CN102704839B - Hanging carrying type integral hydraulic rock drilling machine - Google Patents
Hanging carrying type integral hydraulic rock drilling machine Download PDFInfo
- Publication number
- CN102704839B CN102704839B CN201210189804.1A CN201210189804A CN102704839B CN 102704839 B CN102704839 B CN 102704839B CN 201210189804 A CN201210189804 A CN 201210189804A CN 102704839 B CN102704839 B CN 102704839B
- Authority
- CN
- China
- Prior art keywords
- plate
- bolt
- slide plate
- bearing pin
- bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The invention discloses a hanging carrying type integral hydraulic rock drilling machine, which comprises a bottom supporter and a drill frame, wherein the middle of the drill frame is provided with a seventh pin shaft and an eighth pins haft, a parallel rail is welded on the drill frame, a first slide plate is arranged on the rail, an installing plate is arranged on the first slide plate through a screw bolt, a clamp head is fixedly arranged on the installing plate, a rock drilling machine is arranged in the clamping head and is connected with a drill rod, the top of the drill frame is provided with a driving chain wheel, the lower part of the drill frame is provided with a driven chain wheel, a ring opening chain is matched on the driving chain wheel and the driven chain wheel, the first end and the second end of the ring opening chain are fixedly connected with the installing plate, a dust shielding plate is fixedly arranged on the bottom plate supporter, a rod grasping block is hinged on the dust shielding plate, oil cylinders are hinged at two sides of the dust shielding plate, and the rod grasping block is hinged with piston rods of the oil cylinders. The hanging carrying type integral hydraulic rock drilling machine is based on a digging machine platform, the cost is effectively reduced, the excellent performance of the digging machine is expanded, in addition, the original functions of the digging machine are completely remained, and one machine realizes two purposes.
Description
Technical field
The present invention relates to a kind of rock drilling machine.
Background technology
China is the man of many mountain countries in a rapid economic development, road and rail, mine, the energy, water power, national defence, real estate, economic development zone, in the Infrastructure Field such as quarry, the engineering quantity of various rock drilling exploitation is very great, and current large-scale high performance modern rock drilling rig is nearly all the import of at substantial foreign exchange, and domestic rig always is that Pneumatic down-the-hole drill occupies market.If adopt domestic in low blast pneumatic down-the-hole drill, energy consumption is high, and efficiency is low, and labor strength is large, and air pollution is serious, can not meet the schedule requirement of generous amount rock excavation at all.And adopt the hydraulic drill rig of import to construct, although efficiency is high, original equipment cost is high, and parts price is very high, and delivery cycle is long.
Therefore those skilled in the art are devoted to develop the integrated hydraulic rock drilling machine that a kind of quality is good, cost is low.
Summary of the invention
Because the above-mentioned defect of prior art, technical problem to be solved by this invention is to provide the integrated hydraulic rock drilling machine that a kind of quality is good, cost is low.
For achieving the above object, the invention provides a kind of carry formula integrated hydraulic rock drilling machine, comprise the bottom support and drilling cramp that are fixed to one another connection; The middle part of described drilling cramp is provided with the 7th bearing pin that can connect with engineering truck oil cylinder and the 8th bearing pin that can connect with engineering truck large arm;
Described drilling cramp is welded with parallel orbit; Described track is provided with the first slide plate; Described first slide plate has been bolted installing plate; Described installing plate is fixed with the chuck vertical with described installing plate; Hammer drill is provided with in described chuck; Described hammer drill is connected with drilling rod;
The top of described drilling cramp is provided with drive sprocket, bottom is provided with driven sprocket; Described drive sprocket and driven sprocket are combined with open loop chain; Be fixedly connected with described installing plate with by chain card after the first end of described open loop chain walks around described drive sprocket, be fixedly connected with described installing plate by chain card after the second end walks around described driven sprocket;
Described backplanes support is fixed with the dust guard parallel with described chuck; Described dust guard is provided with the via hole passed through for described drilling rod; Described dust guard has relative first to grab bar block and second by the first bearing pin and the second hinge and grabs bar block; Described first grabs bar block and second grabs bar block and is provided with the cambered surface corresponding with described drilling rod profile; There are the first oil cylinder and the second oil cylinder in the both sides of described dust guard by the 3rd bearing pin and the 4th hinge; Described first to grab bar block hinged by the piston rod of the 5th bearing pin and described first oil cylinder; Described second to grab bar block hinged by the piston rod of the 6th bearing pin and described second oil cylinder.
For preventing drilling rod from bending, described guide rail is combined with the second slide plate in the below of described first slide plate; Described second slide plate is fixed with the support set coordinated with described drilling rod; Described second slide plate is fixed with pull bar; Described pull bar through after described first slide plate with nut screw connection.
For preventing the second slide plate derailing, described guide rail is provided with the block for limiting described second slide plate lower end limit travel.
For adjusting chain degree of tightness, the bottom of described drilling cramp is fixed with clutch shaft bearing box installing rack and the second bearing box installing rack; Described clutch shaft bearing box installing rack is relatively set with the first bolt and the second bolt up and down; Clutch shaft bearing box is provided with between described first bolt and the second bolt; Clutch shaft bearing is provided with in described clutch shaft bearing box; Described second bearing box installing rack is relatively set with the 3rd bolt and the 4th bolt up and down; The second bearing box is provided with between described 3rd bolt and the 4th bolt; The second bearing is provided with in described second bearing box; The sprocket shaft of described driven sprocket is supported by described clutch shaft bearing and the second bearing.
Preferably, the top of described drilling cramp is provided with propelling mount pad; Described propelling mount pad is fixed with tie-plate; Described tie-plate is provided with motor; Described drive sprocket is arranged on the power transmission shaft of described motor, and by pressing plate and the 5th bolt axial location.
The invention has the beneficial effects as follows: the present invention is based on Platform of Excavators, effectively reduces cost, the another expansion of excavator premium properties and original digging machine function are all retained, dual-use.The motor that configuration boring rock drilling power matches and pumping system, install the automatic control valve group that hydraulic rock system needs additional, hammer drill and drilling cramp, the hard rock that making excavator realize import all-hydraulic drill just has is punchinged function, and this kind of equipment plays the flexible quick mobile efficiency high of digging machine, there is again imported hydraulic rig energy consumption low, the feature that cost is low, failure rate is low, personnel's manageability, practicality, durable.
Accompanying drawing explanation
Fig. 1 is the structural representation of the embodiment of the invention.
Fig. 2 is the partial enlarged drawing at I place in Fig. 1.
Fig. 3 is that the A of Fig. 1 is to schematic diagram.
Fig. 4 is that the B of Fig. 1 is to schematic diagram.
Fig. 5 is the left TV structure schematic diagram of Fig. 1.
Fig. 6 is the partial enlarged drawing at II place in Fig. 5.
Detailed description of the invention
Below in conjunction with drawings and Examples, the invention will be further described:
As shown in Figures 1 to 6, a kind of carry formula integrated hydraulic rock drilling machine, comprise the bottom support 1 and drilling cramp 8 that are fixed to one another connection, the middle part of drilling cramp 8 is provided with the 7th bearing pin 19 that can connect with engineering truck oil cylinder and the 8th bearing pin 20 that can connect with engineering truck large arm.
Drilling cramp 8 is welded with parallel orbit 28, track 28 is provided with on the first slide plate 14, first slide plate 14 and has been bolted installing plate 13, installing plate 13 is fixed with the chuck 15 vertical with installing plate 13, be provided with hammer drill 12 in chuck 15, hammer drill 12 is connected with drilling rod 7.
The top of drilling cramp 8 is provided with drive sprocket 16, bottom is provided with driven sprocket 10.Drive sprocket 16 and driven sprocket 10 are combined with open loop chain 17.The first end 17a of open loop chain 17 walks around drive sprocket 16 and is fixedly connected with installing plate 13 with by chain card 18 afterwards, is fixedly connected with after the second end 17b walks around driven sprocket 10 by chain card with installing plate 13.
Backplanes support 1 is fixed with the dust guard 3 parallel with chuck 15, dust guard 3 is provided with the via hole 3a passed through for drilling rod 7.Dust guard 3 is hinged with relative first by the first bearing pin 30a and the second bearing pin 30b grab bar block 4a and second and grab bar block 4b, first grabs bar block 4a and second grabs bar block 4b and is provided with the cambered surface corresponding with drilling rod 7 profile.
The both sides of dust guard 3 are hinged with the first oil cylinder 6a and the second oil cylinder 6b by the 3rd bearing pin 31a and the 4th bearing pin 31b.First to grab bar block 4a hinged by the piston rod of the 5th bearing pin 5a and the first oil cylinder 6a, and second to grab bar block 4b hinged by the piston rod of the 6th bearing pin 5b and the second oil cylinder 6b.
Guide rail 28 is combined with on the second slide plate 33, second slide plate 33 in the below of the first slide plate 14 and is fixed with the support set 11 coordinated with drilling rod 7.Second slide plate 33 is fixed with pull bar 21, and pull bar 21 coordinates with nut 34 through after the preformed hole on the first slide plate 14.The diameter of preformed hole is greater than the diameter of pull bar 21.Guide rail 28 is provided with the block 35 for limiting the second slide plate 33 lower end limit travel.
The bottom of drilling cramp 8 is fixed with clutch shaft bearing box installing rack 36a and the second bearing box installing rack 36b.Clutch shaft bearing box installing rack 36a is relatively set with the first bolt 9a and the second bolt 9b up and down, is provided with clutch shaft bearing box 23a between the first bolt 9a and the second bolt 9b, is provided with clutch shaft bearing 22a in clutch shaft bearing box 23a.
Second bearing box installing rack 36b is relatively set with the 3rd bolt 9c and the 4th bolt 9d up and down, is provided with the second bearing box 23b between the 3rd bolt 9c and the 4th bolt 9d, is provided with the second bearing 22b in the second bearing box 23b.The sprocket shaft 29 of driven sprocket 10 is supported by clutch shaft bearing 22a and the second bearing 22b.
The top of drilling cramp 8 is provided with and advances mount pad 24, advances on mount pad 24 and is fixed with tie-plate 26, tie-plate 26 is provided with motor 27.Drive sprocket 16 is arranged on the power transmission shaft 32 of motor 27, and by pressing plate 25 and the 5th bolt axial location.
Rock drilling drilling cramp being connected with engineering truck oil cylinder by the 7th bearing pin 19, is connected with engineering truck by the 8th bearing pin 20, therefore by regulating the flexible of engineering truck oil cylinder, drilling cramp 8 being rotated around the 8th bearing pin 20, thus the angle of adjustment drilling cramp.After drill bit 2 is connected with drilling rod 7, hotwire 27 and hammer drill 12, can start rock drilling boring work.By controlling the rotating of motor 27, thus make chain 17 clockwise or counterclockwise movement, and then realize the first slide plate 14 and move upward or move downward.When grabbing pricker, first grabs bar block 4a is opened around the first bearing pin 30a rotation by the piston rod retraction of the first oil cylinder 6a, and second grabs bar block 4b is opened around the second bearing pin 30b rotation by the piston rod retraction of the second oil cylinder 6b; Connect pricker when completing, the piston rod of the first oil cylinder and the second oil cylinder stretches out, thus makes first to grab bar block 4a and second to grab bar block 4b and close.
In the process of boring, first slide plate 14 is at the moved downward of chain 17, second slide plate 33 moves downward under gravity, in initial motion process, due to the requirement according to actual condition, the rotating speed of motor 16 is lower, and therefore the movement velocity of the first slide plate 14 is comparatively slow, and the first slide plate 14 and the second slide plate 33 are in the state of roughly geo-stationary.When the second slide plate 33 moves downward extreme position, by stop motion under the effect of block 35, the first slide plate 14, under the effect of chain 17, can continue to move downward, and hammer drill 12 continues rock drilling boring, until the first slide plate 14 contacts with the second slide plate 33.In whole process, support set 11 will be in the middle part of drilling rod 7 all the time, thus avoids drilling rod 7 to bend because suffering larger impact force.
If desired adjust loose chain 17, only need, by the degree regulating the first bolt 9a, the second bolt 9b, the 3rd bolt 9c and the 4th bolt 9d to be screwed into bearing box installing rack, clutch shaft bearing box 23a and the second bearing box 23b be moved upward; To tighten chain, tighten process contrary.
More than describe preferred embodiment of the present invention in detail.Should be appreciated that those of ordinary skill in the art just design according to the present invention can make many modifications and variations without the need to creative work.Therefore, all technician in the art, all should by the determined protection domain of claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.
Claims (3)
1. a carry formula integrated hydraulic rock drilling machine, is characterized in that: comprise the bottom support (1) and drilling cramp (8) that are fixed to one another connection; The middle part of described drilling cramp (8) is provided with the 7th bearing pin (19) that can connect with engineering truck oil cylinder and the 8th bearing pin (20) that can connect with engineering truck large arm;
Described drilling cramp (8) is welded with parallel orbit (28); Described track (28) is provided with the first slide plate (14); Described first slide plate (14) has been bolted installing plate (13); Described installing plate (13) is fixed with the chuck (15) vertical with described installing plate (13); Hammer drill (12) is provided with in described chuck (15); Described hammer drill (12) is connected with drilling rod (7);
The top of described drilling cramp (8) is provided with drive sprocket (16), bottom is provided with driven sprocket (10); Described drive sprocket (16) and driven sprocket (10) are combined with open loop chain (17); The first end (17a) of described open loop chain (17) is walked around described drive sprocket (16) and is fixedly connected with described installing plate (13) afterwards with by chain card (18), is fixedly connected with after the second end (17b) walks around described driven sprocket (10) by chain card with described installing plate (13);
Described bottom support (1) is fixed with the dust guard (3) parallel with described chuck (15); Described dust guard (3) is provided with the via hole (3a) passed through for described drilling rod (7); Described dust guard (3) is hinged with relative first by the first bearing pin (30a) and the second bearing pin (30b) grab bar block (4a) and second and grab bar block (4b); Described first grabs bar block (4a) and second grabs bar block (4b) and is provided with the cambered surface corresponding with described drilling rod (7) profile; The both sides of described dust guard (3) are hinged with the first oil cylinder (6a) and the second oil cylinder (6b) by the 3rd bearing pin (31a) and the 4th bearing pin (31b); Described first to grab bar block (4a) hinged by the piston rod of the 5th bearing pin (5a) and described first oil cylinder (6a); Described second to grab bar block (4b) hinged by the piston rod of the 6th bearing pin (5b) and described second oil cylinder (6b);
The bottom of described drilling cramp (8) is fixed with clutch shaft bearing box installing rack (36a) and the second bearing box installing rack (36b);
Described clutch shaft bearing box installing rack (36a) is relatively set with the first bolt (9a) and the second bolt (9b) up and down; Clutch shaft bearing box (23a) is provided with between described first bolt (9a) and the second bolt (9b); Clutch shaft bearing (22a) is provided with in described clutch shaft bearing box (23a);
Described second bearing box installing rack (36b) is relatively set with the 3rd bolt (9c) and the 4th bolt (9d) up and down; The second bearing box (23b) is provided with between described 3rd bolt (9c) and the 4th bolt (9d); The second bearing (22b) is provided with in described second bearing box (23b); The sprocket shaft (29) of described driven sprocket (10) is supported by described clutch shaft bearing (22a) and the second bearing (22b);
The top of described drilling cramp (8) is provided with and advances mount pad (24); Described propelling mount pad (24) is fixed with tie-plate (26); Described tie-plate (26) is provided with motor (27); Described drive sprocket (16) is arranged on the power transmission shaft (32) of described motor (27), and by pressing plate (25) and the 5th bolt axial location.
2. carry formula integrated hydraulic rock drilling machine as claimed in claim 1, is characterized in that: described track (28) is combined with the second slide plate (33) in the below of described first slide plate (14); Described second slide plate (33) is fixed with the support set (11) coordinated with described drilling rod (7); Described second slide plate (33) is fixed with pull bar (21); Described pull bar (21) coordinates with nut (34) afterwards through described first slide plate (14).
3. carry formula integrated hydraulic rock drilling machine as claimed in claim 2, is characterized in that: described track (28) is provided with the block (35) for limiting described second slide plate (33) lower end limit travel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210189804.1A CN102704839B (en) | 2012-06-11 | 2012-06-11 | Hanging carrying type integral hydraulic rock drilling machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210189804.1A CN102704839B (en) | 2012-06-11 | 2012-06-11 | Hanging carrying type integral hydraulic rock drilling machine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102704839A CN102704839A (en) | 2012-10-03 |
CN102704839B true CN102704839B (en) | 2015-05-20 |
Family
ID=46897866
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210189804.1A Active CN102704839B (en) | 2012-06-11 | 2012-06-11 | Hanging carrying type integral hydraulic rock drilling machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102704839B (en) |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103075110A (en) * | 2013-02-26 | 2013-05-01 | 江苏省无锡探矿机械总厂有限公司 | Double rope propelling mechanism |
CN105064913B (en) * | 2015-07-27 | 2017-07-28 | 桂林理工大学 | A kind of main frame assembly of Geotechnical Engineering rig |
CN105625955B (en) * | 2016-03-09 | 2018-10-23 | 浙江海聚科技有限公司 | A kind of method and device for realizing puncheon centralizing device and falling and promoted automatically |
CN105781434A (en) * | 2016-05-06 | 2016-07-20 | 江苏盖亚环境科技股份有限公司 | Detection frame assembly of soil sampling and repairing integrated drilling machine |
CN106223875A (en) * | 2016-08-31 | 2016-12-14 | 广西徐沃工程机械设备有限公司 | A kind of novel drill carriage changes pricker device automatically |
CN106437510B (en) * | 2016-08-31 | 2019-03-19 | 广西徐沃工程机械设备有限公司 | A kind of drilling machine of excavator transformation |
CN106351596A (en) * | 2016-08-31 | 2017-01-25 | 广西徐沃工程机械设备有限公司 | Dust catching device for drilling rig |
CN107355186A (en) * | 2017-09-05 | 2017-11-17 | 东台市富康机械有限公司 | Punch steady bar machine |
CN109812222A (en) * | 2019-03-21 | 2019-05-28 | 任建利 | Rock drilling tool is crossed in bog-head coal fully mechanized mining |
CN110284841A (en) * | 2019-06-28 | 2019-09-27 | 三峡大学 | A kind of rock drill main arm mechanism |
CN111577123B (en) * | 2020-04-27 | 2022-08-12 | 孔江君 | Cross beam movable rock drilling equipment |
CN113638701B (en) * | 2021-10-13 | 2022-03-25 | 北京恒利新源地热能科技有限公司 | Drill rod centralizer of top drive type geothermal drilling machine |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2081921A (en) * | 1934-08-22 | 1937-06-01 | Sullivan Machinery Co | Rock drill feeding mechanism |
CN2075254U (en) * | 1990-04-04 | 1991-04-17 | 青州市钻井机械厂 | Miniature door frme type well drill for agriculture |
CN201056984Y (en) * | 2006-11-24 | 2008-05-07 | 鲍伟 | Gas-liquid linkage rock drill vehicle |
CN101210482A (en) * | 2006-12-30 | 2008-07-02 | 刘杰 | Drilling machine shaft frame two-layer platform mechanical arm grasping drill pipe device |
DE102007017819A1 (en) * | 2007-04-16 | 2008-10-23 | Liebherr-Werk Nenzing Gmbh, Nenzing | broker |
CN101591911A (en) * | 2009-06-08 | 2009-12-02 | 河北工业大学 | A kind of bi-directional cement soil mixing pile machine |
CN201695948U (en) * | 2010-06-18 | 2011-01-05 | 湖南恒至凿岩科技有限公司 | Multifunctional open-air hydraulic drill rig |
CN202181844U (en) * | 2011-06-18 | 2012-04-04 | 郭勇 | All-hydraulic downhole drill matched with engineering machinery |
CN102418475A (en) * | 2011-12-30 | 2012-04-18 | 中船重工中南装备有限责任公司 | Telescopic arm open-cut rock drilling jumbo with drill rod replacing device |
CN202228010U (en) * | 2011-09-14 | 2012-05-23 | 重庆勤牛工程机械有限责任公司 | Feeding mechanism of drill rod of drilling machine |
CN202673141U (en) * | 2012-06-11 | 2013-01-16 | 重庆迪马工业有限责任公司 | Mount type integrated hydraulic rock driller |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201414283Y (en) * | 2009-03-26 | 2010-03-03 | 冷海峰 | Small-sized engine plow |
-
2012
- 2012-06-11 CN CN201210189804.1A patent/CN102704839B/en active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2081921A (en) * | 1934-08-22 | 1937-06-01 | Sullivan Machinery Co | Rock drill feeding mechanism |
CN2075254U (en) * | 1990-04-04 | 1991-04-17 | 青州市钻井机械厂 | Miniature door frme type well drill for agriculture |
CN201056984Y (en) * | 2006-11-24 | 2008-05-07 | 鲍伟 | Gas-liquid linkage rock drill vehicle |
CN101210482A (en) * | 2006-12-30 | 2008-07-02 | 刘杰 | Drilling machine shaft frame two-layer platform mechanical arm grasping drill pipe device |
DE102007017819A1 (en) * | 2007-04-16 | 2008-10-23 | Liebherr-Werk Nenzing Gmbh, Nenzing | broker |
CN101591911A (en) * | 2009-06-08 | 2009-12-02 | 河北工业大学 | A kind of bi-directional cement soil mixing pile machine |
CN201695948U (en) * | 2010-06-18 | 2011-01-05 | 湖南恒至凿岩科技有限公司 | Multifunctional open-air hydraulic drill rig |
CN202181844U (en) * | 2011-06-18 | 2012-04-04 | 郭勇 | All-hydraulic downhole drill matched with engineering machinery |
CN202228010U (en) * | 2011-09-14 | 2012-05-23 | 重庆勤牛工程机械有限责任公司 | Feeding mechanism of drill rod of drilling machine |
CN102418475A (en) * | 2011-12-30 | 2012-04-18 | 中船重工中南装备有限责任公司 | Telescopic arm open-cut rock drilling jumbo with drill rod replacing device |
CN202673141U (en) * | 2012-06-11 | 2013-01-16 | 重庆迪马工业有限责任公司 | Mount type integrated hydraulic rock driller |
Also Published As
Publication number | Publication date |
---|---|
CN102704839A (en) | 2012-10-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102704839B (en) | Hanging carrying type integral hydraulic rock drilling machine | |
CN208267757U (en) | A kind of efficient pile driving equipment of road construction | |
CN101832102B (en) | Movable two-platform partitioned four-arm hanging wall anchor rod and anchor cable construction drill carriage | |
CN102913130B (en) | Full-hydraulic rock-drilling excavator using hydraulic excavator for production | |
CN102003143B (en) | Multidirectional hydraulic rock drilling machine with integrated drives | |
CN101832103B (en) | Movable two-arm hanging wall anchor rod and anchor cable construction drill carriage | |
CN201835305U (en) | Novel hydraulic full circle swinging gripper device | |
CN205260059U (en) | Roofbolter of group | |
CN201843520U (en) | Integrated driven multidimensional hydraulic rock drilling machine | |
CN203022625U (en) | Full-hydraulic rock drilling excavator produced by means of hydraulic excavator | |
CN203022763U (en) | Hydraulic control system of drill loader | |
CN102996139B (en) | Hydraulic control system of drill loader | |
CN102996063A (en) | Drilling mechanism for mine rock drilling and tunneling | |
CN201826837U (en) | Movable double-platform partitioned four-arm drill carriage for construction of hangwall anchor rods and anchor cables | |
CN109899065A (en) | A kind of coal mine four arm digging and anchoring integrated machines of automation | |
CN112412450A (en) | Drilling, loading and anchoring integrated machine | |
CN106437510B (en) | A kind of drilling machine of excavator transformation | |
CN104775754A (en) | Pole disc type multi-boom drill jumbo | |
CN102606158A (en) | Novel low coal seam coal mine underground mining complete equipment | |
CN205370442U (en) | Drill jumbo | |
CN102434098B (en) | Hydraulic five-arm anchor drill for coal mine | |
CN210622722U (en) | Telescopic structure | |
CN202673141U (en) | Mount type integrated hydraulic rock driller | |
CN204609879U (en) | A kind of pick anchor all-in-one | |
CN202970431U (en) | Drilling mechanism for mine rock drilling tunneling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |