CN102662153A CN2012101611573A CN201210161157A CN102662153A CN 102662153 A CN102662153 A CN 102662153A CN 2012101611573 A CN2012101611573 A CN 2012101611573A CN 201210161157 A CN201210161157 A CN 201210161157A CN 102662153 A CN102662153 A CN 102662153A
Authority
CN
China
Prior art keywords
phase
pressing plate
probes
test
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101611573A
Other languages
Chinese (zh)
Inventor
陈缨
袁世炯
卢斌
金鑫
陈晓静
郑涵月
刘芸
刘鹍
张亦鸣
沈文琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Priority to CN2012101611573A priority Critical patent/CN102662153A/en
Publication of CN102662153A publication Critical patent/CN102662153A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Measurement Of Resistance Or Impedance (AREA)

Abstract

The invention relates to a three-phase smart electricity meter alternating voltage impulse voltage test tool, which is characterized in that a plurality of positioning clamp plates are uniformly distributed on a base seat; a working station is formed between every two ,two adjacent positioning clamp plates; a pressing plate is sleeved on a plurality of guideposts of the base seat; a pressing plate pressing mechanism is arranged; a plurality of groups of probes are fixedly arranged on the lower part of the pressing plate; one group of probes corresponds to terminals of an ammeter to be tested; and each group of probes is formed by ten main probes and fifteen auxiliary probes. The ten main probes in each group of probes are respectively connected with high-end jacks on the base seat through wires and switches; the fifteen auxiliary probes in each group of probes are respectively connected with low-end jacks on the base seat through wires and switches; and the high-end jacks and the low-end jacks are respectively connected with an output end and a ground terminal of a withstand voltage tester. According to the tool, artificial connection in test is avoided, a plurality of meters are used for testing simultaneously, and the tool has the characteristics of high test working efficiency and high test accuracy.

Description

Three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock
Technical field
The present invention relates to electric energy meter proving installation, the particularly intelligent electric energy meter insulating property proving installation under alternating voltage and pulse voltage.
Background technology
GB/T 17215.211-2006 regulation exchanges electric measuring instrument and should carry out the insulating property testing experiment, comprises AC voltage withstand test and impulse test.During test, should carry out test and the test of all line-to-grounds between circuit and circuit respectively.The AC voltage withstand test requirement, the auxiliary line that all current circuits and voltage circuit and reference voltage surpass 40V should be linked as a bit, applies the 4Kv trial voltage between this point and the ground, applies the 2Kv WV between unconnected each circuit in the work.Impulse test is selected different tests voltage according to the intelligent electric energy meter specification.Test connection synoptic diagram such as Fig. 1, shown in Figure 2.
At present; Alternating voltage, pulse voltage test for intelligent electric energy meter are carried out with single ammeter mode usually; Single only making an experiment then needs the time of labor and manpower; Existence needs artificial wiring (for carrying out the insulating property test of different tests point), and it is loaded down with trivial details to work, the lower and poor stability problem of efficient.
Summary of the invention
Do not need artificial wiring, many three-phase intelligent electric energy meter alternating voltage pulses voltage tester frocks that table is tested simultaneously when the purpose of this invention is to provide a kind of the test.
The objective of the invention is to realize like this: a kind of three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock; The base upper surface upper edge long side direction of cuboid is uniformly distributed with through bolt and is fixed with a plurality of positioning splints; Be configured for putting a station of ammeter to be tested between adjacent two positioning splints; Be fixed with many guideposts on the base upper surface, pressing plate is enclosed within on the guidepost through the perforate on it versatilely; Also has the pressing plate press mechanism; The pressing plate bottom is fixed with many group probes, is made up of 10 primary probes and 15 assist probes corresponding to one group of probe of an ammeter to be tested; Every group of probe connects by following mode: when pressing plate is depressed; Contacted 10 primary probes of A phase current+end, A phase current-end, A phase voltage end, B phase current+end, B phase current-end, B phase voltage end, C phase current+end, C phase current-end, C phase voltage end and earth terminal with ammeter to be tested are connected to the high-end jack on the base through lead and switch respectively respectively; When pressing plate is depressed; With the tripping operation Chang Kaiduan of ammeter to be tested, the common port that trips, tripping operation normal-closed end, warning+end, warning-end, meritorious pulse+end, meritorious pulse-end, common, multi-functional+end, multi-functional-as to hold, RS485 communication interface 1+ end, RS485 communication interface 1-end, RS485 communication interface 2+ end, RS485 communication interface 2-end and contacted 15 assist probes of common are connected to the low side jack on the base through lead and switch respectively respectively; Low side jack on the base is used separately as earth terminal and the output terminal that is connected Hi-pot Tester with high-end jack.
Above-mentioned guidepost is four.
Above-mentioned positioning splint is four and constitutes two stations.
Above-mentioned probe adopts German INGUN probe.
Be fixed with riser on the above-mentioned base; Said pressing plate press mechanism is: 305H folder fast is installed on the riser, and vertical bar upper end is hinged on 305H and presss from both sides the bottom fast, and vertical bar lower end is through being bolted on the pressing plate.
Above-mentioned base is a black bakelite base.
Above-mentioned every group of probe stationary is on a needle plate, and needle plate is fixed on the pressing plate bottom.
The present invention has designed and Implemented single-phase intelligent ammeter alternating voltage, pulse voltage test fixture respectively according to the characteristic of intelligent electric energy meter.When defective test specimen occurring, for ease of the test reproduction, single-phase intelligent ammeter test fixture has designed three epi-positions, can carry out three single-phase table dielectric tests simultaneously; The pressure-wire of the electric current line of connecting between the test specimen, parallel connection and the line of test specimen and test fixture all are encapsulated in base inside, have avoided loaded down with trivial details artificial wiring link.
The invention has the beneficial effects as follows: utilize the present invention to carry out the intelligent electric energy meter dielectric test; Can improve work efficiency, reduce manual errors wiring probability, improve safe operation; Strengthen the unitarity of product inspection method and judgment basis simultaneously, reduced the product quality discreteness.Three-phase and four-line intelligent electric energy meter with through mutual inductor is an example, utilizes the present invention to carry out the insulating property testing experiment and makes an experiment with the mode that adopts artificial wiring, and effect comparison is as shown in table 1.
The contrast of table 1 test effect:
The test method effect comparison Employing the present invention make an experiment Adopt the artificial mode of connection to make an experiment
Test efficiency Single only through mutual inductor three-phase and four-line intelligent electric energy meter, accomplish the test of impulse test and alternating voltage, about 6min consuming time Single only through mutual inductor three-phase and four-line intelligent electric energy meter, accomplish the test of impulse test and alternating voltage, about 15min consuming time
Security Security is higher Security is low
Reliability Reliability is high Reliability is lower
Accuracy Accuracy is high Accuracy is lower
Description of drawings
Fig. 1 is alternating voltage, impulse test wiring diagram (line-to-ground).
Fig. 2 is alternating voltage, impulse test wiring diagram (between the circuit).
Fig. 3 is a stereographic map of the present invention.
Fig. 4 is the vertical cross section figure along the vertical bar of Fig. 3.
Fig. 5 is the synoptic diagram of the terminal of three-phase electric energy meter when contacting with probe (among the figure in the frame of broken lines expression be positioned at the wiring of frock base).
Embodiment
Fig. 3, Fig. 4 illustrate this three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock; The base 1 upper surface upper edge long side direction of cuboid is uniformly distributed with through bolt and is fixed with a plurality of positioning splints 2; Be configured for putting a station of ammeter 11 to be tested between adjacent two positioning splints; Be fixed with many guideposts 4 on base 1 upper surface, pressing plate 9 is enclosed within on the guidepost through the perforate on it versatilely; Also has the pressing plate press mechanism; Pressing plate 9 bottoms are fixed with many group probes 8, are made up of 10 primary probes and 15 assist probes corresponding to one group of probe of an ammeter to be tested; Every group of probe connects by following mode: when pressing plate is depressed; Respectively with contacted 10 primary probes of A phase current+end, A phase current-end, A phase voltage end, B phase current+end, B phase current-end, B phase voltage end, C phase current+end, C phase current-end, C phase voltage end and earth terminal of ammeter to be tested respectively through lead and the switch (switch of connecting on each lead; Be connected to the high-end jack on the base 1 down together); When pressing plate is depressed; With the tripping operation Chang Kaiduan of ammeter to be tested, the common port that trips, tripping operation normal-closed end, warning+end, warning-end, meritorious pulse+end, meritorious pulse-end, common, multi-functional+end, multi-functional-as to hold, RS485 communication interface 1+ end, RS485 communication interface 1-end, RS485 communication interface 2+ end, RS485 communication interface 2-end and contacted 15 assist probes of common are connected to the low side jack on the base 1 through lead and switch respectively respectively; Low side jack on the base is used separately as earth terminal and the output terminal that is connected Hi-pot Tester with high-end jack.Every group of probe stationary is on a needle plate 10, and needle plate 10 is fixed on pressing plate 9 bottoms.Positioning splint 2 is four and constitutes two stations.Screw on the positioning splint is a strip, so that the position is finely tuned.Guidepost 4 is four.Be fixed with riser 5 on the base 1; Said pressing plate press mechanism is: 305H presss from both sides 6 fast and is installed on the riser 5, and vertical bar 7 upper ends are hinged on 305H and press from both sides the bottom fast, and vertical bar 7 lower ends are through being bolted on the pressing plate 9.
The pressing plate press mechanism can be following structure, and the one, the spiral press mechanism: fixing screw rod on the pressing plate, nut is screwed on the screw rod, and nut is fixed on (among Fig. 1) riser, the turn screw rod, pressing plate is upstream or downstream thereupon; The 2nd, the cam press mechanism: a cam is arranged at handle 6a bottom among Fig. 1; Vertical bar 7 contacts with cam, and pulling handle makes cam rotation, and vertical bar is pressed down; Descending thereupon with the pressing plate 9 that vertical bar is fixing, the return of pressing plate is realized by the retracing spring that is fixed on pressing plate and the mainboard 5.
Intelligent electric energy meter is placed on the test fixture base plate during test; Adopt the conductive component of German import INGUN probe as frock and test specimen; Realize electric energy meter and contacting of probe and fixing of electric energy meter through quick folder (305H presss from both sides fast) and pressing plate, realize through the high precision linear bearing the accurate location of probe.When quick folder presses down; Probe contacts with the contact of test ammeter; The probe afterbody is connected with test fixture, and then connects testing apparatus, and the difference mode of cut-offfing through the different buttons of test fixture panel makes up; The mode of connection of frock base close beta instrument and test specimen be can change, the alternating voltage and the impulse test of all test points realized.Mini-test is accomplished when needing the change pilot project, and the connecting line that changes testing tool and test fixture gets final product, and need not the intelligent movable electric energy meter.Test will be pressed from both sides handle fast and upwards lift after being accomplished, and probe is separated with tested electric energy meter, accomplish whole test.During test, pressing plate is depressed probe.
Base is made up of header board, back plate, left side plate, upper and lower bottom plate etc.
Utilize the three-phase test fixture to carry out dielectric test to two three-phase intelligent electric energy meters simultaneously, the inner copper cash that insulation course is arranged that adopts of test fixture is as connecting line, and connecting line all is encapsulated in the frock base.Afterbody links to each other with probe, is used for contacting with tested ammeter.Wherein primary probe is 10; Respectively with the A phase current of tested three-phase intelligent electric energy meter+,-end, A phase voltage end; The B phase current+,-end, B phase voltage end; The C phase current+,-end, C phase voltage end and earth terminal link to each other, and 15 of assist probes link to each other with the auxiliary terminal of tested electric energy meter; Be respectively tripping operation Chang Kaiduan, tripping operation common port, tripping operation normal-closed end, warning+,-end, meritorious pulse+,-end, common, multi-functional+,-end, RS485 communication interface 1+ ,-end, RS485 communication interface 2+ ,-hold and common.When handle pressed down, probe fully contacted with table, makes the line conducting.Test fixture base right part has high-end and two jacks of low side; Link to each other with the base inner lead through copper sheet in the jack; Utilize lead that the output terminal of testing tool is linked to each other with the low side jack with the high-end of test fixture respectively with the ground end; Can realize that testing tool provides experimental voltage to frock, accomplish corresponding experiment.
The wiring of two three-phase tables and test fixture is as shown in Figure 5.When testing over the ground; All voltage, current terminal are selected it is linked as a bit through on off state; This point is through the high-end Hi-pot Tester output terminal that is connected to of test fixture, and all auxiliary terminals are through voltage-withstand test frock low side ground connection, and trial voltage is added between voltage, current terminal and the ground.When carrying out testing between each unconnected each circuit in the work; Selection through on off state; Make current voltage or current circuit through the high-end output terminal that is connected to Hi-pot Tester of test fixture; All other routes are linked as a bit, and trial voltage is added in this point and needs between the voltage or current terminal of test.
Carry out impulse test, when testing over the ground, the electric current and voltage terminal is through the high-end Hi-pot Tester output terminal that is connected to of test fixture, and all auxiliary terminals are through voltage-withstand test frock low side ground connection, and trial voltage is added between electric current and voltage terminal and the ground.
Base, pressing plate and clamping plate all adopt the black bakelite as sheet material, bakelite have do not absorb water, characteristic such as non-conductive, high temperature resistant, intensity height, be widely used in electric product; With the conductive component of German import INGUN probe as frock and test specimen, the INGUN probe conducts electricity very well, and elasticity is stronger, and the life-span can reach 1,000,000 times, adopts free plug mode on the probe design, takes off replacing after the damage easily.In addition, the INGUN probe has advantages of higher stability, can reduce False Rate greatly, is widely used in the exact instrument field tests at present.
With the intelligent electric energy meter through mutual inductor is example, and the test embodiment is following:
1, test specimen is positioned on the test fixture base plate, makes the intelligent electric energy meter stationkeeping and depress quick folder, make the corresponding one by one and fully contact of probe and test specimen connection terminal through regulating positioning splint.Connect surge generator and test fixture with connecting line.
2, all buttons of test fixture front panel are out state, carry out the impulse test of all line-to-grounds.
3, carry out of the impulse test of every current circuit respectively to All other routes.The current circuit button of the test of carrying out is opened, and turn-offs all the other buttons.
4, carry out of the impulse test of every voltage circuit respectively to All other routes.The voltage circuit button of the test of carrying out is opened, and turn-offs all the other buttons.Impulse test is accomplished.
5, change connecting line, connect Hi-pot Tester and test fixture.Carry out AC voltage withstand test.
6, after test is accomplished, lift quick folder, take off intelligent electric energy meter, close the testing tool power supply, off-test.
Utilize the three-phase test fixture to carry out dielectric test to two three-phase intelligent electric energy meters simultaneously, the inner copper cash that adopts of test fixture presses down the handle probe and contacts with showing terminal base as connecting line, makes the line conducting.The wiring of two three-phase tables and test fixture is as shown in Figure 5.When testing over the ground; All voltage, current terminal are selected it is linked as a bit through on off state; This point is through the high-end Hi-pot Tester output terminal that is connected to of test fixture, and all auxiliary terminals are through voltage-withstand test frock low side ground connection, and trial voltage is added between voltage, current terminal and the ground.When carrying out testing between each unconnected each circuit in the work; Selection through on off state; Make current voltage or current circuit through the high-end output terminal that is connected to Hi-pot Tester of test fixture; All other routes are linked as a bit, and trial voltage is added in this point and needs between the voltage or current terminal of test.
Carry out impulse test, when testing over the ground, the electric current and voltage terminal is through the high-end Hi-pot Tester output terminal that is connected to of test fixture, and all auxiliary terminals are through voltage-withstand test frock low side ground connection, and trial voltage is added between electric current and voltage terminal and the ground.

Claims (7)

1. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock; It is characterized in that; The base of cuboid (1) upper surface upper edge long side direction is uniformly distributed with through bolt and is fixed with a plurality of positioning splints (2); Be configured for putting a station of ammeter to be tested (11) between adjacent two positioning splints, be fixed with many guideposts (4) on base (1) upper surface, pressing plate (9) is enclosed within on the guidepost through the perforate on it versatilely; Also has the pressing plate press mechanism; Pressing plate (9) bottom is fixed with many group probes (8), is made up of 10 primary probes and 15 assist probes corresponding to one group of probe of an ammeter to be tested; Every group of probe connects by following mode: when pressing plate is depressed; Contacted 10 primary probes of A phase current+end, A phase current-end, A phase voltage end, B phase current+end, B phase current-end, B phase voltage end, C phase current+end, C phase current-end, C phase voltage end and earth terminal with ammeter to be tested are connected to the high-end jack on the base (1) through lead and switch respectively respectively; When pressing plate is depressed; With the tripping operation Chang Kaiduan of ammeter to be tested, the common port that trips, tripping operation normal-closed end, warning+end, warning-end, meritorious pulse+end, meritorious pulse-end, common, multi-functional+end, multi-functional-as to hold, RS485 communication interface 1+ end, RS485 communication interface 1-end, RS485 communication interface 2+ end, RS485 communication interface 2-end and contacted 15 assist probes of common are connected to the low side jack on the base (1) through lead and switch respectively respectively; Low side jack on the base is used separately as earth terminal and the output terminal that is connected Hi-pot Tester with high-end jack.
2. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock according to claim 1 is characterized in that said guidepost (4) is four.
3. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock according to claim 2 is characterized in that said positioning splint (2) is four and constitutes two stations.
4. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock according to claim 3 is characterized in that, said probe (8) adopts German INGUN probe.
5. according to the described three-phase intelligent electric energy meter of the arbitrary claim of claim 1-4 alternating voltage pulses voltage tester frock, it is characterized in that, be fixed with riser (5) on the said base (1); Said pressing plate press mechanism is: 305H presss from both sides (6) fast and is installed on the riser (5), and vertical bar (7) upper end is hinged on 305H and presss from both sides the bottom fast, and vertical bar (7) lower end is through being bolted on the pressing plate (9).
6. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock according to claim 5 is characterized in that said base (1) is a black bakelite base.
7. three-phase intelligent electric energy meter alternating voltage pulses voltage tester frock according to claim 6 is characterized in that said every group of probe stationary is on a needle plate (10), and needle plate (10) is fixed on pressing plate (9) bottom.
CN2012101611573A 2012-05-23 2012-05-23 Three-phase smart electricity meter alternating voltage impulse voltage test tool Pending CN102662153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101611573A CN102662153A (en) 2012-05-23 2012-05-23 Three-phase smart electricity meter alternating voltage impulse voltage test tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101611573A CN102662153A (en) 2012-05-23 2012-05-23 Three-phase smart electricity meter alternating voltage impulse voltage test tool

Publications (1)

Publication Number Publication Date
CN102662153A true CN102662153A (en) 2012-09-12

Family

ID=46771682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101611573A Pending CN102662153A (en) 2012-05-23 2012-05-23 Three-phase smart electricity meter alternating voltage impulse voltage test tool

Country Status (1)

Country Link
CN (1) CN102662153A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103323809A (en) * 2013-06-18 2013-09-25 国家电网公司 Electric energy meter test equipment
CN104162858A (en) * 2014-08-29 2014-11-26 苏州市吴中区胥口广博模具加工厂 Double-handed needle plate downward pressing mechanism of LED displayer main board fast-test clamp
CN104175254A (en) * 2014-08-29 2014-12-03 苏州市吴中区胥口广博模具加工厂 Quick detection clamp of LED displayer mainboard
CN104181351A (en) * 2014-08-29 2014-12-03 苏州市吴中区胥口广博模具加工厂 Double-handed pin plate pressing mechanism for integrated lighting test fixture of LD display device
CN104198903A (en) * 2014-09-05 2014-12-10 江阴力源电子有限公司 Withstand voltage tester fixture for magnetic latching relay
CN104198933A (en) * 2014-09-05 2014-12-10 江阴力源电子有限公司 Test fixture for magnetic latching relay
CN104198775A (en) * 2014-09-01 2014-12-10 苏州市吴中区胥口广博模具加工厂 Small circuit board magnetic field environment testing clamp
CN104237825A (en) * 2014-09-01 2014-12-24 浙江八达电子仪表有限公司 Multi-plate test board of electricity information acquiring terminal
CN106199488A (en) * 2016-06-28 2016-12-07 宁波三星电力发展有限公司 The pressure resistant testing device of electric energy meter
WO2018000178A1 (en) * 2016-06-28 2018-01-04 宁波三星电力发展有限公司 Pressure resistance testing apparatus for electricity meters
CN113917387A (en) * 2021-10-27 2022-01-11 海盐星创电子有限公司 Multistation combination formula electric energy meter automatic check-up test wire

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101054742A (en) * 2007-05-29 2007-10-17 肖颖 Three-roller intelligence drafting machine
CN101655387A (en) * 2009-07-28 2010-02-24 福州科杰电子衡器有限公司 Weighing platform of steel coil weigher
CN201464517U (en) * 2009-06-12 2010-05-12 郑州三晖电气股份有限公司 Positioning and wiring mechanism for electric energy meter
CN101829969A (en) * 2010-05-10 2010-09-15 唐山轨道客车有限责任公司 Pressing device
CN201828907U (en) * 2010-08-25 2011-05-11 芯通科技(成都)有限公司 Program burning tool of power amplification module
CN102069376A (en) * 2010-12-31 2011-05-25 宁波泛亚汽车部件有限公司 Bush fixture
CN201909843U (en) * 2011-01-21 2011-07-27 广东电网公司广州供电局 Wiring device for automatic verification of three-phase electric energy meter
CN202631726U (en) * 2012-05-23 2012-12-26 四川电力科学研究院 Tool for testing three-phase intelligent ammeter under alternating-current voltage and pulse voltage

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101054742A (en) * 2007-05-29 2007-10-17 肖颖 Three-roller intelligence drafting machine
CN201464517U (en) * 2009-06-12 2010-05-12 郑州三晖电气股份有限公司 Positioning and wiring mechanism for electric energy meter
CN101655387A (en) * 2009-07-28 2010-02-24 福州科杰电子衡器有限公司 Weighing platform of steel coil weigher
CN101829969A (en) * 2010-05-10 2010-09-15 唐山轨道客车有限责任公司 Pressing device
CN201828907U (en) * 2010-08-25 2011-05-11 芯通科技(成都)有限公司 Program burning tool of power amplification module
CN102069376A (en) * 2010-12-31 2011-05-25 宁波泛亚汽车部件有限公司 Bush fixture
CN201909843U (en) * 2011-01-21 2011-07-27 广东电网公司广州供电局 Wiring device for automatic verification of three-phase electric energy meter
CN202631726U (en) * 2012-05-23 2012-12-26 四川电力科学研究院 Tool for testing three-phase intelligent ammeter under alternating-current voltage and pulse voltage

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中华人民共和国国家质量监督检验检疫总局: "《交流电测量设备通用要求、试验和试验条件第11部分:测量设备》", 14 March 2006 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103323809A (en) * 2013-06-18 2013-09-25 国家电网公司 Electric energy meter test equipment
CN103323809B (en) * 2013-06-18 2016-08-10 国家电网公司 A kind of electric energy meter test equipment
CN104162858A (en) * 2014-08-29 2014-11-26 苏州市吴中区胥口广博模具加工厂 Double-handed needle plate downward pressing mechanism of LED displayer main board fast-test clamp
CN104175254A (en) * 2014-08-29 2014-12-03 苏州市吴中区胥口广博模具加工厂 Quick detection clamp of LED displayer mainboard
CN104181351A (en) * 2014-08-29 2014-12-03 苏州市吴中区胥口广博模具加工厂 Double-handed pin plate pressing mechanism for integrated lighting test fixture of LD display device
CN104198775A (en) * 2014-09-01 2014-12-10 苏州市吴中区胥口广博模具加工厂 Small circuit board magnetic field environment testing clamp
CN104237825A (en) * 2014-09-01 2014-12-24 浙江八达电子仪表有限公司 Multi-plate test board of electricity information acquiring terminal
CN104198933A (en) * 2014-09-05 2014-12-10 江阴力源电子有限公司 Test fixture for magnetic latching relay
CN104198903A (en) * 2014-09-05 2014-12-10 江阴力源电子有限公司 Withstand voltage tester fixture for magnetic latching relay
CN106199488A (en) * 2016-06-28 2016-12-07 宁波三星电力发展有限公司 The pressure resistant testing device of electric energy meter
WO2018000178A1 (en) * 2016-06-28 2018-01-04 宁波三星电力发展有限公司 Pressure resistance testing apparatus for electricity meters
CN113917387A (en) * 2021-10-27 2022-01-11 海盐星创电子有限公司 Multistation combination formula electric energy meter automatic check-up test wire
CN113917387B (en) * 2021-10-27 2024-03-15 海盐星创电子有限公司 Automatic checking and testing line for multi-station combined electric energy meter

Similar Documents

Publication Publication Date Title
CN102662154A (en) Single phase smart electricity meter alternating voltage impulse voltage test tool
CN102662153A (en) Three-phase smart electricity meter alternating voltage impulse voltage test tool
CN202631725U (en) Equipment for testing alternating-current voltage and pulse voltage of single-phase intelligent electric meter
CN105974348B (en) Low-voltage current mutual inductor comprehensive detection system and its method
CN102540001B (en) Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN111157941B (en) Quick switching and checking device and method for primary winding of power transformer
CN102156273A (en) Electric energy meter verification circuit for error test and direct current and even harmonic test
CA2784338A1 (en) Wiring tester of multifunctional electric energy metering device
CN103852707B (en) A kind of power semiconductor chip test fixture
CN102680865B (en) Integrated device for insulation test of insulation glove
CN201273932Y (en) AC withstand voltage tester
CN105866723B (en) A kind of insulation test device of single-phase intelligent electric energy meter
CN202631726U (en) Tool for testing three-phase intelligent ammeter under alternating-current voltage and pulse voltage
CN203849330U (en) DC (direct current) resistance measuring instrument for AC (alternating current) loop
CN207752134U (en) Portable electric test apparatus function inspection device
CN110196347B (en) Electric energy metering combined wiring terminal strip
CN202502242U (en) Error measurement device for voltage transformer
CN102411097B (en) Test control device for current transformer
CN107942101B (en) Portable wire connector for transformer test
CN201945654U (en) Secondary grounding tester of voltage transformer
CN103376421A (en) Power supply efficiency measuring apparatus
CN202548283U (en) Integrated device for insulation test of insulating glove
CN109342987A (en) A kind of combined instrument transformer calibration equipment in included boosting up-flow source
CN213069060U (en) Automatic line-changing voltage-withstanding testing device for multi-core cable
CN103675469B (en) A kind of high-tension line distributed capacitance measurement mechanism and measuring method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130105

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130105

Address after: Tsing Hua Road Qingyang District of Chengdu City, Sichuan Province, No. 24 610071

Applicant after: Sichuan Electric power Research Institute

Applicant after: State Grid Corporation of China

Address before: Tsing Hua Road Qingyang District of Chengdu City, Sichuan Province, No. 24 610071

Applicant before: Sichuan Electric power Research Institute

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120912