CN102758422A - 一种闸孔过流状态下弧形闸门水上安装施工方法 - Google Patents
一种闸孔过流状态下弧形闸门水上安装施工方法 Download PDFInfo
- Publication number
- CN102758422A CN102758422A CN2012102265652A CN201210226565A CN102758422A CN 102758422 A CN102758422 A CN 102758422A CN 2012102265652 A CN2012102265652 A CN 2012102265652A CN 201210226565 A CN201210226565 A CN 201210226565A CN 102758422 A CN102758422 A CN 102758422A
- Authority
- CN
- China
- Prior art keywords
- gate
- water
- end bank
- simulation
- waterborne
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Barrages (AREA)
Abstract
一种闸孔过流状态下弧形闸门水上安装施工方法,该施工方法括以下步骤:安装基点转移到水面上方,对前期施工检查验收,验收合格后泄洪闸过流;在水面上方制作水上安装平台,在水上安装平台上安装模拟底坎;安置闸顶桥机和闸顶台车;安装支铰及二期混凝土;使用闸顶桥机和闸顶台车进行支臂和门叶的吊装、调整,焊接支臂,门叶与支臂连接;对弧形闸门与模拟底坎止水效果进行调试;进行水上部分划弧检查及调试;验收合格后投入运行。与现有技术相比,本发明所述施工方法将常规弧形闸门旱地作业转化为水上作业,从工期角度保障了工程二期截流作业的按期组织,为工程建设总体进度实施赢得了宝贵时间。
Description
技术领域
本发明涉及一种水电工程中弧形闸门安装的施工方法,特别是涉及一种在闸孔在过流泄洪条件下弧形闸门水上安装施工方法。
背景技术
麒麟寺水电站位于甘肃省文县中庙乡境内,工程施工导流分二期进行,其中二期主河床截流后,通过一期泄洪闸工程进行泄洪导流。由于受工程开工滞后及混凝土供应节点推迟等多方面原因影响,一期泄洪闸主体工程实施工期被迫滞后,至工程既定二期导流施工节点时段,一期泄洪闸工程仅达成土建混凝土施工导流形象,弧形闸门金结安装施工已无有效时间进行组织,考虑水电工程施工枯、汛期施工及导流特点,因闸门安装工期问题将影响整个二期导流施工,直接造成整个工程建设工期被迫推后一年,经济效益影响巨大。
发明内容
鉴于此,本发明的目的在于提供一种不受汛期影响的弧形闸门水上安装施工方法。
为解决上述技术问题本发明提供的技术方案是,提供一种闸孔过流状态下弧形闸门水上安装施工方法,包括闸墩混凝土浇筑、闸墩内型钢支撑预埋、铰座一期混凝土施工、水下底坎埋件安装及二期砼、门槽埋件安装及二期砼步骤,该施工方法还包括以下步骤:
1)安装基点转移到水面上方,对前期施工检查验收,验收合格后泄洪闸过流;
2)在水面上方制作水上安装平台,在水上安装平台上安装模拟底坎;
3)安置闸顶桥机和闸顶台车;安装支铰及二期混凝土;使用闸顶桥机和闸顶台车进行支臂和门叶的吊装、调整,焊接支臂,门叶与支臂连接;
4)对弧形闸门与模拟底坎止水效果进行调试;进行水上部分划弧检查及调试;
5)拆除模拟底坎及水上安装平台;水下部分调试,验收合格后投入运行。
进一步地,所述模拟底坎的止水面与水下底坎的止水面的形体相同。
进一步地,所述模拟底坎与水下底坎同在弧形闸门门槽中心线上,模拟底坎止水面与水下底坎止水面的夹角同弧形闸门分别放置在水下底坎和模拟底坎上时弧形闸门旋转的角度相同。模拟底坎在搭设的水上安装平台基础上进行制作,按过流前水下底坎控制模拟底坎止水面,并由弧形闸门运行轨迹计算出模拟底坎空间对应位置,测量控制模拟底坎平台安装精度,并采用型钢焊接加固确保模拟底坎结构刚度。
进一步地,所述安装基点转移,是在闸顶及侧墩上均设置后续安装所需测量控制点。经反复校核,进行明确标识,并采取防护及覆盖保护。泄洪闸正式过流前,对前期所采用的安装控制点采用测量仪器导引至过过流断面以上,即在闸顶及侧墩上均设置后续安装所需控制基点,由测量反复校核,进行明确标识,并采用防护及覆盖保护。由于弧形闸门处于三维空间,安装精度控制难度大,水上安装控制点设置除按里程、高程布设弧形闸门中心线、孔口中心线、弧形闸门半径控制点外,还要注意控制支铰中心至侧水封座板中心的距离的布设复核工作。
进一步地,所述弧形闸门与模拟底坎止水效果进行调试是采用透光及塞尺检查门体止水与模拟底坎间压缩程度。采用透光及塞尺检查门体止水与模拟底坎间压缩程度是否满足止水要求,并通过调整门体止水达到规范要求。
与现有技术相比,本发明所述施工方法将常规弧形闸门旱地作业转化为水上作业,从工期角度保障了工程二期截流作业的按期组织,为工程建设总体进度实施赢得了宝贵时间。过流后采用土建门机、闸顶布置桥机、台车措施解决了安装构件材料水上吊装、运输、就位等系列问题,而水上安装平台的制作、模拟底坎安装措施及过程中系列控制措施,为水上安装提供了精度及质量保障。经工程实践数据统计,由于工程二期截流处于工程直线工期之上,提前投产按1台机组正常发电考虑,增加效益约450万元。
附图说明
图1是本发明施工示意图。
图2是本发明所述模拟底坎结构示意图。
图3是本发明施工流程图。
具体实施方式
以下结合附图进行说明。
参见图1至图3。本发明所述闸孔过流状态下弧形闸门水上安装施工方法,包括以下步骤:
根据安装规划顺序,分批次将安装金结构件运输至施工现场。
闸墩混凝土浇筑、闸墩内型钢支撑预埋、铰座一期混凝土施工、水下底坎埋件安装及二期砼、门槽埋件安装及二期砼。
安装基点转移到水面上方,对前期施工检查验收,验收合格后泄洪闸过流;所述安装基点转移,是在闸顶及侧墩上均设置后续安装所需测量控制点,反复校核,进行明确标识,并采取防护及覆盖保护。泄洪闸正式过流前,对前期所采用的安装控制点采用测量仪器导引至过过流断面以上,即在闸顶及侧墩上均设置后续安装所需控制基点,由测量反复校核,进行明确标识,并采用防护及覆盖保护。由于弧形闸门处于三维空间,安装精度控制难度大,水上安装控制点设置除按里程、高程布设弧形闸门中心线、孔口中心线、弧形闸门半径控制点外,还要注意控制支铰中心至侧水封座板中心的距离的布设复核工作。
在水面上方制作水上安装平台1,利用水上安装平台1及闸墩内预埋的型钢进行金属构件的临时锁定、组装、调整、加固、焊接等。在水上安装平台1上安装模拟底坎2,该模拟底坎2的止水面与水下底坎的止水面形体6相同,模拟底坎2的基准精度、平直度、局部不平度应与水下底坎6基本相同。模拟底坎2与水下底坎6同在弧形闸门门槽7中心线上,模拟底坎止水面21与水下底坎止水面的夹角同弧形闸门5分别放置在水下底坎6和模拟底坎2上时弧形闸门5旋转的角度相同。模拟底坎在搭设的水上安装平台基础上进行制作,按过流前水下底坎控制模拟底坎止水面,并由弧形闸门运行轨迹计算出模拟底坎空间对应位置,测量控制模拟底坎平台安装精度,并采用型钢焊接加固确保模拟底坎结构刚度。
安置闸顶桥机3和闸顶台车4,使用吊装设备将构件转移至闸顶台车4,通过闸顶台车4完成构件闸顶纵向运输工作,再利用闸孔上布置横向闸顶桥机3吊装构件移动就位;安装支铰及二期混凝土;使用闸顶桥机和闸顶台车进行支臂和门叶的吊装、调整,焊接支臂,门叶与支臂连接。
对弧形闸门5与模拟底坎止水效果进行调试;进行水上部分划弧检查及调试;采用透光及塞尺检查门体止水与模拟底坎2间压缩程度,采用透光及塞尺检查门体与模拟底坎间压缩程度是否满足止水要求,并通过调整门体止水达到规范要求。
拆除模拟底坎2及水上安装平台1;水下部分调试,验收合格后投入运行。
本发明所述施工方法,在闸孔过流后复杂的作业条件下,通过科学组织、合理规划、精心施工顺利完成金结安装作业。规避了一期导流工程拖延的工期,确保了主体工程建设的如期开展,为工程建设总体进度顺利实施提供了保障,取得了良好的经济效益和社会效益。
以上仅是本发明的优选实施方式,应当指出的是,上述优选实施方式不应视为对本发明的限制,本发明的保护范围应当以权利要求所限定的范围为准。对于本技术领域的普通技术人员来说,在不脱离本发明的精神和范围内,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。
Claims (5)
1.一种闸孔过流状态下弧形闸门水上安装施工方法,包括闸墩混凝土浇筑、闸墩内型钢支撑预埋、铰座一期混凝土施工、水下底坎埋件安装及二期砼、门槽埋件安装及二期砼步骤,其特征在于,该施工方法还包括以下步骤:
1)安装基点转移到水面上方,对前期施工检查验收,验收合格后泄洪闸过流;
2)在水面上方制作水上安装平台(1),在水上安装平台上安装模拟底坎(2);
3)安置闸顶桥机(3)和闸顶台车(4);安装支铰及二期混凝土;使用闸顶桥机和闸顶台车进行支臂和门叶的吊装、调整,焊接支臂,门叶与支臂连接;
4)对弧形闸门(5)与模拟底坎(2)止水效果进行调试;进行水上部分划弧检查及调试;
5)拆除模拟底坎(2)及水上安装平台(1);水下部分调试,验收合格后投入运行。
2.根据权利要求1所述的一种闸孔过流状态下弧形闸门水上安装施工方法,其特征在于,所述模拟底坎(2)的止水面与水下底坎(6)的止水面形体相同。
3.根据权利要求2所述的一种闸孔过流状态下弧形闸门水上安装施工方法,其特征在于,所述模拟底坎(2)与水下底坎(6)同在弧形闸门门槽(7)中心线上,模拟底坎止水面(21)与水下底坎止水面的夹角同弧形闸门(5)分别放置在水下底坎(6)和模拟底坎(2)上时弧形闸门(5)旋转的角度相同。
4.根据权利要求1所述的一种闸孔过流状态下弧形闸门水上安装施工方法,其特征在于,所述安装基点转移,是在闸顶及侧墩上均设置后续安装所需测量控制点。
5.根据权利要求1所述的一种闸孔过流状态下弧形闸门水上安装施工方法,其特征在于,所述弧形闸门(5)与模拟底坎(2)止水效果进行调试是采用透光及塞尺检查门体与模拟底坎(2)间压缩程度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102265652A CN102758422A (zh) | 2012-07-03 | 2012-07-03 | 一种闸孔过流状态下弧形闸门水上安装施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102265652A CN102758422A (zh) | 2012-07-03 | 2012-07-03 | 一种闸孔过流状态下弧形闸门水上安装施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102758422A true CN102758422A (zh) | 2012-10-31 |
Family
ID=47053055
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012102265652A Pending CN102758422A (zh) | 2012-07-03 | 2012-07-03 | 一种闸孔过流状态下弧形闸门水上安装施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102758422A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103103964A (zh) * | 2013-02-06 | 2013-05-15 | 中交一航局第三工程有限公司 | 一种船闸反向弧门安装方法 |
CN103953011A (zh) * | 2014-05-19 | 2014-07-30 | 葛洲坝集团第六工程有限公司 | 一种过流条件下导流底孔弧形闸门安装方法 |
CN107288104A (zh) * | 2017-07-11 | 2017-10-24 | 浙江省水利水电勘测设计院 | 一种摇篮式挡水坝结构 |
CN110485389A (zh) * | 2019-09-20 | 2019-11-22 | 中国电建集团成都勘测设计研究院有限公司 | 一种日调节水电站组合式表孔挡水结构 |
CN113981918A (zh) * | 2021-11-09 | 2022-01-28 | 中国葛洲坝集团第三工程有限公司 | 一种用于引水式水电站截流的施工方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006037441A (ja) * | 2004-07-26 | 2006-02-09 | Shimizu Corp | ダムの嵩上げ工法 |
CN202265806U (zh) * | 2011-08-24 | 2012-06-06 | 中国水利水电第五工程局有限公司 | 大型水工弧门快速安装装置 |
-
2012
- 2012-07-03 CN CN2012102265652A patent/CN102758422A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006037441A (ja) * | 2004-07-26 | 2006-02-09 | Shimizu Corp | ダムの嵩上げ工法 |
CN202265806U (zh) * | 2011-08-24 | 2012-06-06 | 中国水利水电第五工程局有限公司 | 大型水工弧门快速安装装置 |
Non-Patent Citations (2)
Title |
---|
曹小丽等: "麒麟寺水电站大型弧门水上安装方案的实施", 《四川水力发电》 * |
黄春平: "弧形闸门安装中常见问题及处理措施", 《广东水利水电》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103103964A (zh) * | 2013-02-06 | 2013-05-15 | 中交一航局第三工程有限公司 | 一种船闸反向弧门安装方法 |
CN103953011A (zh) * | 2014-05-19 | 2014-07-30 | 葛洲坝集团第六工程有限公司 | 一种过流条件下导流底孔弧形闸门安装方法 |
CN107288104A (zh) * | 2017-07-11 | 2017-10-24 | 浙江省水利水电勘测设计院 | 一种摇篮式挡水坝结构 |
CN110485389A (zh) * | 2019-09-20 | 2019-11-22 | 中国电建集团成都勘测设计研究院有限公司 | 一种日调节水电站组合式表孔挡水结构 |
CN113981918A (zh) * | 2021-11-09 | 2022-01-28 | 中国葛洲坝集团第三工程有限公司 | 一种用于引水式水电站截流的施工方法 |
CN113981918B (zh) * | 2021-11-09 | 2023-07-21 | 中国葛洲坝集团第三工程有限公司 | 一种用于引水式水电站截流的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102758422A (zh) | 一种闸孔过流状态下弧形闸门水上安装施工方法 | |
CN103074872B (zh) | 一种闸门门槽施工方法及装置 | |
CN104060544B (zh) | 一种管道悬索跨越桥桥身安装的施工工艺 | |
Morgenthal et al. | Engineering the tower and main span construction of stonecutters bridge | |
CN103388343A (zh) | 超长和大型水平预埋件逆作法 | |
CN206680858U (zh) | 一种落梁装置 | |
CN206279631U (zh) | 一种用于钢梁和核心筒连接的预埋件 | |
CN106120799A (zh) | 地下管线横跨基坑免改迁施工方法 | |
CN106638318A (zh) | 斜拉桥梁端锚固点的定位方法及索导管安装方法 | |
CN108426779B (zh) | 高水压条件下地下工程的结构裂缝试验模拟装置和方法 | |
CN103088843B (zh) | 综合管廊预埋铁件安装施工方法 | |
CN109594838A (zh) | 一种单管通信塔的加固结构 | |
CN103938633A (zh) | 一种洞桩法钢管柱砼浇筑施工方法 | |
CN203701066U (zh) | 土压力计可调式位置固定安装装置 | |
CN101963062B (zh) | 一种隧道防水系统的施工方法 | |
CN107476327B (zh) | 窄基单立柱台阶基础施工方法 | |
CN105606391A (zh) | 大型风机塔架强度试验装置及试验方法 | |
CN205476083U (zh) | 混凝土梁的钢筋保护层结构 | |
CN105155485A (zh) | 一种闸墩预应力锚索套管安装装置及其施工方法 | |
CN203361096U (zh) | 一种闸门门槽施工装置 | |
CN201187060Y (zh) | 深水钢吊箱竖向定位装置 | |
Narayan et al. | Dam Safety Rehabilitation-Indian Experience and Lessons Learnt | |
CN105651239A (zh) | 一种用于水下结构物表面平整度的测量方法 | |
CN107577885A (zh) | 基于基站水位观测的海床基沉降量差分计算方法 | |
CN117847018A (zh) | 一种大直径防洪混流泵安装施工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20121031 |