CN102733606B - The construction method of High Large Cantilever structure - Google Patents

The construction method of High Large Cantilever structure Download PDF

Info

Publication number
CN102733606B
CN102733606B CN201110088550.XA CN201110088550A CN102733606B CN 102733606 B CN102733606 B CN 102733606B CN 201110088550 A CN201110088550 A CN 201110088550A CN 102733606 B CN102733606 B CN 102733606B
Authority
CN
China
Prior art keywords
steel
channel
section steel
construction
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110088550.XA
Other languages
Chinese (zh)
Other versions
CN102733606A (en
Inventor
孙晓阳
李赟
颜卫东
陈思
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201110088550.XA priority Critical patent/CN102733606B/en
Publication of CN102733606A publication Critical patent/CN102733606A/en
Application granted granted Critical
Publication of CN102733606B publication Critical patent/CN102733606B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction method of High Large Cantilever structure, belong to high vacant building Beam-Slab Construction method, especially there is the construction method of moulding large cantilever beam slab.The present invention adopts next structural floor of bridging piece outside to establish and chooses channel-section steel or H profile steel outward, and increase the cast-in-situ concrete together with channel-section steel or H profile steel of structure reversed beam on structure limit, consolidate the stability of shaped steel and bear cantilevered structure transmission load, bottom increases channel-section steel diagonal brace and middle part increases oblique pull channel-section steel, form steel work tripod, erection time crossbeam channel-section steel on steel tripod again, finally on secondary crossbeam channel-section steel, set up common steel tube fastener type support for shuttering, comprehensive load-bearing, bear top to encorbelment all loads of beam slab, structure reversed beam is removed after construction.The invention solves high vacant building long cantilever construction encorbelment long, load large, support system is difficult to the difficult problem selected, be applicable to the outer bridging piece terrain clearance of building at more than 40m, choose the construction of span at the large-scale cantilevered structure of 2.0m ~ 6.0m scope outward.

Description

The construction method of High Large Cantilever structure
Art
The invention belongs to high vacant building Beam-Slab Construction method, especially there is the construction method of the high vacant building beam slab of long cantilever construction.
Background technology
At present, along with the high speed development of economic construction and urbanization, the high level of different modeling or super highrise building promptly one flickeringly to be rised sheer from level ground in each big and medium-sized cities, a lot of building is in order to make widely known building individuation and show the rich and varied of moulding, a certain for high-altitude floor or roof encorbelment outside architectural plane by normal employing High Large Cantilever gimmick, make it the significant scenery together that moulding becomes urban architecture.In this design, cantilever part terrain clearance is usually at more than 40m, chooses length outward and reaches 2.0m ~ 6.0m, and it makes, and building is glorious, solid is abundant, majestic appearance is broken out.Simultaneously, the design of these individual characteies is also for the construction of building brings all difficult problems, the feature that its span greatly, highly high, load is large, difficulty is high, by the words that the formwork-support system of conventional method has been come, difficulty is large, and safety factor is not high, and the duration is long, and disposablely to have high input, with high costs.
Summary of the invention
For a difficult problem of the prior art, the object of this invention is to provide a kind of construction method of High Large Cantilever structure, it can ensure construction safety, can ensure workmanship again, can also save construction fund greatly.
The object of the present invention is achieved like this: the construction method of High Large Cantilever structure, comprise conventional assembling reinforcement, install template, under template, support system is set, concreting, the demoulding, the operations such as concrete curing, its special feature is: described form bracing system have employed a kind of construction method of steel girder platform, namely next structural floor place of bridging piece chooses channel-section steel or H profile steel outside establishing at a certain distance according to superstructure load outside, adopt round steel to make three road clips and fix shaped steel, clip through-flooring and Plate Welding are fixed, and increase the cast-in-situ concrete together with channel-section steel or H profile steel of structure reversed beam on structure limit, consolidate the stability of shaped steel and bear cantilevered structure transmission load, bottom increases channel-section steel diagonal brace and middle part increases oblique pull channel-section steel, form steel work tripod, time crossbeam channel-section steel or H profile steel is set up at a certain distance according to structural load again on steel tripod, after construction after the degree of disturbing of deadweight generation is static, finally on secondary crossbeam channel-section steel or H profile steel, set up common steel tube fastener type bracing frame, comprehensive load-bearing, bear top to encorbelment all loads of beam slab, structure reversed beam is removed after construction.Tradition is landed scaffold support system and is changed high-altitude steel girder platform support system into by the method, owing to need not set up the support system of beam slab of encorbelmenting from ground, formwork-support directly falls within firm high-altitude steel girder platform, so can construction technology be simplified, improve efficiency of construction, reduce cost, increase safety factor, reach object of the present invention.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 is overhanging type steel layout plan
Fig. 2 is overhanging type steel and time crossbeam channel-section steel or H profile steel schematic diagram
Fig. 3 is the condition of construction schematic diagram of High Large Cantilever structure
Fig. 4 is the organigram of end anchorage round steel
Fig. 5 is the structure reversed beam structural section of anchoring shaped steel
Fig. 6 is the organigram of diagonal brace shaped steel
Fig. 7 is diagonal brace shaped steel and anatomical connectivity organigram
Fig. 8 is diagonal brace shaped steel and overhanging type steel connected node schematic diagram
Fig. 9 is middle part oblique pull shaped steel and anatomical connectivity joint structure schematic diagram
Figure 10 is the layout plan of supporting steel pipe at the bottom of plate
Figure 11 is the layout plan of supporting steel pipe at the bottom of beam
Figure 12 is the organigram of lateral crus hand cradle and anatomical connectivity
Detailed description of the invention
As Fig. 1, shown in 3, the present invention is a kind of High Large Cantilever construction method: by overhanging type steel at a certain distance along architectural appearance horizontally after, weld with round steel (Fig. 4) through-flooring, and pouring structure reversed beam (Fig. 5) is fixed, lay bottom diagonal brace (Fig. 6, 7) weld with overhanging type steel (Fig. 8), lay middle part oblique pull shaped steel (Fig. 9) to weld with diagonal brace, after structural concrete strength meets the demands, shaped steel sets up time crossbeam channel-section steel or H profile steel (Fig. 2) at a certain distance, finally on secondary crossbeam channel-section steel or H profile steel, set up common steel tube fastener type bracing frame (Figure 10, 11), and set up steel pipe scaffold in outside, scaffold adopts built-in fitting to carry out being connected (Figure 12) with structure, guarantee stability.Structure reversed beam is removed after construction.

Claims (1)

1. the construction method of High Large Cantilever structure: comprise assembling reinforcement, install template, under template, support system is set, concreting, the demoulding, concrete curing operation, it is characterized in that: described form bracing system have employed a kind of construction method of steel girder platform, namely next structural floor place of bridging piece chooses channel-section steel or H profile steel outside establishing at a certain distance according to superstructure load outside, adopt round steel to make three road clips and fix shaped steel, the end of clip is outwards bent to form bending segment, three described road clips, front twice are imbedded in underfloor placing of reinforcement mesh sheet in advance, build together with floorslab concrete, 3rd road clip floor after structural strength reaches is bored a hole and is adopted 300 × 300mm iron plate to be welded and fixed, and increase the cast-in-situ concrete together with channel-section steel or H profile steel of structure reversed beam on structure limit, consolidate the stability of shaped steel and bear cantilevered structure transmission load, bottom increases channel-section steel or shaped steel diagonal brace and middle part and increases oblique pull channel-section steel or shaped steel, form steel work tripod, time crossbeam channel-section steel or H profile steel is set up at a certain distance according to structural load again on steel tripod, after construction after the degree of disturbing of deadweight generation is static, finally on secondary crossbeam channel-section steel or shaped steel, set up common steel tube fastener type bracing frame, comprehensive load-bearing, bear top to encorbelment all loads of beam slab, structure reversed beam is removed after construction.
CN201110088550.XA 2011-04-08 2011-04-08 The construction method of High Large Cantilever structure Active CN102733606B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110088550.XA CN102733606B (en) 2011-04-08 2011-04-08 The construction method of High Large Cantilever structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110088550.XA CN102733606B (en) 2011-04-08 2011-04-08 The construction method of High Large Cantilever structure

Publications (2)

Publication Number Publication Date
CN102733606A CN102733606A (en) 2012-10-17
CN102733606B true CN102733606B (en) 2015-09-30

Family

ID=46989851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110088550.XA Active CN102733606B (en) 2011-04-08 2011-04-08 The construction method of High Large Cantilever structure

Country Status (1)

Country Link
CN (1) CN102733606B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306479A (en) * 2013-07-09 2013-09-18 中国中铁航空港建设集团有限公司海南分公司 Long-length overhang trusswork high form hanger system
CN103388310A (en) * 2013-08-09 2013-11-13 北京市公路桥梁建设集团有限公司 Single-point fixing adjustable cantilever tripod
CN103669845B (en) * 2013-12-26 2015-11-25 常州第一建筑集团有限公司 High-altitude long-span overhung cornice formwork bracing system and construction method thereof
CN103993735A (en) * 2014-06-06 2014-08-20 山东义泰建设工程有限公司 Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN104989097A (en) * 2015-05-27 2015-10-21 晟通科技集团有限公司 Reverse beam overhanging template device
CN105019639B (en) * 2015-05-28 2017-07-14 河南国基建设集团有限公司 Overhead cantilever formwork and its construction method
CN104989092B (en) * 2015-05-28 2017-03-01 杭州江润科技有限公司 A kind of construction method of high-altitude overhanging superposed type steel truss bearing platform
CN105626138B (en) * 2015-12-31 2017-09-29 中国建筑第八工程局有限公司 A kind of precipice passway for escaping structure and its construction method
CN105971110A (en) * 2016-05-30 2016-09-28 中冶东北建设(沈阳)工程技术有限公司 Construction method for fire control corridor steel structure supporting system
CN106337555A (en) * 2016-09-26 2017-01-18 山东金城建设有限公司 Method for constructing triangular steel support for cantilever structure of outer wall of building
CN107165281A (en) * 2017-06-20 2017-09-15 中国华西企业有限公司 A kind of high-altitude long-span overhung steel platform mould bases construction
CN110259147B (en) * 2019-07-02 2024-05-10 中冶天工集团有限公司 Auxiliary mounting device and method for platform beams of narrow-space opposite overhanging platform
CN110318460B (en) * 2019-07-23 2021-02-09 中冶建工集团有限公司 Construction method of inverted-step-shaped special-shaped steel structure
CN111236640A (en) * 2020-03-26 2020-06-05 张延年 Structure of encorbelmenting is shared with outer scaffold to high altitude formwork support
CN111350338A (en) * 2020-04-14 2020-06-30 中国建筑第四工程局有限公司 Construction steel platform for super-long overhanging structure of high-rise building
CN111424967A (en) * 2020-04-27 2020-07-17 五冶集团上海有限公司 Construction method of high-altitude ring beam cantilever structure
CN115182526A (en) * 2022-08-11 2022-10-14 中国建筑第七工程局有限公司 High-altitude overhanging stair structure and construction method thereof
CN115928883B (en) * 2022-11-29 2024-02-13 北京城建六建设集团有限公司 Structure structure for preventing displacement of continuous overhanging layer of building and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB550078A (en) * 1941-07-09 1942-12-22 Robert Loudon Improvements relating to the casting of roofing structures on upright supports
CN2832995Y (en) * 2005-08-24 2006-11-01 上海市第七建筑有限公司 Suspension scaffold supporting device of light hanging type brandreth
CN200971603Y (en) * 2006-10-11 2007-11-07 刘勇 Triangle section builder's jack
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN201428239Y (en) * 2009-04-09 2010-03-24 温州建设集团公司 Supporting system for combined channel steel cantilever bracket template

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2853570B2 (en) * 1994-05-25 1999-02-03 鹿島建設株式会社 Construction method of building with overhang

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB550078A (en) * 1941-07-09 1942-12-22 Robert Loudon Improvements relating to the casting of roofing structures on upright supports
CN2832995Y (en) * 2005-08-24 2006-11-01 上海市第七建筑有限公司 Suspension scaffold supporting device of light hanging type brandreth
CN200971603Y (en) * 2006-10-11 2007-11-07 刘勇 Triangle section builder's jack
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN201428239Y (en) * 2009-04-09 2010-03-24 温州建设集团公司 Supporting system for combined channel steel cantilever bracket template

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张奋杰.超高悬挑结构的模板支顶架设计与施工实例.《广东土木与建筑》.2008,(第1期),第1-2页第1节、第2.1节,第3页第4节,附图1-4. *
张志强.6m跨悬挑檐模板支架施工技术.《山西建筑》.2008,(第15期),全文. *
浅析混凝土增大截面加固法;刘中伏;《国防交通工程与技术》;20061215(第4期);引言部分,附图1 *

Also Published As

Publication number Publication date
CN102733606A (en) 2012-10-17

Similar Documents

Publication Publication Date Title
CN102733606B (en) The construction method of High Large Cantilever structure
CN102677784B (en) Prefabricated concrete pipe column and reinforced concrete beam node structure and construction method thereof
CN102704575B (en) Node structure of precast concrete tubular column steel rib concrete beam and construction method of node structure
CN108412128A (en) A kind of connection structure of steel core concrete column
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN204826308U (en) Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall
CN109403545B (en) High-assembly-rate steel pipe concrete frame structure system and connection method
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN105089178A (en) Fabricated building of pre-assembling structure of prefabricated section steel concrete shear wall
CN204531338U (en) The builder's jack assembly of ground construction can be shifted to an earlier date
CN105133728A (en) Assembly type concrete structure with cage type connecting components
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN104264706B (en) External elevator steel beam foundation structure and construction method thereof
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN205024833U (en) Reinforcing bar concrete combination prefabricated component
CN204676881U (en) Large span intersection truss steel structure supporting system
CN102003078A (en) Assembling method of net rack
CN102454292A (en) Supporting steel frame of high altitude large-span cantilever structure mold frame
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN204826196U (en) Take prefabricated concrete structure of cage connecting elements
CN213204915U (en) Overweight overhanging suspended component supporting system of super high-rise residential conversion layer
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN204715764U (en) The structure that a kind of constructional column and agent structure are constructed simultaneously
CN203834737U (en) Cross-shaped prefabricated mixed coupled wall
CN204163104U (en) External elevator steel beam foundation constructs

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Sun Xiaoyang

Inventor after: Li Bin

Inventor after: Yan Weidong

Inventor after: Chen Si

Inventor before: Sun Xiaoyang

Inventor before: Yan Weidong

Inventor before: Chen Si

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: SUN XIAOYANG YAN WEIDONG CHEN SI TO: SUN XIAOYANG LI YUN YAN WEIDONG CHEN SI

C14 Grant of patent or utility model
GR01 Patent grant