CN104532869B - Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region - Google Patents

Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region Download PDF

Info

Publication number
CN104532869B
CN104532869B CN201410743635.0A CN201410743635A CN104532869B CN 104532869 B CN104532869 B CN 104532869B CN 201410743635 A CN201410743635 A CN 201410743635A CN 104532869 B CN104532869 B CN 104532869B
Authority
CN
China
Prior art keywords
foundation
sand
basis
transmission line
drift
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410743635.0A
Other languages
Chinese (zh)
Other versions
CN104532869A (en
Inventor
郑卫锋
鲁先龙
苏荣臻
杨文智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Sichuan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Sichuan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI, State Grid Sichuan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410743635.0A priority Critical patent/CN104532869B/en
Publication of CN104532869A publication Critical patent/CN104532869A/en
Application granted granted Critical
Publication of CN104532869B publication Critical patent/CN104532869B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a method used for improving anti-pulling performance of a power transmission line tower foundation in a drift sand region. The method includes the steps of foundation pit excavating, installing the assembly type foundation, string cement with wind-blown sand, laying a straw checkerboard sand barrier or paving gravels, wherein the weight ratio of common silicate cement and drift sand is defined to be 0.03:1, the anti-pulling bearing capability of the power transmission line foundation is remarkably improved, and the wind and sand resistance of the desert region is improved. The cement content is less, meanwhile transportation amount is small for the power transmission line tower foundation distributed in spots, the cost for wind and sand resistance is greatly reduced, and remarkable economical benefit is obtained.

Description

A kind of method for improving drift-sand area transmission line tower foundation extraction-resistant behavior
Technical field
The present invention relates to the foundation engineering technology of a kind of transmission line of electricity, be specifically related to a kind of for improving the transmission of electricity of drift-sand area The method of overhead line structures foundation anti-pulling performance.
Background technology
Drift-sand is a kind of sandy soil with special nature, and its notable engineering characteristic is: granule is uniform, natural moisture content Low (3%~about 10%), chance water have " settlement by soaking ".
Sand Movement is serious to industry harm such as highway, railway, transmission lines of electricity, current drift-sand area electric power line pole tower Basis generally two kinds of modes of checking winds and fixing drifting sand of employing:
1) straw checkerboard barrier sand-protecting barrier fixes the sand: this kind of sand-fixation method generally takes the straw about length 50cm, imbeds 20-30cm in sand, Expose outside Shamian Island 20-30cm, surround the grid of about 1m × 1m, be covered with basis, whole tower position extension with this kind of grid 2-3m.This mode of fixing the sand has a disadvantage in that owing to the things such as straw are easily degenerated, and generally at circuit running, needs Safeguarding in time when patrolling and examining, maintenance period is usually 1-2;If safeguarding the most in time, owing to straw checkerboard barrier sand-protecting barrier fixes the sand mode Single, cause engineering safety hidden danger;Basic stand column and sandy soil contact site, earth's surface easily because of the raw wind erosion of local wind's miscarriage, are led Cause is appeared and is highly increased, and hides some dangers for engineering;
2) rubble paving presses solidly sand: this kind fixes the sand mode generally at the metalling that Shamian Island bedding 20cm is thick, and metalling is covered with whole Individual tower position, basis extension 2-3m.This kind of mode can be prevented effectively from the wind erosion at basic stand column position.But due in desert, Generally engineering materials obtain and manually transport to construction ground, and simple employing rubble paving presses solidly sand, and the rubble amount used is big, increases Freight volume, improves the expense of fixing the sand.
The above-mentioned measure of checking winds and fixing drifting sand belongs to mechanical sand fixation mode, needs to utilize substantial amounts of raw material (straw or rubble), This is for the transmission line tower foundation of some wire distribution, desert area raw material freight volume greatly, costly, and on State the mode of checking winds and fixing drifting sand itself and there is limitation.
Accordingly, it is desirable to provide a kind of sand-fixation method overcomes disadvantages described above so that the overall adhesive aggregation characteristic of drift-sand is carried Height, thus can reach technical measures and the method improving transmission line tower foundation extraction-resistant behavior.
Summary of the invention
For the deficiencies in the prior art, the present invention provides a kind of for improving drift-sand area transmission line tower foundation resistance to plucking The method of performance, described method comprises the steps:
A, in ground excavate upper shed 9m*9m, deep 3m, 45 ° of extended corners, holes of end 3m*3m;
B, installation foundation: after the sandstone that paving 100mm is thick, lay basis;
C, drift-sand mix cement layer: in the drift-sand of drift-sand Yu the ratio of Portland cement weight ratio 100:3 The drift-sand of the batch mixing that mixes cement backfill 300~500mm mixes cement after layer and gives compacting;
After d, backfill foundation ditch to top layer, lay straw checkerboard barrier sand-protecting barrier or gravel paving pressure.
Preferably, described basis is transmission line tower foundation, comprising: arrange from top to bottom on same vertical direction Digging foundation and rock build-in basis;Described digging foundation and rock build-in basis and which is provided with the reinforcing bar of foundation bolt Cylinder mould build-in global formation.
Preferably, described digging foundation is made up of the basic chassis of cylindrical basis principal post and truncated cone-shaped;Described basis principal post Surface layer is exposed on top, and bottom, chassis, basis couples the rock build-in basis of circular platform type.
Preferably, described foundation bolt from top to bottom through digging foundation and rock build-in basis and rebar cylinder mould inside.
Preferably, the length of described foundation bolt is more than the height sum of digging foundation with rock build-in basis, foundation bolt Top is provided with packing ring, locking nut and concrete enclosing cap, and bottom is provided with crotch or is welded with anchor slab.
Preferably, described rebar cylinder mould is by the main muscle of vertical direction, horizontal direction outer ring stirrup and horizontal direction inner ring stirrup Constitute.
Preferably, rebar cylinder mould is the outer ring stirrup of the main ribs by vertical direction and horizontal direction and inner ring stirrup is constituted Cylinder;Main ribs is uniformly arranged between one outer ring stirrup and inner ring stirrup, and described muscle is welded to connect.
With immediate prior art ratio, the invention have the benefit that
The method for improving drift-sand area transmission line tower foundation extraction-resistant behavior that the present invention provides is by by common The weight ratio of portland cement and drift-sand is set to 0.03:1, the breakout capacity anti-than common tower foundation improve 10~ 15%, extend 8~12% service life, desert area can be reached again and check winds and fix drifting sand effect, and cement consumption is little, Transmission line tower foundation freight volume simultaneously for spot distribution is the least, greatly reduces the cost checked winds and fixed drifting sand, and obtains Significant economic benefit.
Accompanying drawing explanation
Fig. 1 is that the present invention improves electric power line pole tower base in the method for drift-sand area transmission line tower foundation extraction-resistant behavior The front view of plinth;
Fig. 2 is A-A sectional view in Fig. 1;
Fig. 3 is B-B sectional view in Fig. 1;
Fig. 4 is the rebar cylinder mould structural representation of transmission line tower foundation in Fig. 1;
Description of reference numerals: 1 digging foundation, 1-1 basis principal post, chassis, 1-2 basis, 2 rock build-in bases, 3 ground Foot bolt, 3-1 crotch, 4 rebar cylinder moulds, the main muscle of 4-1,4-2 outer ring stirrup, 4-3 inner ring stirrup, 5 coagulation graves Close cap
Detailed description of the invention
Below the detailed description of the invention of the present invention is described in further detail.
In order to thoroughly understand the embodiment of the present invention, detailed structure will be proposed in following description.Obviously, the present invention is real The execution executing example is not limited to the specific details that those skilled in the art is familiar with.Presently preferred embodiments of the present invention is detailed It is described as follows, but in addition to these describe in detail, the present invention can also have other embodiments.
In the present invention, transmission line tower foundation selects to see shown in Fig. 1, Fig. 2 and Fig. 3, and the embodiment of the present invention provides A kind of base structure of electric power line pole tower, this basis at least includes: digging foundation 1, rock build-in basis 2, Foot bolt 3, rebar cylinder mould 4, concrete protective cap 5 etc.;Cover by argillic horizon on earth's surface, under cover for severely-weathered or in Deng the base structure using digging foundation 1 and rock build-in basis 2 to combine under the geological conditions of weathered rock formation, it is achieved The transmission line tower foundation such as this kind of area higher enforcement supertension of extraction-resistant behavior, extra-high voltage.
Specifically, as preferably, described digging foundation 1 and rock build-in basis 2 are by foundation bolt 3 and rebar cylinder mould 4 build-ins are solidifying to be integrated, and uses concrete one-time-concreting entirety build-in molding, and wherein, digging foundation 1 is positioned at earth's surface and glues Soil layer, rock build-in basis 2 is positioned at severely-weathered or medium weathering rock stratum;Described digging foundation 1 by basis principal post 1-1 and Basis chassis 1-2 is constituted, and wherein, basis principal post 1-1 is cylinder, and basis chassis 1-2 is circular platform type, described basis The top of principal post 1-1 is exposed surface clay layer and is covered, and bottom couples the basic chassis 1-2 of circular platform type, basis chassis 1-2 Bottom couple circular platform type rock build-in basis 2.
Specifically, as preferably, the top of described basis principal post 1-1 is inserted with many foundation bolts 3, preferably four, The specification of the value range base area foot bolt 3 that each foundation bolt 3 exposes basis principal post 1-1 is different and changes, its thing Matter scope is 200-400mm;Foundation bolt 3 top is provided with packing ring and locking nut, uses concrete after having assembled Pour one concrete enclosing cap 5 of molding, in order to protecting field foot bolt 3 and securing member;The length of described foundation bolt 3 More than the height sum of digging foundation 1 with rock build-in basis 2, foundation bolt 3 is from top to bottom through digging foundation 1 Internal with rock build-in basis 2 and rebar cylinder mould 4, foundation bolt 3 bottom is provided with crotch 3-1 or is welded with anchor slab, To strengthen anchoring effect.
Referring also to shown in Fig. 4, specifically, described rebar cylinder mould 4 is by some main muscle 4-1, several outer ring stirrups 4-2 and several inner rings stirrup 4-3 is constituted;Described each main muscle 4-1 is longitudinally disposed along Y-axis, described outside each Circle stirrup 4-2 and each inner ring stirrup 4-3 is along X-axis horizontally set;Some main muscle 4-1 are circumferentially uniformly distributed, Several outer rings stirrup 4-2 and several inner rings stirrup 4-3 is along Y-axis longitudinal arrangement;Described the most equally distributed often A piece main muscle 4-1 is uniformly arranged between each outer ring stirrup 4-2 and each inner ring stirrup 4-3, described outside each Circle stirrup 4-2 and each inner ring stirrup 4-3 is the most arranged vertically along each main muscle 4-1, and interval is uniform, with each main muscle 4-1 contact point is pad, and is welded to each other together, thus constitutes the rebar cylinder mould 4 that cylinder is netted;Described bar-mat reinforcement The height of cage 4 is more than the height of digging foundation 1, and rebar cylinder mould 4 is from top to bottom through in digging foundation 1 and extend to Rock build-in basis 2 is internal, be mounted in digging foundation 1 and rock build-in basis 2 by concreting together with, institute Stating the design height scope inserted in rock build-in basis 2 bottom rebar cylinder mould 4 is 600-1300mm, embedded depth of foundation 3m.
In order to improve drift-sand area transmission line tower foundation extraction-resistant behavior, mainly it is implemented with following steps:
(1) excavation of foundation pit: using and mechanically or manually excavate, top is excavated according to 45 degree of extended corners, top excavation size 9m*9m, bottom excavation size 3m*3m, cutting depth 3m, foundation ditch sandy soil excavated volume 117 side, drift-sand weight about 163.8 Ton;
(2) assembling type base is installed: require 100mm sand-gravel cushion according to design, lays assembling type base and successively will Each connector is tightened;
(3) drift-sand mixes cement: according to 3% incorporation Portland cement of drift-sand weight, press in whipping process Weight according to bagged cement adds sand, is at once backfilled in foundation ditch after stirring, and enters according to 300~500mm mono-layers Row compacting, amounts to required incorporation Portland cement amount 4914kg.
(4) after foundation ditch is backfilled to top layer, laying straw checkerboard barrier sand-protecting barrier or gravel paving pressure, foundation construction is complete.
Transmission line tower foundation extraction-resistant behavior in above-described embodiment, pulls out in the assembling type base limit under normal conditions and holds Load power is 500kN, and the assembling type base upper and low approximations in mixing cement mixing molding drift-sand ground is 600kN, Its limit upper and low approximations improves about 20%.
According to correlational study achievement, the moisture content of drift-sand is typically about 3%, and Portland cement volume is 3%~6% Time, the adhesive aggregation performance of drift-sand reaches optimal, and its Shear Strength Index C value improves more than 20%, and top layer is easily formed tool Having the flexible bonding course of some strength, form protective layer on surface, sand dune, isolation air-flow directly acts on loose sand bed, Ensure that the moisture of drift-sand is difficult to lose, adhesive aggregation performance is strengthened, reach to check winds and fix drifting sand and improve pole and tower foundation resistance to plucking and hold Carry the effect that can manage it.
The present invention for improving the method for drift-sand area transmission line tower foundation extraction-resistant behavior by by common silicic acid Salt cement is set to 0.03:1 with the weight ratio of drift-sand, and the resistance to plucking carrying significantly improving transmission line tower foundation can be manageed it, Desert area can be reached again check winds and fix drifting sand effect, and cement consumption is little, simultaneously for the transmission line of electricity bar of spot distribution Tower foundation freight volume is the least, greatly reduces the cost checked winds and fixed drifting sand, and achieves significant economic benefit
Finally should be noted that: above example only in order to illustrate that technical scheme is not intended to limit, although Being described in detail the present invention with reference to above-described embodiment, those of ordinary skill in the field still can be to this Bright detailed description of the invention is modified or equivalent, these without departing from spirit and scope of the invention any amendment or Person's equivalent, all within the claims that application is awaited the reply.

Claims (5)

1. the method being used for improving drift-sand area transmission line tower foundation extraction-resistant behavior, it is characterised in that institute The method of stating comprises the steps:
A, in ground excavate upper shed 9m*9m, deep 3m, 45 ° of extended corners, holes of end 3m*3m;
B, installation foundation: after the sandstone that paving 100mm is thick, lay basis;
C, drift-sand mix cement layer: in the drift-sand of drift-sand Yu the ratio of Portland cement weight ratio 100:3 The drift-sand of the batch mixing that mixes cement backfill 300~500mm mixes cement after layer and gives compacting;
After d, backfill foundation ditch to top layer, lay straw checkerboard barrier sand-protecting barrier or gravel paving pressure;
Described basis is transmission line tower foundation, comprising: the digging foundation arranged from top to bottom on same vertical direction (1) and rock build-in basis (2);Described digging foundation (1) and rock build-in basis (2) and described rock build-in basis (2) It is provided with rebar cylinder mould (4) the build-in global formation of foundation bolt (3);
Described digging foundation (1) is made up of the basic chassis (1-2) of cylindrical basis principal post (1-1) and truncated cone-shaped;Described foundation main Surface layer is exposed on post (1-1) top, and chassis (1-2) bottom, basis couples rock build-in basis (2) of circular platform type.
Method for improving drift-sand area transmission line tower foundation extraction-resistant behavior the most according to claim 1, It is characterized in that, described foundation bolt (3) is from top to bottom through digging foundation (1) and rock build-in basis (2) and bar-mat reinforcement Cage (4) is internal.
Method for improving drift-sand area transmission line tower foundation extraction-resistant behavior the most according to claim 2, It is characterized in that, the length of described foundation bolt (3) is more than the height sum of digging foundation (1) and rock build-in basis (2), Foundation bolt (3) top is provided with packing ring, locking nut and concrete enclosing cap (5), and bottom is provided with crotch (3-1) or weldering It is connected to anchor slab.
Method for improving drift-sand area transmission line tower foundation extraction-resistant behavior the most according to claim 1, It is characterized in that, described rebar cylinder mould (4) is by the main muscle (4-1) of vertical direction, horizontal direction outer ring stirrup (4-2) and level side Constitute to inner ring stirrup (4-3).
Method for improving drift-sand area transmission line tower foundation extraction-resistant behavior the most according to claim 4, It is characterized in that, rebar cylinder mould (4) is the main ribs (4-1) by vertical direction and the outer ring stirrup (4-2) of horizontal direction and interior The cylinder that circle stirrup (4-3) is constituted;Main ribs (4-1) is uniformly arranged on one outer ring stirrup (4-2) and inner ring stirrup (4-3) between.
CN201410743635.0A 2014-12-08 2014-12-08 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region Active CN104532869B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410743635.0A CN104532869B (en) 2014-12-08 2014-12-08 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410743635.0A CN104532869B (en) 2014-12-08 2014-12-08 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region

Publications (2)

Publication Number Publication Date
CN104532869A CN104532869A (en) 2015-04-22
CN104532869B true CN104532869B (en) 2017-01-11

Family

ID=52848477

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410743635.0A Active CN104532869B (en) 2014-12-08 2014-12-08 Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region

Country Status (1)

Country Link
CN (1) CN104532869B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109898543A (en) * 2019-03-25 2019-06-18 东北大学 A kind of pulling-resistant and pressure-resistant power transmission tower basis and its construction method

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498973A (en) * 2016-12-27 2017-03-15 国网江苏省电力公司经济技术研究院 A kind of assembled type base for power transmission line iron tower and its installation method
CN106498974A (en) * 2016-12-27 2017-03-15 国网江苏省电力公司经济技术研究院 A kind of assembling type base and its installation method for power transmission tower
CN114592533B (en) * 2022-03-14 2024-03-12 北京恒华伟业科技股份有限公司 Rammed broken stone micro pile photovoltaic foundation and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182172A (en) * 2007-11-28 2008-05-21 盛虹集团有限公司 High-strength high-water-permeability concrete and preparation method thereof
CN201254730Y (en) * 2008-08-11 2009-06-10 国网北京电力建设研究院 Reinforcement tower foundation
RU2451136C1 (en) * 2010-10-20 2012-05-20 Валерий Алексеевич Слесарев Foundation of power transmission line support and method to increase its durability
CN102720223A (en) * 2011-03-31 2012-10-10 上海宝冶集团有限公司 Method for strengthening foundation of transmission line tower
CN103319104A (en) * 2013-04-12 2013-09-25 榆林蒙西水泥有限公司 Aeolian sand cement
CN104018516A (en) * 2014-06-13 2014-09-03 江苏省电力设计院 Power transmission line concrete cast-in-situ sand core gravity type foundation in desert area

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182172A (en) * 2007-11-28 2008-05-21 盛虹集团有限公司 High-strength high-water-permeability concrete and preparation method thereof
CN201254730Y (en) * 2008-08-11 2009-06-10 国网北京电力建设研究院 Reinforcement tower foundation
RU2451136C1 (en) * 2010-10-20 2012-05-20 Валерий Алексеевич Слесарев Foundation of power transmission line support and method to increase its durability
CN102720223A (en) * 2011-03-31 2012-10-10 上海宝冶集团有限公司 Method for strengthening foundation of transmission line tower
CN103319104A (en) * 2013-04-12 2013-09-25 榆林蒙西水泥有限公司 Aeolian sand cement
CN104018516A (en) * 2014-06-13 2014-09-03 江苏省电力设计院 Power transmission line concrete cast-in-situ sand core gravity type foundation in desert area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109898543A (en) * 2019-03-25 2019-06-18 东北大学 A kind of pulling-resistant and pressure-resistant power transmission tower basis and its construction method

Also Published As

Publication number Publication date
CN104532869A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN104452829B (en) A kind of pile-raft foundation float Structure and construction method
CN104532869B (en) Method used for improving anti-pulling performance of power transmission line tower foundation in drift sand region
RU2358063C1 (en) Device for slope surface grouting
CN108360547B (en) Bridge composite foundation suitable for deep water and strong earthquake conditions
CN106638673A (en) Construction method of combined supporting and retaining structure
CN102031760A (en) Anti-rockfall method for subgrade in rock deposit zone
CN110374111A (en) A kind of slope cooperates with support system with steel pipe piled anchor
CN106498973A (en) A kind of assembled type base for power transmission line iron tower and its installation method
RU2392387C2 (en) Device and method for reinforcement of mast base
CN209260749U (en) A kind of prefabricated Rock Bolt Foundation of mountain area iron tower of power transmission line half
CN109252542B (en) Tree root pile light retaining wall for road widening and construction method thereof
CN206844132U (en) Superelevation light supporting structure
CN107447731B (en) A kind of mixed dam and its construction method
CN210317328U (en) Tunnel segment anti-floating structure under ultra-shallow burying earthing condition of shield tunnel in operation period
CN113982001B (en) Construction method of flexible framework slope protection structure
CN2892973Y (en) Strong rammer replacement parapet structure
CN110397091A (en) Ancient building shock insulation barrier
CN102561381A (en) Method for preventing settling and cracking of large-area terrace by using bonded prestressed concrete beams in soft soil layer region
CN209384261U (en) A kind of anti-deformation cracking retaining wall structure
CN201232189Y (en) Composite soil nail wall supporting construction for adding piers
CN110106930B (en) Iron tower foundation reinforcement protection method
CN206570823U (en) A kind of broken rock mass slope protective reinforcing structure
CN205617175U (en) Be applied to temporary support structure of widening fast in place
CN206986915U (en) A kind of fan platform installation foundation
CN206736925U (en) A kind of swelled ground foundation ditch supporting and retaining system formula supporting

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160620

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: China Electric Power Research Institute

Applicant after: State Grid Sichuan Electric Power Corporation

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant before: State Grid Corporation of China

Applicant before: China Electric Power Research Institute

GR01 Patent grant
GR01 Patent grant