CN102720223A - Method for strengthening foundation of transmission line tower - Google Patents

Method for strengthening foundation of transmission line tower Download PDF

Info

Publication number
CN102720223A
CN102720223A CN2011100801294A CN201110080129A CN102720223A CN 102720223 A CN102720223 A CN 102720223A CN 2011100801294 A CN2011100801294 A CN 2011100801294A CN 201110080129 A CN201110080129 A CN 201110080129A CN 102720223 A CN102720223 A CN 102720223A
Authority
CN
China
Prior art keywords
soil
transmission line
foundation
cement paste
vibration head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100801294A
Other languages
Chinese (zh)
Inventor
肖川
龚利文
孙杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN2011100801294A priority Critical patent/CN102720223A/en
Publication of CN102720223A publication Critical patent/CN102720223A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention relates to a construction method of a transmission line and particularly relates to a construction method of a foundation of a transmission line tower. A method for strengthening a foundation of a transmission line tower comprises the following steps of: step 1, deeply vibrating a vibration head in the soil, so that adjacent soil is compacted; step 2, after vibrating, filling gravels in a hole formed by the vibration head, so that gravel columns are formed; step 3, putting casing pipes with lengths same as an embedded depth of the foundation into the soil; and pressing cement paste prepared by cement and coal ash in the soil through slurry discharging openings at the lower parts of the casing pipes, so that the cement paste is extruded into the soil around the bottoms of the pipes and passes through any large gap of backfill soil. The method provided by the invention can be used for strengthening the foundation of the transmission line, so that the costs caused by power-cut construction in line improvement, reconstruction of a former line, and re-manufacture and re-installation of the transmission line tower can be saved.

Description

Electric power line pole tower underpin method
Technical field
The present invention relates to the job practices of transmission line of electricity, relate in particular to the electric power line pole tower foundation construction method.
Background technology
We usually adopt the method to existing circuit upgrading to solve the electric power transportation problem to load center.Adopting the way that increases the lead section, increases line voltage distribution or newly-increased transmission line of electricity to increase power transmission capacity of pow at original transmission line of electricity.And these measures all make the present pole and tower foundation of circuit will bear than original big load action, and must effectively handle pole and tower foundation like this increases its anti-pulling intensity.To satisfy the demand.
At present some conventional methods of adopting of China some areas are: mound around pole and tower foundation, or on pole and tower foundation concreting shell etc.Can increase the resistance to plucking ability on basis.But the anti-pulling insufficient strength, and influence the reason of environment, aspect such as attractive in appearance, obviously not good method.Therefore, research do not have a power failure and environmental protection or attractive in appearance on all be prone to accepted with the also lower underpin method of expense be necessity very.
Consider that original base has passed through long-term actual use, their pulling-resistant and pressure-resistant ability we can say to have enough overload capacity.If can more accurately confirm the weight bearing power that these are basic, obviously can save the improvement expenses of many circuit upgradings.When the basis needs significantly to increase supporting capacity, take the reinforcement means that suits, the expense that often can practice thrift track remodelling expense and interruption of power supply.
Summary of the invention
The present invention is intended to address the aforementioned drawbacks, and a kind of electric power line pole tower underpin method is provided.The present invention is through the consolidation process to transmission line of electricity basis, can save that track remodelling power cut construction, original circuit are constructed again, fabrication and installation electric power line pole tower expense again.
The present invention is achieved in that a kind of electric power line pole tower underpin method, and it comprises:
Step 1 is shaken vibration head deeply and to be buried near the regolith jolt ramming making;
Step 2 after vibration finishes, is inserted rubble in the hole that vibration head forms, make it form rubble post one by one;
Step 3; The sleeve pipe that some length are identical with embedded depth of foundation is squeezed in the soil; In soil, be pressed into the cement paste of cement and flyash preparation then through the bottom plasma discharge mouth of these sleeve pipes, it clamp-oned in the soil of pipe at the end, and be penetrated in any big space of backfill.
Described electric power line pole tower underpin method; Said step 1 also is included in the degree of depth that needs jolt ramming when big; With the moving head of vibration head lengthening by with axis of rotation that motor is connected on eccentric block form, during work, vibration head hangs over one movably on the arm of crane; One of which surface vibration one side is vertically descended, and the deadweight of dependence vibration head is progressively shaken in the ground.
Described electric power line pole tower underpin method, the process of said step 3 operation are in each pipe, to pump into cement paste successively earlier, increase pressure then gradually, till cement paste overflows from adjacent pipe.
Described electric power line pole tower underpin method, in the said step 3, before being pressed into cement paste, the upper end of steel pipe will seal with the stopper of ability distending.
The present invention through to surface compaction, impact compacting, vibratory compaction, slip casing by pressure, etc. method.The consolidation process on transmission line of electricity basis can save that track remodelling power cut construction, original circuit are constructed again, fabrication and installation electric power line pole tower expense again.
The specific embodiment
The supporting capacity of pole and tower foundation depends on the intensity and the compactness of soil around the basis, so one of the method for underpin is that backfill is strengthened or closely knit, and this just needs to differentiate and adopt a kind of suitable method.From this viewpoint, various soil stabilizations and the process densification method that uses in the builing industry is necessary to evaluate.Through to surface compaction, impact compacting, vibratory compaction, slip casing by pressure, etc. method.
At first with 38 centimetres of diameters, long 1.8 meters, nearly weigh 1.8 tons vibration head and shake deeply and bury near the regolith jolt ramming making.When the degree of depth that needs jolt ramming is big, can also with the moving head of vibration head lengthening by with axis of rotation that motor is connected on eccentric block form, motor can drive with miniature gasoline engine.During work, vibration head is to hang over one movably on the arm of crane, and one of which surface vibration one side is vertically descended, and relies on the deadweight of vibration head progressively to shake in the ground.After vibration finishes, in the hole that vibration head forms, insert rubble, make it form rubble post one by one.During general the construction, in graininess soil, do not need these rubble posts, but concerning pole and tower foundation, the rubble of increase can improve composition of the soil, its compactness is increased.
Then; Select diameter 15CM, the sleeve pipe that length is identical with embedded depth of foundation is squeezed in the soil, in soil, is pressed into the cement paste of cement and flyash preparation then through the bottom plasma discharge mouth of these sleeve pipes; It is clamp-oned in the soil of pipe at the end, and be penetrated in any big space of backfill.The process of operation is in each pipe, to pump into cement paste successively earlier, increases pressure then gradually, till cement paste overflows from adjacent pipe.During pressurization, the upper end of steel pipe will seal with the stopper of ability distending, so that cement paste can the degree of depth infiltrate in the soil.Just can extract sleeve pipe in 3 ~ 4 hours after the slip casting, and cement paste is stayed in the soil.When Grouting Pipe was driven underground, the backfill vibratory compaction can improve the sealing between Grouting Pipe and backfill, thereby can use higher grouting pressure, made it on the sole plate horizontal plane, form the concrete column piece.The needed construction machinery of slip casing by pressure is light-duty and movably.
Behind jolt ramming and mud jacking, generally all can make typical pole and tower foundation reinforce the actual anti-uplift force in back increases by 30% ~ 60%.It is better in the backfill of pine, to improve effect.Because densified near the backfill at face of land place, therefore the basis ability of bearing lateral force also can increase.

Claims (4)

1. electric power line pole tower underpin method is characterized in that it comprises:
Step 1 is shaken vibration head deeply and to be buried near the regolith jolt ramming making;
Step 2 after vibration finishes, is inserted rubble in the hole that vibration head forms, make it form rubble post one by one;
Step 3; The sleeve pipe that some length are identical with embedded depth of foundation is squeezed in the soil; In soil, be pressed into the cement paste of cement and flyash preparation then through the bottom plasma discharge mouth of these sleeve pipes, it clamp-oned in the soil of pipe at the end, and be penetrated in any big space of backfill.
2. electric power line pole tower underpin method according to claim 1; It is characterized in that said step 1 also is included in the degree of depth that needs jolt ramming when big, with the moving head of vibration head lengthening by with axis of rotation that motor is connected on eccentric block form; During work; Vibration head hangs over one movably on the arm of crane, and one of which surface vibration one side is vertically descended, and relies on the deadweight of vibration head progressively to shake in the ground.
3. electric power line pole tower underpin method according to claim 1 is characterized in that, the process of said step 3 operation is in each pipe, to pump into cement paste successively earlier, increases pressure then gradually, till cement paste overflows from adjacent pipe.
4. according to claim 1 or 3 described electric power line pole tower underpin methods, it is characterized in that in the said step 3, before being pressed into cement paste, the upper end of steel pipe will seal with the stopper of ability distending.
CN2011100801294A 2011-03-31 2011-03-31 Method for strengthening foundation of transmission line tower Pending CN102720223A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100801294A CN102720223A (en) 2011-03-31 2011-03-31 Method for strengthening foundation of transmission line tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100801294A CN102720223A (en) 2011-03-31 2011-03-31 Method for strengthening foundation of transmission line tower

Publications (1)

Publication Number Publication Date
CN102720223A true CN102720223A (en) 2012-10-10

Family

ID=46946078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100801294A Pending CN102720223A (en) 2011-03-31 2011-03-31 Method for strengthening foundation of transmission line tower

Country Status (1)

Country Link
CN (1) CN102720223A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266620A (en) * 2013-05-16 2013-08-28 国家电网公司 Method for assembling electric transmission lines through coal gangue area towers
CN104532869A (en) * 2014-12-08 2015-04-22 国家电网公司 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Foundation for existing foundation reinforcing steel tower and construction method for it
CN200999346Y (en) * 2006-09-15 2008-01-02 刘海峰 Fully steel-made universal reinforced type pole tower pile
KR20090025776A (en) * 2007-09-07 2009-03-11 성우전자(주) Steel pole tower for mobile communication and method for construction thereof
CN101538868A (en) * 2009-02-06 2009-09-23 青海省电力设计院 Everfrost and saline soil region transmission line pole glass fiber reinforced plastic foundation construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Foundation for existing foundation reinforcing steel tower and construction method for it
CN200999346Y (en) * 2006-09-15 2008-01-02 刘海峰 Fully steel-made universal reinforced type pole tower pile
KR20090025776A (en) * 2007-09-07 2009-03-11 성우전자(주) Steel pole tower for mobile communication and method for construction thereof
CN101538868A (en) * 2009-02-06 2009-09-23 青海省电力设计院 Everfrost and saline soil region transmission line pole glass fiber reinforced plastic foundation construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
余自强: "输电线路杆塔基础加固的两种方法", 《江西电力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266620A (en) * 2013-05-16 2013-08-28 国家电网公司 Method for assembling electric transmission lines through coal gangue area towers
CN103266620B (en) * 2013-05-16 2015-09-16 国家电网公司 Transmission line of electricity is through the method for assembling of coal gangue area shaft tower
CN104532869A (en) * 2014-12-08 2015-04-22 国家电网公司 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region
CN104532869B (en) * 2014-12-08 2017-01-11 国家电网公司 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region

Similar Documents

Publication Publication Date Title
CN101736738B (en) Production method of pressure resistance and pull-out resistance grouted gravel pile
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN102733378B (en) Construction method of concrete pile
CN104074186B (en) The casing device of pore-forming and construction method thereof in a kind of building lot
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN103184734A (en) Implanted and grouted compound pile and construction method
CN105714773A (en) Foundation treatment method
CN102900079A (en) High-frequency hydraulic vibratory construction method for cement-soil core-inserted combined pile
CN104314078A (en) Concrete pile construction equipment and construction method thereof
CN104099925A (en) Construction device for concrete pile and construction method thereof
CN103835292B (en) High frequency vibrating rushes the construction method of base-extending deposited pile tube
CN111794216A (en) Construction method of uplift carrier pile
CN201770942U (en) Support for soft soil foundation cast-in-place concrete continuous beam bridge
CN203213101U (en) Embedding grouting combined pile
CN103215944A (en) Multi-vibroflot resonance ground treatment equipment and method
CN202595757U (en) Grouting type reinforced filling pile foundation structure
CN202220341U (en) Support structure for foundation pit in sludge
CN204000848U (en) A kind of socketed pile for subaqueous construction
CN203701112U (en) Composite foundation grouting steel tube type reinforced slope
CN102720223A (en) Method for strengthening foundation of transmission line tower
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN105064332A (en) Construction method for bearing base piles of square pile bodies
CN204225100U (en) The construction equipment of concrete pile
CN204252120U (en) The construction equipment of concrete pile
CN205776209U (en) The construction equipment of concrete-pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121010