CN102650157A - Detachable anchor device for cantilever section steel beam - Google Patents

Detachable anchor device for cantilever section steel beam Download PDF

Info

Publication number
CN102650157A
CN102650157A CN2012101218777A CN201210121877A CN102650157A CN 102650157 A CN102650157 A CN 102650157A CN 2012101218777 A CN2012101218777 A CN 2012101218777A CN 201210121877 A CN201210121877 A CN 201210121877A CN 102650157 A CN102650157 A CN 102650157A
Authority
CN
China
Prior art keywords
plate
anchor device
base plate
screw rod
concrete slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101218777A
Other languages
Chinese (zh)
Inventor
姚晓东
陆建飞
沈映
李晓莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2012101218777A priority Critical patent/CN102650157A/en
Publication of CN102650157A publication Critical patent/CN102650157A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a detachable anchor device for a cantilever section steel beam, which comprises a bottom plate arranged on the bottom surface of a concrete plate and a pressure plate for fixing the cantilever section steel beam on the top surface of the concrete plate. A plastic thin film is paved on the bottom plate and is isolated from the concrete plate; four screws are respectively and vertically fixed on four corners of the bottom plate; the screws pass through the concrete plate and sleeves are sleeved outside the screws to separate the screws from the concrete plate; the four corners of the pressure plate are sleeved on the screws; and nuts are screwed on the screws; and the pressure plate is pressed down by the nuts. The anchor device disclosed by the invention is detachable, can be turned around for use, has no waste and has high safety performance; and the using safety of an outer frame is ensured.

Description

A kind of removable anchor device of shaped steel girder steel of encorbelmenting
Technical field
Shaped steel girder steel fastening devices the present invention relates to encorbelment.
Background technology
The form of building scaffold demonstrates diversified development trend, and builder's jack big with its held job area, save material, cost low, set up simple and convenient, safe and reliable and used widely.The tradition frame of encorbelmenting adopts steel pipe as supporting mechanism, less stable, and the frame of encorbelmenting in recent years all adopts shaped steel as support, and it is way different fixedly, makes the frame of encorbelmenting support the economy and the safety that are produced very big parameter has taken place.
The shaped steel girder steel of encorbelmenting is fixing to adopt traditional round steel collar usually, and it is lack of standardization to bend moulding, and the i iron installation difficulty is big; The collar and plate muscle need the electric welding location when pre-buried; Need workman's torch operation during dismounting; Cutting off the remaining reinforcing bar in back is waste product; Waste is big, and input cost is bigger.
Summary of the invention
Technical problem to be solved by this invention just provides a kind of removable anchor device of shaped steel girder steel of encorbelmenting, and simple in structure, convenient disassembly can have enough to meet the need use.
For solving the problems of the technologies described above; The present invention adopts following technical scheme: a kind of removable anchor device of shaped steel girder steel of encorbelmenting; It is characterized in that: comprise that the base plate of being located on the concrete slab bottom surface and the shaped steel girder steel of will encorbelmenting are fixed in the pressing plate on the concrete slab end face; Lay plastic sheeting and concrete slab isolation on the base plate, four jiaos of difference of base plate vertical fixing, one screw rod, screw rod pass concrete slab and screw jacket has sleeve pipe and concrete slab to isolate; Pressing plate is socketed on the screw rod for four jiaos, and nut is combined on the screw rod and downward clamping platen.
As preferably, said sleeve pipe is a pvc pipe.
As preferably, said base plate and pressing plate are thick Q235 plate of 16mm and base plate and pressing plate and are the square plate that the length of side is 300mm.
As preferably, said screw rod bottom is welded in 50mm place, base plate four angular distance sideline holes.
As preferably, said pressing plate is provided with two, and two block pressur plates laterally arrange, and every block pressur plate connects two screw rods.
Anchor device of the present invention is detachable, can have enough to meet the need use, does not have waste; Though it is bigger that cost drops into, turnover back average unit cost is low, and security performance is high; Ensure the safety in utilization of outrigger, had good economic benefit and social benefit, had good popularizing value.
Description of drawings
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is further described:
Fig. 1 is a mounting structure sketch map of the present invention.
The specific embodiment
As shown in Figure 1; Be the encorbelment embodiment of the removable anchor device of shaped steel girder steel of kind of the present invention, comprise and be located at the base plate 1 on concrete slab 7 bottom surfaces and the shaped steel girder steel 5 of will encorbelmenting is fixed in the pressing plate 2 on the concrete slab end face, lay plastic sheeting and concrete slab isolation on the base plate; Four jiaos of difference of base plate vertical fixing, one screw rod 3; Screw rod passes concrete slab and screw jacket has sleeve pipe 6 and concrete slab to isolate, and pressing plate is socketed on the screw rod for four jiaos, and nut 4 is combined on the screw rod and downward clamping platen.Said sleeve pipe is a pvc pipe.Said base plate and pressing plate are thick Q235 plate of 16mm and base plate and pressing plate and are the square plate that the length of side is 300mm.Said screw rod bottom is welded in the boring of 50mm place, base plate four angular distance sideline.Said pressing plate is provided with two, and two block pressur plates laterally arrange, and every block pressur plate connects two screw rods.
The boring at 50mm place, base plate steel plate four angular distance sideline is welded on the high strength screw rod on the base plate successively, and the pvc pipe cover is inserted on the screw rod, and the top adds two block pressur plates and nut, two screw rods of correspondence is coupled together to get final product respectively.Lay plastic sheeting and concrete slab isolation on the base plate, the protection of bolt sleeve pvc pipe is isolated with concrete slab, and mounting or dismounting are convenient, and base plate is the useless template bar of nail all around, can not cause the concrete slab corner damaged.

Claims (5)

1. removable anchor device of shaped steel girder steel of encorbelmenting; It is characterized in that: comprise and be located at the base plate (1) on concrete slab (7) bottom surface and the shaped steel girder steel (5) of will encorbelmenting is fixed in the pressing plate (2) on concrete slab (7) end face; Lay plastic sheeting and concrete slab isolation on the base plate; Four jiaos of difference of base plate vertical fixing one screw rod (3); Screw rod passes concrete slab (7) and screw jacket has sleeve pipe (6) and concrete slab to isolate, and pressing plate is socketed on the screw rod for four jiaos, and nut (4) is combined on the screw rod and downward clamping platen.
2. a kind of removable anchor device of shaped steel girder steel of encorbelmenting according to claim 1, it is characterized in that: said sleeve pipe is a pvc pipe.
3. a kind of removable anchor device of shaped steel girder steel of encorbelmenting according to claim 2, it is characterized in that: said base plate and pressing plate are thick Q235 plate of 16mm and base plate and pressing plate and are the square plate that the length of side is 300mm.
4. a kind of removable anchor device of shaped steel girder steel of encorbelmenting according to claim 3 is characterized in that: said screw rod bottom is welded in the boring of 50mm place, base plate four angular distance sideline.
5. a kind of removable anchor device of shaped steel girder steel of encorbelmenting according to claim 3, it is characterized in that: said pressing plate is provided with two, and two block pressur plates laterally arrange, and every block pressur plate connects two screw rods.
CN2012101218777A 2012-04-24 2012-04-24 Detachable anchor device for cantilever section steel beam Pending CN102650157A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101218777A CN102650157A (en) 2012-04-24 2012-04-24 Detachable anchor device for cantilever section steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101218777A CN102650157A (en) 2012-04-24 2012-04-24 Detachable anchor device for cantilever section steel beam

Publications (1)

Publication Number Publication Date
CN102650157A true CN102650157A (en) 2012-08-29

Family

ID=46692274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101218777A Pending CN102650157A (en) 2012-04-24 2012-04-24 Detachable anchor device for cantilever section steel beam

Country Status (1)

Country Link
CN (1) CN102650157A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174285A (en) * 2013-03-20 2013-06-26 中天建设集团有限公司 Cantilever frame anchoring element
CN104563481A (en) * 2014-11-06 2015-04-29 云南省第三建筑工程公司 Detachable anchoring device for tail end of common cantilever scaffold section steel
CN110206288A (en) * 2019-05-30 2019-09-06 中国十七冶集团有限公司 A kind of Detachable anchor device formula construction method of suspending scaffold

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201310186Y (en) * 2008-11-17 2009-09-16 江苏省建筑工程集团有限公司 Cantilever beam shelve end self-release anchor device for construction
CN201420310Y (en) * 2009-06-09 2010-03-10 中天建设集团有限公司天津分公司 Pre-buried crimping rack for mounting overhanging steel beam
CN201786013U (en) * 2010-09-19 2011-04-06 中达建设集团股份有限公司 Reusable anchor member for cantilever scaffold
CN201809963U (en) * 2010-09-06 2011-04-27 中建三局第一建设工程有限责任公司 Fixing type profile steel anchor clamp for suspended external scaffold
CN202559710U (en) * 2012-04-24 2012-11-28 中天建设集团有限公司 Dismountable anchoring device for overhanging type steel-steel beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201310186Y (en) * 2008-11-17 2009-09-16 江苏省建筑工程集团有限公司 Cantilever beam shelve end self-release anchor device for construction
CN201420310Y (en) * 2009-06-09 2010-03-10 中天建设集团有限公司天津分公司 Pre-buried crimping rack for mounting overhanging steel beam
CN201809963U (en) * 2010-09-06 2011-04-27 中建三局第一建设工程有限责任公司 Fixing type profile steel anchor clamp for suspended external scaffold
CN201786013U (en) * 2010-09-19 2011-04-06 中达建设集团股份有限公司 Reusable anchor member for cantilever scaffold
CN202559710U (en) * 2012-04-24 2012-11-28 中天建设集团有限公司 Dismountable anchoring device for overhanging type steel-steel beam

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174285A (en) * 2013-03-20 2013-06-26 中天建设集团有限公司 Cantilever frame anchoring element
CN104563481A (en) * 2014-11-06 2015-04-29 云南省第三建筑工程公司 Detachable anchoring device for tail end of common cantilever scaffold section steel
CN110206288A (en) * 2019-05-30 2019-09-06 中国十七冶集团有限公司 A kind of Detachable anchor device formula construction method of suspending scaffold

Similar Documents

Publication Publication Date Title
CN202937005U (en) Cast-in-situ concrete beam lateral template reinforcement device
CN203559594U (en) Combined type protection shed
CN104153555A (en) Detachable overhung steel beam pre-buried fixing device with horizontal fixing assembly
CN203475806U (en) Tool type anchoring bolt assembly used for fixing shape steel cantilever beam in construction sites
CN102650157A (en) Detachable anchor device for cantilever section steel beam
CN102561392A (en) Structure for supporting construction elevator foundation on basement top plate and construction method thereof
CN202559710U (en) Dismountable anchoring device for overhanging type steel-steel beam
CN102733604A (en) Reusable overhanging scaffold embedded ring and construction method thereof
CN202596148U (en) Reusable cantilever scaffold anchoring compression ring
CN102587638A (en) Steel girder anchoring device of overhanging scaffold
CN204266571U (en) A kind of builder's jack i iron pre-embedded device
CN103225396A (en) Beam frame type construction template system
CN206815804U (en) A kind of new builder's jack girder steel built-in fitting
CN202440833U (en) Structure for supporting construction elevator base on top plate of basement
CN102650158A (en) Connecting device used in casting of shear walls in upper and lower layers
CN102286920A (en) Floating resistance device for inner mold of box beam
CN204781520U (en) Detachable die block steel bar truss building carrier plate
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN210976594U (en) Auxiliary mounting device for laminated plate
CN202672701U (en) Overhanging scaffold pre-buried ring capable of being repeatedly used
CN202810179U (en) Overhanging element anchoring tool for overhanging scaffold
CN202467153U (en) Suspension scaffold steel girder anchor device
CN206987374U (en) A kind of formwork reinforcement system external corner fixture
CN203514764U (en) Overhanging scaffold tool type bolt anchoring device
CN202658571U (en) Special adjusting device for bi-directional suspension supporting system of steel hoop

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120829