不中断铁路运营的既有路基改为隧道的方法 Download PDFInfo
- Publication number
- CN102691242A CN102691242A CN2012101988669A CN201210198866A CN102691242A CN 102691242 A CN102691242 A CN 102691242A CN 2012101988669 A CN2012101988669 A CN 2012101988669A CN 201210198866 A CN201210198866 A CN 201210198866A CN 102691242 A CN102691242 A CN 102691242A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- existing roadbed
- existing
- roadbed
- inner formword
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
本发明公开了一种不中断铁路运营的既有路基改为隧道的方法包括如下步骤:(1)在既有路基的两侧设置隧道结构基础;(2)利用天窗时间在位于同一侧的相邻两个既有路基的接触网立柱之间横跨既有路基将内模板架设在隧道结构基础上;(3)在内模板上铺设隧道衬砌;(4)内收内模板,沿既有路基延伸的方向移动内模板至下一个相邻的两个既有路基的接触网立柱之间;(5)将既有路基的接触网导线移至隧道衬砌内侧顶部并拆除既有路基的接触网立柱;(6)重复步骤(3)~步骤(5),直到既有路基上方的整条隧道衬砌铺设完毕。本发明的方法可改善铁路沿线的交通、消除噪声污染并提升铁路周边地块的价值。
Description
技术领域
本发明涉及既有铁路路线改造领域,尤其涉及一种不中断铁路运营的既有路基改为隧道的方法。
背景技术
随着城市化建设的脚步越来越快,很多铁路干线都穿过城市的主城区。虽然这些历史修建的铁路为城市的繁荣做出了不可磨灭的贡献,但是随着时代的发展,主城区铁路,尤其是路堑形式的铁路将城市分隔为多个地块,造成了铁路两侧的交通不便,列车行驶带来的噪音影响了铁路沿线的居民生活。另外,铁路沿线通常堆积有很多垃圾,如果垃圾处理不及时,会破坏周边铁路沿线景观,从而降低铁路沿线的地块价值。
因此,有必要提供一种不中断铁路运营的既有路基改为隧道的方法克服上述缺陷。
发明内容
本发明的目的是提供一种不中断铁路运营的既有路基改为隧道的方法,可改善铁路沿线的交通、消除噪声污染并提升铁路周边地块的价值。
为了实现上述目的,本发明提供了不中断铁路运营的既有路基改为隧道的方法,包括以下步骤:(1)在既有路基的两侧设置隧道结构基础;(2)利用天窗时间在位于同一侧的相邻两个既有路基的接触网立柱之间横跨既有路基,将内模板架设在隧道结构基础上;(3)在内模板上铺设隧道衬砌;(4)内收内模板,沿既有路基延伸的方向移动内模板至下一个相邻的两个既有路基的接触网立柱之间;(5)将既有路基的接触网导线移至隧道衬砌内侧顶部并拆除既有路基的接触网立柱;(6)重复步骤(3)~步骤(5),直到既有路基上方的整条隧道衬砌铺设完毕。
较佳地,所述步骤(2)和所述步骤(3)之间还包括以下步骤:在内模板两侧架设防抛网。
较佳地,所述步骤(6)之后还包括:在铺设完毕的隧道衬砌上方进行土石回填。通过土石回填,可将由铁路划分开的分块土地合为一个整体,从而不仅改善了交通状况,而且保护了周边铁路沿线的景观。
较佳地,所述步骤(2)具体为:在既有路基的一侧铺设导轨,移动模板台车利用天窗时间在导轨上移动至位于同一侧的相邻两个既有路基的接触网立柱之间并横跨既有路基将内模板架设在隧道结构基础上。
较佳地,隧道衬砌为钢筋混凝土衬砌。
较佳地,隧道衬砌呈拱形或矩形。
较佳地,所述步骤(3)具体为:在内模板上方架设外模板,在内模板和外模板之间搭设结构钢筋,在内模板和外模板之间浇筑钢筋混凝土形成隧道衬砌,并拆除外模板。
较佳地,内模板为钢架。
较佳地,隧道结构基础为扩大基础或桩基础。
与现有技术相比,本发明的有益效果如下:
(1)本发明利用天窗时间改建隧道,因而能够不中断既有铁路的运营;
(2)将路基形式改为隧道形式,消除了噪声污染,提升了周边地块的价值,缓解了铁路沿线的垃圾对铁路运行的影响。
通过以下的描述并结合附图,本发明将变得更加清晰,这些附图用于解释本发明的实施例。
附图说明
图1为本发明不中断铁路运营的既有路基改为隧道的方法的流程图。
图2为经过本发明的方法改造后的隧道的示意图。
具体实施方式
现在参考附图描述本发明的实施例,附图中类似的元件标号代表类似的元件。
如图1-2所示,本实施例的不中断铁路运营的既有路基改为隧道的方法包括如下步骤:
步骤S1:在既有路基10的两侧设置隧道结构基础20;
步骤S2:在既有路10的一侧铺设导轨,移动模板台车利用天窗时间在导轨上移动至位于同一侧的相邻两个既有路基10的接触网立柱11之间并横跨既有路基10,将内模板架设在隧道结构基础20上;
步骤S3:在内模板两侧架设防抛网;
步骤S4:在内模板上方架设外模板,在内模板和外模板之间搭设结构钢筋,在内模板和外模板之间浇筑钢筋混凝土形成隧道衬砌21,并拆除外模板;
步骤S5:内收内模板,沿既有路基10延伸的方向移动内模板至下一个相邻的两个既有路基10的接触网立柱11之间;
步骤S6:将既有路基10的接触网导线12移至隧道衬砌21内侧顶部并拆除既有路基10的接触网立柱11;
步骤S7:重复步骤S4~步骤S6,直到既有路基10上方的整条隧道衬砌21铺设完毕;
步骤S8:在铺设完毕的隧道衬砌21上方进行采用土石22进行回填。
需要说明的是,可通过千斤顶泄压的方式使内模板内收。
由上述技术方案可知,一方面,本发明利用天窗时间改建隧道,因而能够不中断既有铁路的运营。另一方面,将路基形式改为隧道形式,消除了噪声污染,提升了周边地块的价值,缓解了铁路沿线的垃圾对铁路运行的影响。
以上结合最佳实施例对本发明进行了描述,但本发明并不局限于以上揭示的实施例,而应当涵盖各种根据本发明的本质进行的修改、等效组合。
Claims (9)
1.一种不中断铁路运营的既有路基改为隧道的方法,包括以下步骤:
(1)在既有路基的两侧设置隧道结构基础;
(2)利用天窗时间在位于同一侧的相邻两个既有路基的接触网立柱之间横跨既有路基,将内模板架设在隧道结构基础上;
(3)在内模板上铺设隧道衬砌;
(4)内收内模板,沿既有路基延伸的方向移动内模板至下一个相邻的两个既有路基的接触网立柱之间;
(5)将既有路基的接触网导线移至隧道衬砌内侧顶部并拆除既有路基的接触网立柱;
(6)重复步骤(3)~步骤(5),直到既有路基上方的整条隧道衬砌铺设完毕。
2.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,所述步骤(2)和所述步骤(3)之间还包括以下步骤:
在内模板两侧架设防抛网。
3.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,所述步骤(6)之后还包括:
在铺设完毕的隧道衬砌上方进行土石回填。
4.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,所述步骤(2)具体为:
在既有路基的一侧铺设导轨,移动模板台车利用天窗时间在导轨上移动至位于同一侧的相邻两个既有路基的接触网立柱之间并横跨既有路基,将内模板架设在隧道结构基础上。
5.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,隧道衬砌为钢筋混凝土衬砌。
6.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,隧道衬砌呈拱形或矩形。
7.如权利要求5所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,所述步骤(3)具体为:
在内模板上方架设外模板,在内模板和外模板之间搭设结构钢筋,在内模板和外模板之间浇筑钢筋混凝土形成隧道衬砌,并拆除外模板。
8.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,内模板为钢架。
9.如权利要求1所述的不中断铁路运营的既有路基改为隧道的方法,其特征在于,隧道结构基础为扩大基础或桩基础。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210198866.9A CN102691242B (zh) | 2012-06-15 | 2012-06-15 | 不中断铁路运营的既有路基改为隧道的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210198866.9A CN102691242B (zh) | 2012-06-15 | 2012-06-15 | 不中断铁路运营的既有路基改为隧道的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102691242A true CN102691242A (zh) | 2012-09-26 |
CN102691242B CN102691242B (zh) | 2015-02-04 |
Family
ID=46856969
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210198866.9A Active CN102691242B (zh) | 2012-06-15 | 2012-06-15 | 不中断铁路运营的既有路基改为隧道的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102691242B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105178980A (zh) * | 2015-09-07 | 2015-12-23 | 中南大学 | 一种隧道开天窗衬砌结构修复方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN86204286U (zh) * | 1986-06-24 | 1987-05-06 | 郑州铁路局西安科学技术研究所 | 铁道线路上方建筑施工装置 |
WO1993002264A1 (en) * | 1991-07-19 | 1993-02-04 | International Dome Systems Cyprus Ltd. | Method of manufacturing a hollow self-supporting concrete structure, means for performing said method and structures obtained by means of the method |
WO1994016173A1 (en) * | 1993-01-07 | 1994-07-21 | Bohn Arne | Formwork for use by the production of logitudinal structures |
CN1116437A (zh) * | 1993-11-17 | 1996-02-07 | 国际圆顶系统(塞浦路斯)有限公司 | 在公路或铁路之类交通道路上建造隧道形盖或隔离屏的方法 |
CN1834350A (zh) * | 2006-07-11 | 2006-09-20 | 董国良 | 一种噪音全隔离的机动车道路系统 |
CN101148911A (zh) * | 2007-10-29 | 2008-03-26 | 中铁二院工程集团有限责任公司 | 接长既有电气化铁路隧道的施工方法 |
CN102277839A (zh) * | 2011-04-29 | 2011-12-14 | 中铁二院工程集团有限责任公司 | 既有电化铁路增建明洞构造及其快速施工方法 |
-
2012
- 2012-06-15 CN CN201210198866.9A patent/CN102691242B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN86204286U (zh) * | 1986-06-24 | 1987-05-06 | 郑州铁路局西安科学技术研究所 | 铁道线路上方建筑施工装置 |
WO1993002264A1 (en) * | 1991-07-19 | 1993-02-04 | International Dome Systems Cyprus Ltd. | Method of manufacturing a hollow self-supporting concrete structure, means for performing said method and structures obtained by means of the method |
WO1994016173A1 (en) * | 1993-01-07 | 1994-07-21 | Bohn Arne | Formwork for use by the production of logitudinal structures |
CN1116437A (zh) * | 1993-11-17 | 1996-02-07 | 国际圆顶系统(塞浦路斯)有限公司 | 在公路或铁路之类交通道路上建造隧道形盖或隔离屏的方法 |
CN1834350A (zh) * | 2006-07-11 | 2006-09-20 | 董国良 | 一种噪音全隔离的机动车道路系统 |
CN101148911A (zh) * | 2007-10-29 | 2008-03-26 | 中铁二院工程集团有限责任公司 | 接长既有电气化铁路隧道的施工方法 |
CN102277839A (zh) * | 2011-04-29 | 2011-12-14 | 中铁二院工程集团有限责任公司 | 既有电化铁路增建明洞构造及其快速施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105178980A (zh) * | 2015-09-07 | 2015-12-23 | 中南大学 | 一种隧道开天窗衬砌结构修复方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102691242B (zh) | 2015-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101831873B (zh) | 一种运营轨道交通地面线下方修建箱涵的便桥盖挖法 | |
CN103114592B (zh) | 一种紧邻地铁站的深基坑组合支护施工方法 | |
CN103215894B (zh) | 移动式临时预应力张拉锚块 | |
CN104213514B (zh) | 一种覆土波纹钢板-混凝土组合拱桥的加强方法 | |
CN101294447B (zh) | 建筑物桩基托换方法 | |
CN105672347A (zh) | 盾构穿越既有桩基的预制桩-板托换结构及施工方法 | |
CN105736001A (zh) | 一种采用预制构件建造地铁车站的施工方法 | |
CN105908639A (zh) | 一种预制箱涵及快速定位施工方法 | |
CN202273169U (zh) | 栈桥 | |
CN204959762U (zh) | 挡墙式龙门吊轨道梁结构 | |
CN105350409B (zh) | 城市轨道交通长枕式钢弹簧浮置板道床道岔施工方法 | |
CN105041348B (zh) | 一种采用复合顶板的地下空间暗挖构筑方法 | |
CN104164839B (zh) | 一种拓宽箱涵的施工方法 | |
CN104164884B (zh) | 一种组合体系护坡固堤方法 | |
CN112983493A (zh) | 一种盾构近距离下穿大断面桥涵的加固结构及施工方法 | |
CN102691242B (zh) | 不中断铁路运营的既有路基改为隧道的方法 | |
CN105986578A (zh) | 路边管状地下车库的顶管建造方法 | |
KR101187282B1 (ko) | 2주식교대 구조를 이용한 철도 교량 시공방법 | |
JP2005290889A (ja) | 掘割道路の構造及びその施工方法 | |
CN103243662B (zh) | 一种既有铁路桥梁的改造加固方法 | |
CN108343085A (zh) | 城市主干道的地铁施工方法 | |
CN101660418B (zh) | 一种用于隧道施工的箱涵顶进置换矩形管撑法 | |
CN104674625A (zh) | 下穿道结构和施工方法 | |
CN210797573U (zh) | 一种基于板下滑槽的地下结构内部运输系统 | |
CN105951839B (zh) | 一种利用膨胀加强带处理盖挖临时立柱的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |