩芯及桩周反出。
2.本发明加入砂子保证了泵送压灌过程中具有较好的流动性,及增强了形成的水泥混凝土的强度;加入水泥使粘土、砂形成粘土水泥砂浆,成桩后,桩周的粘土水泥砂浆凝固,与预应力管桩形成复合桩体,增加了桩的侧阻力。
3.本发明解决了静压管桩遇坚硬土层无法进入或贯穿的难题,能将桩端送入承载力较高的土层,发挥静压预应力管桩端承载力大的特点,又能保证设计的有效桩长,同时桩侧的水泥土与管桩形成复合桩,加大桩身侧阻力,有效提高桩的整体承载能力。
具体实施方式:
实施例1:
一种用钻孔护壁法进行预应力混凝土管桩静压施工方法,本方法首先测设桩点,在压桩之前先用长螺旋钻机钻孔,然后向孔内压灌粘土水泥砂浆护壁,再清理桩孔周围浮土,压机就位压桩并经复压成桩。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的钻孔是桩点测设完成后,先用长螺旋钻机钻孔,孔径为预应力管桩直径+100mm;钻孔深度为孔底高出设计桩底标高0.3m——0.6m,所述的钻孔深度根据桩端持力层类型、密实程度进行调整。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压灌流态粘土水泥砂浆是钻孔至预定深度后,用砼输送泵从钻杆中心压灌流态粘土水泥砂浆,粘土水泥砂浆具有一定的可以用泵输送的流动性和粘稠度;所述的粘土水泥砂浆中的粘土和中砂的重量比为1:0.8—1.2,并掺入15%--20%的普通硅酸盐水泥。
所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压桩是在泥浆压灌完成后,移走桩机,清理干净钻出的土方;静压机就位,开始压入管桩,泥浆一部分被挤入桩周土体,一部分将从管芯及管侧向外返出;将管桩桩端送至引孔底部后,加大压力值,将桩端压入原土层,达到设计终压值后,反复复压4—5次,保证端部的承载力,成桩。
实施例2:
实施例1所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的钻孔是桩点测设完成后,先用长螺旋钻机钻孔,孔径为预应力管桩直径+100mm;钻孔深度为孔底高出设计桩底标高0.3m或0.4 m 或0.5m 或0.6m,所述的钻孔深度根据桩端持力层类型、密实程度进行调整。
实施例3:
实施例1所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压灌流态粘土水泥砂浆是钻孔至预定深度后,用砼输送泵从钻杆中心压灌流态粘土水泥砂浆,粘土水泥砂浆具有一定的可以用泵输送的流动性和粘稠度;所述的粘土水泥砂浆中的粘土和中砂的重量比为1:0.8—1.2,并掺入15%或16%或17%或18%或19%或20%的普通硅酸盐水泥。
实施例4:
实施例1所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的压桩是在泥浆压灌完成后,移走桩机,清理干净钻出的土方;静压机就位,开始压入管桩,泥浆将从管芯及管侧向外返出;将管桩桩端送至引孔底部后,加大压力值,将桩端压入原土层,达到设计终压值后,反复复压4或5次,保证端部的承载力,成桩。
实施例5:
实施例1所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的引孔直径为500-800 mm。
实施例6:
实施例5所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,所述的引孔直径为500 mm或600 mm或700 mm或800 mm。
实施例7:
上述实施例所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,本方法的工艺条件为只要长螺旋钻机能够钻透的土层,采用此工艺均能将桩压至设计深度。
Claims (4)
1.一种用钻孔护壁法进行预应力混凝土管桩静压施工方法,其特征是:本方法首先测设桩点,在压桩之前先用长螺旋钻机钻孔,然后向孔内压灌粘土水泥砂浆护壁,再清理桩孔周围浮土,压机就位压桩并经复压成桩。
2.根据权利要求1所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,其特征是:所述的钻孔是桩点测设完成后,先用长螺旋钻机钻孔,孔径为预应力管桩直径+100mm;钻孔深度为孔底高出设计桩底标高0.3m—0.6m,所述的钻孔深度根据桩端持力层类型、密实程度进行调整。
3.根据权利要求1或2所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,其特征是:所述的压灌流态粘土水泥砂浆是钻孔至预定深度后,用砼输送泵从钻杆中心压灌流态粘土水泥砂浆,粘土水泥砂浆具有适合用泵输送的流动性和粘稠度;所述的粘土水泥砂浆中的粘土和中砂的重量比为1:0.8—1.2,并掺入15%--20%的普通硅酸盐水泥。
4.根据权利要求1或2或3所述的用钻孔护壁法进行预应力混凝土管桩静压施工方法,其特征是:所述的压桩是在泥浆压灌完成后,移走桩机,清理干净钻出的土方;静压机就位,开始压入管桩,泥浆一部分被挤入桩周土体,一部分将从管芯及管侧向外返出;将管桩桩端送至引孔底部后,加大压力值,将桩端压入原土层,达到设计终压值后,反复复压4—5次,保证端部的承载力,成桩。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102900903A CN102767181A (zh) | 2012-08-15 | 2012-08-15 | 用钻孔护壁法进行预应力混凝土管桩静压施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102900903A CN102767181A (zh) | 2012-08-15 | 2012-08-15 | 用钻孔护壁法进行预应力混凝土管桩静压施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102767181A true CN102767181A (zh) | 2012-11-07 |
Family
ID=47094731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012102900903A Pending CN102767181A (zh) | 2012-08-15 | 2012-08-15 | 用钻孔护壁法进行预应力混凝土管桩静压施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102767181A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105239574B (zh) * | 2014-06-17 | 2017-08-29 | 中建二局第一建筑工程有限公司 | 应用于填海地质的静压预应力管桩的施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1912254A (zh) * | 2006-08-11 | 2007-02-14 | 胡柏英 | 一种预应力混凝土钢管叠合桩及其制作和施工方法 |
CN102535464A (zh) * | 2012-03-02 | 2012-07-04 | 程松林 | 在厚层软土中打入预应力空心桩的施工方法 |
CN102587371A (zh) * | 2012-02-27 | 2012-07-18 | 侯隆飙 | 空心护壁桩埋入施工方法 |
JP2012140787A (ja) * | 2010-12-28 | 2012-07-26 | Nomura Shoten Co Ltd | 杭体の施工方法およびそれに用いられるケーシングパイプとそれによって施工された基礎構造体 |
-
2012
- 2012-08-15 CN CN2012102900903A patent/CN102767181A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1912254A (zh) * | 2006-08-11 | 2007-02-14 | 胡柏英 | 一种预应力混凝土钢管叠合桩及其制作和施工方法 |
JP2012140787A (ja) * | 2010-12-28 | 2012-07-26 | Nomura Shoten Co Ltd | 杭体の施工方法およびそれに用いられるケーシングパイプとそれによって施工された基礎構造体 |
CN102587371A (zh) * | 2012-02-27 | 2012-07-18 | 侯隆飙 | 空心护壁桩埋入施工方法 |
CN102535464A (zh) * | 2012-03-02 | 2012-07-04 | 程松林 | 在厚层软土中打入预应力空心桩的施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105239574B (zh) * | 2014-06-17 | 2017-08-29 | 中建二局第一建筑工程有限公司 | 应用于填海地质的静压预应力管桩的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103184734B (zh) | 一种植入注浆组合桩的施工方法 | |
CN105625293A (zh) | 溶岩强发育施工场地填充式地质处理结构及其施工方法 | |
CN102011399A (zh) | 一种基于phc桩的多重高喷扩底桩施工方法 | |
CN206070508U (zh) | 一种加固地基基础的装置 | |
CN111395300A (zh) | 一种原竹注浆桩加固软土地基结构的方法 | |
CN103696416A (zh) | 一种地基处理新方法 | |
CN109440757A (zh) | 一种用于岩溶区的地基加固方法 | |
CN203213101U (zh) | 一种植入注浆组合桩 | |
CN101701459B (zh) | 对潮间带软土地基处理形成施工作业面的方法 | |
CN204023559U (zh) | 一种多孔注浆管异形桩 | |
CN108071110A (zh) | 复杂地质条件下旋挖钻机嵌岩桩施工方法 | |
WO2017133373A1 (zh) | 一种用于桩基的小直径桩簇及其施工方法 | |
CN104563100A (zh) | 水泥土搅拌桩后植压灌桩支护结构及施工方法 | |
CN105672329B (zh) | 深基坑大尺寸预制围护结构及施工方法 | |
CN106869153A (zh) | 一种井点降水快速处理软地基的方法 | |
CN102767181A (zh) | 用钻孔护壁法进行预应力混凝土管桩静压施工方法 | |
CN103821140B (zh) | 一种加固松软土地基的施工方法 | |
CN104213553A (zh) | 振冲沉箱无接缝防渗墙施工工艺 | |
CN105421446A (zh) | 一种用于软基处理的混合土挤压固化预制桩及施工方法 | |
CN103114615B (zh) | 用渗透浸渍聚凝粘结体对地下水位下的水泥构件加固方法 | |
CN102677671B (zh) | 一种厚渣石层场地预制桩施工方法 | |
CN103374912A (zh) | 一种高承载力微沉降抗剪预应力管桩及其设计和施工方法 | |
CN101024957A (zh) | 预应力混凝土管桩的复合处理的工艺 | |
CN103556621B (zh) | 一种淤泥质地基的加固方法 | |
CN106759267A (zh) | 一种便于硬岩层钢板桩打入的辅助引孔方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20121107 |